Loading...
HomeMy WebLinkAbout23-86 RESOLUTIONA; • RESOLUTION NO. ,23-86 A RESOLUTION AUTHORIZING THE MAYOR AND CITY CLERIC TO EXECUTE CHANGE ORDER NO. 11 IN THE CITY'S WASTEWATER TREATMENT PLANT CONSTRUCTION CONTRACT WITH OLSON CONSTRUCTION CO., TO RESOLVE ELECTRICAL DESIGN CHANGES. SCAM N ED BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF FAYETTEVILLE, ARKANSAS: That the Mayoi and City Clerk are hereby authorized and diiected to execute Change Order No. 11 in the City's Wastewater Treatment Plant construction contract with Olson Construction Co. to resolve electrical design changes. A copy of the Change Order authorized for execution is hereby attached hereto, marked Exhibit "A" and made a part hereof. PASSED AND APPROVED this 18th day of February, 1986. '13 Sacte,44• ,* P +�,,ts krtt m 7 a sFy•• :�.. APPROVED • • • CONTRACT MODIFICATION (Change Order) Contract Modification No.: 11 ,y6 Owner: Fayetteville, Arkansas Project Name: Wastewater Treatment Plant Improvements Contractor: Olson Construction Company MICROFILMED DATE: 2/6/86 Project No.MG18766.A2,.A5,& .A6 The following modifications to the contract are hereby ordered: (Use additional pages if required) Add electrical circuits for Scum Pump Station & revise RPC feeder breaker $ 3,931 Add electrical circuit for supply fan SF -2 and hoist in Primary P.S. 521 Add electrical circuit for exhaust fans 21 & 22 in Admin. Bldg. 329 Change underground circuit to Effluent P.S. to overhead and use Ozark's stds. (11,202)!l Add electrical circuit disconnect for hoist in Filter Bldg. and relocate FP -06-1. 152 Add electrical circuit to Fuel Station Add electrical circuit heater circuit for Switching Station. Add electrical circuit for hoist in Digested Sludge P.S. Add electric circuit for intake filter motors, M-07-24-1&2 717 411 152 1 652 This contract modification constitutes full and mutual accord and satisfaction for all time and all costs related to this change. By acceptance of this contract modification, the contractor hereby agrees that the modification represents an equitable adjustment to the contract, and further, agrees to waive all right to file any further claims or changes arising out of or as a result of this change, or the accumulation of executed Contract Modifications on this Contract. Contract Amount: Contract Duration/Completion Date: Belt Filter Press Administration Bldg Phase I&II Phase III Original Contract $21,232,000 365 days 1/1/1987 9/1/1987 Previous This Changes Change $203,023.48 ($4,337) *14 Weeks 90 Days *From receipt of written order. Completion date is 12/5/85. CM #6, a force account modification estimated to cost $2,000, was approved. CM #8, a force account modification estimated to cost $500, was approved. CM #9, a force account modification estimated to cost $300, was approved. APPROVED: FAYETTEVILLE P.O. Drawer F Fa etevi e, Ark sas 72701 By Date jd/MGDS 011 OLSON CONSTRUCTION CO. 3300 Rock Island Road Irving, Texas 95060 By: $25 Date: Revised Contract $21,430,686.48 *14 Weeks 455 Days 4/1/86 Phase I $4,781 Phase II ($9,922) Phase III $804 TOTAL ($4,337) lane Drive ry, AL 361