HomeMy WebLinkAbout147-90 RESOLUTIONE
RESOLUTION NO. 147=90
A RESOLUTION AUTHORIZING MCGOODWIN, WILLIAMS &
YATES TO PROCEED WITH PHASE III OF THE WHITE
RIVER WATERSHED•SEWER SYSTEM.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Board of Directors hereby authorized
McGoodwin, Williams & Yates to proceed with Phase III of the White
River Watershed Sewer System at a cost of $293,500.00.
PASSED AND APPROVED this 2nd day of October , 1990.
r
ATTEST:
f.. i
APPROVED: Mayor
FAYETTEVILLE
THE CITY OF FAYETTEVILLE, ARKANSAS
DEPARTMENTAL CORRESPONDENCE
TO: Fayetteville Board of Directors
THRU: Scott Linebaugh, City Manager��L�
FROM: John Merrell, Planning Management Director
DATE: September 14, 1990
SUBJECT: Authorization to Start Phase 3
Sewer System Study, White River Watershed
McGoodwin, Williams, and Yates
McGoodwin, Williams, and Yates began the study of the part of
Fayetteville's sewer system within the White River watershed in
August of 1989. The study was divided into three phases. Phase 1
involved physical inspections of the sewer system, dry weather
monitoring, smoke testing, and some televising. That phase was
completed in January of this year. The cost of Phase 1 was
approximately $230,000.00.
The Board of Directors authorized the beginning of the Phase
2 work in the fall of 1989. Phase 2 was the wet weather monitoring
part of the project. The authorization to begin Phase 2 was asked
for early in the project so that we could do the wet weather
monitoring in the fall if the rains were sufficient. As it turned
out it was not wet enough last fall to do any of the wet weather
monitoring, and the actual monitoring took place in April and May
of 1990. The Phase 2 report containing the results of the
monitoring has now been submitted to the City by McGoodwin,
Williams, and Yates. The cost of Phase 2 was approximately
$115,000.00.
Phase 3 of the study consists of further detailed
investigations of the sewer system based on the results of the
first two phases of the work. The work includes further physical
inspections, additional smoke testing and additional televising.
The scope and cost of Phase 3 as given in the Engineering Contract
with McGoodwin, Williams, and Yates was an estimate based on the
amount of work that might be expected as a result of Phases 1 and
2.
Based on the actual results of the first two phases of the
work, McGoodwin is recommending that the scope of the Phase 3 work
be expanded to include work in addition to the original estimates.
The contract calls for the Phase 3 work to cost $293,500.00.
McGoodwin is recommending additional work that would increase that
figure by an estimated $120,000.00.
The schedule tktat had been worked out with McGoodwin called
for Phase 3 to be completed and a final report to be submitted to
the City by December 31, 1990. The additional work as recommended
by McGoodwin will require a modification of that schedule. It is
estimated that if all of the additional work was done,the date for
a final report would be April 1, 1991.
It is the recommendation of the Staff that McGoodwin,
Williams, and Yates be authorized to begin the Phase 3 work
immediately, but only to the funding level given in the original
contract ($293,500.00). That would let them begin work in some of
the critical areas. We would then propose that the Staff work with
McGoodwin to develop more precisely the scope and cost involved in
any additional work and to develop a schedule which would be
acceptable to the City and to the EPA.
The Staff would at some later time bring a recommendation to
the Board on any increased funding and schedule modifications.
The projects that result from this study will be eligible for
low interest loans from the Arkansas Department of Pollution
Control and Ecology Loan Program.
MICROFILMED
'V AGREEMENT FOR ENGINEERING SERVICES
SEWER SYSTEM STUDY
WHITE RIVER WATERSHED
THIS AGREEMENT, entered into this / v day of • / , 1989,
by and between the City of Fayetteville, Arkansas, hereinaf`/- r ferred to as
the "Owner," and the engineering firm of McGoodwin, Willia s and Yates, Inc.,
of Fayetteville, Arkansas, hereinafter referred to as the "Engineer,"
WITNESSETH THAT:
WHEREAS, the Owner has been experiencing overflows and bypasses from its
sanitary sewage collection system; and
WHEREAS, the Owner has requested proposals from qualified engineering
firms for the performance of a sewer system study to be used as a master plan
for future rehabilitation work in the city; and
WHEREAS, based on proposals received, the Engineer was deemed to be the
best qualified to perform such a study; and
WHEREAS, the Owner desires to employ the Engineer to perform this work;
NOW THEREFORE, in consideration of the mutual covenants and agreements
herein contained, the Owner and the Engineer, the parties hereto, stipulate
and agree that the Owner does hereby employ the Engineer to perform the
required engineering services as hereinafter set out and the Engineer agrees
to provide said services.
Section I. Scope of Services
The Engineer shall provide at his own expense a suitable engineering
staff to perform the necessary studies and evaluations and to report his
findings and recommendations to the Owner.
It is understood and hereby agreed that the Engineer will employ two
subcontractors on this project to assist with flow monitoring and field
investigation services. These firms are ADS Services, Inc., of Huntsville,
Alabama (flow monitoring) and Southeast Environmental Services, Inc., of
Murfreesboro, Tennessee (field investigation services).
The Sewer System Study will be completed in accordance with the "Plan of
Study" included herein as Appendix "A."
Section II. Payment
In consideration of the performance of the foregoing services by the
Engineer, the Owner shall compensate the Engineer on the basis of lump sum
and unit prices as set out below:
Phase 1
1. Mobilization by Subconsultants (Lump Sum) $11,000
2. Installation and Calibration of Flow Monitoring
Stations (20 @ $500.00 per site) 10,000
3. Operation, Maintenance, and Data Collection of
Flow Monitoring Stations (20 at $21.00 per site
per day x 14 days) 5,880
4. Installation, Maintenance and Data Collection
of Rain Gauges (6 @ $15.00 per site x 14 days) 1,260
5. Demobilization of Flow Monitoring Installations
(Lump Sum) 1,000
6. Manhole Inspection (500 @ $50.00) 25,000
7. Smoke Testing (250,000 L.F. @ 15t/ft.) 37,500
8. Dye and/or Flooding Test (50 @ $120.00) 6;000
9. Normal Line Cleaning (30,000 L.F. @ 75t/ft.) 22,500
10. Heavy Line Cleaning (1,000 L.F. @ $2.50/ft.) 2,500
11. Root Removal (1,000 L.F. @ $2.00/ft.) 2,000
12. T. V. Inspection (30,000 L.F. @ 75t/ft.) 22,500
13. Manhole Exposure, if required (50 @ $25.00) 1,250
14. Field Engineering and Supervision (Lump Sum) $61,000
15. Engineering Review, Analysis of Data, and Report
Preparation (Lump Sum) 22,000
Subtotal Phase 1 Estimated Costs $231,390
2
Phase 2
1. Mobilization by- Subtonsultants (Lump Sum) $ 4,000
2. Installation and Calibration of Flow Monitoring
Stations (20 @ $400.00 per site) 8,000
3. Operation, Maintenance and Data Collection of
Flow Monitoring Stations (20 @ $19.00 per site
per day x 45 days) 17,100
4. Installation, Maintenance and Data Collection
of Rain Gauges (6 @ $14.00 per site per day x 45
days)
Demobilization of Flow Monitoring Installations
(Lump Sum)
Hydraulic Modeling of Key Lines and Interceptors
(Lump Sum)
7. Field Engineering and Supervision (Lump Sum)
3,780
1,000
42,000
19,000
8. Engineering Review, Analysis of Data, and Report
Preparation (Lump Sum) 20,000
•
Subtotal Phase 2 Estimated Costs $114,880
Phase 3
1. Mobilization by Subconsultants (Lump Sum) $ 2,000
2. Manhole Inspection (1,000 @ $50.00) 50,000
3. Flow Isolation Readings (500 @ $50.00) 25,000
4. Wet Weather Inspection (40 Subconsultant Crew
Hours @ $100.00/hr.) 4,000
5. Dye and Flooding Test (50 @ $120.00) 6,000
6. Smoke Testing (200,000 L.F. @ 15t) 30,000
7. Normal Line Cleaning (50,000 L.F. @ 754/ft.) 37,500
8. Heavy Line Cleaning (1,000 L.F. @ $2.50/ft.) 2,500
9, Root Removal (1,000 L.F. @ $2.00/ft.) $ 2,000
*It is hereby agreed that for the lump sum price set out the amount
of hydraulic modeling is limited to 250,000 L.F.
Phase 3 (Continued)
10. T. V. Inspection (50,000 L.F. @ 75t/ft.)
11. Field Engineering and Supervision (Lump Sum)
12. Engineering Review, Analysis of Data, and Report
Preparation (Lump Sum)
37,500
61,000
36,000
Subtotal Phase 3 Estimated Costs $293,500
Total Estimated Costs $639,770
It is hereby understood and agreed that the quantities given under the
unit price items are estimates only. Payment shall be made on the basis of
actual number of units completed; consequently, the final costs may vary
considerably from those estimated.
For any additional work not included under the unit and lump sum prices
set out above, compensation to the Engineer shall be based on salary cost
times a factor of 2.3, plus reimbursable expenses.
Salary cost is defined as the cost of salaries of engineers, draftsmen,
stenographers, surveyors, clerks, laborers, etc., for time directly
chargeable to the project, plus Social Security contributions, employment
compensationinsurance, payroll taxes, medical and insurance benefits, sick
leave, vacation, and holiday pay.
The reimbursable expenses for which the Engineer will be reimbursed
shall include travel expenses when traveling outside Northwest Arkansas in
connection with the project, rental expenses for special equipment needed for
completion of the work, purchase of material and other expenses directly
attributable to the project, including any work performed by subcontractors.
The Engineer shall charge the Owner for reimbursable expenses at actual cost
plus eight percent (8%).
Payment under this agreement shall be made monthly based upon unit
prices of work completed plus a pro rata share of lump sum fees based on
percentage of work completed as calculated by the Engineer and verified by
the Owner. Payment shall be made within 15 days after claim submittal by the
Engineer. If any of the work is suspended for an extended period of time or
abandoned as a result of orders from the Owner, the Engineer shall be paid
for work actually completed; payment to be based insofar as possible upon the
unit and lump sum prices established herein.
It is hereby understood and agreed that Phases 2 and 3 of the study may
be delayed. In this event, the unit and lump sum prices shown above will be
valid so long as all work contemplated is completed within 18 months. If the
Owner determines to delay the later phases of the work beyond this 18 -month
time frame, prices will be subject to renegotiation. Work under Phases 2
and 3 above will not commence until authorized by the Owner.
4
Section III. Responsibilities of the Owner
In connection with 'the project, it is hereby agreed that the Owner,
without cost to the Engineer, will be responsible for the following:
A. Providing all available pertinent information required by the
Engineer for conduct of the study, including maps, drawings and
specifications and complete water consumption records and sewer
system records.
B. Providing water from the fire hydrant nearest the line segment
being televised or, if necessary, water and a water truck for
rainfall simulation tests (flooding) and sewer line cleaning.
C. Providing fire department and police department assistance when
necessary for public safety.
D. Providing access to the site of work with sufficient area for the
placement of personnel and equipment, including all rights of way
and points of public access. The Engineer will not be responsible
for restoration of easements during the course of normal operations
unless said damage is the result of negligence on the part of the
Engineer.
E. Providing a method of transportation and a site for disposal of
sand, debris and other material removed when the cleaning of lines
is necessary to perform the study.
F. Locating and exposing any or all manholes as required to perform
the study. This item of work will be completed prior to the
initiation of the physical survey by the Engineer.
G. Providing all local or city licenses and permits.
H. Clearing all blockages which, in the opinion of the Engineer, need
to be cleared to continue the study. Blockages, if any, will be
reported by the Engineer.
I Removing of the device and repairing of the sewer line should the
cleaning jet or television camera become lodged due to a blockage
in the line.
J. Providing any information related to
hazards in the wastewater collection
of the hazards sufficiently to allow
personnel.
K. Cleaning debris from sewer lines and
flow monitoring.
L.
the existence of known safety
system and clearing the system
safe access by the Engineer's
manholes when required for
Cutting samples and repairing ductile or cast iron pipe as required
for inspection purposes.
M. Giving thorough consideration to all documents presented by the
Engineer and informing the Engineer of all decisions within a
reasonable time so as not to delay the work of the Engineer.
N. Giving prompt written notice to the Engineer whenever the Owner
observes or otherwise becomes aware of events which might
substantially alter the Engineer's performance under this
agreement.
•
Section IV. Insurance
The Engineer hereby agrees to carry the following insurance with respect
to the services he performs for the duration of this agreement:
A. Workmen's Compensation
B. Public Liability, including Automobile Liability
C. Professional Liability.
This agreement shall be binding upon the parties hereto, their partners,
heirs, successors, administrators and assigns; and neither party shall
assign, sublet or transfer his interest in this agreement without the prior
written consent of the other party hereto.
IN WITNESS WHEREOF, the Owner has caused these presents to be executed
in its behalf by its duly authorized representatives, and the said Engineer
by its duly authorized representatives, and the parties hereto have set their
hands and seals on the date heretofore set out.
Attest:
a Mc et y, City
Attest:
•
CITY OF FAYETTEVILLE, ARKANSAS
iam V: Martin
McG00DWIN, WILLIAMS AND YATES, INC.
(-pace
Ulmer, Vice
6
11ASK-ORDERNO:v7
EENGINEERING`SERVICES
SSEWER LINE AND MANHOLE?
)REPLACEMENT/RENOVATION
MINISYSTEM,5 'W
This Task Order is executed pursuant to the Basic Agreement between
McCLELLAND CONSULTING ENGINEERS, INC., (ENGINEER) and the CITY OF
FAYETTEVILLE, ARKANSAS (OWNER) which was executed on the 6th f
t!!!),t-Uary7-19913
Article 1
The OWNER hereby authorizes the ENGINEER to perform all engineering
services associated with field surveys and design andconstruction
phase functions required to replace a portion of the existing
sewage, collection and conveyance system in Minisystem 5, as
identified in the Phase III, Volume I report entitled White River
Watershed Sewer System Study. dated November, 1990. Approximately
4,950 LF .of sewer line replacement and approximately 48 manhole
rehabilitations are involved. Some 30 of these manholes are to be
removed from the scope of previously -executed Task Order No. 3 and
inserted into the scope of Task Order No. 7. In order to assist
the OWNER, the ENGINEER will complete the following tasks under
this Task Order:
o Evaluation of alternative piping materials.
o Field alignment and profile surveys, as required to
supplement Record Drawing information.
o Detailed design of recommended improvements.
o Preparation of Plans and Specifications
(construction documents).
o Cost estimates.
o Coordinate the project with the State Department of
Health.
o Assist the City in bidding the construction
project.
o Pre -construction meeting assistance.
o Observation of construction for compliance with
Plans and Detailed Specifications.
o Review of Shop Drawings.
o Preparation of Change Orders.
o Preparation of Pay Estimates for work completed.
o Preparation of Record Drawings.
o Final review of work and recommendations for
acceptance.
Article 2
The compensation for services to be provided in Article 1 is to be
based upon the Hourly Rate and Unit Price Schedules attached hereto
as Appendix A, with estimated fees as follows:
o. Field Surveys and
Design Phase
o Bidding
o Construction Phase
Services
o Easement Preparation -
$11,580
$ 650
$18,500
Hourly Rates
The total fee will not exceed $35,000 without the express written
consent of the OWNER. It is understood that construction
observation services are to be provided on a "full-time" basis,
while "critical" work is being performed by the Contractor. The
Construction Phase Services fee, above, has been estimated on the
basis of providing 400 hours of on-site observation.
Article 5
IN WITNESS WHEREOF, the parties hereto subscribe the same in
triplicate.
ATTEST:
TY Fj�CYETTEVILLE, ARKANSAS
/�
(Name) (Title)
9>42--
day of , 1990.
Dated this
/44 y 6 C`vGG'c�Jvyt u o�
ATTEST:
FORM
By
D CONSUL
C
(Name)
Dated this �. day
ENGINEERS, INC.
P.
1)1'. (Title)
of , 1990.
•
mi
HOURLY RATE SCHEDULE*
July 1, 1990
Principal Engineer
Project Manager/Senior Engineer
Electrical Engineer
Mechanical Engineer
Structural Engineer
Civil Engineer
Senior Engineering Technician
Construction Observer
Chief Draftsman/Designer
Senior Draftsman
HVAC Designer/Draftsman
Junior Draftsman
CADD Station
Survey Crew (2 -Man)
Survey Crew (3 -Man)
Soils Lab Supervisor
Soils Lab Technician
Water Lab Supervisor
Water Lab Technician
Clerical Support
Mileage
Travel Expense
Appendix A
Task Order No. 7
$75.00
$65.00
$60.00
$50.00
$65.00
$45.00
$40.00
$42.50
$45.00
$35.00
$35.00
$22.00
$20.00
$60.00
$75.00
$40.00
$27.00
$38.00
$22.00
$25.00
$ 25/mile
At Cost
Hourly rates are subject to adjustment on an annual basis,
beginning July 1 of the calendar year.