HomeMy WebLinkAbout102-92 RESOLUTIONRESOLUTION NO. 132-92
A RESOLUTION AUTHORIZING THE MAYOR AND CITY
CLERK TO EXECUTE CHANGE ORDER NO. 5 WITH
BRANCO ENTERPRISES IN THE AMOUNT OF $10,721
FOR THE FAYETTEVILLE HIGH SCHOOL CONSTRUCTION
PROJECT.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Mayor and City Clerk are hereby
authorized and directed to execute Change Order No. 5 with Branco
Enterprises in the amount of $10,721 for the Fayetteville High
School Construction Project. A copy of the contract authorized for
execution hereby is attached hereto marked Exhibit "A" and made a
part hereof.
PASSED AND APPROVED this 7th day of July , 1992.
ATTEST:
APPROVED:
•..CHANGE
ORDER
AIA DOCUMENT G701
OWNER
ARCHITECT
CONTRACTOR
FIELD
OTHER
G
�1
PROJECT- FAYETTEVILLE R.S. ADDITION
(name, address) 1001 W. Stone St.
Fayetteville, AR 72701
TO CONTRACTOR:
(came. address) BRANCO ENTERPRISES, INC.
P. 0. Box 459/107 N. Jefferson
Neosho, MO 64850
Attention: Mr. John Branham, P.E.
President
The Ccntnct is changed as follows:
ITEM NO. 1 . . . ADD . . . $14,558.00
Revise grading and site concrete between Addition and existing building as per Proposal
Request (P.R.) No. 01 and attached reply dated February 24, 1992.
CHANGE ORDER NUMBER:
DATE:
ARCHITECT'S PROJECT NO:
CONTRACT DATE:
CONTRACT FOR:
05
04-28-92
8901
05-28-91
Gereral Construction
ITEM NO. 2 . . . DEDUCT . . . (S8,890.00)
Revise fireproofing requirements as per P.R. No. 04 and attached letter of reply dated
February 12, 1992.
ITEM NO. 3 . . . ADD . . . $5,C53.00
Construct new retaining wall and revise site grading north of Addition as per P.R. No. 03.
Delete ground cover allowance; install sod at area scheduled to receive ground cover, as
per attached reply dated April 27, 1992.
IOTAL . . . ADD . . . $10,72:.00
Not valid until slurred by the Owner, Architect end Contractor.
PFCFIMFD
JUN 0 2 1992
iiA{Lt.Y / AJSGI.rrt I tS
fii..h1•C.C.S, P.A.
The original (Comma Sum)(0SesdcMzedasesiban was . .... . ......
Net change by previously authorized Change Orders .. .. 5
The;Contract Sum) afaixamkatzstromenat prior to this Change Order was f
The (Contract Sum) ;5ssitip extxactwi will he (increased) ?dansuln
SUDS tvapdiby this Change Order in :he amount of ... .... .. f
The new (Contact Sum) incuding this Change Order will be f
The Contract Time will be doriarodkabrantacd(unct anged) by z ero
The date of Substantial Completion as of the due of this C•.ange Order therefore is
NOTE: This retunazy dues nor
Conswcann Change L'
Hailey/Associates
Architects, P.A.
ARCHITECT
P. O. Box 790
Address
r rovil'o
4,375,000.00
36,618.00
4,41:,618.00
10,721.00
4,422,339.00
(
the same.
refkc crianga in dle Cinnract San Contract -here or G.urotees Ma:crlum PrIcc w rh have eq. a rux
thod by
inaptFayettevil a School Dist. «ne
77707
eliti%P -CS
DATE 6. 3 • -1 2
Branco Enterprises, Inc.
CONTRACTOR
P. 0. Box 459
Address
Neosho 'mn ASf}SO
HYI.
DATIL; id'
if
The City of Fayetteville, Arkansas
Fayetteville, Washington County, A:
Ow:NER
Bv: GJ..... FS_ � e
A4dress
BY cnaQr e/ -
DA -F
2—
jeln
7- Tot—
AIA 0001T G7a1 • CHANGE ORDER • leer EDITION
AMERICAN RKTnl'lE OF ARCHITECTS. l'3S NEa' YCRR AVE. NW
A.A° • Drl'kl• • THE
WA..HC:GTON. DC. 210116
WARNING: Unhorsed photocopying wastes US. copyright In end Is subleII to Iegel prosecution.
G701-1987
February 24. 1992
BRANCO.
ENTERPRISES, INC.
GENERAL CONTRACTORS
P.O. 459. 107 NORTH JEFFERSON • NEOSHO, MO 84850 • 417-451.5250
'cam n rAvir l
FEB 2 5 1992
HAILEY / ASSCr.::ATES
": .A.
Hailey/Associates
112 W. Center St.
ist Place 4440
Fayetteville. AR 72702-0790
Attn: Bill Browner
RE: Fayetteville
Dear Bili:
The following is a detailed breakdown of Proposal
High School Addition
Request
Proposal r1 -
General condition
Credit site excavation (258 yds. @ $4)
Limestone fill at stairs & ramps 145 ton
Footing excavation, backfill & tamping
Rebar & installation
Concrete footing - 10 yds - 2 yds (net add 8 yd)
Concrete Foundation - 19 yds - 3 yds
(net add 16 yds)
Stairs w/nosings 1671F-156LF (net add 11LF)
Toe down 157LF-410LF (net deduct 253LF)
Thickened slab at ramp 2 cu. yds.
Rub walls
Handrails installed
Painting handrails
Extend architectural base 8 1/2 LF
5% Overhead
5% Profit
1% Bond
a1 and :3:
l
290.00
1,032.00]
1,489.00
779.00
933.00
640.00
2,560.00
154.00
1,690.0C]
120.00
274.00
6,269.00
1,650.00
638.00
$13,074.00
654.00
$13,728.00
686.00
$14,414.00
144.00
$14,558.00
The change in price is a result of our understanding on the amount of
stairs and seating benches.
•
PROPOSAL REQUEST ;3
General conditions
Increased cut and waste 765 yds
Excavate footing, backfill & tamping
Granular backf111 58 ton
Perforated PVC pipe
12" drain tile 32LF & bends
Concrete footing 16 yds.
Concrete foundation 19 yds.
Rub walls
Catch basin
Rebar installed
Handrail installed
Painting
5% Overhead
5% Profit
1% Bond
$ 290.00
3,060.00
845.00
770.00
140.00
1,059.00
1,760.00
4,780.00
274.30
726.00
1,361.00
1,901.00
475.00
$16,841.00
842.00
$17,683.00
884.00
518,567.00
186.00
$18,753.00
Please advise immediately as these change orders are beginning to impact
certain work elements.
Since;dly,
r
John E. Branham
President
JEB/lt
enc.
FEB 251992
HA1LEY ; ASSOCIATES
Ar:`.;c,:'.s, P.A.
February 12, 1992
BRANCO
ENTERPRISES, INC.
GENERAL CONTRACTORS
P.O 459. 107 NORTH JEFFERSON • NEOSHO. MO 84850. 417-45' -5250
Ha;iey/Associates
112 W. Center St.
1st Place 4440
Fayetteville, AR 72702-0790
Attn: BI11 Browner
Dear Bill;
Per your proposal
Hundred Ninty Dol
Fireproofing now
Sincerely
hn E. Branham
¢¢¢¢¢President
JEB/it
RE: Fayetteville High School
reouest 1i4 we quote
lars ($8,890.00). P1
and we can not delay
a deduct price of Eight Thousand Eignt
ease advise immediately as Cumbie is
him.
Fri; 3 1992
HAIL.. ASSOCIATES
/. . •
April 27, 1992
BRANCO.
ENTERPRISES, INC.
GENERAL CONTRACTORS
P.O 459. 107 NORTH JEFFERSON • NEOSHO, MO 64850. 417-451-5250
Hailey & Associates
112 West Center St., Suite 440
1st Place Building
P.O. Box 790
Fayetteville. AR 72702
ATTN: Mr. Bill Browner
Dear Bill:
PRCFMCIn
APR 2 8 1992
HAILEY / ASSOCIATES
Archil; cts, P.A.
RE: Fayetteville High School Addition
We still have not received signed change orders 12 and *3. As you are aware.
we billed ill on our last billing and we are proceeding on *3 and proposal re-
quest 11 per your verbal authorization. Irregardless of whether we have them
back signed, we will bill for work completed and expect payment as any further
delays would impact our cost and completion date.
We have again reviewed proposal request *3 and stand by the price quoted in
our letter of February 24. 1992. At your request we make the following pro-
posals covering proposal request a3 and the ground cover.
Proposal Request *3
Delete ground cover allowance
Sod ground cover area
Total
Proposal Request *3
Delete ground cover allowance
Delete sod ground cover
Hydromulch ground cover area
and areas shown to be sodded
Total
Proposal Request 43
Delete ground cover allowance
Delete sod ground cover
Hydromulch sodded areas shown
on drawings
Sod round cover areas as
shown on drawings
Total
$18,753.00
120,000.00J
6,300.00
3 5,053.00
$18,753.00
120,000.O0J
( 7,600.001
4,370.00
IS 4,477.001
$18,753.00
120,000.00j
( 7,600.001
2,800.00
5,106.00
IS 941.001
Note, we will not accept responsibility for any areas that erode if hydro -
mulching is used.
Page 2:
We reviewed the possible south curb and gutter change from concrete to
asphalt, but it is not cost effective.
It is imperative that we have direction on the change within the next 2 weeks,
or we will proceed as shown on the prints and the above prices will be subject
to increase.
Sincerely,
C -- b
John E. Branham
President