HomeMy WebLinkAbout64-87 RESOLUTIONRESOLUTION 64-87
No resolution written for this.
•
September 1, 1987
SPRINKLER BIDS
Public Works Director Burch reported bids were opened today on 280.1
the sludge management irrigation equipment which had been rebid.
Speaking for CH2M Hill, Dennis Sandretto reported one bid was 280.2
received from Hobbs -Adams, which had submitted one of the initial
bids. He said bid documents had been modified, in that delivery
time has been shortened from 180 days to 90 days. He reported
the bid was $302,'800, as opposed to their earlier bid of
$329,322, a decrease of $26,432, resulting in a savings of about
$22,000.
Director Marinoni,
the award of bid
the motion passed,
seconded by Kelley, made a motion to approve
to Hobbs -Adams for $302,800. Upon roll call,
7-0.
TREATMENT PLANT SURETY CONTRACT
Public Works Director Burch told the Board that the surety on the
treatment plant project, USF&G, has been contacted by Olson
Construction Company and notified that Olson cannot financially
complete the project. He said he, the City Attorney, and
Sandretto have been working on a new construction contract which
they expect to have •available in the morning. Burch asked the
Board to approve a resolution authorizing a contract. He said a
new contractor could begin the day following Labor Day. He said
Olson's workers have "pulled off the job and the project is dead
in the water".
Burch explained the agreement would be a three-way agreement
between the City, USF&G and the new contractor being recommended,
Hubert, Hunt and Nichols. He said the new contract is not much
different in scope, with the bonding company still responsible
for fines and penalties. He explained that, as part of a "walk
away,. no claims against the City from Olson" concession to the
City which was negotiated, the staff wishes to pay a bill owed to
CH2M Hill for resident overtime due them from 1985 in the amount
of $44,517. He added that the contract price has not increased.
The City Attorney said the new contract contains the original
contract price plus change orders to date, the new contractor
will. complete the 'contract and correct any defects in
construction Olson made, the City will realize $403,000 to be
used to pay additional engineering costs, is released from claims
by Olson _for alleged additional work, alleged right to extension
of completion date, the City and the engineer are released from
any alleged improper administration of the contract, and the City
will not have to fund excess costs of completing the project. He
280.3
280.4
280.5
280.6
2.
September 1, 1987
281.1 said the surety will have to pay a substantial amount for this
aspect.
281.2 Kelley asked why the engineer did not have legal action against
Olson for the $44,517.. McCord said Olson was unable to pay, and
this was part of the settlement reached with USF&G which is
making the cash settlement. He added that Olson released its
claim that the City wrongfully withheld contract funds for
delays.
281.3 Director Hess, seconded by Lancaster, made a motion to approve a
resolution authorizing the Mayor and City Clerk to execute an
agreement with USF&G and HH&N for completion of the wastewater
treatment plant project. Upon roll call, the motion passed, 6-0-
1, Director Bumpass abstaining because of an attorney-client
relationship with one of the parties.
RESOLUTION NO. 64-87 APPEARS ON PAGE OF ORDINANCE AND
RESOLUTION BOOK
CHANGE ORDER
II1.4 Burch introduced Contract Modification No. 21 resulting in a
deduct to the contract price of $24,824 due toless quantities of
slurry.
•
281.5 Director Kelley, seconded by Johnson, made a motion to approve
the change order. Upon roll call, the motion passed,16-0-1, with
Director Bumpass abstaining.
281.6 Director Martin noted the completion date of the project,
according to the modification, has been changed to June 1, 1988..
He commented that CH2M Hill's letter of August 4 included a
statement that "The City has experienced a series of unfortunate
events on the treatment plant and sludge management projects" and
that "Olson Construction Company has been less than cooperative
throughout the project." Martin said if they had been less than
cooperative throughout the project the City should have put an
end to it early on. Martin quoted from the letter " ..their
workmanship has been poor." He said that was apparently not a
new discovery, he said the City had told the public the plant
would be completed 18 months late, and has spent hundreds of
thousands of dollars on consultants, engineers and staff to get
the job done. He said the City had failed abysmally and "he
hoped the public. was sick and tired of this stupid project
dragging along because of "unfortunate events". He asked for
some responsiveness from the consultants and staff, and for a
weekly report. He said it was absurd that the community taxes
• itself to the tune of millions of dollars and there were overruns
of 18 months.