RESOLUTION, NO. 105-90
A RESOLUTION APPROVING CHANGE ORDERS NO. 1 AND
2 FOR WATER AND SEWER RELOCATION PROJECT AT
HIGHWAY 71 AND CATO SPRINGS ROAD.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1. That the Mayor and City Clerk are hereby
authorized and directed to execute Change Order No. 1 and 2 for
water and sewer relocation project at Highway 71 and Cato Springs
Road. A copy of the change orders authorized for execution hereby
is attached hereto marked Exhibit "A" and made a part hereof.
PASSED AND APPROVED this 3rd day of July
401
_ATTEST:::
�^q
-'By :
'City Cie rk
C.3
J�
. r_
, ^ :.�
is as "
APPROVED:
Mayor
, 1990.
'CHANGE ORDER
PROJECT: City of
(Name, Address)
TO CONTRACTOR:
(Name, Address)
The Contract
Delete 239.5
Fayetteville -Utility Relocations
at Relocated U.S. Hwy 71
Fayetteville, AR.
Don Mitchell, Inc.
883 White Oak Drive
Rogers, AR. 72756
is changed as follows:
open cut trench on crossing #3 and
taking place and a large amount of fill material
to 237' proposed bore for a total bore
opposed to $70,405.10 as bid with open
$3,357.10.
OWNER Q.]
ENGINEER (�
CONTRACTOR IN
OTHER ❑
CHANGE ORDER NO: 1
DATE: June 1, 1990
ENGINEER'S PROJECT NO: 88098
CONTRACT DATE: April 30, 1990
CONTRACT FOR: Water & Sewer crossing
under.relocated U.S Hwy -71
Fayetteville, AR.
bore because of highway construction
in open cut trench area. Add 239.5'
of 476.5' @ $154.80 L.F. = $73,762.20 as
cut crossing for an increase in price of
NOT VALID UNTIL SIGNED BY THE OWNER, ENGINEER AND CONTRACTOR
The original (Contract Sum) 4,+5};fxuoteekc:lkSod:arioPrrxooed was $ 354,395.45
Net change by previously authorized Change Orders $ -0-
The (Contract Sum/AAmmxautambalSmroimmosvi ixmO prior to this
Change Order was $ 354,395.45
The (Contract Sum)alIuaKARARRAx*daial:lm &A)G&d will be (increased)
kdennamsmdtaammxhamg»l by this Change Order in the amount of$
The new (Contract Sum)>(1naa>t•aTRAROxal6aoxainetakaP)oexX0 including
this Change Order will be $ 357,752.55
The Contract Time will be (increased)(decreased)(unchanged) by ( 0 ) days.
The-date=of`Subsiantial-Caipletaon as of the date'of the Change Order
therefore is
3,357.10
NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or
Guaranteed Maximum Price which have been authorized by Construction Change
Directive.
Grafton, Tull & Assoc., Inc.
ENGINEER
P.O. Drawer 549
ADDRESS
Rogers, Arkansas 72757-0549
cn-.1
/o/iI,o
BY
DATE
nnn Mitrhel),
CONTRACTOR
883 White Oak
ADDRESS
Rogers
Inc. City of Fayetteville
OWNER
Drive
Arkansas 72756
1/4
113 West Mountain
ADDRESS
Fayetteville, All. 72701
•
•
CHANGE ORDER
PROJECT: Utility Relocations at Relocated
(Name, Address> U.S. Hwy 71, Fayetteville, AR.
TO CONTRACTOR:
Don Mitchell, Inc.
(Name, Address) 883 White Oak Drive
Rogers, AR. 72756
The Contract is changed as follows:
OWNER x]
ENGINEER
CONTRACTOR ID
OTHER [l
CHANGE ORDER NO: 2
GAZE: June 13, 1990
ENGINEER'S PROJECT NO: 88098
CONTRACT DATE: April 30, 1990
CONTRACT FOR: Water & Sewer Relocation
See Attached Page
NOT VALID UNTIL SIGNED BY THE OWNER, ENGINEER AND CONTRACTOR
The original (Contract Sum) )4TlogAmAgg4AIa$4*%Smx:Pr4:t401 was $ 354,395.45
Net change by previously authorized Change Orders $ 3,357.10
The (Contract Sum)1kNAR*Rtgejxllaxixnaxtr*x Jxprior to this
Change Order was $ 357,752.55
The (Contract Sum)jrivawamtaedxllxxianaxtx:itivi will be (increased)
kdcaacacaastadkiwwakawgmdk by this Change Order in the amount of$ 17,536.98
The new (Contract Suml*Gaa,awtaadxMaxiaaax#x:ite* including
this Change Order will be $375,289-53
The Contract Time will be:fkpRRRpnnftWzxxaaszdA(unchanged) by ( 0 ) days.
The date of Substantial Completion as of the date of the Change Order
therefore is
NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or
Guaranteed Maximum Price which have been authorized by Construction Change
Directive.
Grafton, Tull & Assoc.
ENGINEER
2800 No. 2nd
ADDRESS
Rogers, Arkansas
BY c'rn /Jv)r ` '
DATE Tc/nice /3 /%/`o
Don Mitchell, Inc.
CONTRACTOR
883 White Oak Drive'
ADDRESS
Rogers, Arkansas
-- /S - 40
City of Fayetteville
OWNER
113 West Mountain
ADDRESS
Fayetteville, R.
It
This Change Order is contingent on being able to
(formerly bid as Open Cut Item 4.1) and to push
existing casing through bore. If this cannot be
change order will follow:.
A.
bore the 178'
the 300' of
done, another
Dig bore pit, set up boring rail and
install equipment $ 1,069.00
B . Excavate and uncover existing casing
C.
D .
E .
and weld
a cutting head to existing casing $ 1,159.00
Backfill and compact existing excavation $ 2,686.00
Bore and extend existing casing $26,996.98
Backfill and compact bore pit $ 1,112.00
BORE TOTAL $33,022.98
ADD ITEM 4.11 Bored Highway Crossing, Including 16" Steel Casing,
0.344" Wall thickness installed complete:
UNIT QUANTITY
L.F. 178
COST/UNIT TOTAL PRICE
$185.51 $ .3,022.98
Completed and accepted work performed under this item shall be
paid for at the price per linear foot bid in the proposal.
This item shall consist of installing a specified diameter bored
steel casing, as specified, including boring pit, labor,
materials, area cleanup, etc. necessary to complete casing
insatllation as specified. Existing utility locations should be
carefully examined and located. Contractor shall extend existing
16" casing the additional 178 feet to make a 478 foot run of 16"
steel casing installed complete. All work shall be completed
according to this existing contract specifications.
DELETE ITEM 4.1 OPEN CUT HIGHWAY CROSSING INCLUD. 16" STEEL
CASING 0.255 WALL THICKNESS INSTALLED COMPLETE INCLUDING
EXCAVATION AND BACKFILL SHERE REQUIRED:
UNIT QUANTITY
L.F. 178
COST/UNIT
$87.00
•
TOTAL PRICE
$15,486.00
TOTAL CHANGE ORDER $17,536.98