RESOLUTION NO. 38-91
A RESOLUTION AUTHORIZING CHANGE ORDER NO. 1 TO
THE ENGINEERING CONTRACT WITH CEI ENGINEERING
ASSOCIATES, INC. AND CHANGE ORDER NO. 1 TO
CONSTRUCTION CONTRACT WITH APAC ARKANSAS-
MCCLINTON ANCHOR DIVSION.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Mayor and City Clerk are hereby
authorized and directed to execute Change Order No. 1 to the
engineering contract of CEI Engineering Associates, Inc. in the
amount of $1,045.00 and to the construction contract with McClinton
Anchor Divsion of APAC Arkansas in the amount of $14,298.36 for the
Armstrong Avenue Improvements project. A copy of the amendments to
the contracts authorized for execution hereby is attached hereto
and made a part hereof. z
•
PASSED AND APPROVED this 5th day of March , 1991.
It
APPROVED: '
1
ATTEST:
9
By: J
.-_. City Clgrk:�. Z
,i4`
By:
Mayor
•
'O0O
a
a
•
dim. Oa
INDUSTRIAL
r
r
MMMMMM ONO
POW, STATION
ROAD
PARR
s
V
0
am
COMM( ORM
•
f m Anel
m pv /em evil;
,00
rE
•
11
AMENDMENT TO
AGREEMENT FOR ENGINEERING SERVICES
This is an amendment to the Agreement for Engineering Services
executed on the 6th day of September, 1989 between the City of
Fayetteville, Arkansas and CEI Engineering Associates, Inc. for
the Armstrong Ave. Street construction.
The City intends to increase the scope of the referenced
agreement to include an additional length of street construction
to the gate at Superior Wheel, the length being approximately 150
LE.
CEI Engineering Associates, Inc. agrees to perform the
professional engineering services for the design and construction
of said additional length.
Section B Compensation for Engineering Services from the
referenced agreement shall be amended as follows:
Part 1A: For professional services required to complete detailed
plans and specifications for the above referenced
project, including surveys for easement purposes, the
CITY shall compensate the ENGINEER with the lump sum fee
of
(Five thousand six hundred eighty five dollars)
$5,685.00
18: For professional services required to complete the
preparation of easement documents and plats, the CITY
shall compensate the ENGINEER with the lump sum fee of
(Two thousand dollars)
$2,000.00
Said amount to be adjusted to actual effort involved
according to ENGINEERS standard hourly rate (27.50) for
a Registered Land Surveyor
Part 2 : For professional services for the bid phase of the
project, through the recommendation of awards, the CITY
shall compensate the ENGINEER with the lump sum fee of
(One thousand dollars)
$1,000.00
Part 3 : For professional services required to perform
construction management including one full time inspector
for the entire estimated construction period and
preparation of "As -Built" drawings, the CITY shall
compensate the ENGINEER with the lump sum fee of
(Five thousand four hundred thirty five dollars)
$5,435.00
Said amounts reflecting a proportional amount of a total
increase of $1,045.00 (One thousand and forty-five dollars) in
contract price.
This amendment does not affect or alter any contract provision
other than what is clearly stated herein.
4301AMDT/7s
1/9/91
ORDER NUMBER:
DATE:
1/8/91
01
CHANGE ORDER
AGREEMENT DATE:
NAME OF PROJECT: Armstrong Ave. - Street Reconstruction
OWNER: City of Fayetteville
CONTRACTOR: APAC Arkansas McClinton Anchor Division
The following changes are hereby made to the CONTRACT DOCUMENTS:
Justification: Extending project approximately 150 LF to serve Superior Wheel
in the Fayetteville Industrial Park.
Change to CONTRACT PRICE:
Original CONTRACT PRICE: $ 166,325.50
Current CONTRACT PRICE adjusted by previous
The CONTRACT PRICE due to this CHANGE ORDER
by: $ 14,298.36
The new CONTRACT PRICE due to
Change to CONTRACT TIRE:
The CONTRACT TIME will be (increased) mil€aNi€7d)
The date for completion of all work will be
CHANGE ORDER $ 166,325.50
will be (increased) (IDSOUK 4)
this CHANGE ORDER will be $ 180,623.86
Approvals Required:
To be effective this Change Order
changes the scope or objective of the PROJECT, or
required.
by - 12
must be approved
Requested by: Mr. Richard Shewmaker
Recommended by: Mr. Sid Norbash, City of Fayetteville
Ordered by: Mr. Mark Johnson, P.E. CEI Engineering Associates, Inc.
calendar days.
(Date).
by the OWNER if it
as may otherwise
c/
Accepted by: Mr Jim Cole APAC Arkansas McClinton Anchor Division
Owner:
IC -1
AMENDMENT TO
AGREEMENT FOR ENGINEERING SERVICES
CHANGE ORDER NO. 1
This is an amendment to the Agreement for Engineering Services
executed on the 6th day of September, 1989 between the City of
Fayetteville, Arkansas and CEI Engineering Associates, Inc. for
the Armstrong Ave. Street construction.
The City intends to increase the scope of the referenced
agreement to include an additional length of street construction
to the gate at Superior Wheel, the length being approximately 150
LF.
CEI Engineering Associates, Inc. agrees to perform the
professional engineering services for the design and construction
of said additional length.
Section B Compensation for Engineering Services from the
referenced agreement shall be amended as follows:
Part 1A: For professional services required to complete detailed
plans and specifications for the above referenced
project, including surveys for easement purposes, the
CITY shall compensate the ENGINEER with the lump sum fee
of
•
(Five thousand six hundred eighty five dollars)
$5,685.00
1B: For professional services required to complete the
preparation of easement documents and plats, the CITY
shall compensate the ENGINEER with the lump sum fee of
(Two thousand dollars)
$2,000.00
Said amount to be adjusted to actual effort involved
according to ENGINEERS standard hourly rate (27.50) for
a Registered Land Surveyor
Part 2 : For professional services for the bid phase of the
project, through the recommendation of awards, the CITY
shall compensate the ENGINEER with the lump sum fee of
(One thousand dollars)
$1,000.00
Part 3 For professional services required to perform
construction management including one full time inspector
for the entire estimated construction period and
preparation of "As -Built" drawings, the CITY shall
compensate the ENGINEER with the lump sum fee of
(Five thousand four hundred thirty five dollars)
$5,435.00
Said amounts reflecting a proportional amount of a total
increase of $1,045.00 (One thousand and forty-five dollars) in
contract price.
This amendment does not affect or alter any contract provision
other than what is clearly stated herein.
(SEAL)
4.0 i: --FST r 'S4 rte' .
—j,
mis
i 4-¢- J 3.
='Type Name a iI. ll
Sherrw
ers
�' 2 `,
,:Title=�.`Cityfi * k
.r. ilj.. ' i„ �`
t 0
(SEAL)
ATTEST
Thomas
Type Name David Sbanotto
By
Type Name k.
TitleAsst. Mayor
Date
CITY:
By
Type Name Robert E. Holmes, P.E.
Title Construction Technician Title Principal
Date 3-6—q/
CITY:
i:A(ween
4301AMDT/js
3/6/91