HomeMy WebLinkAbout77-86 RESOLUTIONT RESOLUTIONNO. 77-86 A. RESOLUTION AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 13 TO THE CITY'S CONTRACT 'WITH OLSON CONSTRUCTION COMPANY FOR CONSTRUCTION OF THE NEW WASTEWATER TREATMENT PLANT TO RESOLVE SIX (6) CONTRACT CHANGES RESULTING IN A NET CONTRACT ADDITION OF $22,104.00. 4 4 BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THECITYOF FAYRITRtV11 IR, ARKANSAS: That the Mayor and. City Clerk are hereby authorized and directed to execute Change Order No. 13 in the City's contract with Olson Con- struction Company for construction of the new Wastewater Treatment Plant to resolve six (6) contract changes resulting in a net contract addition of $22,104.00. A copy of the change order authorized for execution hereby is attached hereto marked Exhibit "A" and made a part hereof. PASSED AND APPROVED this 15th day of July , 1986. APPRO By Mayor CONTRACT MODIFICATION (Change Order) Contract Owner. Modification NO.: 13 Fayetteville, Arkansas Project Name: Wastewater Treatment Plant Improvements Contractor: Olson Construction Company DATE: 6/27/86 Project No.: MG18766.A5,&.A6 The following modifications to the contract are hereby ordered: required) Modify parshall flume slab - CMIR #32 Chance dye requirement for electrical (Use additional pages if 318 encasement concrete - CMIR #34 (1,345) Add support angles for storm sewer inlet #'s, 1, 2, 3, 4, 5, 6, 8, and 10 - CMIR #34 4 1,898 Impact due to delay on aeration basin wall - CMIR #36 213 Add method of penetration for effluent reservoir piping of slurry trench CMIR #37 d 19,329 Provide flanges between -rubber expansion joints'and wafer valves in Blower Bldg. CMIR #38 1,691 Phase 2 $20,413 Phase 3 1,69 - - - Total ;$22,1044- This 522,104This contract modifications constitutes full and mutual accord and satisfaction for all time and all costs related to this change. By acceptance of this contract modification, _ the contractor hereby agrees that the modification represents an equitable adjustment to the contract,' and further, agrees to waive all right to file any further claims or changes arising out of or as a result of this change, or the accumulation of executed Contract Modifications on this Contract. Contract Amount: Contract Duration/Completion Belt Filter Press . Administration Bldg Phase I&II Phase III Original Contract $21,232,000 Date: Previous Changes $193,410.44 *14 Weeks '365 days 90 Days 1/1/1987 9/1/1987 This Change $22,104 Revised Contract $21,447,514.44 *From receipt of written order. Completion date is 12/5/85. CM #8, a force account modification estimated to cost $500, was approved. CM #9, a force account modification estimated to cost $300, was approved. CM #10,'a force account modification estimated to cost $500, was approved. APPROVED: FAYETTEVILLE P. 0, Drawer F Fayetteville, Arkansas Byy� Date: ,..,;(4i;,,,46 jd/MGDS/008 Li ii "1 OLSON CONSTRUCTION CO. 3300 Rock Island Road 72701 Irving, Texas 95060 By: Date: 0574-1 v$ CH2M HILL 2567 Fairl a Drive Montgom Alabama By: ' Y/,!/ 'x0 xA7/6 Date: *14 Weeks 455 Days 4/1/86 n�> 123.- \ 234 A ' JUL 1986 lo; `� nrj4z_ • IL L LU r