HomeMy WebLinkAbout105-90 RESOLUTIONt • 1 RESOLUTION, NO. 105-90 A RESOLUTION APPROVING CHANGE ORDERS NO. 1 AND 2 FOR WATER AND SEWER RELOCATION PROJECT AT HIGHWAY 71 AND CATO SPRINGS ROAD. BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That the Mayor and City Clerk are hereby authorized and directed to execute Change Order No. 1 and 2 for water and sewer relocation project at Highway 71 and Cato Springs Road. A copy of the change orders authorized for execution hereby is attached hereto marked Exhibit "A" and made a part hereof. PASSED AND APPROVED this 3rd day of July 401 _ATTEST::: �^q -'By : 'City Cie rk C.3 J� . r_ , ^ :.� is as " APPROVED: Mayor , 1990. 'CHANGE ORDER PROJECT: City of (Name, Address) TO CONTRACTOR: (Name, Address) The Contract Delete 239.5 Fayetteville -Utility Relocations at Relocated U.S. Hwy 71 Fayetteville, AR. Don Mitchell, Inc. 883 White Oak Drive Rogers, AR. 72756 is changed as follows: open cut trench on crossing #3 and taking place and a large amount of fill material to 237' proposed bore for a total bore opposed to $70,405.10 as bid with open $3,357.10. OWNER Q.] ENGINEER (� CONTRACTOR IN OTHER ❑ CHANGE ORDER NO: 1 DATE: June 1, 1990 ENGINEER'S PROJECT NO: 88098 CONTRACT DATE: April 30, 1990 CONTRACT FOR: Water & Sewer crossing under.relocated U.S Hwy -71 Fayetteville, AR. bore because of highway construction in open cut trench area. Add 239.5' of 476.5' @ $154.80 L.F. = $73,762.20 as cut crossing for an increase in price of NOT VALID UNTIL SIGNED BY THE OWNER, ENGINEER AND CONTRACTOR The original (Contract Sum) 4,+5};fxuoteekc:lkSod:arioPrrxooed was $ 354,395.45 Net change by previously authorized Change Orders $ -0- The (Contract Sum/AAmmxautambalSmroimmosvi ixmO prior to this Change Order was $ 354,395.45 The (Contract Sum)alIuaKARARRAx*daial:lm &A)G&d will be (increased) kdennamsmdtaammxhamg»l by this Change Order in the amount of$ The new (Contract Sum)>(1naa>t•aTRAROxal6aoxainetakaP)oexX0 including this Change Order will be $ 357,752.55 The Contract Time will be (increased)(decreased)(unchanged) by ( 0 ) days. The-date=of`Subsiantial-Caipletaon as of the date'of the Change Order therefore is 3,357.10 NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive. Grafton, Tull & Assoc., Inc. ENGINEER P.O. Drawer 549 ADDRESS Rogers, Arkansas 72757-0549 cn-.1 /o/iI,o BY DATE nnn Mitrhel), CONTRACTOR 883 White Oak ADDRESS Rogers Inc. City of Fayetteville OWNER Drive Arkansas 72756 1/4 113 West Mountain ADDRESS Fayetteville, All. 72701 • • CHANGE ORDER PROJECT: Utility Relocations at Relocated (Name, Address> U.S. Hwy 71, Fayetteville, AR. TO CONTRACTOR: Don Mitchell, Inc. (Name, Address) 883 White Oak Drive Rogers, AR. 72756 The Contract is changed as follows: OWNER x] ENGINEER CONTRACTOR ID OTHER [l CHANGE ORDER NO: 2 GAZE: June 13, 1990 ENGINEER'S PROJECT NO: 88098 CONTRACT DATE: April 30, 1990 CONTRACT FOR: Water & Sewer Relocation See Attached Page NOT VALID UNTIL SIGNED BY THE OWNER, ENGINEER AND CONTRACTOR The original (Contract Sum) )4TlogAmAgg4AIa$4*%Smx:Pr4:t401 was $ 354,395.45 Net change by previously authorized Change Orders $ 3,357.10 The (Contract Sum)1kNAR*Rtgejxllaxixnaxtr*x Jxprior to this Change Order was $ 357,752.55 The (Contract Sum)jrivawamtaedxllxxianaxtx:itivi will be (increased) kdcaacacaastadkiwwakawgmdk by this Change Order in the amount of$ 17,536.98 The new (Contract Suml*Gaa,awtaadxMaxiaaax#x:ite* including this Change Order will be $375,289-53 The Contract Time will be:fkpRRRpnnftWzxxaaszdA(unchanged) by ( 0 ) days. The date of Substantial Completion as of the date of the Change Order therefore is NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive. Grafton, Tull & Assoc. ENGINEER 2800 No. 2nd ADDRESS Rogers, Arkansas BY c'rn /Jv)r ` ' DATE Tc/nice /3 /%/`o Don Mitchell, Inc. CONTRACTOR 883 White Oak Drive' ADDRESS Rogers, Arkansas -- /S - 40 City of Fayetteville OWNER 113 West Mountain ADDRESS Fayetteville, R. It This Change Order is contingent on being able to (formerly bid as Open Cut Item 4.1) and to push existing casing through bore. If this cannot be change order will follow:. A. bore the 178' the 300' of done, another Dig bore pit, set up boring rail and install equipment $ 1,069.00 B . Excavate and uncover existing casing C. D . E . and weld a cutting head to existing casing $ 1,159.00 Backfill and compact existing excavation $ 2,686.00 Bore and extend existing casing $26,996.98 Backfill and compact bore pit $ 1,112.00 BORE TOTAL $33,022.98 ADD ITEM 4.11 Bored Highway Crossing, Including 16" Steel Casing, 0.344" Wall thickness installed complete: UNIT QUANTITY L.F. 178 COST/UNIT TOTAL PRICE $185.51 $ .3,022.98 Completed and accepted work performed under this item shall be paid for at the price per linear foot bid in the proposal. This item shall consist of installing a specified diameter bored steel casing, as specified, including boring pit, labor, materials, area cleanup, etc. necessary to complete casing insatllation as specified. Existing utility locations should be carefully examined and located. Contractor shall extend existing 16" casing the additional 178 feet to make a 478 foot run of 16" steel casing installed complete. All work shall be completed according to this existing contract specifications. DELETE ITEM 4.1 OPEN CUT HIGHWAY CROSSING INCLUD. 16" STEEL CASING 0.255 WALL THICKNESS INSTALLED COMPLETE INCLUDING EXCAVATION AND BACKFILL SHERE REQUIRED: UNIT QUANTITY L.F. 178 COST/UNIT $87.00 • TOTAL PRICE $15,486.00 TOTAL CHANGE ORDER $17,536.98