Loading...
HomeMy WebLinkAbout72-83 RESOLUTIONRESOLUT7om-u5. 7014.3- A RESOLUTION AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE A CONTRACT WITH BRAUN EXCAVATING COMPANY FOR THE REHABILITATION OF PORTIONS OF THE CITY'S SEWER SYSTEM AT A TOTAL CONTRACT PRICE OF�198,428.60. BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF FAYETTEVILLE, ARKANSAS: That the Mayor and City Clerk are hereby authorized and directed to execute a contract with Braun Excavating Company for the rehabilitation of portions of the City's sewer system at a total contract .price of $198,428.60. A copy of the contract authorized for execution hereby is attached hereto, marked Exhibit "A" and made a part hereof. PASSED AND APPROVED this 7 " day of bF, `tYf'f� 44 A A. r t4711 r•-• { 4 Actin g`....;;C ty,. Clerk ter.. APPROVED: Mayor , 1983. Change Order No. 4 SANITARY SEWER SYSTEM REHABILITATION AND RECONSTRUCTION Minisystems 2, 4, 7, 8, 11 and 16 City of Fayetteville, Arkansas Plans No. Fy-116 Dated April, 1983 /�J L -V' � The contract/dated June 29, 1983, between the City of Fayetteville, Arkansas, and Braun Excavating Company of Seymour, Missouri, is hereby changed as follows: 1. Line Segments 2-7 and 2-8 shall be sliplined in accordance with the specifications below, instead of being replaced as originally shown on the plans. Payment for sliplining will be made at the unit price set forth under new item No. 29 of this change order. The sewer liner pipe shall be polyethylene and shall be Type III C5P34 in conformance to ASTM D-1248, and shall have recommended designation values of 3-3-5-4-3-3-C as referenced in ASTM D-3350. The liner outside diameter shall be 6.625 inches and shall have a minimum wall thickness of 0.204 inch. The pipe shall be installed in accordance with the National Association of Sewer Service Companies Recommended Specifications for Sewer Collection System Rehabilitation, Section XI - Slip -Lining of Sewers. At the junction of the manhole and liner, the annular space between the polyethylene liner and existing sewer line shall be filled with a quick settling, non -shrink grout mixture. This fill shall extend 12 inches into the annular space. The Contractor shall be responsible for locating and reconnecting all service lines on the segments to be sliplined. During insertion,if the liner is refused and a complete liner from existing manhole to existing manhole cannot be obtained, there will be no payment made under this item. Otherwise, payment will be made per linear foot of liner installed, and shall include all bypass pumping, removal of line obstructions, insertion pit excavation, pipe joining, insertion of the liner and sealing the polyethylene pipe in the manhole. 2. The contract shall be extended sixty (60) calendar days, changing the date of completion of construction to December 31, 1983. 3. Change estimated quantities for Bid Items No. 3, 22 and 29 as follows: Bid Item No. 3. DEDUCT 22. DEDUCT 29. ADD 612 L.F. 8" ABS Composite Pipe Sewer @ $13.81/L.F. $( 8,451.72) 205 S.Y. Topsoiling, Fertilizing, Seeding and Mulching @ $1.80/S.Y. ( 369.00) 612 L.F. 6" Sliplining @ $16.00/L.F. 9,792.00 Net Addition, This Change Order $ 971.28 Total Contract Price, Including Change Orders No. 1, 2, 3 and 4 $204,016.99 All other provisions of the contract remain in force. Approved this day of , 19 ENGINEER: McGoodwin, Williams and Yates, Inc. rc�c� i L./iic aids, Project Manager CONTRACTOR: Braun Excavating Company, Inc. ' 'e Braun, President APPROVED: City of Fayetteville, Arkansas Donald R. Bunn, C ti y ngin • MICROFILMED Change Order No. 5 (Reconciliation Change Order) SANITARY SEWER SYSTEM REHABILITATION AND RECONSTRUCTION Minisystems 2, 4, 7, 8, ll and 16 City of Fayetteville, Arkansas Plans No. Fy-116 Dated April, 1983 This change order reconciles the difference between the quantities set out in the contract and the work done during construction. The following items are hereby changed. Contract Amount as shown on Change Order No. 4 $204,016.99 Deduct $350.00 for error of unit times price extension on Bid Item No. 19 on Change Order No. 3 -350.00 Total Contract Price, Change Orders 1 through 4 $203,666.99 Bid Item Quantity* Description Deduct Add 1. 2,800 DEDUCT 230 L.F. 6" VCP Sewer @ $10.52 $ 2,419.60 $ 2. 237 ADD 411 L.F. 6" DIP Sewer @ $21.58 8,869.38 588 DEDUCT 588 L.F. 8" ABS Truss Pipe Sewer @ $13.81 8,120.28 4. 700 DEDUCT 76 L.F. 8" DIP Sewer @ $22.00 1,672.00 5. 200 DEDUCT 62 L.F. 10" ABS Truss Pipe Sewer @ $16.20 1,004.40 6. 700 ADD 235 L.F. Extra Depth Trench (6-8') @ $0.80 .188.00 7. 200 ADD 25 L.F. Extra Depth Trench (8-10') @ $2.00 50.00 8. 175 DEDUCT 25 L.F. Extra Depth Trench (10-12') @ $6.50 162.50 *Quantities as set out in Proposal and Change Orders No. 1 through 4. r. Bid Item Quantity*' Description Deduct Add 9. 275 DEDUCT 275 L.F. Extra Depth Trench (over 12') @ $10.80 $ 2,970.00 11. 9 DEDUCT 2 Each Main Line Tap Repairs @ $394.00 788.00 12. 22 DEDUCT 3 Each MH Adjustment/Grouting @ $232.00 696.00 13. 46 DEDUCT 2 Each MH Patching/Filling Cracks @ $600.00 1,200.00 14. DEDUCT 1 Each MH/Sewer Line Repair @ $390.00 390.00 15. 55 DEDUCT 1 Each Raising Manholes @ $238.00 238.00 16. 1 DEDUCT 1 Each Raise MH and Plug Lid'@ $280.00 280.00 17. 1 DEDUCT 1 Each Manhole Replacement @ $2,080.00 2,080.00 18. 1,515 DEDUCT 263.07 Tons SB -2 @ $9.00 2,367.63 19. 672 DEDUCT 313.70 S.Y. Hot -Mix Asphalt @ $27.00 8,469.90 20. 75 DEDUCT 13 S.Y. Nonreinforced Concrete Drive @ $15.00 195.00 21. 30 DEDUCT 13.5•C.Y. Concrete Pipe Encasement @ $100.00 1,350.00 22. 1,880 DEDUCT 93.62 S.Y. Topsoiling, Fertili- zing, Seeding @ $1.80 168.52 23. 2 ADD 2 Each Abandonment of Tap ,Repair @ $260.00 520.00 24. 72 DEDUCT 8 Each Sewer Service Connections @ $248.00 1,984.00 25. 2 ADD 1 Each Manhole @ $700.00 700.00 26. 90 DEDUCT 37 S.Y. Native Stone Riprap @ $13.50 499.50 *Quantities as set out in Proposal and Change Orders No. 1 through 4. Bid Item Quantity* Description Deduct Add 27. 500 DEDUCT 83.22 S.Y. Reinforced Concrete Repair @ $21.25 $ 1,768.43 $ 29. .612 ADD 14 L.F. Sliplining @ $16.00 224.00 Total Decrease $38,823.76 Total Increase Contract Price (Change Orders No. 1. through 4) Net Deduction, This Change Order $10,551.38 $203,666.99 28,272.38 Adjusted Total Contract Price, Including Change Orders No. 1, 2, 3, 4 and 5 $175,394.61 *Quantities as set out in Proposal and Change Orders No. 1 through 4. All other provisions of the contract remain in force. Approved this day of , 1984. ENGINEER: McGoodwin, Williams and Yates, Inc. e L %Richards, Proj42 ect Manager CONTRACTOR: Braun Excavating Company, Inc. (kart/ rid Braun, President APPROVED. City of Fayetteville, Arkansas Donald R. Bunn, City Engineer �•t SPECIFICATIONS CONTRACT - FAY ETTEVILLE SANITARY SEWER SYSTEM REHABILITATION 1 �'-_ AND.- RECONSTRUCTION If 1 1 1� MINI -SYSTEMS 2, 4, 7, 8, 11, AND =16 __ •• OR -„THE _ - +- -FAYET TEVI LLE an - R. .ITY5OF. T . s ARKANSAS PLANS NO. FY -116 APRIL, 1983 - 1 1 • - •McGOODWIN,. WILLIAMS, AND YATES, INC. CONSULTING ENGINEERS_ . FAYETTEVILLE;` ARKANSAS - ---s- _ _ .:_ • 1 INSURANCE TYPE EXPIRES RENEWED TO GENERAL LIABILITY 7/1/84 AUTO LIABILITY 7/1/84 EXCESS LIABILITY 7/1/84 WORKERS' COMPENSATION 7/1/84 INSTALLATION FLOATER 7/1/84 OWNERS AND CONTRACTORS 4bO'AD PROTECTIVE CHANGEtORDERS 4... NO; AMOUNT (+ OR -) ADJUSTED CONTRACT AMOUNT 1 1 1 1 1 1 .1� ADJUSTED COMPLETION DATE SPECIFICATIONS SANITARY SEWER SYSTEM REHABILITATION AND RECONSTRUCTION MINI -SYSTEMS 2,4, 7, 8, 11, AND 16 FOR THE CITY OF FAYETTEVILLE ARKANSAS PLANS NO. FY -116 APRIL, 1983 McGOODWIN,WILLIAMS, AND YATES, INC. CONSULTING ENGINEERS FAYETTEVILLE, ARKANSAS 1� 1 1 1. 1 1 1 1 1 1 1 1 1 1 1 1 1. 1 Advertisement for Bids Instructions to Bidders Wage Rates Proposal Contract TABLE OF CONTENTS Performance Bond Payment Bond Section 009 Section 010-A B C D E F G H I J K L M N Section 011. Section 040 Section 050 Section 090 Section 095 Section 099 Section 100 General Conditions Scope of the Work Completion Date and Liquidated Damages Sequence of the Work Special Provisions of the Contract Safety and Health Regulations Quality of the Plans Elevation Data Lands and Rights of Way Protecting and Replacing Utility Services Traffic Control Open Specifications Notice to Proceed Payment for Extra Work Continuing Responsibility of Contractor General Clearing Rights of Way, Cutting and Repairing Fences Storage and Handling of Materials Bypass Pumping Surface Removal Replacement of Line Segments Vitrified Clay Sewer Pipe and Vitrified Clay Sewer Pipe Fittings A General B Materials C Vitrified Clay Pipe Sewer Line Construction Page No. 1-1 2-1 4-1 5-1 6-1 7-1 7-3 009-1 010-1 010-1 010-1 010-2 010-2 010-3 010-4 010-4 010-4 010-4 010-4 010-7 010-7 010-7 011-1 040-1 050-1 090-1 095-1 099-1 100-1 100-1 100-2 1 I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Page No. Section 110 Ductile Iron Sewer Pipe and Ductile Iron Sewer Pipe Fittings A General 110-1 B Materials 110-1 C Ductile Iron Pipe Sewer Line Construction 110-2 Section 140 Acrylonitrile -Butadiene -Styrene (ABS) Section 145 Composite Sewer Pipe A General 140-1 B Materials 140-1 C ABS Composite Pipe Sewer Line Construction 140-2 Manhole Rehabilitation A General 145-1 B Classification of Manhole Rehabilitation 145-1 C Materials 145-1 D Construction 145-3 Section 146 Placing Pipe Protection Cover and Backfill A General 146-1 B Materials 146-1 C Construction 146-1 Section 150 Cast -In -Place Manholes A General 150-1 B Materials 150-1 C Manhole Construction 150-1 Section 160 Classification of Excavated Materials 160-1 Section 180 Mandrel Test 180-1 Section 190 Low Pressure Air Testing for Sewer Lines 190-1 Section 300 Street Overlay, Driving Surface, Sidewalk, and Curb and Gutter A General 300-1 B Materials 300-1 C Materials and Construction 300-1 D Construction 300-2 Section 500 Point Repairs A General 500-1 B Classification of Point Repairs 500-1 ii 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Page No. C Materials 500-1 D Construction 500-1 Section 800 Concrete 800-1 Section 810 Reinforcing Steel 810-1 Section 900 Pipeline Cleanup 900-1 Section 995 Final Inspection 995-1 Section 1000 Methods of Measurement and Payment 1000-1 iii 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ADVERTISEMENT FOR BIDS Notice is hereby given that, pursuant to an order of the City Board of Directors of the City of Fayetteville, Arkansas, sealed bids will be received at the office of McGoodwin, Williams and Yates, Consulting Engineers, until 10:00 a.m. on the 26th day of May, 1983, for the furnishing of all tools, materials and labor, and performing the necessary work in performing Sanitary Sewer System Rehabilitation and Reconstruction,. consisting of: The plugging of sewer overflow lines, the construction of approximately 8 main line .tap repairs, rehabilitation of approximately 215 manholes, and the construction and/or repair of asphaltic pavement, concrete curb and gutter, and concrete sidewalk. Also included is the replacement of approximately 5,125 linear feet of 6 inch, 8 inch and 10 inch sewer lines. All necessary work, materials and every item of construction shall be in accordance with the plans and specifications as approved by the City Board. Said plans and specifications are on file in the office of the consulting engineer, McGoodwin, Williams and Yates, Inc., Consulting Engineers, 909 Rolling Hills Drive, Fayetteville, Arkansas 72701. Copies of these documents may be obtained from the office of said engineers upon the payment of $50.00. Payments for plans and specifications are not refundable. Contractors shall make such inspection and studies of the site of the work as to familiarize themselveswith all conditions to be encountered. Each bid must be accompanied by a certified or cashier's check-, or surety bond, in the amount equal to five percent of the whole bid, said bond to be issued by a surety company licensed to do business in the state of Arkansas. In the event successful .bidder fails, neglects or refuses to enter into contract for the construction of said work, and furnish the necessary bonds within ten days from and after the date the award is made, said bid bond or check shall be retained as liquidated damages. Bids must be made upon the official proposal sheets contained in the specifications, and such proposal sheets shall not be removed from the remainder of the contract documents. All bids shall be sealed and the envelopes addressed to McGoodwin, Williams and Yates, Inc., 909 Rolling Hills Drive, Fayetteville, Arkansas 72701. All bids shall be plainly marked on the outside of the envelope specifying that it is a proposal or bid for Sanitary Sewer System Rehabilitation and Reconstruction, and the time for opening of bids. Bids will be opened and read aloud at the office of McGoodwin, Williams and Yates, Inc., and considered at a scheduled meeting of the City Board. All bidders must be licensed under the terms of Act 150 of the 1965 Acts of the Arkansas Legislature. 1-1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 The City Board reserves the right to reject all bids and informalities in the proposal. .The Board further reserves award the contract to the lowest responsive, responsible Board further reserves the right to withhold the awarding of for a period not to exceed sixty days after receipt of bids. Dated this 6th day of May, 1983. to waive any the right to bidder. The the contract /s/ Sturman Mackey Sturman Mackey, Purchasing Agent 1-2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ,INSTRUCTIONS TO BIDDERS 1. EXAMINATION OF SITE AND DOCUMENTS. Bidders are advised that the plans, profiles, specifications and estimates of the Engineer on file in the office of the official as set out 'in the Notice to Contractors shall constitute all of the information which the Owner shall furnish. No other information given, or soundings made by the Owner or any official thereof, prior to the execution of said contract, shall ever become a part of, or change the contract, plans, profiles,specifications and estimates, or be binding on the Owner. Prior to submitting any bid, bidders are required to read carefully the specifications, contract and bonds, to examine carefully all plans, profiles, and estimates, to visit the site of the work to examine carefully local conditions, to inform themselves by their independent research and sounding of the difficulties to be encountered, and to judge for themselves of the accessibility of the work and the quantities and character of the materials to be encountered, and all attending circumstances affecting the cost of doing the work and the time specified for its completion; and to obtain all information required to make an intelligent bid. Bidders shall rely exclusively upon their surveys, estimates, investigations, soundings and other things which are necessary for full and complete information upon which the bid may be made and for which a contract is to be awarded. The Proposal, providing for unit and lump sum prices bid by the Contractor, contains a statement that all bids are made with the full knowledge of the difficulties and conditions that may be encountered, the kinds, quality and quantity of the plans, work to be done, excavation, and materials required and withfull knowledge of the plans, profiles, specifications and estimates and all provisions of the contract and bonds. The submission of a bid shall constitute the acceptance of these provisions. 2. APPROXIMATE ESTIMATE OF QUANTITIES. The Engineer's estimate of quantities, approved by the Owner and on file in the office of the official as set out in the Notice to Contractors, is approximate only, and shall be the basis for receiving unit price bids for each item, but shall not be considered by the bidders as the actual quantities that may be required for the completion of the proposed work. Such quantities, however, at the unit and lump sum .prices bid for each item, shall determine the amount of each bid for comparison of bids and aid in determining the lowest and best bidder for the purpose of awarding the contract, and will be used as a basis for fixing the amount of the required bonds. 3. BIDS AND BIDDING FORMS. A copy of the plans, profiles, specifications, Engineer's estimate and bidding forms may be obtained as provided in the Advertisement for Bids. All papers bound with or attached to the Proposal forms are necessary parts thereof and must not be detached. Bids must be made out in ink on bidding specifications. Bids shall be sealed and in the advertisement, and the title of • forms included as part of these addressed to the Owner, as given the project, the name of the Instructions to Bidders 2-1 • contractor submitting the bid and the time and date for receipt of bids written on the envelope. No bidder shall divulge the information in the sealed bid to any person whomsoever, except those having a partnership or other financial interest with him in the bid, until after the sealed bids have been opened. Bids which are incomplete, unbalanced, conditional, or obscure, or which contain additions not called for, erasures, alterations or irregularities of any kind, or which do not comply with the Instructions to Bidders may be rejected as informal at the option of the Owner. However, the Owner reserves the right to waive technicalities as to changes, alterations or revisions and to make the award in the best interest of the Owner. 4. UNIT PRICES AND FILLING IN BIDDING FORMS. Bidders must state a unit price for each item or work named in the Engineer's estimate of quantities or work to be done. Unit prices shall include amounts sufficient for the furnishing of all labor, materials, tools, equipment and apparatus of every description, to construct, erect, and finish completely all of the work as called for in the specifications or shown in the plans. Unit prices bid and totals shown in the proposal shall not include any of the costs of engineering, advertising, appraising, or printing. The price bid for each item must be stated in figures and in words in the appropriate blank spaces provided on the bidding forms. The figures must be clear and distinctly legible so that no question can arise as to their intent and meaning. In case of a difference in the written words and figures in a Proposal, the amount stated in the written words shall govern. 5. PRICES BID TO BEAR RELATIONSHIP TO COST OF WORK. Prices bid on the various items in the Proposal shall bear a fair relationship to the cost of the work to be done. Bids which appear unbalanced and deemed not to be in the best interest of the Owner may be rejected at the discretion of the Owner 6. SIGNATURE ON BIDS. If the bid is made by an individual, his firm name must be given, and the Proposal signed by him or his duly authorized agent. If the bid is made by a partnership, the firm name and the names of each member must be given, and the bid signed by a member of the partnership, or a person duly authorized. If the bid is made by a company or corporation, the company or corporate name must be given, and the bid signed by an officer or agent duly authorized. Powers of attorney, properly certified, for agents and others to sign bids must be in writing and filed with the Owner. 7. BIDS OF SUBCONTRACTORS. The general contractor will be required to furnish the names of subcontractors and the amounts of their subcontracts as required by Act 183, Arkansas Acts of 1957. The subcontracts may be for mechanical, electrical, roofing, and sheet metal work. Subcontract amounts must be submitted on a separate list in a sealed envelope and must accompany the bid Proposal. The subcontractor's name and license number shall appear Instructions to Bidders 2-2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 on the outside of .the sealed envelope._x:‘Subcontractors must be licensed according to the laws of the -State of. Arkansas. -t. 8. WITHDRAWAL OF BIDS.- Permission will not be granted to withdraw or modify any bid after it has been filed. Requests for non -consideration of bids must be made in writing, addressed to the governing body of the Owner; and filed with the representative of the Owner designated to receive bids before .the expiration of the time limit for opening of bids. After other bids are opened and read, the bid for which withdrawal is requested will be returned unopened. 9. COMPLIANCE WITH STATE LICENSING LAW. Contractors must be licensed in accordance- with the requirements of Act 150, Arkansas Acts of 1965, the "Arkansas State Licensing Law for Contractors." Bidders who submit proposals in excess of $20,000 must submit evidence of their having a contractor's licence before their bids will be considered, andshall note their license number on the outside of their Proposal. 10. QUALIFICATIONS AND RESPONSIBILITY . OF BIDDERS. Each bidder, if requested to do so by either .the Owner or the Engineer, shall furnish satisfactory evidence of his competency to perform the work contemplated. The Owner reserves the right to reject a bid if the bidder has not submitted, upon request, a statement of his qualifications prior to the date of the opening of bids. • 11. DISQUALIFICATION OF BIDDERS. Any one or more of the following causes may be considered as sufficient for the disqualification of bidders and the rejection of bids: - More than one Proposal for the same work from an individual, firm, partnership, or corporation under the same or different names. Evidence of collusion among bidders. Participants in such collusion may receive no recognition as bidders for any future work. 1 Unbalanced proposals in which the prices for some items are out of proportion to the prices for other items, or changes written in, or amendments by letter. Failure to submit a unit price for each item of work for which a bid price is required by the Proposal, or failure to include all required contract documents. Lack of competency as revealed by the financial statement, experience, plant and equipment statements submitted Lack of responsibility as shown by past work judged from the standpoint of workmanship and progress. A bid by an unlicensed contractor bidding under a licensed contractor's name. Uncomplete work which, in the judgment of the Owner, might hinder or prevent the prompt completion of additional work if awarded. Instructions to Bidders 2-3 Being in arrears on existing contracts, in litigation with the Owner, or having defaulted on a previous contract. 12. CONSIDERATION OF PROPOSALS. After the Proposals are opened and read, the quantities will be extended and totaled in accordance with the bid prices of the accepted Proposals, and the results of the prices will be made public. Until the final award of the contract, the Owner reserves the right to reject any or all Proposals, to waive technicalities, and to advertise for new Proposals, or proceed to do the work otherwise when the best interests of the Owner will be promoted thereby. 13. RIGHT TO REJECT BIDS. The owner reserves the right to reject any and all bids. All bids are subject to this reservation, and the Owner reserves to itself the right to decide which shall be deemed the lowest responsive and responsible bid. Due consideration will be given to the reputation, financial ability, experience and equipment of the bidder. 14. AWARDING OF CONTRACT. The Owner reserves the right to withhold the awarding of a contract a reasonable period of time from the date of opening of bids, said length of time not to exceed sixty (60) days except with the consent of the bidder. The awarding of a contract upon a successful bid shall give the bidder no right to action or claim against the Owner upon the contract until the contract is reduced to writing and signed by the contracting parties. The letting of a contract shall not be complete until the contract is executed and the necessary bonds approved. 15. BIDDING CHECKS OR BONDS. Each bid must be accompanied by a certified check, or a surety bond issued by a company licensed to do business in the state of the Owner, in the sum of five percent (5%) of the amount of the bid, made payable to the Owner as a guarantee that a contract will be entered into and the required bonds furnished within the required time, in the event a contract is awarded. 16. SEPARATE ENVELOPE FOR BID BOND OR CERTIFIED CHECK. If provided for in the Advertisement for Bids, the bidder shall submit a bid bond or certified check enclosed in a separate sealed envelope firmly attached to the outside of the sealed bid envelope. At official bid opening, the envelope containing the bid bond or certified check shall be opened first, and if the documents are not found in order, the bid shall be returned unopened. 17. FORFEITURE OF BIDDING BOND. The person or persons, partnership, company, firm or corporation to which the contract is awarded shall within ten (10) days after such contract is awarded, execute and deliver the contract and bonds as required; such bonds to be executed and approved (but not dated) prior to the execution of the contract by the Owner. Any applications for extension of time shall be made by the Contractor in writing and signed by proper officials. The inclusion of this provision, whereby extension of time in signing the contract and submission of bonds may be granted, in no way obligates the Owner to act upon any application unless it sees fit to do so. Upon failure of the bidder to execute the contract and bonds within the specified time after the award of the contract, he will be considered to Instructions to Bidders 2-4 ■ 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1. 1 1 1 1 1 1 1 1 1 1 1 1 1 • have abandoned said bid, and the Owner may_ relet same. By reason of the uncertainty of the marketprices of materials#and of damages and expenses which the Owner might sustain by reason of said bidder's failure to execute said bond and contract within the specified time, the bid bond or certified check accompanying the bid shall be the agreed amount of damages which the Owner will suffer by reason of such failure upon the part of the bidder, and shall thereupon immediately be forfeited to the Owner. The filing of a bid under these instructions shall be considered as acceptance of this provision. 18. RETURN OF BIDDER'S CHECK OR BOND. Checks and bonds deposited with bids will be returned to the bidders as soon as the contract is awarded, except the bond or check of the successful bidder, which will be returned after the contract is executed and the bonds approved. Unless the Owner has a good reason to hold bidding bonds or checks, the bonds or checks of all except the three low bidders will be returned as soon as the bids have been considered. 19. SUBCONTRACTOR. The Contractor shall not assign or sublet all or any part of this contract without the prior written approval of the Owner nor shall the Contractor allow such subcontractor to commence work until he has provided .and obtained approval of such compensation and public liability insurance as may be required. The approval of each subcontract by the Owner will in no manner release the Contractor from any of his obligations as set out in the plans, specifications, contract and bonds. 20. MATERIAL GUARANTY. Before any contract is awarded the bidder may be required to furnish a complete statementof the origin, composition, or manufacture of ..any or all materials proposed to be used in the construction of the work, together with samples, which may be subjected to the tests provided for in these specifications to determine their quality and fitness for the work. 21. FAMILIARITY WITH LAWS. The bidder is presumed to be familiar with all federal, state and city laws, ordinances and regulations which in any manner affect those engaged or employed in the work, or the materials or equipment used, or in any way affecting the work, and shall in all respects comply with said laws, ordinances and regulations. No claim of misunderstanding or ignorance on the part of the Contractor will in any way serve to modify the provisions of the contract. No representations shall be binding unless embodied in the contract. 22. LABOR LAWS. The Contractor shall abide by all federal, state, and local laws governing labor. The Contractor further agrees to save the Owner harmless from the payment of any contribution under the State Unemployment Compensation Act, and the Contractor agrees that if he is subject to the Arkansas State Unemployment Act, he will make whatever contributions are required under and by virtue of the provisions of said Act. 23. WAGES AND LABOR. Minimum wage rates shall be equal to basic rates as established by common usage in the city and adjacent community for the various types of labor and skills performed. In case wage rates are specified in the contract documents, the rates as specified shall be the Instructions to Bidders 2-5 minimum rates which apply to the project. Whenever available, local common labor shall be used and whenever practical, skilled and semi -skilled labor, if available, shall be used. The Contractor and each subcontractor, where the contract amount exceeds $75,000.00, shall comply with the provision of Act 74, as amended by Act 275 of 1969 (Ark. Stat. 14-630). The provisions are summarized below. The Contractor and subcontractor shall: (1) pay the minimum prevailing wage rates for each craft or type of workman and the prevailing wage rate for holiday and overtime work, as determined by the Arkansas Department of Labor. (2) post the scale of wages in a prominent and easily accessible place at the site of the work. (3) keep an accurate record showing the names and occupation and hours worked of all workmen employed by them, and the actual wages paid to each of the workmen, which record shall be open at all reasonable hours to the inspection of the Department of Labor or the Owner, its officers and agents. The Owner shall have the right to withhold from amounts due the Contractor so much of accrued payments as may be considered necessary to pay the workmen employed by the Contractor or any subcontractor, the difference between the rates of wages required by this contract and the rates of wages received by such workmen. If it is found that any workman employed by the Contractor or a subcontractor has been or is being paid a rate of wages less than the rate of wages required by this contract, the Owner may by written notice to the Contractor, terminate his right to proceed with the work or such party of the work as to which there has been a failure to pay the required wages and to prosecute the work to completion by contract or otherwise, and the Contractor and his sureties shall be liable for any excess costs occasioned thereby. 24. WITHHOLDING STATE INCOME TAXES. The Contractor shall deduct and withhold Arkansas income taxes, as required by Arkansas law, from wages paid to employees, whether such employees are residents or nonresidents of Arkansas. 25. ANTI -KICKBACK PROVISIONS (WHERE APPLICABLE). When provided for in the specifications, the Contractor shall comply with the regulations of the Secretary of Labor made pursuant to the Anti -Kickback Act of June 13, 1934, 40 U.S.C. 276(c), and any amendments or modifications made thereto and shall see that such provisions are included in all subcontracts. A copy of such provisions is included hereinafter in these specifications. Instructions to Bidders 2-6 26. COMPLIANCE WITH EQUAL ;OPPORTUNITY PROVISIONS, NONSEGREGATED FACILITIES REQUIREMENTS, AND MINORITY BUSINESS ENTERPRISE PARTICIPATION (WHERE APPLICABLE). Where Federal funds are used to pay a portion of the cost of a project, the prospective bidder will be required to comply with the provisions of Title VI of the Civil Rights Act of 1964 and Executive Orders 11246 and 11375, and, where applicable, shall include such provisions in subcontracts or purchase orders. Further, certain construction contracts are subject to compliance with Minority Business Enterprise requirements. Where provided for in the specifications the Contractor, as a part of his bid, shall complete forms relative to compliance, or participation, with the above. 27. COMPLIANCE WITH ACT 125, ARKANSAS ACTS OF 1965. The attention of all bidders is ailed to the provisions of Act 125, Arkansas Acts of 1965. This act provides for payment for certain taxes on materials and equipment brought into the state. It. further provides for methods of collecting said taxes. All provisions of this act will be complied with under this contract. 28. INSURANCE. During the life of this contract, the successful bidder shall carry insurance as hereinafter set out. Also, he shall require all of his subcontractors to carry insurance as outlined below, in case they are not protected by the policies carried by the prime Contractor. Insurance companies underwriting the required insurance shall be licensed in Arkansas. Licensed companies are listed in the State Insurance "Department's Annual Report of the Insurance Commissioner. ' In Arkansas the prevailing law requires that insurance on public works contracts be issued by and through a duly licensed agent resident in the State of Arkansas. The mere countersigning by a resident agent is not acceptable. IInsurance is to be approved by the Owner. If any insurance contracted for becomes unsatisfactory or unacceptable to the Owner after the acceptance and ' approval thereof, the Contractor shall promptly, upon being notified to that effect, execute and furnish acceptable insurance in the amounts herein specified. Upon presentation of acceptable insurance, the unsatisfactory insurance may be canceled at the discretion of the Contractor. The Contractor shall have his resident insurance agent submit to the Owner, through the Engineer, a schedule of insurance policies proposed to be ' furnished, which shall be approved before certificates of insurance and/or policies are issued. Once the Owner has concurred in the proposal of insurance coverages, the Contractor shall then furnish to the Engineer, in ' the name of the Owner, certificates of insurance for the following. 1. Workmen's Compensation. Workmen's compensation, as required by the laws of the state in which the work is to be done, shall be furnished. I. In case any hazardous occupations are required for the execution of the work which are not covered by the above insurance, special employer's ' Instructions to Bidders 2-7 liability policies shall be obtained to cover workmen engaged in such hazardous occupations. 2. Contractors' Public Liability Insurance and This insurance shall provide bodily injur person and $3,000,000 for each accident; $600,000 for each accident. This insurance explosion, collapse and underground hazards, Property Damage Insurance. y of $1,500,000 for each and property damage of shall be endorsed to cover and blasting. 3. Motor Vehicle Public Liability and Property Damage Insurance. This policy shall provide bodily injury of $1,500,000 for each person and $3,000,000 for each accident; and property damage of $600,000 for each accident. 4. Owner's and Engineer's Contingent Protective Liability Insurance. The Contractor shall indemnify and same harmless the Owner and Engineer from and against all losses and claims, demands, payments, suits, actions, recoveries and judgments of every nature and description brought or recovered against them by reason of any omission or act of the Contractor, his agent or employees in the execution of the work or in the guarding of it. The Contractor shall obtain in the name of the Owner and Engineer (either as co-insured or by endorsement), and shall maintain and pay the premiums for such insurance in an amount not less than $600,000 property damage and $1,500,000 bodily injury limits, and with such provisions as will protect the Owner and Engineer from contingent liability under this contract. 5. Builder's Risk Insurance. The Contractor shall procure and maintain during the life of the contract builder's risk insurance (fire, lightning, extended coverage, vandalism and malicious mischief) on the insurable portion of the project on a 100 percent completed value basis, against damage to the equipment, structure or material. The Contractor, his subcontractors, and the Owner (as their interest may appear) shall be named as the insured. 6. All -Risk Floater Insurance. Until the project is completed and is accepted by the Owner, the Contractor is required to maintain an all-risk installation floater policy. The Contractor shall submit to the Owner written evidence of insurance upon the entire work at the site to the full insurable value thereof including the interests of the Owner, the Contractor, the subcontractors, and any others with an insurable interest. The policy shall insure against all risk of physical damage except as modified by the contract documents and subject to the normal all-risk exclusions. The policy by its own terms or by endorsement shall specifically permit partial or beneficial occupancy prior to completion or acceptance of the entire work. 7. Other Insurance. The Contractor is to protect the Owner against all loss during the course of the contract. If, due to the nature of the project, insurance coverage other than that specified above is needed by the Contractor to protect the Owner against all losses, the Instructions to Bidders 2-8 Y Contractor is responsible for determining the type of insurance needed and purchasing same.; Each insurance certificate and/or policy shall contain a clause providing that it shall not be canceled by the insurance company without fifteen (15) days written notice to the Owner of intention to cancel. It shall be the responsibility of the Contractor to maintain insurance as set out above, and to furnish current certificates and/or policies. 29. PERFORMANCE BOND AND PAYMENT BOND. The Contractor shall furnish both a surety performance bond and a payment bond, each equal to one hundred percent (100%) of the contract price. The performance bond and the payment bond shall be two totally separate bonds and shall bear two different bond numbers. The Contractor is to pay all expenses in connection with the obtaining of said bonds. The bonds shall be conditioned that the Contractor shall faithfully perform the contract, and shall pay all indebtedness for labor and materials furnished or performed in the construction and installation of such alterations and additions asprescribed in this contract. The surety company issuing the bonds must be a solvent company on the "Surety Companies Annual. List" issued by the U,. S. Department of the Treasury, and the bonds are not to be issued in an amount greater than the underwriting limitations for the surety company as set out therein. I. Resident Agent Required. In Arkansas, prevailing law requires that performance and payment bonds on public works contracts shall be executed by a resident local agent who is licensed by the Insurance Commissioner to I. represent the surety company executing said bonds, and filing with such bonds his Power of Attorney as his authority. The mere countersigning of the bonds will not be sufficient. ' The date of the bonds, and of the Power of Attorney, must not be prior to the date of the contract. At least six copies of the bonds shall be furnished, each with Power of Attorney attached. ' Bonds are to be approved by the Owner. If any bonds contracted for become unsatisfactory or unacceptable to the Owner after the acceptance and approval thereof, the Contractor, upon being notified to that effect, shall ' promptly execute and furnish acceptable bonds in the amounts herein specified. Upon presentation of acceptable bonds, the unsatisfactory bonds may be canceled at the discretion of the Contractor. ' Instructions to Bidders 2-9 • • w ARKANSAS DEPARTMENT OF LABOR . 1022 HIGH STREET LITTLE ROCK 72202 (501) "' ' J1i 375-8442 May 10, 1983 Mr. Jeff Richards McGoodwin, Williams & Yates Engineers 909 Rolling Hills Drive Fayetteville, Arkansas 72701 Re: Fayetteville Sanitary Sewer System Rehabilitation & Reconstruction Washington County Dear Mr. Richards: Enclosed is Arkansas Prevailing Wage Determination 82-82 estab- lishing the wages to be paid on the referenced project. • These rates are adopted pursuant to Section 9(1) of Act 74 of 1969 as amended by Act 275 of 1969, and to Section 5(d) of the Rules Pertaining to the Administration of the Arkansas Prevailing Wage Taw. In compliance with Section 5 of the law, this scale of wages must be posted in a "prcaninent and easily accessible place at the site of the Dark." If you have any questions or we can be of further assistance, please contact Becky Bryant at 375-8442, Extension 403. BE:kj Enclosures Sincerely, %�Jn.CC 7 GGtt i Bill Everett 64 Director 4-1 IL Page 1 of 3 ARKANSAS DEPARTMENT OF LABOR PREVAILING WAGE DETERMINATION -HEAVY CONSTRUCTION DATE: May 10, 1983 DETERMINATION ti 82-82 PROJECT: Fayetteville Sanitary COUNTY STATEdIDE Sewer System EXPIRATION DATE: 9-10-83 Rehabilitation & Reconstruction BASIC HOURLY RATE Bricklayers $6.40 Carpenters 6.40 Concrete finishers 6.40 El :ccricians 7.75 IRONWORKERS: Structural 5.50 Reinforcing 4.30 LABORERS: Air cool operator 4.55 Asphalt heater operator 4.55 Asphalt raker 5.20 Carpenter helper 4.65 Chain saw operator 4.65 Checker grade 4.80 Concrete finisher helper 4.55 Concrete joint sealer 4.55 Concrete saw operator 4.65 Form setter 4.80 Laborer 3.60 Pipelayer 4.80 Powderman 5.60 Vibratorman 4.55 Painter 5.60 Pile driver leadman 5.60 PO,dER EQUIPMENT OPERATORS: Aggregate spreader op. 5.10 Asphalt plant fireman 4.30 Asphalt drier operator 4.30 Batch plant operator 5.10 BULLDOZER OPERATORS: .Finish - 6.15 Rough 5.35 Bull float operator 4.95 Concrete curing machine op.5.20 CONCRETE MIXER OPERATOR: !.ess than 5 sacks 4.65 5 sacks or over 5.60 Backhoe op.-rubbertired (1 yard or less) 5.35 Cherry picker operator 5.35 Concrete paver operator 5.90 H Education & and/or W Pensions Vacdcion Appr. Tr. 4-2 Page 2 of 3 ARKANSAS DEPARTMENT OF LABOR PREVAILING WAGE DETERMINATION -HEAVY CONSTRUCTION DATE: May 10, 1983 DETERMINATION 0 82-82 PROJECT: Fayetteville Sanitary COUNTY. STATEWIDE Sewer System EXPIRATION DATE:. 9-10-83 Rehabilitation & Reconstruction BASIC H HOURLY & RATE W Pensions Vacation Concrete spreader op. 5.'30 CRANES, DERRICK, DRAGLINE, SHOVEL, BACKHOE OPERATORS: 1-1/2 yard or less 6.15 Over 1 1/2 yard 6.40 Crusher operator 4.95 Distributor operator 4.95 Drill operator (wagon or truck) 5.35 ' Elevating grader operstor5.90 Euclid or like equipment op. (bottom or end dump)4.80 ' Finishing machine operator 5.35 Forklift operator 4.45 Form grader operator 4.45 FRONT END LOADER OPERATOR: ' Finish . 5.90 Rough 5.35 Hydro seeder operator 4.30 • Mechanic 6.15 • Mechanic helper 4.80 MOTOR PATROL OPERATOR: ' Finish 6.15 Rough 5.35 Mulching machine operator 4.80 Oiler and greaser 4.80 ' Pile Driver Operator .5.60 Pug Mill operator 4.55 Roller op. (self-propelled)4.30 ' SCRAPER OPERATORS: Finish 6.15 Rough 5.35 Sod slicing machine op. 4.40 ' Stabilizer mixing machine 4.95 TRACTOR OPERATORS: Crawler type 4.30 ' Farm and wheel 4.55 dneel type (with attach- ments 1 yard or under) 4.95 Drenching machine operator4..95 Education and/or Appr. Tr. Page 3 of 3 ARKANSAS DEPARTMENT OF LABOR PREVAILING' WAGE DETERMINATION -HEAVY CONSTRUCTION DATE: May 10, 1983 DETERMINATION II 82-82 PROJECT: Fayetteville Sanitary COUNTY STATEWIDE Sewer System EXPIRATION DATE: 9-10-83 Rehabilitation & Reconstruction BASIC HOURLY RATE STONEMASONS 6.40 TRUCK DRIVERS; Distribu;.or truck drvr.4.3O Semi -trailer 4.80 Lowboy driver 5.35 Transit mix truck driver 4.30 Truck driver (heavy -max- imum pay load in excess of 3000 lbs.) 4.55 Truck driver (light -max- imum pay load 3000 ios.)4.30 WELL DRILLERS 6.15 WELDERS - receive rate prescribed for craft performing operation to which welding is incidental. H Education & and/or d Pensions Vacation Appr. Tr. 4-4 P R O P O S A L SANITARY SEWER SYSTEM REHABILITATION AND RECONSTRUCTION FAYETTEVILLE, ARKANSAS Plans No. Fy-116 Dated April 1983 To the Board of Directors City of Fayetteville Fayetteville, Arkansas The undersigned, of the firm of Braun Excavating Company C states that he has carefully examined the Plans, profiles, Specifications, maps and drawings on file in the office of the City Clerk of the City of Fayetteville, Arkansas, relative to the proposed construction of this contract, Sanitary Sewer System Rehabilitation and Reconstruction; that he is familiar, with the same and understands each and all; has examined the location and site; that all bids are made with the full knowledge of the difficulties and conditions that may be encountered, the kind, quality and quantity of the Plans, work to be done, excavation, and materials required; and with full knowledge of the Plans, profiles, Specifications and estimates and all provisions of the contract and bonds; and that this Proposal is made without collusion on the part of any person,.firm or corporation. He further states that he wi11 enter into contract to construct said Sanitary Sewer System Rehabilitation and related work as designated in the title of this Proposal, in accordance with the Plans and Specifications, and have said work completed within ninety (90) consecutive calendar days from the date of the Notice to Proceed, for the following prices. ' Bidder agrees to perform all the construction work described in the Specifications and shown on the Plans, for the following unit prices. I I I Item Estimated Item and Unit Price Bid No. Quantity 1. 2,800 Linear Feet, 6" Vitrified Clay Pipe Sewer Line, 0-6' in depth, complete in place Ten and 52/100------- -- - - ---dollars( 10.52)L.F. (Dollar amount written in words.) (In figures.) 2. 225 Linear Feet, 6" Ductile Iron Pipe Sewer Line, 0-6' in depth, complete in place Twenty -One and 58/100 -----------------------dollars( 21.58)L.F. Total Amount $ 29,456.00 (In figures.) $ 4,855.50 5-1 ■ • Item Estimated Item and Unit Price Bid No. Quantity 3. 1,200 Linear Feet, 8" Vitrified Clay or ABS Composite Pipe Sewer Line, 0-6' in depth, complete in place I Thirteen and 81/100----------------- -- dollars(, 13.81 )L.F. 4. 700 Linear Feet, 8" Ductile Iron Pipe Sewer ' Line, 0-6' in depth., complete in place • Twenty -Two and no/100-----------------------_dollars( 22.00 )L.F. 5.• 200 Linear Feet, 10" Vitrified Clay or ABS Composite Pipe Sewer Line, 0-6' in depth, complete in place Sixteen and 20/100---------------------- --- dollars( 16.20)L.F. 6. 700 Linear Feet, Extra Depth Trench, 6-8' Only 80/100 ---------------------------------dollars( ' 7. 200 Linear Feet, Extra Depth Trench, 8-10' Two and no/100------------------------------ dollars( 2.00)L.F. ' 8. 175 Linear Feet, Extra Depth Trench, 10-12' Six and 50/100 ------------------------------dollars( 9. 275 Linear Feet, Extra Depth Trench, over 12' ' Ten and 80/100--------------------- - - dollars( 10.80)L.F. • 10. 2 Each, Plug Sewer Overflow or Bypass Lines Fifty -Three and 30/100 ----------------------dollars( 53.30)Each 11. 9 Each, Main Line Tap Repair Three Hundred Ninety -Four and no/100--------dollars( 394.00)Each '12. 22 Each, Adjustment and/or Grouting Casting . to Cone Two Hundred Thirty -Two and no/100-----------dollars( 232.00)Each 13. 46 Each, Cleaning, Patching and Filling Cracks, and Waterproofing Manholes Six Hundred and no/100----------------------dollars( 600.00)Each Total Amount $ 16,572.00 $ 15,400.00 $ 3,240-:00 $ 560.00 $ 400.00 $ 1,137.50 $ 2,970.00 $ 106.60 $ 3,546.00 $ 5,104.00 $ 27,600.00 5-2 Item Estimated Item and Unit Price Bid No. Quantity 14. 7 Each, Repair Manhole/Sewer Line Connections Three Hundred Ninety and no/100------------- dollars( 390.00 )Each S Total Amount 2,730.00 • 15. 55 Each, Raising Manholes 1 Two Hundred Thirty -Eight and no/100--------- dollars( 238.00 )Each $ 13,090.00 16. 1 Each., Raise Manhole and Plug Vent Holes in Lid Two Hundred Eighty and no/100--------------- dollars( 280.00 )Each $ 280.00 1 Each, Manhole Replacement • 2,080.00 • Two Thousand Eighty and no/100-------------- dollars( / )Each $ 2,080.00 18. 1,.500 Tons, SB-2 Crushed Stone Backfill, complete in place Nine and no/100----------• ------------------- dollars( 9.00 )Ton $ 13,500.00 19. 1,100 Square Yards, Hot -Mixed, Hot -Laid Asphalt Concrete Pavement Repair (3" Thickness) Twenty -Seven and no/100--------------------- dollars( 27.00)S.Y. 20. 75 Square Yards, Nonreinforced Concrete Drive and Sidewalk Repair $ 29,700.00 Fifteen and no/100-------------------------- dollars( 15.00)g.y, $ 21, 30 Cubic Yards, Concrete for Pipe Encasement and Cover One Hundred and no/100----------------------dollars( 100.00)C.Y. $ 22. 2,000 Square Yards, Topsoiling, Fertilizing, Seeding and Mulching One and 80/100 ------------------------------dollars( 1.80)s.Y. 23. 2 Each, Abandonment of Main Line Tap or Manhole/Sewer Line Connection. Repair Two Hundred Sixty and no/100----------------dollars( 260.00)Each 24. 72 Each, Sewer Service Line Reconnections Two Hundred Forty -Eight and no/100----------dollars( 248,00)Each 1,125.00 3,000.00 $ 3,600.00 $ 520.00 $ 17,856.00 Total Bid, Items I through 24 ----------------------------- $ 198,428.60 5-3 The foregoing prices shall include all labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc., to cover the finished work of the several kinds called for. Bidder understands that the Owner reserves the right to reject any or all bids and ,_ - - -to_waive_i any _informalities in the bidding. The bidder agrees that this bid shall bf good and may not be withdrawn'for a. period of 60 calendar days after the scheduled closing time for receiving bids. Upon receipt of written notice of the acceptance of this bid, bidder will execute the formal contract and bond attached as called for in the specifications within 10 days. ' The bid security attached in the sum of. 5% of contract amount dollars ($ ) is to become the t property of the Owner in the event the contract and bond are not executed within the time above set forth, as liquidated damages for the delay and additional expense to the Owner caused thereby. ' t Receipt of the following addenda to the plans and specifications is hereby acknowledged AND SUCH ADDENDA ARE ATTACHED TO THE SPECIFICATIONS. Respectfully submitted, Braun Excavating. Company Firm Name 14 -� By /s/ Jerid Braun Title President Route 3, Box 157 C Seymour, Missouri 65746 (Business Address & Zip Code) Arkansas License No. 82-2624 (Seal - if bid is by corporation.) II C 5-4 MICROFILMED CONTRACT State of Arkansas ) County of Washington THIS AGREEMENT, made 1983, by and betwe Washington, State of the Owner, and ) and entered into this day of , !en the City of Fayetteville, Arkansas, County of Arkansas, Party of the First Part, hereinafter called Braun Excavating Company of the City of Seymour, Missouri , Party of the Second Part, hereinafter called the Contractor. WITNESSETH THAT: ' WHEREAS, the Owner has called for bids for Sanitary Sewer System Rehabilitation and Reconstruction, as set out in the plans and specifications and approved by the Board of Directors of the City of • Fayetteville, Arkansas, and WHEREAS, pursuant to the published calls for bids under said plans and specifications, the Contractor is the low, responsive, responsible bidder ' for the construction of said Sanitary Sewer System Rehabilitation and Reconstruction, NOW THEREFORE: The Contractor agrees with the Owner to commence and complete the construction of: Sanitary Sewer Line Rehabilitation and Reconstruction, which consists of all items as set out in the Proposal, these Specifications and Plans No. Fy-116, including all items of work for a complete installation, for the unit prices bid in the Proposal, all of which become t and are a part of this contract, the total sum being One Hundred Ninety -Eight Thousand Four Hundred Twenty -Eight and 60/100 ----- dollars ($ 198,428.60 ), such sum being the agreed amount upon which bonds I. and liabilities are based, and at his own cost and expense furnish all materials, supplies, labor, machinery, equipment, tools, supervision, bonds, insurance and other accessories and services necessary to complete the said I. construction in accordance with the conditions and prices stated in the Proposal attached hereto and make a part hereof,. and in accordance with the Specifications and the General Conditions, all as set out in these ' Specifications, and in accordance with the Plans, which include all maps, plats, blue prints, and other drawings, and written or printed explanatory matter thereof. 6-1 ■ MICROFILMfL) ' The Contractor agrees to commence work under this contract within ten days • of the issuance of the Notice to Proceed and fully complete all work within ninety (90) calendar days from the date of the issuance of the Notice to Proceed. The Owner agrees to pay the Contractor in current funds for the performance of the contract in accordance with the accepted Proposal therefor, subject to additions and deductions, as provided in the specifications, and to make payment on account thereof as provided below. As soon as is practicable after the first of each calendar month, the Owner will make partial payments to the Contractor for work performed during the preceding calendar month, based upon the Engineer's estimate of work completed, said estimate being certified by the Contractor and accepted by the Owner. Except as otherwise provided by law, ten percent (10%) of each approved estimate shall be retained by the Owner until final completion and acceptance by the Owner and Engineer. The Engineer shall then issue a Final Estimate of work done based upon the original contract and subsequent changes made and agreed upon, if any. Time is hereby expressly declared to be of the essence of this contract, and the time of beginning, mariner of progress and -time of completion of the work hereunder shall be and are essential conditions hereof. The Contractor agrees to commence work within ten (10) calendar days from the date of the Notice to.Proceed and to proceed with the construction of the work and. to prosecute the work with an adequate force and in a manner so as to complete the work within the time stipulated herein. If the Contractor fails to completing the contract within the time stipulated herein, the Contractor agrees to pay the Owner, as liquidated damages, the sum of two hundred dollars ($200.00) per day for each calendar day of delay in completion, said amounts being fixed and agreed upon by and between the parties hereto. Because. of the impracticability and extreme difficulty in fixing and ascertaining the actual damages Owner would in such event sustain, said amounts are to be presumed by the parties to this contract to be the amounts of damage Owner would sustain. Said amounts of liquidated damages shall be deductible from any amount due Contractor under the Final Estimate of said work, after the completion thereof, and Contractor shall be entitled only to the Final Estimate less such amounts of liquidated damages.. If the Contractor be delayed at any time in the progress of the work by any act or neglect of the Owner or of the Owner's employees, or by any other contractor employed by the Owner, or by changes ordered in the work, or by strikes, lockouts, fire, unusual delay in transportation, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Engineer pending arbitration, or by any cause which the Engineer shall decide to justify the delay, then the time of completion shall be extended for such reasonable time as the Engineer may decide. No such extension shall be made for delay occurring more than seven days before claim therefor is made in writing to the Engineer. In the case of a continuing cause for delay, only one claim is necessary. 6-2 In the event the Contractor abandons the work hereunder or fails, neglects or refuses. to continue the work after ten (10) days written notice, given Contractor by the Owner or by the Engineer, then the Owner shall have the option of (1) declaring this contract at an end, in which event the Owner shall not be liable to the Contractor for any work theretofore performed hereunder, of (2) requiring the surety hereto, upon ten (10) days notice, to complete and carry out the contract of Contractor; and in that event, should the surety fail, neglect or refuse to carry out said contract, (3) said Owner may complete the contract at its own expense and maintain an action against the Contractor and the surety hereto for the actual cost of same, together with any damages or other expense sustained or incurred by Owner in completing this. contract, less the total amount provided for --hereunder to be paid Contractor upon the completion of this contract. This contract shall be binding upon the heirs, representatives, successors or assigns of the parties hereto, including the surety. IN WITNESS WHEREOF, the Owner and Contractor have hereto set their hands and seals respectively. 'V ' r .r« Witnesses* Attest City Clerk Braun Excavating Company Firm Name By Jnq,L 13AW Y CITY OF FAYETTEVILLE, ARKANSAS Paul R. Noland, Mayoral! :_ - 4 * If corporation, Secretary shall attest. 6-3 MICROFILMED PERFORMANCE BOND KNOW ALL MEN BY THESE PRESENTS: That we (1) Braun Excavating Company a (2) corporation hereinafte called "Principal" and (3) Heritage Insurance Company of America of Lincolnwood , State of Illinois Ihereinafter called the "Surety," are held and firmly bound unto (4) the City of Fayetteville, Arkansas , hereinafter called "Owner," in penal sum of One Hundred Ninety -Eight Thousand Four Hundred Twenty -Eight and 60/101 ----------------- --------dollars ($ 198,428.60 ) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind our- selves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered i a certain contract with Owner, dated the day of , 19 a copy of which is hereto attached and made a part hereof for the construction of: Sanitary Sewer System Rehabilitation and Reconstruction for the City of Fayetteville, Arkansas; Plans No. Fy-116 NOW THEREFORE, if the Principal shall well, truly and faithfully perform its duties, all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety, and if he shall satisfy all claims and demands incurred under such contract, and which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety, for value received hereby stiuplates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any wise affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to thg terms of the contract or to the work or to the specifications. PROVIDED, FURTHER, that no final settlement between the Owner and the Contract shall abridge the .right of any beneficiary hereunder, whose claim may be unsatisfie This bond is given in compliance with Act 351, Arkansas Acts of 1953, and Act 209, Arkansas Acts of 1957, the same appearing as Arkansas Statutes (1957), Section 51-635, Cumulative Supplement. 7-1 ...O,iL1l IN WITNESS WHEREOF, this instrument is executed in six (6) counterparts, each one of which shall be deemed as original, this the day of 19 rn µ h r 7 h V` ? 4d1aSaa Secretary Witness as to Principal Braun Excavating Company Principal By: LA��inI Address Address I _ ATTEST: Heritage Insurance Company of America �.., Surety t U� X1A ure )'S retary ' hyllis Fields //)) // •, 4 (SEAL) By: �! ��1 9�1- • /� t_ Attorney -in -Fact t 1 ! D. Michael Babb ) Babb & Associates, Inc. • iS �?�,. / L�/tlXi d/yt�/ P.O. Drawer 15430 Witness a&t Surety GMF Little Rock, AR 72231 Marilyn Williams Babb & Associates, Inc. Address P.O. Drawer 15430 - GMF Little Rock, AR 72231 Address ' NOTE: Date of bond must not be prior to date of contract. ' (1) Correct name of Contractor. (2) A Corporation, a Partnership, or an individual, as the case may be. (3) Correct name of Surety. (4) Correct name of Owner. (5) If Contractor is a Partnership, all partners should execute bond. (6)' This bond must be filed with the Circuit Court of the County where the work is to be performed prior to the start of construction. ■ 7-2 PAYMENT BOND KNOW ALL MEN BY THESE PRESENTS: That we. (1) a (2) Braun Excavating Company Corporation hereinaft called "Principal" and (3) Heritage Insurance Company of America of Lincolnwood , State of Illinois hereinafter called the "Surety," are held and firmly bound unto (4) the City of Fayetteville, Arkansas , hereinafter called "Owner," in penal sum of One Hundred Ninety -Eight Thousand Four Hundred Twenty -Eight and 60/100-- "' " "- '- -" ---- ----- dollars ($ 198,428.60 in lawful money the United States, for the payment of which sum well and truly to be made, we bind ou selves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered int a certain contract with Owner, dated the day of , 19 a copy of which is hereto attached and made a part hereof for the construction of: Sanitary Sewer System Rehabilitation and Reconstruction for the City of Fayetteville, Arkansas; Plans No. Fy,116 NOW THEREFORE, if the Principal shall promptly make payment to all persons, firm subcontractors and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such contract, and any authorized extension o modification thereof, all amounts due for but not limited to, materials, lubricants, oil, gasoline, coal and coke, repair on machinery, equipment and tools, consumed or used in connection with the. construction of said work, fuel oil, camp equipment, food for men, feed for animals, premium for bonds and liability and workmen's compensation insurance, rentals on machinery, equipment and draft animals; also for taxes or pay= ments due the State of Arkansas or any political subdivisions thereof which shall hav arisen on account of or in connection with the wages earned by workmen covered by the bond; and for all labor, performed in such work whether by subcontractor or otherwise then this obligation shall be void, otherwise to remain in full force and effect. I The Surety agrees the terms of this bond shall cover the payment by the Principa of not less than the prevailing hourly rate of wages as found by the Arkansas Depart- ment of Labor or as determined by the court on appeal to all workmen performing work under the contract. PROVIDED, .FURTHER, that the said Surety, for value received hereby stipulates an agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder of the specifications accompanying the same shall in any wise affect its obligation on this bond, and it does hereby.wai notice of any such change, extension of time, alteration or addition to the terms of the contract as to the work or to the specifications. 7-3 MICROFILMED e,. PROVIDED, FURTHER, that no final settlement between the OwneryinviLtheontractc shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfiec ' This bond is given in compliance with Act 351, Arkansas Acts of 1953, and Act 209, Arkansas Acts of 1957, the same appearing as Arkansas Statutes (1957) Section 51-635, Cumulative Supplement. IN WITNESS WHEREOF, this instrument •is executed in six (6) counterparts, each c of which shall be deemed an original, this the day of , 19_ Braun Excavating Company c/ ,'2ta aete Principal Secretary Witness as to Principal Address ATTEST: { (urely) (S�"ietary hyllis .Fields (SEAL) rx Witness -as t'o Surety Marilyn Williams. Babb & Associates, Inc. P.O. Drawer 15430 GMF Little Rock, AR Address By: Lg V4(G,LI Address Heritage Insurance Company of America Surety BY Attorney -in- act ct D. Michael Babb Babb & Associates, Inc. P.O. Drawer 15430 GMF Little Rock. AR 72; Address 72231 NOTE: Date of bond must not be prior to date of contract. (1) Correct name of Contractor. (2) A Corporation, a Partnership,.or an individual, as the case may be. (3) Correct name of. Surety. (4) Correct name of Owner. (5) If Contractor is a Partnership, all partners should execute bond. (6) This bond must be filed with the Circuit Court of the County where the work is to be performed prior to the start of construction. 7-4 { t1f L I1 t 'IIERITACE INSURANCE COMPANY OF AMERICA ₹ I l ,. ! ;LINCOLNWOOD, ILLINOIS ... 1 •p , l l Ill lIr� 1f ' • 1,!-.C ;I Ill I.( .I, ' "_ :Lli. , i1 ICROFI'r.Mf.1 I. t II r• Power of Attorney I₹._ I , 1Ti 11+_+1r 1, l;l 11,1 I.}li'. r , 18�{ �' i {' Ilf r e f, i₹1 4 .. ' . • ..} { I 11`.r ^,11 ,I•. • `I 11 I : r _--n, f!-.:''.Hut:Y.S PRINCIPAL Braun Excavating Company EFFECTIVE DATE' June15,'; 19831; t� rl₹ Ir ; DBA AMOUNT OF BOND $'198, 428:60 L• Y•'•' qq 1 POWERNO.'H 29321 .: 1.Itj.kt: KNOW ALL MEN BY THESE PRESENTS: Thai the Heritage Insurance Company, a Corporation in the State of Illinois; having its principal office in Lincolnwood, Blinois, pursuant to the following resolution, adopted by the Board of Directors of the said Company on the 9th day of March, 1979, to wit: ^ •i i r I. .- . r Y 1 '. I The President, or`any Vice -President, or other officer designated by the Board of Executive Committeeshall have authority,. severally, to make, execute and deliver a power of attorney constituting as Attorney -in -Fact such persons, firms or corporations as such officers may select from time to time" H; does hereby make, constitute and appoint D. Michael Babb — -of North sr& Little Rock in the State of Arkansas its true and lawful attorney(s)-in-fact, with full power and authority hereby confereed in its name, place. and stead, to sign, execute, acknowledge and deliver in its behalf, and its'act and deed as'follows:'.. The obligation of the Company shall not exceed the sum of three hundred and twenty five thousand ($325,000.00) dollars. Z ;';:; and to bind Heritage Insurance Company thereby as fully and to the same extent as if such bond or undertaking was signed by the duly: authorized officers of the Heritage Insurance Company, and all the acts of said Attorney(s) pursuant to the authority herein given, are ' hereby ratifiedandconfirmed. I' ,`- ,1. .?:-. IN WITNESS WHEREOF, the Heritage Insurance Company has caused these presents to be signed.by'its President and/or its Vice -President, and its Corporate Seal to be hereto affixed. HERITAGE INSURANCE' COMPANY OF AMERICA 1t . .. ' I I�"��rorr��to I. rl �Y I I SEAL � ,, i _ i?I s,. _ilt" 1r ll � ₹I i Vincent M. Giacrnto, President 1 I w i - i Ip f .}• ili •, 1.• - , t I ll ate of Illinois ) r � I t � •' County of Cook ) I ... t1 , , • - t {I 11" I;I Ji' •- I 1 »C: • '• •. ...:. 1� 't i .' 1 / t{₹.-. ll I{r � lIt is t•,n I' ... 'I'�•i On this 9th day of March, 1979, before the subscriber, a Notary Public of the State Of Ilhnois,in and. for the County 'of Caoki duly commissioned and qualified, came V. M. Giacinto of the Heritage Insurance Company, to me personally known to be the indivlduul and officer described herein, and who executed the preceding instrument, and acknowledged the'executionof the'same, and being by me:; duly, sworn, deposed andisaid; that he is.the offtcer'of.said Company aforesaid, and that the seal affixed to.the preceding ins tiument.is the Corporate Seal of said. Company, and the said Corporate Seal and signature as an officer were duly affixed and subscribed to the said" ' Instrument by the authority'and direction of the said Corporation, and that the resolution of said Company; referred to'.ln the'preceding. t :..- , .- II a -. . , _. , hMrument, is now in foroe: 1.- F ... . til 3'll I t r. 1, ...1₹. -:Il 1 ,II; ill ,11 .,11 Jam. IN TESTIMONY WHEREOF, 1 -have hereunto set my hand, and affixed my official seal.at I�ncolriwood, Blinois, the da and stove writteir .. , • 1 1 - \ I1. r ly • y� '.. 1.- i t .. A Ill,i: - 'i �, .• ₹ . ! iisr �' l t. _ I. plr 'nil}.,.1 'I{I ; 11 I 1 I ; 11 r— i t ' ' ' r;:l{ Y IJ1 ' II rli v •{ • �₹ Ir •y ,I{r �.r Y{l Ill r{I -';₹ ..� . • 1 ( :-, •.�. {' a o ! { ' ll' '₹1 1 t li, _ IIt n 'i t{I {i � '₹1 Ir i a-i' . t X11 —� ' o T X'� IiY - f tl " `�,� 11 1' Ili r'`•"+'I"t ar • a . tiva !I: i ' •r• Notary Public tEf —Ia . I. 4 •' j ' - 11� 'i -. �\� ! }!i . - 1- ri -."irl r, if1,-.III II• ' . 11 .:c-1 131 j,l t r• cl I l x 1}, I 1._ �' - fll JOSEPH D. I l f ' r 1 1' i •— { { I+s {{ �� Itl 1l t • 8 .•.' t It NOTARY PUBLIC; State:oflflmon } 1 y'i Ix• ' 1 ; 1{, Ill w ' Qualified State,of rBlinoo ll1 ,14`l in ' ;l^s.- "i 1 ; r1 s _ .. r i Com •es rc 9 I I � l`Ir � • t. .' . { ; ( fission Ex it h tl j14 ; , 8{ , rvi1 X111 1 I. 1..1,1 I. r1 { N�,.-al 11, -1t,. ,,ij -x Pt• :L -I0 ' 84.,84» �1 1.� State of Illinois ). ` :�if r . II I. V I %'I 111 1� il t r' t1 County of Cook), ;+1y`' t ' �1 1. I ' r rnR'li' ;{I l" I Ili 1 111 r ip --- ill 1I �l " , ' ' I{t Ill•_.;' !I! t' ;I 11 ( I '111: IIr-- , ! "I l • l 1 �,r •• .l• .. ,irwt,I , , . I• 1.. r ill "- , , 1• - , •Fl l- , •'j { CERTIFICATE 1 ll. { #h; f{I i{+I{ ;'[ II( •.11 11. ,._ 171 ,�, ₹ 1 - :i{.:. '. ,.:i, .11 m` i•..,.. jr •;: l�i�m !{),.-ltl+i--1{1=sY<'t{...i� - 11; the undersigned;: Secretary •:of.IILR/TAGE,/NSURANCErCO» a l stock- corporauan orthe'Staii:'of Bliiidis;" BO`{HEREY Ft' ,CERTIFY, that the foregoing and attached Power of Attorney and Certificate of Authority remains. in full force and has not bean revoked; and furthermore; that the. Resolution of .the Board of Drectors, as set forth m the Certificate (of Authority, are no iu i {� w A. 'l `s. I • 1 ,� ( ,i I ♦.• ,r,l 'I I a I/ ,•I 111 I 1 .r ... hi: ,l .� n _4. �II l.n .,: {f . i.�t w 41 { tl "'I ₹II In, ll11 .<r1,11+M lil I₹ .Ic..ilr n• Siyted and Sealed at the Home ~Office of; ihe: Company, at% Lincolnwood, Blinois Dated; this' I i. !'• I F L I. J. r' .. •- r • 1 i .r •'F rn ��... June ' AD; 19 8311 ; 1.11 { I1 r, tl tl{I I(I I 1. { r{8- 'ti N.lj rl�lr" (; 11 ` : if i I x 11 fill t:. ,1_— 4l 1 111yT r - ! -. 1 .. , rWiS I 1 +4• .........................'---I •`• �k F 11 1. ' ! ; I, a l lr i r1 • 1 ,}I,1.___..Ii.._._. l L r rt 1 � { l 1;₹ { ••. fir- '1rv11' 1f fn ill rII , 'I lll�gl1i�,'e��•�:� I, 11+^t.l�l 7. i . SEAL �, 8 ; ., dt i ₹i3 I ill t(l x$�eretq .'1' i{t I ₹ 8............ 111 : I{8 F.18", 'x11' I} If l ^ !sG 1 I S c -187 tL Itl "........---•I '' . 'e. I'.'i,+.. f! i I'. !)s..-.fll '�'-ii1=1iL1 4... ."'.-_. i. G+'. r. Section 009 GENERAL CONDITIONS 009-A. DEFINITIONS. Whenever the words herein defined, or pronouns used in. their stead, occur in this contract and documents, they shall have and are mutually understood to have the meaning herein given. The words "City" and "Owner" shall mean the City of Fayetteville Arkansas, a municipal corporation, acting through its duly authorized representatives. The words "Board of Directors" shall mean the duly elected or appointed governing body of said City of Fayetteville, Arkansas. The word "Mayor" shall mean the Mayor of the City of Fayetteville, Arkansas. The words "City Manager" shall mean the City Manager of the City of Fayetteville, Arkansas. The words "City Attorney" or "Attorney" shall mean the attorney for the City of Fayetteville. The words "City Clerk" shall mean the City Clerk of the City of Fayetteville. The words "City Engineer" or "Water Superintendent" shall mean the superintendent in charge of the Water Department of the City of Fayetteville. The word "Engineer" shall mean McGoodwin, Williams and Yates, Inc., Consulting Engineers, Fayetteville, Arkansas, who have been employed by the City of Fayetteville for this work, or their duly authorized agents. The word "Inspector" shall mean the engineering or technical personnel duly authorized by the Engineer, limiting to the particular duties entrusted to him or them. The word "Contractor" shall mean the person, persons, partnership, company, firm or corporation entering into this contract for the performance of the work required of it, and the legal representatives of said party, or the agent appointed to act for such party in the performance of the work._ The word "surety" or "sureties" shall mean the bondsmen or party or parties who have made sure the fulfillments of the contract by bonds, and whose signatures are attached to said bonds. The word "Advertisement" shall mean all, the legal publications pertaining to the work of this contract. The word "Specifications" shall mean, collectively, all of the terms and stipulations contained in the written portion of information furnished. The word "Plans" shall mean, collectively, all of the drawings pertaining to the contract and made a part hereof, and also such supplementary drawings as the Engineer may issue from time to time in order to clarify the drawings, or for the purpose of showing changes in the work as authorized under the section 009-1 "Modifications and Alterations," or for showing details which are not shown thereon. The words "Work Order" or "Notice to Proceed" shall mean a notice to the Contractor of the date on or before which he is to begin the prosecution of the work for which he has contracted. The words "Contract Price" shall mean either the unit prices, or lump sum prices, named in the contract, or the total of all payments according to the schedule of the prices in the contract, as the case may be. The term "Grade" used in these Specifications is understood to refer to and indicate the established elevations of the paving, flow line of sewers or other appurtenances as shown on the Plans on file in the office of the official designated in the "Advertisement for Bids." The word "Bid" or "Proposal" shall mean the written statements, duly filed with the Owner, by the person or persons, partnership, company, firm or corporation proposing to do the work and furnish the materials called for on the Plans at the prices named on said statements. "The work" shall mean the work to be done and the equipment, supplies, and materials to be furnished under this contract, unless some other meaning is indicated by the contract. Whenever in these contract documents the words "as ordered," "as directed," "as permitted," "as allowed," or words or phrases of like import are used, it shall be understood that the order, direction, requirements, permission or allowance of the Owner and Engineer is intended. But in no instance shall such directions by the Engineer apply to the supervision of the Contractor or his work forces, but shall apply only to ensure that the completed work meets the requirements of the Plans and Specifications. Similarly the words "approved," "reasonable," "suitable," "acceptable," "proper," "satisfactory," or words of like effect and import, unless otherwise particularly specified herein, shall mean approved, reasonable, suitable, acceptable, proper, or satisfactory in the judgment of the Owner and Engineer. Whenever the following abbreviations are used, they shall have the meanings given below: ASTM - American Society for Testing Materials ASA - American Standards Association AWWA - American Water Works Association AGA - American Gas Association NEMA - National Electrical Manufacturers Association gpm - gallons per minute MGD - million gallons per day ppm - parts per million Hp - horsepower T.D.H. - total dynamic head V - volt A - ampere 009-2 Section 009 T.D. - time delay R - motor starter relay .xM N.O. - normally open N.C. - normally closed PVC - polyvinyl chloride (pipe) psi -. pounds per square inch cfm - cubic feet per minute rpm - revolutions per minute 009-B. COPIES OF CONTRACT. Not less than six copies of the bound volumes of the proposal, contract and stipulations shall be prepared,. each containing an exact copy of the Contractor's proposal as submitted, the bond or bonds properly executed and contracts signed by both parties thereto. However, the Contractor and the surety executing the bond shall not date the contract or the bond upon submission for execution by the Owner. These documents will be dated the date the Owner Executes -the contract. 009-C. SCOPE, NATURE, AND EXTENT OF CONTRACT, SPECIFICATIONS AND PLANS. The said Specifications and Plans are intended to supplement, but not necessarily duplicate each other, and together constitute one complete set of Specifications and Plans, so that any work exhibited in the one and not in the other shall be executed just as if it had been set forth in both, in order that the work shall be completed according to the complete design or designs as decided and determined by the Engineer. Should anything. be omitted from the Specifications and Plans which is necessary to. a clear understanding of the work, or should it appear various instructions are in conflict, then the Contractor shall secure written instructions from the Engineer before proceeding with the construction affected by such omission or discrepancies. It is understood and agreed that the work shall be performed and completed according to the true spirit, meaning, and intent of the contract, Specifications and Plans. 009-D. FIGURED DIMENSIONS TO GOVERN. Figured dimensions, when given on the Plans, shall be accurately followed, even though they differ from scaled measurements. No work shown on the Plans, the dimensions of which are not figures, shall be executed until instructions have been obtained from the Engineer as to the dimensions to be used. Large stale and full size drawings shall be followed in preference to small scale drawings. 009-E. CONTRACTOR TO CHECK PLANS AND SCHEDULES. The Contractor is required to check -all dimensions and quantities on the Plans and schedules given to him by the Engineer, and shall notify the Engineer of any discrepancy between the Plans and the conditions on the ground, or any error or omissions in the Plans, or in the layout as given by stakes, points, or instructions, which he may discover in the course of the work. The Contractor will not be allowed to take advantage of any error or omission in the Plans or contract documents, as full instructions will be. furnished by the Engineer should error or omission be discovered, and the Contractor shall carry out such instructions as if originally specified. 009-F. METHODS OF OPERATION. The Contractor shall give to the Engineer full information, in advance, as to his plans for carrying on any part of the work. 009-3 JCl...1Vll VVl 009-G. GRADES AND MEASUREMENTS. At such tine as the Contractor is ready to proceed with construction work, he shall notify the Engineer in order that proper grades and alignments, prints and stakes may be furnished. The Contractor shall notify the Engineer a reasonable length of time prior to the commencement of such work, and the Contractor shall not proceed with construction work until such grade and line stakes have been set. The work shall be in conformity with such prints, stakes and instructions as related to the finished quality of the work. Where plans, building, or mass movement of earth is being undertaken, the Engineer will set such control lines and basic elevations as are required for the Contractor to make such unit or plant layouts as are required. When work is undertaken which requires a constant or generally intermittent checking of lines and elevations, the Contractor shall maintain such equipment and personnel as are essential to the actual prosecution of the work. In these instances, the final grades, alignment and dimensions are subject to checking by the Engineer. 009-H. CONTRACTOR TO FURNISH STAKES AND HELP. The Contractor shall furnish, without charge, competent men from his force and such tools, stakes, and other materials as the Engineer may require for the proper staking out of the work and in making measurements and surveys and in establishing temporary or permanent reference marks in connection with said work. 009-I. DIRECTION AND PROSECUTION OF THE WORK. The Contractor shall commence work at such points as the Engineer may direct, and shall prosecute the work in the order as laid out by the Engineer. 009-J. LANDS FOR WORK. The Owner shall provide the lands upon which the work under this contract is to be done, except that the Contractor shall, when necessary, provide land required for the erection of temporary construction facilities and storage of his materials, together with right of access to same. 009-K. RIGHT OF VARIOUS INTERESTS. Wherever forces or by other contractors is contiguous to the respective rights of the various interests by the Engineer to secure the completion of th in general harmony. work being done by the Owner's work covered by this contract, involved shall be established e various portions of the work 009-L. SEPARATE CONTRACTS. The Owner reserves the right to let other contracts in connection with this work. The Contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work, and shall properly connect and coordinate his work with theirs. If any part of the Contractor's work depends for proper execution of results upon the work of any other contractor, the Contractor shall inspect and promptly report to the Engineer any defects in such work that render it unsuitable for such proper execution and results. His failure so to inspect and report shall constitute an acceptance of the other contractor's work as fit and proper for the reception of his work, except as to defects which may develop in the other contractor's work after the execution of his work. 009-4 Section 009 To insure the proper execution: of his subsequent work, the Contractor shall measure work already in place"aiid' shall``at"once report to the Engineer any discrepancy between the executed work and the drawings. 009-M. SUPERINTENDENTS AND FOREMEN. When the Contractor is not present at the work, the superintendent or foreman in immediate charge thereof shall be deemed to be in authority and shall receive and execute orders in connection with the provisions and in conformity with these Specifications. 009-N. WORKMEN. The. Contractor shall employ foremen and skilled laborers where necessary. Line of authority shall be observed, and it shall be the responsibility of the superintendent representing the Contractor to transmit all necessary orders and instructions. 009-0. AUTHORITY OF ENGINEER. Where specifically contracted for and authorized in the contract documents, the Engineer shall be the Owner's representative and shall observe the work in process for the Owner. He shall make periodic inspections in an effort to protect the Owner against defects and deficiencies. In so doing, the Engineer does not guarantee performance of the work but acts in a professional capacity. He does not assume responsibility of any nature or kind for personal injury, death or property damage to any person or corporation arising out of the methods, operations or degree of care exercised by the Contractor or subcontractors in the performance of the work. The manner and methods in which the Contractor and his subcontractors perform work pursuant to the Plans and Specifications and the degree of care exercised with relation thereto, is the exclusive responsibility of the Contractor. The Engineer will decide all questions that may arise as to interpretation of the Plans and Specifications. He shall also decide questions as to acceptability of materials furnished and work performed. 009-P. ENGINEER TO DECIDE. All work performed under this contract shall be done in a first class, workmanlike manner, and, from the viewpoint of the quality of the finished job, shall be done to the satisfaction of the Engineer who shall determine the quality of the finished product. The Engineer shall in all cases determine the amount, quality, acceptability and fitness of the several kinds of work and materials herein specified. 009-Q. INSPECTION. The improvement shall at all times be subject to inspection by the Owner and representatives of the State Department of Health, and the Contractor shall provide proper facilities for such access and inspection. Such inspection shall not relieve the Contractor from any obligation to perform said work strictly in accordance with the Plans and Specifications, and work not so constructed shall be removed and made good by the Contractor whenever so ordered without reference to any previous oversight in inspection. This shall apply both to workmanship and materials. All rejected materials shall be immediately removed from the site of the work, and shall not again be returned to it. It shall be the duty of the Contractor to notify the Engineer in advance of the beginning of work after delays, shutdown, change of work program or change of location. 009-5 The failure or neglect on the part of the Engineer or the Inspector to inspect, condemn or reject inferior materials or work shall not be construed to imply an acceptance of same should inferiority become evident at any time prior to the final acceptance of the work by the Owner, or within the time limit of one year as set out in Section BBB herein. 009-R. INSPECTOR. The Engineer may appoint an Inspector, who shall represent him on the work, and such orders as he may give, relative to the quality of the construction as it relates to the finished project being in accordance with the Plans and Specifications, shall have the same effect as if given by the Engineer in person. No work of a permanent nature which cannot be inspected after completion shall be prosecuted except when an Engineer or inspector is present. Contractors shall notify the Engineer at last 24 hours prior to time of commencing work which demands the presence of an Inspector, except in case an Inspector has been regularly on the job, then 12 hours notice will be sufficient. The inspection of the work by the Engineer or his representative shall not, in any way, relieve the Contractor (or obligate the Engineer) of any of the provisions of the contract as to quality of materials, performance of the work, safety of the public or safety of the Contractor's employees. These are the sole responsibility of the Contractor. The Engineer does not guarantee the performance of the contract by the Contractor, nor shall his inspection be construed as supervision of actual construction, nor make him responsible for providing a safe place for the performance of the work by the Contractor, or the Contractor's employees, or those of the suppliers, his subcontractors, nor for access, visits, use, work, travel or occupance by any person, as these responsibilities are covered under the provisions of this contract and the Contractor's insurance and performance bond, and are not the responsibility of the Engineer. 009-S. PROTECTION OF PUBLIC UTILITIES. The Contractor shall give reasonable notice to the owner or owners of steam, gas, water, sewer and other pipe lines or conduits, overhead and underground wires or other structures, either public or private, railroads and other owners of property, when such property is liable to injury or damage by reason of the execution of the work, in order that the owner or owners of such utility or other property may remove or protect the same. If any railroad, or other owner or owners of any property liable to be affected, endangered or damaged by the construction of the work, does not protect its or their property, then the Contractor must do so. The Contractor shall receive no compensation over the unit and lump sum prices specified in the proposal for the completion of this contract, which prices shall cover every item of additional cost for all the material and labor necessary to support, protect, or remove such tracks, pipes, conduits, overhead wires and structures, and other improvements, during the construction of said work across, under, over, along, or near the same. The Contractor shall use every precaution on the work to prevent harm or accident to the property, passengers, employees, or patrons of public utilities, either publicly or privately owned, and to any other person legitimately employed on the premises, and the Contractor shall assume all liability for damages accruing from an accident, which may be due to his 009-6 Section 009 carelessness, omission or: neglect once work has begun, the Contractor shall prosecute the work as rapidly; as'x'pbssibler under along and near such property as may be liable to damage thereby. Except as provided in the these Specifications, all permits and licenses required in the prosecution of any and all parts of the work shall be secured and paid for by the Contractor. The Contractor shall take such measures as are necessary to protect any and all pipes, sewers, and other structures belonging to the Owner and shall be responsible for any damage resulting thereto. The Contractor shall not be entitled to any damages or extra pay on account of any postponement, interference, or delay caused by any such structures being on the line of the work, whether such structures are shown on the Plans or not. 009-T. PROTECTION OF MONUMENTS. The protection of local, state or Federal ' government monuments, street signs or other property is of prime importance. If the Contractor should destroy such a monument, he shall be responsible for the cost of replacing such to the satisfaction of the governing agency. ' 009-U. ACCIDENT PREVENTION. Reasonable precautions shall at all times be exercised for the safety of, employees on the work;.and applicable provisions • of the federal; state or municipal safety laws and building and construction ' codes shall be observed. The Department of Labor of the State of Arkansas has prepared a safety code, Safety Code No. 9, for the guidance of contractors and the protection of workmen and the public. The Contractor shall familiarize himself with the • provisions of this code, and shall comply with the rules and regulations provided therein. The code requirements are enforceable by the Department of ' Labor, and it is the responsibility of the Contractor to see that they are carried out. The responsibility for the interpretation and implementation of the provisions of the code does not rest with the Owner, the Engineer, or itheir representatives. 009-V. USE OF EXPLOSIVES. When the use of explosives is necessary for the prosecution of the work, the Contractor shall observe all local, state and ' Federal laws in purchasing and handling explosives. The Contractor shall take all necessary precaution to protect completed work, neighboring property, water lines, or other underground structures. Where there is danger to structures or property from, blasting, the charges shall be reduced and the ' material shall be covered with suitable timber, steel or rope mats. The Contractor shall notify all owners of public utility property of intention ' to use explosives at least eight hours before blasting is done close to such property. ' The Contractor shall submit to the Owner a certificate of insurance covering such blasting operations. Such insurance shall be in the same amount as is the public liability requirements under Section 28 of the Instructions to Bidders. 1 009-7 009-W, DANGER SIGNALS AND SAFETY DEVICES. The Contractor shall take all necessary precautions to guard against damages to property and injury to persons. He shall put up and maintain in good condition sufficient red or warning lights at night and shall provide suitable barricades and other devices necessary to protect the public. In case the Contractor fails or neglects to take such precautions, the Owner may put up such lights and barricades and charge the cost of this work to the contract. Such action by the Owner does not relieve the Contractor of any liability incurred under these Specifications or contract. 009-X. PROVISION FOR EMERGENCIES. If, in the absence of the Contractor or his representative, an emergency shall arise and immediate action shall be considered necessary in order to protect the public or private or personal property, then, and in that event, the Owner, with or without notice to the Contractor, may provide suitable protection to the said interests by causing such work to be done and material to be furnished and placed as may be considered necessary and adequate. The cost and expenses of such work and materials so furnished shall be borne by the Contractor, and if the same shall not be paid on presentation of the bill therefor, then such costs will be deducted from any amounts due or to become due the Contractor. 009-Y. SIDEWALK CROSSINGS. The Contractor will provide suitable sidewalk crossings wherever sidewalks are obstructed. 009-Z. PRIVILEGES OF CONTRACTORS IN STREETS. The Contractor will be entitled to use such streets, alleys, roadways, or parts of the streets and alleys as are necessary for the prosecution of the work. The Contractor will take care to keep streets open for use whenever practicable; cross streets will be kept open wherever possible. The Contractor will notify the Fire Chief when a street is closed and shall again notify him when it is opened for traffic. In case no adequate detour can be provided, the Contractor will stand in readiness to provide a crossing in case of any emergency. 009 -AA. LAWS AND ORDINANCES. The Contractor shall keep himself fully informed of all existing and current ordinances and regulations of the Owner, and of county, state and federal laws in any way limiting or controlling the actions or operations of those engaged upon the work, or affecting the materials supplied to or by them. He shall at all times observe and comply with all such ordinances, regulations and laws, and shall protect and indemnify the Owner and its officers and agents against any claims or liability arising from or based on any violation of the same. 009 -BB. SOURCE OF SUPPLY AND QUALITY OF MATERIALS. The Contractor shall not start delivery of materials until the Engineer has approved the source of supply. Only materials conforming to the requirements of these Specifications will be used in the work and such materials shall be used only after written approval has been given by the Engineer and only so long as the quality of said materials remains equal to the requirements of the Specifications. The Contractor shall furnish approved materials from other sources if for any reason the product from any source at any time before commencing or during the 009-8 Section 009 prosecution of the work proves unacceptable," After approval, any materials which have become mixed with or'coated with: dirt or any other foreign substance during delivery and handling shall not be used in the work, 009 -CC. INSPECTION OF MATERIALS. All materials used and equipment furnished for the construction of the project shall be subject to test according to accepted standards, when necessary in the opinion of the Engineer or so required in these Specifications. The laboratory or inspection agency will be approved by the Owner. The Contractor will pay for all laboratory inspection service, except when otherwise provided in these Specifications. All material shall be subject to the inspection of the Engineer and only such materials shall be used as are in his opinion suitable or of acceptable ' quality, and in accordance with the terms and conditions of the contract, Plans, and Specifications. Where required by the Specifications, the Contractor shall furnish a simple field laboratory for making the most common ' field or plant tests of materials. Where required by the Specifications, the Contractor shall, in addition, to furnishing the usual samples of materials, forward to the Engineer or to the laboratory selected by the Engineer, samples ' of materials taken at their source. In case such samples are requested, the Contractor shall not ship materials from such sources until the source has been approved by the Engineer. The approval of the source of materials does not in any way relieve the Contractor from furnishing materials as specified. 009 -DD. OPEN SPECIFICATIONS. Where materials or equipment are specified by a trade or brand name, it is not the intention of the Owner to discriminate ' against an equal product or another manufacturer, but rather to set a definite standard of quality or performance, and to establish an equal basis for the evaluation of bids. Where the words "equivalent," "proper," or "equal to" ate ' •used, they shall be understood to mean that the thing referred to shall be proper, the equivalent of or equal to some things, in the opinion or judgment • of the Engineer. ' Unless otherwise specified, all materials shall be the best of their respective kinds and shall be in all cases fully equal to approved samples. Notwithstanding that the words "are equal to" or other such expression may be ' used in the Specifications in connection with a material, manufactured article or process, the material, article or process specifically designated shall be • used, unless a substitute shall be approved in writing by the Engineer, and the Engineer shall have the right to require the use of such specifically ' designated materials, articles or processes. In case the Owner has good and sufficient reason to choose a particular brand or product, it reserves the right to require at the time of the award of the contract or the approval of the item, the use of said product and pay from its own funds (not federal matching funds) the net added cost to the Contractor over that of any item •which would otherwise meet the Specifications. ' 009 -EE. STORAGE OF MATERIALS. Materials shall be stored so as to insure the preservation of their quality and fitness for.the work. When directed by the Engineer, they shall be placed on a wooden platform or other hard, clean ' surfaces and not on the ground, and shall be placed under cover when directed. Stored materials shall be located so as to facilitate prompt inspection. 009-9 009-FF. PATENT RIGHTS. All fees for any patented invention, article, or arrangement that is used in any manner connected with the construction, erection or maintenance of the work, or any part thereof embraced in the contract and these Specifications, shall be included in the price stipulated in the contract for such work, and the Contractor must protect and hold harmless the Owner against any and all demands of such fees and claims. 009 -CC. SETTING AND FINAL ADJUSTMENT OF EQUIPMENT. When a particular manufacturer's equipment is furnished, it shall be the responsibility of the Contractor to furnish an engineering representative of the manufacturer who shall supervise the final setting and adjustment of the equipment. 009-HH. SANITARY CONVENIENCES. Sanitary conveniences, consistent with good health standards and decency, shall be provided for the workmen. 009 -II. DRINKING WATER. The Contractor shall provide safe drinking water for all workmen. The water shall come from a safe source approved by the State Department of Health. Water shall be delivered to workmen through an approved water spigot or angle jet fountain; the use of common drinking cups will be prohibited. 009-JJ. USE OF WATER. Water, if available, will be furnished without cost to the Contractor. The Contractor will furnish all material and make all connections under the supervision of the Owner. 009-KK. SUNDAY, HOLIDAY AND NIGHT WORK. No work shall be done between the hours of 6:00 p.m. and 7:00 a.m., or on Sundays or legal holidays, except work as is necessary for the proper care and protection of work already performed, or in case of any emergency. It is understood, however, that night work may be procedure by the Contractor if he first obtains the Engineer, but that such permission may be revoked at if the Contractor fails to maintain at night an ad( for providing finished work in accordance with Specifications. established as a regular written permission of the any time by the Engineer, !quate force and equipment the requirements of the 009 -LL. REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK. All work which has been rejected or condemned shall be repaired, or if it cannot be satisfactorily repaired, it shall be removed and replaced at the Contractor's expense. Defective materials shall be removed immediately from the site of the work. Work done without lines and grades having been given, work done beyond the lines, or not in conformity with the grades shown on the Plans, or as given (save as herein provided), work done without proper inspections, or any extra or unclassified work done without written authority and prior agreement in writing as to prices, will be done at the Contractor's risk and will be considered unauthorized, and at the option of the Engineer may not he measured and paid for, and may be ordered removed at the Contractor's expense. Upon the failure of the Contractor to satisfactorily repair, or to remove or replace, if so directed, rejected, unauthorized or condemned work or materials immediately after receiving notice from the Engineer, the Engineer shall, 009-10 Section UU9 after giving written notice..to the Contractor;have the authority to cause y... defective work to be remedied or t. IL'i•.. removed`.ethr'and replaced, or to cause unauthorized work to be removed and to deduct the cost thereof from any compensation due or to become due the Contractor. 009 -MN. TEMPORARY SUSPENSION. The Engineer shall have the authority to suspend the work wholly or in part for such period or. periods as he may deem necessary due to unsuitable weather, or such other conditions as are considered unfavorable for the production of work to meet the requirements of the Plans and Specifications. If it should become necessary to stop work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the traveling public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed, and shall provide suitable drainage about the work and erect temporary structures where necessary. The Contractor shall not suspend work without written authority from the Engineer and shall proceed, with the work promptly when notified by the Engineer to resume operations. 009 -NN. LIQUIDATED DAMAGES. The Contractor shall commence work within the ' time limits set out in the contract. If the Contractor fails to complete the contract within the time stipulated in the proposal and provided in the contract, the Contractor shall pay the Owner liquidated damages as provided in ' the contract for each calendar day of delay in completion. If the Contractor be delayed at any time in the progress of the work, or by strikes, lockouts, fire, unusual delay in transportation, unavoidable casualties or any causes ' beyond' the Contractor's control, or by delay authorized by the Engineer pending arbitration, or by any cause which the 'Engineer shall decide to justify the delay, then the time of completion shall be extended for such reasonable time as the Engineer may decide. I. No such extensions shall be made for delay occurring more than 7 days before claim therefor is made in writing to the Engineer. In the case of a continuing cause of delay only one claim is necessary. 009-00. EXTRA TIME ALLOWANCE. Except as provided in Article 009 -NN above, no allowance shall be made of additional time for the contract unless the Contractor shall be delayed or restrained from prosecuting the work or some part thereof by injunction or other legal proceedings or delay on the part of the Owner to comply with the obligations imposed upon it by the law of the contract; provided that the time limit herein provided may be extended by Resolution or Ordinance of the Owner for any number of days to be stated in such Resolution or Ordinance. The liability of the Contractor and the Surety Company shall not be affected or in any manner released by an extension of the time of the. completion and acceptance thereof. Any extension of the time to the Contractor by Resolution or Ordinance shall not release the Contractor and Surety herein from the payment of the liquidated damages as provided for any period.of time not included in the original contract or the time extension, as herein provided. 009-11 In no event shall the Owner be liable or responsible to the Contractor, Surety, or any person, for, or on account of, any stoppage or delay of work herein provided for by injunction or any other kind of legal, equitable proceedings, or from or by, or on account of, any delay from any other cause whatsoever. 009 -PP. MODIFICATIONS AND ALTERATIONS. The Contractor agrees that the Owner shall have the right, when in its opinion it becomes necessary in the prosecution of the work to modify the arrangement, character, grade or size of the work or appurtenances, but such modifications or alterations shall only be made on the order of the Owner, except as provided in Section 009 -TT herein. Such order shall be of no effect until the price to be paid for the work or material under such modified or altered contract has been agreed upon in writing and signed by the Contractor and the Owner and the Contractor shall not be allowed to recover anything for work performed or materials used by reason of any modifications or alteration of this contract, unless an order is made and agreement signed as aforesaid, nor shall the Contractor in any case be allowed to recover more for such work and materials than said agreed price. 009-QQ. TRANSFER OF CONTRACT. If the Contractor shall at any time assign, sell or sublet, pledge or mortgage any part of this contract without the written consent of the Owner, the same may work as a forfeiture on the part of the Contractor. 009 -RR. ANNULMENT OF CONTRACT. The power is reserved to the Owner to suspend or annul the contract in whole or in part or to suspend the doing of any work thereunder at any time for any failure on the part of the Contractor to comply with the terms of these Specifications. If the contract be so suspended or annulled in whole or in part on account of the fault of the Contractor to fulfill his obligations hereunder, then the Contractor shall not be entitled to anything on account of damages thereby, nor shall annulment or suspension in any way affect the right of said Owner to damages and penalties claimed by it on account of failure of said Contractor; but said annulment or suspension must be ratified by the Owner before becoming final. 009 -SS. DEFENSE OF SUITS. In case any action at law or suit in equity is brought against the Owner or any of its officers or agents for or on account of the failure, omission or neglect of the Contractor or his subcontractors or his or their employees or agents, to do and perform any of the covenants, acts, matters or things by this contract undertaken to be done or performed by the Contractor or his subcontractors or his or their employees or agents, or for any injury or damage caused by the negligence or alleged negligence of the Contractor or his subcontractors or his or their employees or agents, the Contractor shall indemnify and same harmless the Owner, its officers and agents of and from all losses, costs, actions, or lawsuits as may be brought as aforesaid. 009 -TT. ESTIMATED QUANTITIES. The Contractor agrees that the quantities of work as stated in his proposal and bid or indicated on the Plans are only approximate, and that during the progress of the work the Owner may find it advisable, and it shall have the right, to omit portions of the work and to increase or decrease the quantities, and that the Owner reserves the right to add to or take from any item as may be deemed necessary or desirable. Changes 009-12 in the total amount (such restriction not to apply. to individual items) of the contract price is not to exceed..10 percent.of.the-,base bid without the written ,-. ms to consent of the Contractor. Under no circumstances or conditions will the Contractor be paid anything on account of anticipated profits upon the work or any portion thereof covered by this contract, which is not actually performed and which has not actually entered into the construction of said improvements. 009-UU. METHODS OF MEASUREMENTS. Unless specifically stated otherwise in this contract, no extra measurement or measurements according to local custom of any kind shall be allowed in measuring the work under this contract, but only the length, area, solid contents, number, weight or time in standard units, as the case may be, shall be considered. 009 -VV. PRICES. In consideration of the faithful performance by the Contractor of all the conditions, provisions and covenants of the contract and the Specifications, to the satisfaction of the Owner,. the Owner shall pay and the Contractor shall receive, the prices stipulated in his proposal and bid attached hereto and made a part hereof, and full compensation for everything furnished or done by the Contractor under the contract. The Owner also agrees to pay in addition such amounts as may be agreed upon for alterations and changes as set out in these Specifications. 009 -WW. MONTHLY ESTIMATES.AND PAYMENTS. On or about the first day of each I month the Engineer will make an approximate estimate of the value of the work done and materials furnished in place on the work during the previous calendar month. He will also include the cost value of freight for equipment and materials readily accounted' for, but not such items as cement, aggregate, lumber, nails and miscellaneous items. The Contractor shall furnish to the Engineer such detailed information as he ' may request to aid him as a guide in the preparation of monthly estimates. After each such estimate shall have been approved by the Owner, the Owner shall pay to the Contractor 90 percent of the amount of such estimated value of materials furnished and work done during said previous calendar month. If ' the Owner shall at any time fail to make the Contractor a monthly estimate at the time herein specified, such failure shall not be held to vitiate or void the contract. 009-XX. CLEANING UP. The Contractor shall not allow the site of the work to become littered with trash and waste materials, but shall maintain the same in ' a neat and orderly condition throughout the construction period. On or. before the completion of the work, the Contractor shall, without charge. therefor, carefully clean all paving and clean out all pits, pipes, chambers or conduits, and. shall tear down and remove all temporary structures built by ' him, and shall remove all rubbish of all kinds from any of the tracts or grounds which he had occupied, and shall leave them in first class condition. ' 009-YY. ACCEPTANCE OF THE WORK. It shall be the duty of the Engineer to determine when the work is complete and the contract fulfilled, and to recommend its acceptance by the Owner. 009-ZZ. I FINAL ESTIMATE AND PAYMENT. After official approval and acceptance of the work by the Owner, the Engineer shall be authorized to prepare a final 009-13 estimate of the work done under this contract and the value thereof. Such final estimate shall be submitted to the Owner within 10 days after its preparation has been authorized as aforesaid. And the Owner shall, within 30 days after said final estimate is made and certified, pay the entire sum so found to be due hereunder, after deducting all amounts to be kept and retained under any provisions of this contract. All prior estimates and payments shall be subject to correction in the final estimate and payment. But, in the absence of error or manifest mistakes, it is agreed that all estimates, on the certificate of the Engineer, when approved by the Owner, shall be conclusive evidence of the work done and materials furnished. Where part of the monies for construction of the project is being obtained by grant or loan from Federal agencies, such as often is the case, the final estimate will not be certified until the project has been approved by the responsible Federal agency, and the final payment will not be made until the monies are received from such agency. Consequently, there is under such circumstances the possibility and likelihood of a delay in making said final payment in excess of the customary 30 days as is the case when the Owner has all necessary monies on hand. 009 -AAA. RELEASE OF LIABILITY. No person, firm or corporation, other than the signer of this contract as Contractor, has any interest hereunder, and no claim shall be made or be valid, and neither the Owner nor any employees or agent thereof shall be liable or be held to pay any money, except as herein provided. The acceptance by the Contractor of the last payment shall operate as, and shall be, a release to the Owner and every officer and agent thereof, from all claims and liability to the Contractor for anything done or furnished for, or relative to the work, or for any act or neglect of the Owner or of any person relating to or affecting the work. 009 -BBB. CORRECTION OF WORK AFTER FINAL PAYMENT. Neither the final certificate nor payment nor any provision in the contract documents shall relieve the Contractor of responsibility for faulty materials or workmanship, and unless otherwise specified, he shall remedy any defects due thereto and pay for any damage to other work resulting therefrom, which shall appear within a period of one year from the date of substantial completion. The Owner shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the Engineer subject to arbitration. 009-14 aectlon Ulu S,.P E C IF IC A T I O:N S n r.. SANITARY SEWER SYSTEM REHABILITATION AND RECONSTRUCTION FAYETTEVILLE, ARKANSAS Plans No. Fy-116 Dated April 1983 010-A. SCOPE OF THE WORK. The work to be done under this contract is as shown on the Plans and provided for in these Specifications, and shall include the furnishing of all materials, equipment, tools and supplies and the performing of all labor in the construction of work generally as follows: The replacement of approximately 6,475 linear feet of sanitary sewer line, the plugging of sewer overflow lines, and the construction of approximately 8 main line tap repairs. Also included is the construction and/or rehabilitation of approximately 130 manholes and the construction and/or repair of asphaltic pavement, concrete curb and gutter, and concrete sidewalk. ' For line segments schedule to be replaced, unless ductile iron pipe or Vitrified clay pipe is specifically set out on the Plans and/or in the Proposal, the Contractor shall furnish and install either vitrified clay • pipe or acrylonitrile-butadiene-styrene (ABS) composite sewer pipe, at his option, of the size and at the locations shown on the Plans. 010-B. COMPLETION DATE AND LIQUIDATED DAMAGES. The Contractor shall ' complete the work provided for in these Specifications within ninety (90) calendar days from the effective date of the Notice to Proceed. Liquidated damages as provided in the contract shall be two hundred dollars ($200.00) per day for each calendar day of delay in completion beyond the time 'stipulated herein and provided in the contract. 010-C. SEQUENCE OF THE WORK. It is the intent of these Specifications ' that the new. sewer line segment shall be laid in the same trench and along the same alignment as the existing sewer line unless otherwise shown on the Plans or. directed by the Engineer. ' The Contractor shall be responsible for disconnecting existing service connections, removing and replacing the existing sewer line, air testing the new sewer line, reconnecting the existing service lines, and backfilling the ' sewer line, all within one calendar day for each line segment shown on the Plans. Furthermore, the Contractor has seven calendar days to complete cleanup on each individual line segment as set out in Section 900. ' Sewer lines will be included on partial payment estimates only when every item of work required to construct each individual sewer line segment has 1 010-1 been completed, including reconnection of existing services, trench backfill, cleanup, topsoiling, fertilizing, seeding and mulching. (Seeding, fertilizing and mulching shall only be done between the months of March through October.) When seeding, fertilizing and mulching cannot be completed (during the months of November through February), an additional 10 percent retainage on work under these bid items shall be withheld until completion. The Contractor shall also be responsible for providing bypass pumping as is necessary during the time of construction. The Contractor shall notify the City of Fayetteville, Arkansas, and all sewered customers affected by the construction one day in advance of beginning work on the proposed line segment. Prior to beginning work, the Contractor shall submit a schedule of proposed work which shows the number of construction crews to be utilized, and a proposed schedule for each crew indicating the order of work for that crew, subject to the approval of the Engineer. 010-D. SPECIAL PROVISIONS OF THE CONTRACT. This set of contract documents includes several provisions which are called to the particular attention of the Contractor. They include the following: 1. Insurance. Among the above referred to provisions certain bond and insurance requirements are set out. It should be noted that some of these provisions are clarified or superseded by provisions set out in the Instructions to Bidders. 2. Special Provisions of Arkansas Law. Attention is called to Sections 24 and 27 of the Instructions to Bidders, which point out the obligation of the Contractor to withhold state income taxes on wages paid and to comply with the provisions of Act 125 of the 1965 Arkansas Legislature regarding payment of certain taxes on material and equipment. 010-F. SAFETY AND HEALTH REGULATIONS. The provisions covering safety standards and accident prevention as set out in the General Conditions are particularly called to the attention of the Contractor. In order to protect the lives and health of his employees under the contract, the Contractor shall comply with all pertinent provisions of the "Manual of Accident Prevention in Construction" issued by the Associated General Contractors of America, Inc., and shall maintain an accurate record of all cases of death, occupational disease and injury requiring medical attention or causing loss of time from work arising out of and in the course of employment on work under the contract. The Department of Labor of the State of Arkansas refers to the Federal Register (OSHA Regulations) for the guidance of contractors and the protection of workmen and the public. The Contractor shall familiarize himself with the provisions of the Register and shall comply with the rules and regulations provided therein. 010-2 section uiu The Register requirements,are.enforceable by,the;Department of Labor, and it is the responsibility .. `Contractor''td''seie that they are carried out. The responsibility for the interpretation and implementation of the provisions of the Register does not rest with the Owner, the Engineer, or their representatives. The Contractor alone shall be responsible for the safety, efficiency and adequacy of his plant, appliances, and methods and for any damage which may result from their failure or their improper construction, maintenance or operation. Although the Engineer and his personnel may recognize safety hazards and in such case will require that changes be made to reduce or eliminate the hazards, the Engineer by such action does not take the responsibility as safety engineer for the Contractor. Neither does such action indicate that the Engineer or his personnel are trained, safety engineers. It means only that a specific safety hazard has been recognized in the ordinary course of engineering inspection of the technical aspects of the work being done and such hazard has been called to the attention of the Contractor. Any safety procedures initiated by the Engineer shall not be construed as supervision of the Contractor's work force, nor make him responsible for providing ,a safe place for the performance of the work by the Contractor or the Contractor's employees or those of the suppliers, his subcontractors, nor for access, visits, use, work, travel, or occupance by any person, as these responsibilities are covered under the provisions of the contract and the Contractor's insurance and performance bond and cannot be the responsibility of the Engineer. ' 010-F. QUALITY OF THE PLANS. The Plans have been made with care, but cannot be expected to be correct in every detail when some of the conditions to be encountered are underground. The Contractor shall work in close ' cooperation with the City operating personnel in locating underground lines in advance so as to reduce damage to the lines resulting in disruption of service and added cost to the Contractor. The Owner reserves the right to make normal changes in location, length, or grade of pipe as will facilitate construction, provide for better service, ' or reduce the construction costs to keep within the monies provided for this work. It is expected that the Contractor may find minor discrepancies as to ' dimensions or other details which might not fit the materials approved for construction. When such discrepancies or needed changes are found, the Engineer shall be notified immediately. If such items are of significant importance, they shall be presented to the Engineer in writing. Where the Plans provide for rock excavation and other general conditions, it is understood that this information is placed in the Plans and proposal for t general bidding information and as an aid to the Contractor. The placing of such information in no way obligates the Owner as to the correctness of this information. ' It is the express intent of these Plans and Specifications that the • Contractor has made his own investigation of conditions to be encountered, 010-3 and the filing of a bid hereunder constitutes the acceptance of this provision. 010-C. ELEVATION DATA. Elevations as shown are assumed elevations. 010-P. LANDS AND RIGHTS OF WAY. The work is to be constructed on property owned by the City of Fayetteville and on privately owned property. The City of Fayetteville will provide easements for work to be performed on private property. 010-I. PROTECTING AND REPLACING UTILITY SERVICES. In some instances the pipe will be installed under, alongside and over existing utility services. Much of the time these will be difficult to locate, and in some instances impractical to locate. The Contractor shall be responsible for locating and protecting or repairing and replacing such services. The various utility owners, the Owner (water mains and sewers), gas company (gas lines), telephone company (cable and conduits) and others not named will cooperate with the Contractor in helping locate the underground services, but cannot afford to keep men on the job full time. Where the Contractor cannot make adequate repairs, the various utilities will make repairs to all services, and such costs will be charged to the Contractor. The Contractor shall make arrangements for this service with the various utilities either before the bid is presented or before construction starts. The Plans do not indicate location of sewer services. The Contractor shall speedily repair all broken services and shall make sure that the line is clean and there are no obstructions or rough pipe left to catch waste material. The Plans show a portion of the line to be laid adjacent to power lines. It shall be the responsibility_ of the Contractor to make any arrangements with the power company for "tying off" poles. It also shall be the responsibility of the Contractor to take whatever steps are necessary to provide for the safety of the workmen and equipment when working in the vicinity of these power lines. 010-J. TRAFFIC CONTROL. Traffic control on state or federal highways shall be conducted and maintained as set forth in the "Manual on Uniform Traffic Control Devices" as published by the U. S. Department of Transportation, Federal Highway Administration. The following data sheets are intended as guidelines for typical sign dimensions and application for various types of installations. 010-K. OPEN SPECIFICATIONS. Where materials or equipment are specified by a trade name, it is not the intention of the Owner to discriminate against an equal product of another manufacturer, but rather to set a definite standard of quality or performance and to establish an equal basis for the evaluation of bids. Where the words "equivalent," "proper," or "equal to" are used, they shall be understood to mean that the thing 010 i It -'� �seei •� a k Eli QI a I II ; I —•fir— :II I i I I I I = I 1'11'1 = £l ii II I II I I I I I 1 ' O E T I i a-i II I I 1 u g• I I I I. I • • ' I Y Y • FI I J I _ . I Y .Y } I 1 j I =•Do } I e• I YD .'. Ta ZDY • • 2 a.D tr Jy• ' I { y I - • e (0 : Y; O Y 1 '•yi • �• I FJT C_ n91 D • Q I • 16� ^'f u •i Iiy • b Y Y :a8 . b •+: { i o BYO •• Y I • J -Se•7i e • . + y p I . i • b .. r I. • •\• [ 1 I: r • I I lvii - I I _ 1 II. •K•: .11111 • I I � i I I Iii I \`O • tij y � 1 • u 111111 I I Iii LH • II it i u —vi 1 I I •r16' III I n oio-s I Q Y ti Q O y 3 Q O'r • "s 6 [ -• Cc -a ' E 6 c:a a i I - - - • , : a . • :•o e . a = 2 as s. a= i a - - II , i S9e!•a'�• • .�i rFFieap: S. Un F TO S. a M 09- 1 . f II I N II o Y NY. a♦ �.N Y N{ YN Y I. V V V V V V • s - i S. _ . •jI Ni rI. f I I iIfl 1 ViV �y uu V Y •u ii sZ�. in / �-0F In II I c.JI : SQO _Q z -0 3 J:O 3 w_J=� / 3 v-, _w -p 010-6 Section 010 referred to shall be proper, the equivalent of, or equal to some things, in the opinion or judgment ofthe Engineer. Even though the words "or equal to" or other such expressions may be used in the Specifications in connection with a material, manufactured article, or process, the material, article, or process specifically designed shall be used, unless a substitute shall. be approved in writing by the Engineer; and the Engineer shall have the right to require the use of such specifically designated material, article, or process. The words "equal to" shall also mean that the cost to the Owner shall be no greater in extra concrete, piping, grading, etc., for items which are to be furnished at a unit price. In case basic changes in units are made in order to use equipment required because of unit changes, the Contractor shall furnish all necessary detailed drawings for the Engineer's approval. In addition to the above factors, the "or equal" shall also include the ability of the supplier to supervise, in certain instances, the construction of the work and the quality of his engineering organization and the ability to provide service after the works are complete.. Unless otherwise specified, all materials shall be the best of their respective kinds and shall in all cases be fully equal to approved samples. ■ 010-L. NOTICE TO PROCEED. After the contract bonds and insurance have been furnished to the Owner and the contract has been executed, the Engineer ' will issue a Notice to Proceed designating the date the work will begin. Such Notice to Proceed will be issued within thirty (30) days of the date of signing of the contract. By mutual agreement between the Engineer and ' Contractor, issuance of the Notice to Proceed may be delayed if there is a delay in obtaining materials, equipment or rights of way, or other factors beyond the control of the Contractor or Owner. 010-M. PAYMENT FOR EXTRA WORK. Whenever work is required which is not provided for under these Plans, Specifications and contract, or work which is not in keeping with the general work for which there are unit prices, the ' Contractor shall perform the work as directed by the Engineer and shall receive as compensation therefor the total cost of the work based upon the actual Contractor's expense, plus 15 percent. for overhead and profit. Such expense shall include insurance and bonds, but shall not include overhead of ' any other nature. No extra work shall be performed except upon the written order of the Engineer.. ' 010-N. CONTINUING RESPONSIBILITY OF CONTRACTOR. The Contractor shall be responsible for faulty materials and workmanship; and, unless otherwise. specified, he shall remedy any defects due thereto and pay for any damage to I other work resulting therefrom which shall appear within a period of one year from date of substantial completion. The Owner shall give notice of observed defects with reasonable promptness. All questions arising under this article shall be decided by the Engineer, subject to arbitration. 1 1 010-7 u.. V. l lv\l V11 GENERAL During the period from July 1977 through October 1978, a Sewer System Evaluation Survey was performed for the City of Fayetteville, Arkansas. The conclusion of the above referenced survey demonstrated the existence of excessive infiltration and inflow. Under this contract, the Contractor shall rehabilitate probable inflow sources in six of the original twenty designated minisystems in the City of Fayetteville. Work shall be performed in Minisystems 2, 4, 7, 8, 11 and 16. This work shall be considered a demonstration project to determine the effectiveness of inflow removal. Consequently, flow monitoring will be conducted prior to reconstruction and/or rehabilitation and immediately following such reconstruction and/or rehabilitation. The Contractor is advised that the City of Fayetteville will also be conducting sewer system rehabilitation in these areas and the Contractor under this contract shall, cooperate to the fullest with City forces in the area. A copy of the Sewer System Evaluation Survey and attendant data shall be made available to qualified bidders for review at the locations set out in the Advertisement for Bids. Additionally, a copy of relevant sections of the Fayetteville Sewer System Evaluation Survey and attendant data shall be made available to the Contractor during the performance of this contract. 011-A. FORMAT. A table listing the proposed general rehabilitation methods to be performed under this project is set out in Table 011-A below. The rehabilitation code listed for each method is the basis of reference for the Plans and these Specifications. Also listed in this table are the approximate number of cost-effective occurrences to be rehabilitated under this contract. ' TABLE 011-A Cost- ' Rehab. Effective Code Rehabilitation Method Occurrences 1 1 Plug Overflow at Exit 2 8 Replace Section or Entire Main Line 17 • 18 Excavate & Repair Faulty Main Line Tap under Pavement 7 ' 19 Excavate & Repair Faulty Main Line Tap under Easement 2 • 23 Realign and Grout Casting, MH in Street 3 I. 24 Realign and Grout Casting, MH in Easement 4 25 Regrout Casting to Cone 15 I Cost - Rehab, Effective Code Rehabilitation Method Occurrences 27 Clean MH Walls, Fill Small Cracks, & Waterproof Walls 28 28 Clean MH Walls, Plug Large Cracks, & Waterproof Walls 11 29 Clean MH Walls, Plug Large Cracks, Plaster & Waterproof Walls 7 30 Excavate MH in Easement & Repair Line Connection from Outside 3 31 Excavate MH in Street & Repair Line Connection from Outside 5 32 Replace MH 1 33 Raise MH to Street Level, 0-2" 4 34 Raise MH to Street Level, 2-18" 5 35 Raise MH to Street Level, 18" Up 0 36 Raise MH to Grade in Easement, 0-12" 2 37 Raise MH to Grade in Easement, 12" Up 1 38 Raise MH above Grade in Easement 42 40 Plug Vent Holes & Raise Casting to Street Level 1 011-2 QC..l1Vll VYV CLEARING RIGHTS OF WAY, CUTTING AND REPAIRING*FENCES 040-A. CLEARING RIGHTS OF WAY. Parts of construction are indicated on the Plans as being through lawns, gardens, brush, timbered areas and fields of tall grass. Clearing of these areas shall be in conformance with the Specifications hereinafter set out depending upon the area of work. There is not an extra pay item for the clearing of rights of way or for the disposing of brush, timber or other debris resulting from the clearing operation. 1. Brush, Timbered Areas, Fields. Where construction is indicated on the Plans as being through brush, timbered areas, and fields of tall grass, the Engineer shall stake the general location of the rights of way. The Contractor shall clear the rights of way of brush and other debris and do such right of way construction as is necessary to provide a relatively level working area. Upon completion of this work, the Engineer will then provide line and grade stakes required for construction. In clearing right of way the Contractor shall remove only those trees necessary for the construction of the line. Where sewer lines are to be constructed in close proximity with shade trees or other fine trees, the Contractor will be expected to work near the trees without removing or damaging them and shall remove only such trees as are flagged by the Engineer. All brush, timber and other debris required to be removed from the construction of the work shall be hauled from the site and disposed of at the option of the Contractor. A portion of the work is across private property in which livestock is at large. It is the responsibility of the Contractor to see that the livestock is kept in the original pastures. It has been found that wilted wild cherry leaves are poisonous to livestock. Consequently, wherever wild cherry is removed or damaged, the branches shall be removed immediately from the site of the work, and shall be burned or disposed of so that it will be impossible for the livestock to have access to them. 2. Lawns, Gardens and Other Well -Kept Areas. Where construction is shown on the Plans as being through lawns, gardens, or other well -kept areas, the Engineer shall stake the general location of the rights of way, and shall provide line and grade stakes. The Contractor shall then clear any debris from the rights of way. All shrubbery, small trees (less than 4 inches in diameter), and other items of landscape shall either be protected or shall be replaced at the Contractor's expense. All limbs and other debris requiring removal shall be hauled from the site and disposed of at the option of the Contractor. 3. Fences - Cutting and Repairing. The Plans show fences to be crossed during the course of construction. Prior to clearing the right of way, the Contractor shall install a braced post assembly on each side of the right of 040-1 way so that when the fence is cut, the tension on the fence is not reduced. He shall then construct temporary gates so as to maintain livestock in the original pasture during construction. After all construction, including cleanup, is complete, the fences shall be rebuilt to equal or better than original condition, using new posts and wire. The wire used in rebuilding of the openings shall be of the same general type of the existing fences. Posts shall be pressure treated pine, having a minimum top diameter of 4 inches. Where removal, replacement or repair of required, the fence shall be repaired original condition, and be of the size Contractor shall retain a professional There is not an extra pay item for the i chain link, wooden, or other fences is or rebuilt to equal or better than and type of the existing fence. The fence company to perform this work. emoval or repair of fencing. C 040-2 JecLlon UJV Storage & Handling STORAGE AND HANDLING M OF MATERIALS 050-A. GENERAL. The Contractor shall be responsible for all material furnished by him and shall replace at his own expense all such material found defective in manufacture or damaged in handling after delivery by the manufacturer. This shall include the furnishing of all material and labor required for the replacement of installed material discovered defective prior to the final acceptance of the work. 050-B. STORAGE OF MATERIALS. The Contractor shall be respbnsible for the safe storage of material furnished by or to him and accepted by him, and intended for the work, until it has been incorporated in the completed project. The interior of all pipe, fittings and other accessories shall be kept free from dirt and foreign matter at all times. Valves and hydrants shall be drained and stored in a manner that will protect them from damage by freezing. All materials shall be stored in strict conformance to the manufacturer's'recommendations. 050-C. HANDLING OF MATERIALS. All materials furnished by the Contractor shall be delivered and distributed at the site by the Contractor. Pipe, fittings, valves, hydrants, and accessories shall be loaded and unloaded by lifting with hoists or skidding so as to avoid shock or damage. Under no circumstances shall such materials be dropped. Pipe handled on skidways shall not be skidded or rolled against pipe already on the ground. In distributing the material at the site of the work, each piece shall be unloaded opposite or near the place where it is to be laid in the trench. Care of Pipe Coating and Lining. Pipe shall be so handled that the coating and lining will not be damaged. However, if any part of the coating or lining is damaged, the repair shall be made by the Contractor at his expense in a manner satisfactory to the Engineer. 050-1 Section 090 Bypass Pumping BYPASS PUMPING 090-A. GENERAL. The work to be included in this section of the Specifications consists of furnishing all pumps, conduits, labor, supervision, equipment, appliances, and materials necessary to perform all operations in connection with bypass pumping of sewage flows, to divert the flow of sewage around the line section(s), or manholes .in which work or testing is to be performed. 090-B. PUMPING CAPACITY. The bypass system shall be of sufficient capacity to handle existing flows plus additional flow that may occur during periods of a rainstorm. The Contractor will be responsible for furnishing the necessary labor and supervision to set up and operate the pumping and bypassing system. All engines shall be equipped in a manner to keep the pump noise to a minimum. 090-C. BYPASS. PUMPING. On all line segments where parallel line segment construction is not indicated, it shall be the responsibility of the Contractor to provide bypass pumping of raw sewage from one manhole to another manhole in order to eliminate flow through a section of sewer pipe and to prevent back-up and overflow of sewage. The Contractor shall be responsible for plugging off and pumping down the sewer lines in the designated areas, and to correct any problems which may arise as a result of the pumping operations. The sewer line shall be pumped down from an upstream manhole to a downstream manhole using trailer mounted pumps of sufficient size and capacity as set out in Section 090-B above. Such pumping operations shall continue until such time as the sewer line replacement is successfully completed, the new sewer line air tested, and all service lines reconnected. ' 090-D. FLOW CONTROL PRECAUTIONS. Whenever flows in a sewer line are blocked, plugged or bypassed, it shall be the responsibility of the Contractor to take sufficient precautions to protect the sewer lines from damage that might be inflicted by excessive sewer surcharging. Further, precautions must be taken to ensure that sewer flow control operations do not cause flooding or damage to public or private property being served by the sewers involved. ' 090-E. PAYMENT. There shall be no separate pay item for bypass pumping. All bypass pumping shall be considered as subsidiary to pipe laying. 090-1 Section U95 Surface Removal SURFACE REMOVAL 095-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all materials, labor, equipment, tools, and incidentals necessary for removing surfaces within the limits of lawns, gardens, mowed, cultivated, or other well -kept areas or within the limits of any paved or unpaved driving surface, curb and gutter, or sidewalk. This specification does not apply to state or interstate highways, or driving surfaces, within railroad rights of way unless otherwise directed by the Engineer. 095-B. ALLOWABLE REMOVAL. In all areas where sewer lines, manholes, and other appurtenances are to be constructed and/or repaired, the surface shall be removed prior to excavating the trench. There is no pay item for surface removal and surface removal shall be considered part of trench excavation. The allowable limits of removal are dependent upon the type of area in or through which construction occurs, and are set out below. No payment for surface repair will be made outside the width of allowable removal. 1. Lawns, Gardens, Mowed or Cultivated Areas, and Other Well -Kept Areas. In these areas, the Contractor shall excavate the top 6 inches of topsoil from the ditch line and store such along the ditch line so that it does not become mixed with the remaining excavation. The width of allowable surface removal shall be the standard trench width as shown on the detail sheet of the Plans, or, the depth of the trench to the existing sewer flow line at its deepest point, whichever is greater. The length of ground cover removed for the installation of pipe, fittings, manholes, or other appurtenances shall be the linear dimension of such structure plus 6 inches. 2. Wooded and Rocky Areas. In wooded or rocky areas the ground cover shall be removed as set out in Section 095-B.1 above except that the Contractor is not required to separate and store the top 6 inches of topsoil along the ditch line. 3. Driving Surfaces. Excavation within the limits of any driving surface, including paved and gravel streets or roads, driveways or parking areas shall be in accordance with the following specifications. The Contractor shall remove pavement and road surface as a part of the trench. excavation, and the amount removed shall depend upon the width of trench specified for the, installation of pipe, and the width and length of pavement area required to be removed for the installation of pipe, fittings, manholes, and other appurtenances. The Contractor shall use such methods, either drilling, chipping or ' sawing as will assure the breaking of the pavement along straight lines. The face of the remaining pavement shall be approximately vertical. Driving surface pavement and road surfaces shall be removed to the 1 095-1 Surface Removal dimensions set out below depending upon the type of driving surface to be ' removed. a. Asphaltic Pavement Removal. Asphaltic pavements shall be removed in I accordance with the dimensions set out below. (1) Removal of Pavement Around Existing Manhole Rings and Lids. A square cut shall be made in the pavement within an area extending 18 inches each side of the manhole ring. The pavement and underlying base and/or subgrade material shall then be removed to the depth necessary to expose the ring and lid. This material shall be hauled from the site and disposed of at the option of the Contractor. (2) Removal of Pavement Around Manholes. Where an existing manhole is to be removed and/or a new manhole is to be constructed, a square cut shall be made in the pavement within an area extending 18 inches each side of the outside manhole wall. The pavement and underlying material shall be removed to the depth necessary for the manhole removal and/or construction. (3) Removal of Pavement for Sewer Line Construction. The width of asphaltic pavement removed along the normal trench line for the removal and/or installation of pipe, fittings, or other appurtenances shall be the standard trench width as defined on the detail sheet of the Plans plus 18 inches each side of the standard trench. The length of the asphaltic pavement to be removed for the installation of pipe, fittings, or other appurtenances shall be the linear dimension of such structure plus 6 inches. b. Concrete Pavement Removal. Concrete pavements shall be removed in accordance with the dimensions set out below. (1) Removal of Pavement Around Existing Manhole Rings and Lids. A square cut shall be made in the concrete pavement within an area extending 12 inches each side of the manhole ring. The pavement and underlying base and/or subgrade material shall be removed to the depth necessary to expose the ring and lid. The material shall be hauled from the site and disposed of at the option of the Contractor. (2) Removal of Pavement Around Manholes. Where an existing manhole is to be removed and/or a new manhole is to be constructed, a square cut shall be made in the concrete pavement within an area extending 12 inches each side of the outside manhole wall. The pavement and underlying material shall be removed to the depth necessary for the manhole removal and/or construction. (3) Removal of Pavement for Sewer Line Construction. The width of concrete pavement removed along the normal trench line for the I I 095-2 JCLLSVll VJJ Surface Removal removal and/or installation of pipe, fittings, or other . y.s appurtenancest�shall be the normall trench width as defined on the detail sheet of the Plans plus 12 inches on each side of the trench. The length of the concrete pavement to be removed for the installation•of pipe, fittings, or other appurtenances shall be the linear dimension of such structure plus 6 inches. c: Unpaved Driving Surfaces. The width and length of unpaved driving surface removal shall be the same as that set out for asphaltic pavement removal set out in Section 095-B.3.a of these Specifications. . 4. Sidewalk and Curb and Gutter Removal. Sidewalk and curb and gutter shall only be removed as shown on the Plans or at the direction of the Engineer. The width of concrete removed when so directed shall be the standard trench width as shown on the plans plus 18 inches each side of the trench. 5. Additional Surface Removal. Wherever, in the opinion of the Engineer, existing conditions make it necessary or advisable to remove additional surfaces, the Contractor shall remove it as directed by the Engineer. No extra compensation: will be allowed for the extra surface removal. However, additional payment will be made at the unit price bid for the appropriate surface repair/replacement item as set out under the Methods of Measurement and Payment section of these Specifications. However, if the Contractor removes or damages pavements beyond the limits specified above without approval of the Engineer, such surfaces shall be replaced or repaired at the expense of the Contractor. 095-3 Section 099 REPLACEMENT OF LINE SEGMENTS 099-A. GENERAL. The location and grade of sewer line segments to be replaced are shown on the Plans. Unless ductile iron pipe or vitrified clay pipe is specifically set out on the Plans and/or in the Proposal, the contractor shall furnish and install either vitrified clay pipe or acrylonitrile-butadiene-styrene (ABS) composite sewer pipe, at his option, of the size and at the locations shown on the Plans, It is the intent of these Specifications that the new sewer line segment shall be laid in the same trench and along the same alignment as the existing sewer line unless otherwise shown on the Plans or directed by the Engineer. The Contractor shall be responsible for disconnecting existing service connections, removing and replacing the existing sewer line, air testing the new sewer line, reconnecting the existing service lines, and backfilling the sewer line, all within one calendar day for. each line segment shown on the Plans. Furthermore, the Contractor has seven calendar days to complete cleanup on each individual line segment as set out in Section 900. Sewer lines will be included on partial payment estimates only when every item of work required to construct each individual sewer line segment has been completed, including reconnection of existing services, trench backfill, cleanup, topsoiling, fertilizing, seeding and mulching. (Seeding, fertilizing and mulching shall only be done between the months of March through October.) When seeding, fertilizing and mulching cannot be completed (during the months of November through February), an additional 10 percent retainage on work under these bid items shall be withheld until completion. The Contractor shall also be responsible for providing bypass pumping as is necessary during the time of construction. The Contractor shall notify the City of Fayetteville, Arkansas, and all sewered customers affected by the construction, one day in advance of beginning work on the proposed line segment. 099-B. MATERIALS AND CONSTRUCTION. Materials and construction shall be in accordance with the Pipe Specifications, dependent upon the type of pipe used. 099-1 • Section 100 VCP Sewer VITRIFIED CLAY SEWER PIPE AND VITRIFIED CLAY SEWER PIPE FITTINGS 100-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all labor, equipment, tools, supplies, and incidentals necessary for the construction of vitrified clay pipe sanitary sewer lines. The work shall include every item of construction necessary fora complete and acceptable installation as shown on the Plans and hereinafter specified. 100-B. MATERIALS. 1. Vitrified Clay Sewer Pipe. All vitrified clay sewer pipe shall conform to the Extra Strength Provisions of ASTM Designation C-700, latest revision. 2. Vitrified Clay Sewer Pipe Fittings. All vitrified clay sewer pipe fittings shall conform to the Extra Strength Provisions of ASTM Designation C-700, latest revision. 3. Factory -Installed Joints. All vitrified clay pipe and vitrified clay pipe fittings shall have factory installed joints as follows: a. Vitrified clay pipe joints 18 inches and smaller shall conform to the requirements of ASTM Standard Specification for Compression Coupling for Vitrified Clay Plain -End Pipe, ASTM Designation C-425,, latest revision. b. Vitrified clay pipe joints 21 inches and larger shall conform to the requirements of ASTM Standard Specifications for Compression Joints for Vitrified Clay Bell and Spigot Pipe, ASTM Designation C-425, latest revision. 4. Vitrified Clay Pipe Joint Lubricant. Joint lubricant shall be provided by the pipe manufacturer. 5. Vitrified Clay Pipe Bedding Gravel. Gravel used for bedding of vitrified clay pipe and vitrified clay pipe fittings shall be crushed limestone, Class SB-2, as defined in Section 306 of the 1978 Edition of the Arkansas State Highway Department Specifications. The crushed limestone supplier shall submit certificates stating that the materials provided are in accordance with these Specifications. NOTE: There is no special pay item for vitrified clay pipe bedding gravel. This item shall be considered subsidiary to the vitrified clay pipe. 6. Crushed Stone Trench Backfill. Crushed limestone trench backfill (where required) shall be Class SB-2, as defined in Section 306 of the 1978 Edition of the Arkansas State Highway -Department Specifications. The crushed limestone supplier shall submit certificates stating that the materials provided are inaccordance with these Specifications. NOTE: This item shall be paid for at the unit price bid in the proposal, and as set out in Methods of Measurement and Payment. 100-1 VCP Sewer 7. Independent Laboratory Inspection. All vitrified clay pipe and vitrified clay pipe fittings furnished and installed on this project shall be inspected and tested by the manufacturer. The manufacturer shall furnish to the Engineer, prior to delivery, certificates stating that all pipe will be manufactured in compliance with these Specifications. The certificate shall also fully describe the pipes proposed to be furnished. If evidence appears that all provisions of the applicable ASTM Standards have not been complied with after the pipe has been delivered, the Owner will require such field testing and sampling as necessary for certified statements of compliance to the provisions of said standards to be furnished by an approved independent laboratory. The cost for the testing and sampling or job delay will be the responsibility of the pipe supplier if the pipe is not in compliance. The Owner will pay the cost of the testing and sampling if the pipe is in compliance with the Specifications; however, the Owner will not be responsible for job delay. The independent laboratory shall be one which may be chosen by the pipe manufacturer and approved by the Engineer. 100-C. VITRIFIED CLAY PIPE SEWER LINE CONSTRUCTION. I. Installing Vitrified Clay Pipe. Vitrified clay pipe and vitrified clay pipe fittings shall be installed in conformance with the "Standard Recommended Practice for Installing Vitrified Clay Pipe Lines," ASTM Designation C12, latest revision, and in conformance with the Specifications hereinafter set out. 2. Construction Sequence. Construction of sanitary sewers shall begin at the low point of the line and continue in orderly succession throughout the work. Any deviation from this procedure shall be made only with the specific approval of the Engineer, and only after the right of way has been cleared and the entire section staked and all elevations carefully checked by the Engineer. Unless specifically approved by the Engineer, appurtenances such as fittings, manholes, etc. shall be constructed as the work progresses. 3. Requirements Preparatory to Trench Excavation. In all areas where sewer lines, manholes, or other appurtenances are to be constructed and/or repaired, the existing surface shall be removed prior to excavating the trench. There is no pay item for these requirements and shall be considered part of the trench excavation. These requirements are dependent upon the type of area in which sewer line construction occurs and are set out in Section 095 of these Specifications. 4. Excavation and Prepz the pipe can be laid excavated only so Section 100.C.4.c of and drained that the is essential that conducted to natural tration of Trench. The trench shall be dug so that to the alignment and depth required, and it shall be far in advance of pipe laying as set out in these Specifications. The trench shall be so braced workmen may work therein safely and efficiently. It the discharge of any trench dewatering pumps be drainage channels, drains or sewers. 100-2 Section 100 VCP Sewer a. Trench Depth and' -Pipe Bedding. The tr n ch shall be excavated to at least, 4 inches and`•not more than 6 "inches below the established grade as shown on the Plans. The vitrified clay pipe shall then be bedded in a crushed limestone bedding as set out in Section 100—B.5 of these Specifications. The pipe shall be bedded from a point 4 inches below the bottom of the pipe barrel to the pipe springline by the full width of the excavated ditch. The bedding shall be placed and shaped so as to provide an uniform and continuous bearing support for the pipe at every point along the pipe barrel. All overexcavation below the pipe shall be backfilled with pipe bedding material at the Contractor's expense. The additional material required will be placed in 3 inch lifts and hand or machine tamped. This procedure will be repeated until the established grade has been reached. b. Width. The excavated sewer trench shall not exceed the width as shown on the standard detail sheet of the Plans at any point from the trench bottom to a point 12 inches above the top of the pipe barrel. If the Contractor overexcavates the trench, he shall provide additional pipe bedding gravel or concrete as necessary to prevent crushing of the sewer pipe due to excessive earth loads. All additional bedding material or concrete required shall be furnished at the Contractor's expense. c. Length. The Engineer shall have the right to limit the amount of trench excavated in advance of laying the pipe. In general, such excavation shall not exceed 300 feet, and trench excavated to grade shall not exceed 150 feet. Every trench in rock shall be fully opened at least 50 feet in ' advance of the place where pipe is being laid or masonry work is in process. ' 5. Excavation in Poor Soil and Refilling to Grade. Where the bottom of the trench at subgrade is found to be. unstable or to include ashes, cinders, all types of refuse, vegetable •or other organic materials, or large I. pieces of fragments of inorganic material which in the judgment of the Engineer should be removed, the Contractor shall excavate and remove such unsuitable material to the width and depth ordered by the Engineer. Before the pipe is laid, the subgrade shall be made by backfilling with I. trench backfill gravel as set out in Section 100-B.6 of the Specifications, in 3 inch uncompacted layers. The layers shall be hand or machine tamped as directed by the Engineer so as to provide a uniform ' and continuous bearing and support for the pipe at all points along the pipelength. Payment will be made for the additional trench backfill required in accordance with the Method of Measurement and Payment Section of these Specifications. However, no additional compensation will be made to the Contractor for the additional excavation. • 6. Bracing and Shoring. The sides of any excavation, when deemed necessary, 'shall be properly supported with bracing, shoring or sheeting as the need 100-3 PCP Sewer may be. Such bracing and shoring shall be withdrawn as the work ' progresses. In case the excavation is close enough to buildings or other foundations as to endanger their stability by the removing of such bracings, then they shall be made secure and left in place, and the sewer trench backfilled and thoroughly tamped with the bracing in place. The Contractor will not be paid for such bracing, sheeting, or shoring whether it is withdrawn or left in the trench. 7. Removal of Water and Muck. The Contractor shall provide sufficient pumps and other necessary equipment to keep the trench free of water which may accumulate. If the bottom of the trench becomes soft and muddy, the Contractor shall remove all such soft material and replace it with dry loam, sand, or crushed limestone bedding gravel at his own expense. ' Under no conditions will vitrified clay pipe sewer be laid in a trench that has not been properly dewatered. 8. Laying Vitrified Clay Pipe Sewers - Factory Jointed Pipe. Vitrified clay sewer pipe shall be laid on a firm bed, as previously specified, in perfect conformity with lines and levels given. The pipe shall be laid with even bearing on the bottom of the trench, which shall be shaped and prepared to conform to the form of pipe. Niches of sufficient dimensions shall be cut in the bottom of the trench to give perfect clearance to the sleeve or bell end of the pipe, but no larger than is necessary to make a proper joint. In jointing vitrified clay pipe, the mating surfaces shall be wiped free of dust, dirt, gravel, or other foreign materials prior to the application of the lubricant. The vitrified clay pipe shall be connected by first brushing upon the mating surfaces the proper lubricant as recommended by the pipe manufacturer. The spigot end shall then be centered on grade into the bell end of the last downstream clay pipe length and shoved "home" and properly seated with the application of a moderate force by a pry or lever device. To protect the pipe and coupling when using a pry bar, a timber fulcrum shall be inserted into the coupling end of the pipe. The timber fulcrum shall extend a minimum of 1/2 inch past the end of the pipe. The coupling end of the pipe in all cases shall be laid toward the high end of the sewer. a. Connections to New Manholes. Where manholes are to be constructed over newly constructed line segments, or at the ends of newly constructed vitrified clay pipe line segments, a vitrified clay pipe nipple or short stub with flexible compression joints shall be used at the manhole walls. b. Connections to Existing Manholes and Pipe Sewers. Connections to existing manholes and pipe sewers (main or service sewers) shall be made in conformance with Section 100-C.14 of these Specifications. 9. Pipe Protection Cover and Backfill. Pipe protection cover and backfill shall be placed in accordance with Section 146 of these Specifications. 100-4 Section 100 VCP Sewer N�. 10. Cleanup. Cleanup shall be in accox Specifications. 11. Infiltration. After the contract is infiltration, or pipe leakage, for new exceed 200 gallons per day per mile of dance♦3'with Section 900 of these completed and the ditch settled, sewer line construction, shall not pipe per inch of pipe diameter. If infiltration or leakage exceeds this amount, the Contractor shall make such repairs as are necessary, to bring infiltration or leakage within specified limits. The Contractor shall test the line by blocking off the various sections of pipe, filling the line with water and measuring the leakage. 12. Testing. Vitrified, clay pipe sewer lines shall be air tested in accordance with Section 190 of these Specifications with the following exception. Any line segment on which only a partial replacement has been performed shall not be air tested. 13. Replacement and Repair of Driving Surfaces, Sidewalks, curb and Gutter. Replacement and repair of driving surfaces, sidewalks, and curb and gutter shall be made in accordance with Section 300 of these Specifications. I. 14. Special Connections to Existing Manholes and Existing Pipe Sewers. Where manholes are to• be constructed over or at the end of the newly constructed vitrified clay pipe sewers, such connections shall be made in ' accordance with Section 100-C.8.a of these Specifications. Where an entire line segment is to be replaced between existing manholes, and no new manhole construction is indicated on the Plans, the connections to I existing manholes or pipe sewers shall be made in conformance with the following Specifications. All work shall be in a workmanlike manner so as not to damage any other.structures involved. I a. Connection of Newly Constructed Sewer Lines to 'Existing Manholes. Unless otherwise directed by the Engineer, connections of newly constructed sewer lines to existing manholes shall be made at the ' first pipe joint outside the manhole wall, and shall be dependent upon the condition of that joint. After excavation, if the joint is determined by the Engineer to be sound and usable, the existing bell -end gasket shall be removed from the pipe and disposed of by ' the Contractor. The pipe shall be thoroughly cleaned inside for a distance of one foot up the existing sewer line and a new pipe gasket of the appropriate diameter installed. The new pipe sewer I. shall then be installed according to the line and grade as shown on the Plans and in accordance with Sections 100-C.1 and 100-C.8 of these Specifications. If the first pipe joint outside the manhole wall is determined by the Engineer to be partially usable, the Contractor, at his option, may use either of the methods set out below to connect newly constructedsewer lines to existing manholes. 100-5 VC'.L IL lyy VCP Sewer If the first pipe joint outside the manhole wall is determined by the Engineer to be totally unusable, a connection through the manhole wall shall be made as set out in 14.a.(2) below. (1) Use of Couplings. The Contractor may use the proper straight, transition, or other coupling of the appropriate diameter(s) to connect the existing sewer line to the newly constructed sewer line. The coupling shall be located so that all existing pipe between the coupling and the manhole is sound and free from defects. The Contractor will be required to cut the existing pipe joint back to a point so the remainder of the pipe is fit and usable. All couplings shall be manufactured by the pipe manufacturer and made specifically for the type of pipe connection being made, or shall be Fernco pipe connectors, or equal. All couplings or connectors shall be installed in accordance with the manufacturer's recommendations. (2) Connections Through Manhole Walls. If couplings are not used, the Contractor shall make a tie to he existing manhole by drilling, chipping or jack -hammering a hole of sufficient diameter for the installation of the pipe sewer in the existing manhole wall. Unless otherwise shown on the Plans, the pipe sewer shall be installed at the same invert elevation as the existing pipe. A vitrified clay pipe nipple or short stub with flexible compression joints shall be used at the manhole wall. After the pipe is installed the manhole -to -pipe connection shall be repaired using a non -shrink grout. The repair shall be watertight. Any damage to the manhole caused during the connection construction shall be repaired by the Contractor at his expense. b. Pipe to Pipe Connections. The Plans show the location of line segments to be replaced, where the line segment to be replaced is a partial replacement and does not begin and terminate at manholes; proper straight, transition, or other couplings as provided by the pipe manufacturer, or as manufactured by Fernco, or equal, shall be used to join the ends of the newly constructed line segment to the existing sewer line. All pipe couplings or connectors shall be installed in accordance with the manufacturer's recommendations. 15. Sewer Service Reconnections. All existing service lines disturbed or broken during the construction of the new sanitary sewer lines shall he reconnected to the newly constructed sewer line after the sewer line has been air tested. During construction, sewer service ties or wves shall be placed on the downstream side of the existing sewer service line to make the service connection as shown on the Plans and hereinafter specified. Tapping the 100-6 Section 100 VCP Sewer newly constructed sewer line shall only be allowed at the direction of the Engineer. After air testing, the sewer service lines shall be reconnected as shown on the Plans, according to the type of main pipe line, and size and type of service line. All new service lines installed shall have a minimum diameter of 4 inches. If the existing service line has a diameter larger than 4 inches, the new service line shall have a diameter equal to that of the existing service line. the Contractor shall be responsible for providing all couplings and fittings necessary for transition from one pipe type or size to another type or size of pipe. All couplings shall be manufactured by the pipe manufacturer and made specifically for the type of pipe connection being made, or shall be Fernco pipe connectors, or equal. All couplings or connectors shall be installed, in accordance with the manufacturer's recommendations. Ii 100-7 Section 110 DIP Sewer DUCTILE IRON SEWER PIPE AND DUCTILE IRON SEWER PIPE FITTINGS 110-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all materials, labor, equipment, tools, supplies, and incidentals necessary for the construction of ductile iron pipe sanitary sewer lines. The work shall include every item of construction necessary for a complete and acceptable installation as shown on the Plans and hereinafter specified. 110-B. MATERIALS. 1. Ductile Iron Pipe. All ductile iron pipe shall conform to the requirements of the "Standard Specification for Ductile Iron Gravity Sewer Pipe" ASTM A 746, latest revision, and shall be thickness Class 50, unless otherwise shown on the Plans. 2. Ductile Iron Pipe Fittings. All fittings shall be ductile iron fittings ' and shall conform to the requirements of AWWA C110, latest revision. All fittings shall have a minimum pressure rating of 150 pounds per square inch unless otherwise shown on the Plans. • 3. Ductile Iron Pipe Joints. All ductile iron pipe and ductile iron pipe • fittings shall have rubber gasket joints in conformance with ANSI/AWWA C111/A-21.11, latest revision, for either push on joints or mechanical joints. 4. Cement Mortar Lining. All ductile iron pipe and ductile iron pipe ' fittings shall have a standard thickness cement mortar lining in conformance to ANSI/AWWA C104/A-21.4. 5. Outside Coating. All ductile iron pipe shall have an outside coating. I The coating shall be a bituminous coating approximately 1 mil thick. The coating shall be factory applied to the outside of all pipe and fittings. The finished coating shall be continuous, smooth, neither brittle when exposed to the cold, nor sticky when exposed to the sun, and shall be strongly adherent to the pipe or fitting. 6. Ductile Iron Pipe Joint Lubricant. Joint lubricant shall be provided by Ithe pipe manufacturer. 7. Ductile Iron Pipe Bedding Gravel. No fl -2 pipe bedding gravel shall be ' required except for driving surfaces and curb and gutter crossings (see Section 110-C.4.a of these Specifications). Gravel used for bedding ductile iron pipe at driving surfaces and curb and gutter crossings shall ' be crushed limestone, Class SB-2, as defined in Section 306 of the 1978 Edition of the Arkansas State Highway Department Specifications. The crushed limestone supplier shall submit certificates stating that the materials provided are in conformance with these Specifications. NOTE: ' There is no special pay item for ductile iron pipe bedding gravel. This item shall be considered subsidiary to the ductile iron pipe. JCCl1V11 11V DIP Sewer 8. Crushed Stone Trench Backfill. Crushed limestone trench backfill (where required - see Section 110-C.5 of these Specifications) shall be Class SB-2, as defined in Section 306 of the 1978 Edition of the Arkansas State Highway Department Specifications. The crushed limestone supplier shall submit certificates stating that the materials provided are in conformance with these Specifications. NOTE: This item shall be paid for at the unit price bid in the proposal, and as set out in Methods of Measurement and Payment. 9. Independent Laboratory Inspection. All ductile iron pipe and ductile iron pipe fittings furnished and installed on this project shall be inspected and tested by the manufacturer. The manufacturer shall furnish to the Engineer, prior to delivery, certificates stating that all pipe will be manufactured in compliance with these Specifications. The certificate shall also fully describe the pipes proposed to be furnished. If evidence appears that all provisions of the applicable ASTM Standards have not been complied with after the pipe has been delivered, the Owner will require such field testing and sampling as necessary for certified statements of compliance to the provisions of said standards to be furnished by an approved independent laboratory. The cost for the testing and sampling or job delay will be the responsibility of the pipe supplier if the pipe is not in compliance. The Owner will pay the cost of the testing and sampling if the pipe is in compliance with the Specifications; however, the Owner will not be responsible for job delay. The independent laboratory shall be one which may be chosen by the pipe manufacturer and approved by the Engineer. 110-C. DUCTILE IRON PIPE SEWER LINE CONSTRUCTION. 1. Installing Ductile Iron Pipe. Ductile iron pipe and ductile iron pipe fittings shall he installed in conformance with the recommendations of AWWA C600, latest revision, and in conformance with the Specifications hereinafter set out. 2. Construction Sequence. Construction of sanitary sewers shall begin at the low point of the line and continue in orderly succession throughout the work. Any deviation from this procedure shall be made only with the specific approval of the Engineer, and only after the right of way has been cleared and the entire section staked and all elevations carefully checked by the Engineer. Unless specifically approved by the Engineer, appurtenances such as fittings, manholes, etc. shall be constructed as the work progresses. 3. Requirements Preparatory to Trench Excavation. In all areas where sewer lines, manholes, or other appurtenances are to be constructed and/or repaired, the existing surface shall be removed prior to excavating the trench. There is no pay item for these requirements and shall he considered part of the trench excavation. These requirenents are dependent upon the type of area in which sewer line construction occurs and are set out in Section 095 of these Specifications. 110-2 Section 110 DIP Sewer 4. Excavation and Preparation of Trench.. ;The' trench shall be dug so that the. pipe can be laid to'the alignment and depth required, and it shall be excavated only so far in advance of pipe laying as set out in Section 110.C.4.c of these Specifications. The trench shall be so braced and drained that the workmen may work therein safely and efficiently. It is essential that the discharge of any trench dewatering pumps be conducted to natural drainage channels, drains or sewers. a. Trench Depth and Pipe Bedding. The trench shall be excavated to at least 4 inches and not more than 6 inches below the established grade as shown on the Plans. The ductile iron pipe shall then be bedded in a bedding material of good earth, sand, or gravel, free from large stones or organic material. The pipe shall be. bedded from a point 4 inches below the bottom of the pipe barrel to the pipe springline by the full width of the excavated ditch. The bedding shall be placed and shaped so as to provide an uniform and continuous bearing support for the pipe at every point along the pipe barrel. All overexcavation below the pipe shall be backfilled with pipe bedding materialat the Contractor's expense. The additional material required will be placed in 3 inch lifts and hand or machine tamped. This procedure will be repeated until the established grade has been reached. Driving Surfaces and Curb and Gutter. Where the sewer line excavation is within the limits and approximately perpendicular to or crossing curb and gutter or driving surfaces, including paved and unpaved roads, driveways or parking lots, the pipe bedding material shall be SB-2 crushed limestone as set out in Section 110-B.7 of these Specifications. b. Width. The excavated sewer trench shall not exceed the width as shown on the standard detail sheet of the Plans at any point from the trench bottom to a point 12 inches above the top of the pipe barrel. If the Contractor overexcavates the trench, he shall provide additional pipe bedding gravel or concrete as necessary to prevent crushing of the sewer pipe due to excessive earth loads. All additional bedding material or concrete required shall be furnished at the Contractor's expense. c. Length. The Engineer shall have the right to limit the amount of trench excavated in advance of laying the pipe. In general, such excavation shall not exceed 300 feet, and trench excavated to grade shall not exceed 150 feet. Every trench in rock shall be fully opened at least 50 feet in advance of the place where pipe is being laid or masonry work is in process. 110-3 DIP Sewer 5. Excavation in Poor Soil and Refilling to Grade. Where the bottom of the trench at subgrade is found to be unstable or to include ashes, cinders, all types of refuse, vegetable or other organic materials, or large pieces of fragments of inorganic material which in the judgment of the Engineer should be removed, the Contractor shall excavate and remove such unsuitable material to the width and depth ordered by the Engineer. Before the pipe is laid, the subgrade shall be made by backfilling with trench backfill gravel as set out in Section 110-B.8 of these Specifications, in 3 inch uncompacted layers. The lavers shall be hand or machine tamped as directed by the Engineer so as to provide a uniform and continuous bearing and support for the pipe at all points along the pipe length. Extra payment will be made for the additional trench backfill required in accordance with the Method of Measurement and Payment Section of these Specifications. However, no additional compensation will be made to the Contractor for the additional excavation. 6. Bracing and Shoring. The sides of any excavation, when deemed necessary, shall be properly supported with bracing, shoring or sheeting as the need may be. Such bracing and shoring shall be withdrawn as the work progresses. In case the excavation is close enough to buildings or other foundations as to endanger their stability by the removing of such bracings, then they shall be made secure and left in place, and the sewer trench backfilled and thoroughly tamped with the bracing in place. The Contractor will not be paid for such bracing, sheeting, or shoring whether it is withdrawn or left in the trench. 7. Removal of Water and Muck. The Contractor shall provide sufficient pumps and other necessary equipment to keep the trench free of water which may accumulate. If the bottom of the trench becomes soft and muddy, the Contractor shall remove all such soft material and replace it with dry loam, sand, or crushed limestone bedding gravel at his own expense. Under no conditions will ductile iron pipe sewer be laid in a trench that has not been properly dewatered. 8. Laying Ductile Iron Pipe Sewers. Ductile iron sewer pipe shall be laid on a firm bed, as previously specified, in perfect conformity with lines and levels given. The pipe shall be laid with even bearing on the bottom of the trench, which shall be shaped and prepared to conform to the form of pipe. Niches of sufficient dimensions shall be cut in the bottom of the trench to give perfect clearance to the sleeve or bell end of the pipe, but no larger than is necessary to make a proper joint. The pipe shall then be installed in accordance with Section 110-C.1 of these Specifications. The coupling end of the pipe in all cases shall be laid toward the high end of the sewer. a. Connections to New Manholes. Pipe connections to manholes are a constant source of potential trouble. In order to ensure that pipe will not break immediately adjacent to the manhole, care shall be taken that excavation for the manhole bottom is limited to the area to be filled with concrete. The Contractor shall support pipe 110-4 Section 110 DIP Sewer is entering the manhole ALL under the pipe anup to b. Connections to Existing existing manholes and pi made in conformance with ¼.- OF. THE WAY-.xoA.solid bedding by backfilling midspring'line with concrete. Manholes and Pipe Sewers. Connections to pe sewers (main or service sewers) shall be Section 110—C.14 of these Specifications. . 9. Pipe Protection Cover and Backfill. Pipe protection cover and. backfill shall be placed in accordance with Section 146 of these Specifications. 10. Cleanup. Cleanup shall be in accordance with Section 900 of these Specifications. 11. Infiltration. After the contract is completed and the ditch settled, infiltration, or pipe leakage, for new sewer line construction, shall not exceed 200 gallons per day per mile of pipe per inch of pipe diameter. If infiltration or leakage exceeds this amount, the Contractor shall make such repairs as are necessary to bring infiltration or leakage within ' specified limits. The Contractor shall test the line by blocking off the various sections of pipe, filling the line with water and measuring the leakage. ' 12. Testing. Ductile iron pipe sewer lines shall be air tested in accordance with Section 190 of these Specifications with the following exception. Any line segment on which only a partial replacement has been performed shall not be air tested. 13. Replacement and Repair of Driving Surfaces, Sidewalks, Curb and Gutter. Replacement and repair of driving surfaces, sidewalks, and curb and gutter shall be made in accordance with Section 300 of these Specifications. 14. Special Connections to Existing Manholes and Existing Pipe Sewers. Where manholes are to be constructed over or at the end of the newly constructed ductile iron pipe sewers, such connections shall be made in accordance with Section 110-C.8 of these Specifications. Where an entire line segment is to be replaced between existing manholes, and no new manhole construction is indicated on the Plans, the connections to existing manholes or pipe sewers shall be made in conformance with the following Specifications. a. Connection of Newly Constructed Sewer Lines to Existing Manholes. Unless otherwise directed by the Engineer, connections of newly constructed sewer line to existing manholes shall be made at the first pipe joint outside the manhole wall, and shall be dependent upon the condition of that joint. After excavation, if the joint is determined by the Engineer to be sound and usable, the existing bell -end gasket shall be removed from the pipe and disposed of by the Contractor. The pipe shall be thoroughly cleaned inside for a distance of one foot up the existing sewer line and a new pipe gasket of the appropriate diameter installed. The new pipe sewer shall then be installed according to the line and grade as shown on 110-5 DeCLiUll 11V DIP Sewer the Plans and in accordance with Sections 110-C.1 and 110-C.8 of these Specifications. If the first pipe joint outside the manhole wall is determined by ' the Engineer to be partially usable, the Contractor, at his option, may use either of the methods set out below to connect newly constructed sewer lines to existing manholes. If the first pipe joint outside the manhole wall is determined by the Engineer to be totally unusable, a connection through the manhole wall shall be made as set out in 14.a.(2) below. (1) Use of Couplings. The Contractor may use the proper straight, transition, or other coupling of the appropriate diameter(s) to connect the existing sewer line to the newly constructed sewer line. The coupling shall be located so that all existing pipe between the coupling and the manhole is sound and free from defects. The Contractor will be required to cut the existing pipe joint back to a point so the remainder of the pipe is fit and usable. ■ All couplings shall be manufactured by the pipe manufacturer, and made specifically for the type of pipe connection being made, or shall be Fernco pipe connector, or equal. All couplings or connectors shall be installed in accordance with the manufacturer's recommendations. (2) Connections Through Manhole Walls. If couplings are not used, the Contractor shall make a tie to he existing manhole by drilling, chipping or jack -hammering a hole of sufficient diameter for the installation of the pipe sewer in the existing manhole wall. Unless otherwise shown on the Plans, the pipe sewer shall be installed at the same invert elevation as the existing pipe. After the pipe is installed, the manhole -to -pipe connection shall be repaired using a non -shrink grout. The repair shall be watertight. Any damage to the manhole caused during the connection construction shall be repaired by the Contractor at his expense. b. Pipe to Pipe Connections. The Plans show the location of line segments to be replaced. where the line segment to be replaced is a partial replacement and does not begin and terminate at manholes; proper straight, transition, or other couplings as provided by the pipe manufacturer, or as manufactured by Fernco, or equal, shall be used to join the ends of the newly constructed line segment to the existing sewer line. All pipe couplings or connectors shall be installed in accordance with the manufacturer's recommendations. 15. Sewer Service Reconnections. All existing service lines disturbed or broken during the construction of the new sanitary sewer lines shall be 110-0 Section 110 DIP Sewer reconnected to the newly. constructed sewer„)fine after the sewer line has been air tested. During construction, sewer service ties or wyes shall be placed on the downstream side of the existing sewer service line to make the service connection as shown on the Plans and hereinafter specified. Tapping .the newly constructed sewer line shall only be allowed at the direction of the Engineer. After air testing, the sewer service lines shall be reconnected as shown on the Plans; according to the type of main pipe line, and size and type of service line. All new service linesinstalled shall have a minimum diameter of 4 inches. If the existing service line has a diameter larger than 4 inches, the new service line shall have a diameter equal to that of the existing service line. the Contractor shall be responsible for providing all couplings and fittings necessary for transition from one pipe type or size to another type or size of pipe. All couplings shall be manufactured by the pipe manufacturer, and made specifically for the type of pipe connection being made, or shall be Fernco pipe connector, or equal. All couplings or connectors shall be installed in accordance with the manufacturer's recommendations. I I I I 110-7 Section 140 ABS Composite ACRYLONITRILE-BUTADIENE-STYRENE. (ABS) COMPOSITE SEWER PIPE 140-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all labor, equipment, tools, supplies, and incidentals necessary for the construction of acrylonitrile-butadiene-styrene (ABS) pipe sanitary sewer lines. The work shall include every item of construction necessary for a complete and acceptable installation as shown on the Plans and hereinafter specified. 140-B. MATERIALS. 1. Acrylonitrile-Butadiene-Styrene (ABS) Composite Sewer Pipe. All ABS composite sewer pipe shall conform to the requirements of ASTM D-2680, latest revision. The thermoplastic material shall be a virgin rigid ABS plastic and shall conform to the requirements of ASTM Specification D-1788 for cell classification 2-2-3. The ABS composite pipe shall consist of two concentric thermoplastic tubes integrally braced across the annulus. The resultant annular space is to be filled with Portland cement perlite concrete to provide continuous support between inner and outer tubes. 2. Acrvlonitrile-Butadiene-Styrene (ABS) Composite Sewer Pipe Fittings. All ABS composite sewer pipe fittings shall conform to the requirements of ASTM D-2680, latest revision. 3. Factory -Applied Joints. All pipe shall have factory applied type SC joints on one end. The inert pipe filler shall also be factory -sealed on the joint end of the pipe. ' 4. Joint Primer and Cement. Primer for priming solvent cemented joints shall be MEK (methyl ethyl ketone) and the cement shall be MEK containing a minimum of 20 weight .% of dissolved ABS. All primer and cement shall I be supplied by the pipe manufacturer. 5. ABS Composite Pipe Bedding Gravel. Gravel used for bedding of ABS composite pipe and ABS composite pipe fittings shall be crushed ' limestone, Class SB-2, as defined in Section 306 of the 1978 Edition of the Arkansas State Highway Department Specifications. The crushed limestone supplier shall submit certificates stating that the materials I. provided are in accordance with these Specifications. NOTE: There is no special pay item for ABS composite pipe bedding gravel. This item shall be considered subsidiary to the ABS composite pipe. ' 6. Crushed Stone Trench Backfill. Crushed limestone trench backfill (where required) shall be Class SB-2, as defined in Section 306 of the 1978 Edition. of the Arkansas State Highway Department Specifications. The ' crushed limestone supplier shall submit certificates stating that the materials provided are in accordance with these Specifications. 140-1 ABS Composite NOTE: This item shall be paid for at the unit price bid in the proposal, and as set out in Methods of Measurement and Payment. 7. Special Pipe Cover. Special pipe cover (where required - see Section 140-C.9 of these Specifications) shall be as set out for bedding gravel, Section 140-B.5 of these Specifications. NOTE: There is no special pay item for special pipe covers. 8. Independent Laboratory Inspection. All ABS composite pipe and ABS composite pipe fittings furnished and installed on this project shall be inspected and tested by the manufacturer. The manufacturer shall furnish to the Engineer, prior to delivery, certificates stating that all pipe will be manufactured in compliance with these Specifications. The certificate shall also fully describe the pipes proposed to be furnished. If evidence appears that all provisions of the applicable ASTM Standards have not been complied with after the pipe has been delivered, the Owner will require such field testing and sampling as necessary for certified statements of compliance to the provisions of said standards to be furnished by an approved independent laboratory. The cost for the testing and sampling or job delay will be the responsibility of the pipe supplier if the pipe is not in compliance. The Owner will pay the cost of the testing and sampling if the pipe is in compliance with the Specifications; however, the Owner will not be responsible for job delay. The independent laboratory shall be one which may be chosen by the pipe manufacturer and approved by the Engineer. 140-C. ACRYLONITRILE-BUTADIENE-STYRENE (ABS) COMPOSITE PIPE SEWER LINE CONSTRUCTION. 1. Installing ABS Composite Pipe. ABS composite pipe and ABS composite pipe fittings shall be installed in conformance with the "Standard Recommended Practice for Underground Installation of Flexible Thermoplastic Sewer Pipe" ASTM Designation D2321, latest revision, and in conformance with the Specifications hereinafter set out. 2. Construction Sequence. Construction of sanitary sewers shall begin at the low point of the line and continue in orderly succession throughout the work as directed by the Engineer. Any deviation from this procedure shall be made only with the specific approval of the Engineer, and only after the right of way has been cleared and the entire section staked and all elevations carefully checked by the Engineer. Unless specifically approved by the Engineer, appurtenances such as fittings, manholes, etc. shall be constructed as the work progresses. 3. Requirements Preparatory to Trench Excavation. lines, manholes, or other appurtenances are repaired, the existing surface shall be remove trench. There is no pay item for these requirements shall be considered part of the requirements are dependent upon the type of In all areas where sewer to be constructed and/or d prior to excavating the requirements and these trench excavation. These area in which sewer line 140-2 v a.V V1VLL s-, ABS Composite construction occurs ..and are. set out, in Section 095 of these Specifications. 5;i` 4. Excavation and Preparation of Trench. The trench shall be dug so that the pipe can be laid to the alignment and depth required, and it shall be excavated only so far in advance of pipe laying as set out in Section 140-C.4.c of these Specifications. The trench shall be so braced and drained that the workmen may work therein safely and efficiently. It is essential that the. discharge of any trench dewatering pumps be conducted to natural drainage channels, drains or sewers. a. Trench Depth and Pipe Bedding. The trench shall be excavated to at least 4 inches and not more than 6 inches below the established grade as shown on the Plans.. The ABS composite pipe shall then be bedded in •a crushed limestone bedding as set out in Section 140-B.5 of these Specifications. The pipe shall be bedded from a point 4 inches below the bottom of the pipe barrel to the pipe springline by the full width of the excavated ditch. The bedding shall be placed and shaped so as to provide an uniform and continuous bearing support for the pipe at, every point along the pipe barrel. All overexcavation below the pipe shall be backfilled with pipe bedding material at the Contractor's expense. The additional material required will be placed in 3 inch lifts and hand or machine tamped. This procedure will be repeated until the established grade has been reached. b. Width.. The excavated sewer trench shall not exceed the width as shown on the standard detail sheet of the Plans at any point from the trench bottom to a point 12 inches above the top of the pipe barrel. If the Contractor overexcavates the trench, he shall provide additional pipe. bedding gravel or concrete as necessary to prevent crushing of the sewer pipe due to excessive earth loads. All additional bedding material required shall be furnished at the Contractor's expense. c. Length. The Engineer shall have the right to limit the amount of trench excavated in advance of laying the pipe. In general, such excavation shall not exceed 300 feet, and trench excavated to grade shall not exceed 150 feet. Every trench in rock shall be fully opened at least 50 feet in advance of the place where pipe is being laid or masonry work is in process. 5. Excavation in Poor Soil and Refilling to Grade. Where the bottom of the trench at subgrade is found to be unstable or to include ashes, cinders, all types of refuse, vegetable or other organic materials, or large pieces of fragments of inorganic material which in the judgment of the Engineer should be removed, the Contractor shall excavate and remove such unsuitable material to the width and depth ordered by the Engineer. 140-3 V..t. L 1VLL L1V ABS Composite Before the pipe is laid, the subgrade shall be made by backfilling with trench backfill gravel as set out in Section 140-B.6 of these Specifications in 3 inch uncompacted layers. The layers shall be hand or hand or machine tamped as directed by the Engineer so as to provide an uniform and continuous bearing and support for the pipe at all points along the pipe length. Extra payment will be made for the additional trench backfill required in accordance with the Method of Measurement and Payment Section of these Specifications. However, no additional compensation will be made to the Contractor for the additional excavation. 6. Bracing and Shoring. The sides of any excavation, when deemed necessary, shall be properly supported with bracing, shoring or sheeting as the need may be. Such bracing and shoring shall be withdrawn as the work progresses. In case the excavation is close enough to buildings or other foundations as to endanger their stability by the removing of such bracings, then they shall be made secure and left in place, and the sewer trench backfilled and thoroughly tamped with the bracing in place. Such work shall be done under the direction of the Engineer. The Contractor will not be paid for such bracing, sheeting, or shoring whether it is withdrawn or left in the trench. 7. Removal of Water and Muck. The Contractor shall provide sufficient pumps and other necessary equipment to keep the trench free of water which may accumulate. If the bottom of the trench becomes soft and muddy, the Contractor shall remove all such soft material and replace it with dry loam, sand, or crushed limestone bedding gravel at his own expense. Under no conditions will ABS composite pipe sewer be laid in a trench that has not been properly dewatered. 8. Laying ABS pipe shall conformity bearing on to conform cut in the or bell enc joint. Composite Pipe be laid on a with lines and the bottom of to the form of bottom of the of the pipe, t Sewers - Factory Jointed Pipe. ABS composite firm bed, as previously specified, in perfect levels given. The pipe shall be laid with even the trench, which shall be shaped and prepared pipe. Niches of sufficient dimensions shall be trench to give perfect clearance to the sleeve ut no larger than is necessary to make a proper In jointing ABS composite pipe, the mating surfaces shall be wiped free of dust, dirt, gravel, or other foreign materials prior to the application of the primer. The ABS composite pipe shall be connected by first brushing upon the mating surfaces the proper primer as recommended by the pipe supplier. The primer shall be liberally applied to the outside of the spigot and inside of the coupling using "Johnny Mops" or other brushes as provided by the pipe manufacturer. The cement shall be immediately applied to the same mating surfaces. The spigot end of the pipe shall then be centered on grade into the bell end of the last downstream ABS pipe length and shoved "home" with 1/4 turn rotation. The joint shall be made within one minute of the cement application. The coupling end of the pipe in all cases shall be laid toward the high end of the sewer. 140-4 Section 14U ABS Composite a. Connections to flew Manholes. Pipe , connections to manholes are a constant source of= potential trouble.,d ! In order to ensure that pipe will not break immediately adjacent to the manhole, care shall be taken that excavation for the manhole bottom is limited to the area to be filled with concrete. The Contractor shall support pipe entering the manhole ALL OF THE WAY to solid bedding by backfilling under the pipe and up to midspring line with concrete. Additionally, manhole waterstops as provided by the pipe manufacturer shall be installed on the pipe prior to pouring the manhole. b. Connections to Existing Manholes and Pipe Sewers. Connections to existing manholes and pipe sewers (main or service sewers) shall be made in conformance with Section 140-C.16 of these Specifications. 9. Pipe Protection Cover and Backfill. Pipe protection cover and backfill shall be placed •in accordance with Section 146 of these Specifications. 10. Special Pipe Cover. In areas where groundwater is evident, a minimum of 12 inches of special pipe cover as defined in Section 140-B.7 shall be placed over the top of the pipe prior to backfilling the trench. There shall be no special pay item for this work and the special pipe cover shall be considered subsidiary to pipe laying. 11. Cleanup. Cleanup shall be in accordance with Section 900 of these Specifications. 12. Infiltration. After. the contract is completed and the ditch settled, infiltration, or pipe leakage, for new sewer line construction shall not exceed 200 gallons per day per mile of pipe per inch of pipe diameter. If infiltration or leakage exceeds this amount, the Contractor shall make such repairs as are necessary to bring infiltration or leakage within specified limits. The Contractor shall test the line by blocking off the various sections of pipe, filling the line with water and measuring the leakage. 13. Air Testing. ABS composite pipe sewer lines shall be air tested in accordance with Section 190 of these Specifications with the following exception: any line segment on which only a partial replacement has been performed shall not be air tested. 14. Mandrell Test. On all line segments which have been replaced using ABS composite pipe, the Contractor shall pull a mandrell through the line segment (except line segments on which only a partial replacement has been performed). 15. Replacement and Repair of Driving Surfaces, Sidewalks, Curb and. Gutter. Replacement and repair of driving surfaces, sidewalks, and curb and gutter shall be made in accordance with Section 300 of these Specifications. 140-5 ABS Composite 16. Special Connections to Existing Manholes and Existing Pipe Sewers. Where manholes are to be constructed over or at the end of the newly constructed sewers, such connections shall be made in accordance with Section 140-C.8.a of these Specifications. Where an entire line segment is to be replaced between existing manholes, and no new manhole construction is indicated on the Plans, the connections to existing manholes or pipe sewers shall be made in conformance with the following Specifications. All work shall be in a workmanlike manner so as not to damage any other structures involved. a. Connection of Newly Constructed Sewer Lines to Existing Manholes. Unless otherwise directed by the Engineer, connections of newly constructed sewer lines to existing manholes shall be made at the first pipe joint outside the manhole wall, and shall be dependent upon the condition of that joint. After excavation, if the joint is determined by the Engineer to be sound and usable, the existing bell -end gasket shall be removed from the pipe and disposed of by the Contractor. The pipe shall be thoroughly cleaned inside for a distance of one foot up the existing sewer line and a new pipe gasket of the appropriate diameter installed. The new pipe sewer shall then be installed according to the line and grade as shown on the Plans and in accordance with Sections 140-C.1 and 140-C.8 of these Specifications. If the first pipe joint outside the manhole wall is determined by the Engineer to be partially usable or has an incompatible outside pipe diameter to join to ABS pipe, the Contractor, at his option, may use either of the methods set out below to connect newly constructed sewer lines to existing manholes. If the first pipe joint outside the manhole wall is determined by the Engineer to be totally unusable, a connection through the manhole wall shall be made as set out in 16.a.(2) below. (1) Use of Couplings. The Contractor may use the proper straight, transition, or other coupling of the appropriate diameter(s) to connect the existing sewer line to the newly constructed sewer line. The coupling and the manhole is sound and free from defects. The Contractor will be required to cut the existing pipe joint back to a point so the remainder of the pipe is fit and usable. All couplings shall be manufactured by the pipe manufacturer and made specifically for the type of pipe connection being made, or shall be Fernco pipe connectors, or equal. All couplings or connectors shall be installed in accordance with the manufacturer's recommendations. (2) Connections Through Manhole Walls. If couplings are not used, the Contractor shall make a tie to the existing manhole by drilling, chipping or jack -hammering a hole of sufficient diameter for the installation of the pipe sewer in the existing manhole wall. Unless otherwise shown on the Plans, the pipe 140-6 Section 14U ABS Composite sewer shall'7�be installed at the r same invert elevation as the existing piS; A manhole watrecstoprovided by the P P P by pipe manufacturer shall be placed on the ABS pipe prior to installation. After the pipe is installed the manhole -to -pipe connection shall be repaired using a non -shrink grout. The repair shall be watertight. Any damage to the manhole caused during the connection construction shall be repaired by the Contractor at. his expense. b. Pipe to Pipe Connections. The Plans show the location of line segments to be replaced. Where the line segment to be replaced is a partial replacement and does not begin and terminate at manholes; proper straight, transition, or other couplings as provided by the pipe manufacturer, or as manufactured by Fernco, or equal, shall be used to join the ends of the newly constructed line segment to the existing sewer line. All pipe couplings or connectors shall be installed in accordance with the manufacturer's recommendations. 17. Sewer Service Reconnections. All existing service lines disturbed or broken during the construction of the new sanitary sewer lines shall be reconnected to the newly constructed sewer line after the sewer line has been air tested. During construction sewer service ties or wyes shall be placed on the downstream side of. the existing sewer service line to make the service connection as shown on the Plans and hereinafter specified. Tapping the newly constructed sewer line shall only be allowed at the direction of the Engineer. After air testing, the sewer service lines shall be reconnected as shown on the Plans, according to the type of main pipe line, and size and type of service line. All new service lines installed shall have a minimum diameter. of 4 inches. If the existing service line has a diameter larger than 4 inches, the new service line shall have a diameter equal to that of the existing service line. the Contractor shall be responsible for providing all couplings and fittings necessary for transition from one pipe type or size to another type or size of pipe. All couplings shall be manufactured by the pipe manufacturer, and made specifically for the type of pipe connection being made, or shall be Fernco pipe connector, or equal. All couplings or connector shall be installed in accordance with the manufacturer's recommendations. I I I I 140-7 bection 14) Manhole Rehabilitation MANHOLE REHABILITATION 145-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all materials, labor, equipment, tools, supplies, bypass pumping, and incidentals necessary to repair existing manholes or construct•new manholes. 145-B. CLASSIFICATION OF MANHOLE REHABILITATION. shall include such repairs as are generally set out hereinafter specified. Also listed in Table 1 is the code as referenced on the Plans and in these Specific bid item(s) under which payment will be made as set Measurement and Payment. TABLE 1 Rehabilitation Method Manhole rehabilitation in Table 1 below, and related rehabilitation ations, and the primary out in the Methods of Rehabilitation Primary Code Bid Item Realign and Grout Casting, MH in Street 23 12 Realign and Grout Casting MH in Easement 24 12 Regrout Casting to Cone 25 12 Clean MH Walls, Fill Small Cracks, & Waterproof Walls 27 13 Clean MH Walls, Plug Large Cracks, & Waterproof Walls 28 13 Clean MH Walls, Plug Large Cracks, Plaster and Waterproof Walls 29 13 Excavate MH in Easement & Repair Line Connection from Outside 30 14 Excavate 14H in Street and Repair Line Connection from Outside 31 14 Replace MH 32 17 Raise MH to Street Level, 1 to .2 Inches 33 15 Raise MH to Street Level, 2 to 18 Inches 34 15 Raise MR to Street Level, More than 18 Inches 35 15 Raise MH to Grade in Easement, 0 to 12 Inches 36 15 Raise MH to Grade in Easement, More than 12 Inches 37 15 Paise MH Above Grade in Easement 38 15 Plug Vent Holes and Raise Casting to Street Level 40 1.6. The manholes upon which rehabilitation work is required are set out in tabular form in Table 2 at the end of this section of the Specifications. 145-C. MATERIALS. 1. Concrete. Concrete used in the construction of standard and drop ' cast -in -place manholes shall be in conformance with the Concrete section of these Specifications. 2. Mortar and Grout. Mortar or grout used intheraising of manholes shall be mixed in the proportion of one part of Portland cement and two parts mortar sand as defined in the Concrete section of these I 145-1 Manhole Rehabilitation Specifications. The mixture shall be dry -mixed until it has a uniform color, after which water shall he added or the mixing continues until the mortar has a consistency such that it can be easily handled and spread with a trowel. Mortar or grout that has not been used within 30 minutes after water has been added shall not be used. 3. Materials for Use in Cleaning Manholes, Filling and Patching Cracks, and Waterproofing Manhole Walls and Base (Rehabilitation Codes 27, 28 and 29). The Contractor shall place a formed manhole liner in the manholes set out on the Plans and in these Specifications. The City reserves the right to delete this repair item from these Plans and Specifications, or to order the work to be performed under Rehabilitation Code 32 (manhole replacement). a. Concrete. Concrete shall be in conformance with the Concrete section of these Specifications, except the maximum size aggregate shall be no greater than 3/4 inch and the minimum cement content shall be 7 bags per yard of concrete. b. Waterstop Cement Mixture. The waterstop cement mixture shall consist of a mixture of Ipanex-R, as manufactured by IPA Systems, Inc., or equal, and Type I Portland cement. c. Epoxy Bonding Agent. The adhesive for bonding new concrete to the existing manhole surface shall be Top -Bond 40 two component epoxy adhesive as manufactured by Nox-Chem, or equal. d. Concrete Waterproofing Admixture. The concrete waterproofing admixture shall be Ipanex concrete admix, as manufactured by IPA Systems, Inc., or equal. e. Manhole Replacement Steps. Manhole replacement steps shall be in conformance with the Manhole section of these Specifications (Section 150.B.4). 4. Manhole Brick. Brick used in raising manholes shall be in conformance to ASTM C62, latest revision, Grade SW pavers. 145-D. CONSTRUCTION. Methods for performing each of the rehabilitation methods contained in Section 145-B above are set out as follows. 1. General Construction. a. Flow Control and Bypass Pumping. All flow control and bypass pumping as necessary shall be provided by the Contractor. All bypass pumping required during construction shall be in accordance with Section 090 of these Specifications. There is no separate pay item for bypass pumping and bypass pumping shall be considered subsidiary to all rehabilitation methods employed. b. Surface Removal. Surface removal shall be in is accordance with Section 095 of these Specifications. There is no separate pay 145-2 Section 145 Manhole Rehabilitation item for the removal of existing cover or excavation, and any such removal or excavation shall be considered subsidiary to the rehabilitation method employed. c. Driving Surface, Sidewalk, and Curb and Gutter Repair. After the proposed manhole rehabilitation has been completed, all paved and unpaved driving surfaces, driveways, parking lots, sidewalks, and • curb and gutter shall be repaired as set out in Section 300 of these Specifications. Payment for the different types of surface repairs shall be made to the Contractor as set out in the Methods of Measurement and Payment except that damage to any surface, driving surface, sidewalk or curb and gutter while performing manhole rehabilitation under Rehabilitation Codes 27, 28 and 29 shall be considered ,non -essential, and the Contractor shall be responsible for repairing any damaged areas at his own expense. d. Cleanup. After the proposed manhole rehabilitation has been completed, the Contractor shall clean up the area in accordance with Section 900 of these Specifications. Payment for cleanup shall be made to the Contractor as set out in the Methods of Measurement and Payment section of these Specifications except that damage to any surface while performing manhole rehabilitation under Rehabilitation Codes 27, 28 or 29 shall be considered non -essential, and the Contractor shall be responsible for repairing damaged areas at his own expense. 2. Realign and Grout Casting to Cone to be included under this item existing off -center manhole ring correct position over the center shall be performed on manholes as in Table 2. (Rehabilitation Code 23). The work generally. consists of removing the and cover, and grouting it into a of the manhole. This rehabilitation shown on the Plans and as specified a. Removal of Existing Ring and Lid. The manhole ring and lid shall be removed from the cone. Any damage to the existing ring and lid or to the manhole during the removal of the ring and lid shall be repaired at the expense of the Contractor. b. Replacing the Ring and Lid. The top of the manhole shall be thoroughly cleaned of any loose mortar, mud, dirt or other debris and a 3/8 inch layer of grout shall be applied to the cleaned surface to accept the new manhole ring and lid. The existing ring shall be centered on the manhole and firmly seated in the grout. An additional 2 inches of grout shall be applied over the outside of the casting flange. Grout shall be applied to the inside of the manhole at the joint of the castingand cone to a thickness of 1/4 inch, and shall extend 1 inch either side of the joint. c. Backfilling. The excavated area shall be backfilled according to the existing ground conditions in accordance with Section 146 of these Specifications. 1.45-3 Manhole Rehabilitation 3. Cleaning Manholes, Filling and Patching Cracks, and Waterproofing Manhole Walls and Base (Rehabilitation Codes 27, 28 and 29). It is the intent of these Specifications to provide for the sealing out of extraneous water leakage into manholes that are otherwise structurally sound. If the structural integrity of the manhole has been lost, the Engineer shall direct the Contractor as to the alternate rehabilitation method to be employed. All standard and drop manholes shall this rehabilitation item. This shall over the entire depth and sealing the paid to areas around steps, at the around all pipes entering the manhole ring and cone. be completely sealed inside under include sealing the manhole walls base. Special attention shall be junction of the base and wall, and the junction of the manhole a. Step 1 (Surface Preparation) and Step 2 (Application of Waterstop Cement Mixture) shall be as previously specified, except that all existing manhole steps shall be removed to provide a surface free of obstructions. b. Step 3. After all points of visible infiltration have been plugged, the manhole shall be air dried and the two component epoxy bonding agent shall be applied using either a brush or short -nap paint roller at the rate of approximately 160 square feet per gallon. c. Step 4. Once the epoxy based bonding agent has been applied, concrete liner forms shall be set in the manhole and new manhole steps inserted. The height and dimensions of the liner are as shown on the detail sheet of the Plans. Ipanex waterproofing admixture shall be added to the Portland cement concrete at the rates and in accordance with the manufacturer's recommendations and thoroughly mixed immediately prior to placement in the forms. The forms shall be adequately tapped to insure thorough consolidation of the concrete so as to eliminate any possibility of honeycombs. Placement of the concrete shall be within 6 to 8 hours (depending upon temperature) of application of the epoxy based bonding agent. Once the concrete liner has adequately cured, the forms shall be removed. 4. Excavate and Repair the Manhole Line Connection from Outside the Manhole (Rehabilitation Codes 30 and 31). This type of repair shall generally include excavating the defective line and/or joint immediately adjacent to the manhole, and making a watertight repair by pouring a concrete collar around the exposed line adjacent to the manhole. This type of repair shall be performed at manholes as shown on the Plans and in accordance with these Specifications. a. Trench Preparation. All trench preparation and construction shall be made in accordance with the detail sheet of the Plans and Pipe 145-4 section 14) Manhole Rehabilitation Specifications Section. 100-C.4 of these Specifications except that the trench shallb'e`-excavated*to ad'epth so that a concrete collar may be placed in conformance to the dimensions as shown on the Plans. b. Repairing the Manhole Line Connection. After the manhole connection has been excavated, the outside surface of the manhole, manhole base, and pipe shall be thoroughly cleaned of rocks, mud, and other debris. The concrete collar shall then be poured to the dimensions as shown on the standard detail sheet of the Plans and to the length directed by the Engineer. After the initial set of the concrete, the trench shall be backfilled. c. Backfilling. The excavated area shall then be backfilled according to the existing ground surface conditions in accordance with Section 146 of these Specifications. 5. Manhole Replacement (Rehabilitation Code 32). The work set out under this rehabilitation method generally includes excavating and completely removing the existing manhole and .base, and constructing a. new cast -in -place manhole and base. The new manhole and base shall be in conformance to the dimensions shown on the standard detail sheet of the Plans and these Specifications. Prior to removing the existing manhole, the manhole ring and lid shall be salvaged for use with the newly constructed manhole. The manhole and manhole base shall then be completely removed,.hauled from the site and disposed of by the Contractor.. Any damage to the existing sewer line shall be repaired: or replaced at the Contractor's expense. After the manhole has been removed, a new manhole shall be constructed over the existing sewer lines in conformance with Section 150 of these Specifications. 6. Raising Manholes (Rehabilitation Codes 33, 34, 35, 36, 37, 38 and 40). The, work set out under this rehabilitation method generally includes removing the existing manhole ring and cover and raising the manhole with brick to the grade directed by the Engineer. This type of repair shall be performed on manholes as shown on the Plans and in accordance with these Specifications. a. Removal of the Ring and Lid. The manhole ring and lid shall be removed from the cone and salvaged. Any damage to the manhole, ring, or lid during the removal process shall be repaired or replaced at the expense of the Contractor. b. Raising the Manhole. The top of the manhole shall be thoroughly cleaned of any loose mortar, mud, dirt, or other debris and a 3;8 inch laver of mortar shall be applied to the cleaned surface to accept the first ring of manhole brick. A sufficient number of brick and mortar rings shall be applied to reach the desired elevation. All brick or block shall have full mortar joints on the bottom and sides. Every joint shall be 145-5 Manhole Rehabilitation formed at one operation by placing sufficient mortar on the bed and forcing the brick or block into it. Horizontal joints shall not exceed 3/8 inch and the vertical joints on the inside of the manhole shall not exceed 1/4 inch. The brick shall be plastered on both the inside and outside with 1/2 inch of cement mortar. The plaster shall be smoothly laid, and on the inside of the manhole all rough projections shall be removed. Details for the construction of manholes are shown on the standard detail sheet of the Plans. c. Plugging Vent Holes in Manhole Lids (Rehabilitation Code 40 Only). Where shown on the Plans or set out in the Specifications, vent holes in existing manhole lids shall be plugged using stainless steel bolts and neoprene washers. The Contractor shall plug all vent holes in the existing manhole lid. Plugs used shall be stainless steel bolts with neoprene washers on both top and bottom of the lid. The bolt head and washer shall not extend more than 3/8 inch above the cover surface. The bolt shall have a minimum diameter of 1/16 inch less than the vent hole and shall be secured using nuts on the underside of the lid. All bolts shall have rounded heads. d. Backfilling. The backfill shall then be placed in accordance with Section 146 of these Specifications. 7. Testing of Rehabilitated Manholes. All manholes repaired or constructed under Sections 145-D.3 and 145-D.5 of these Specifications shall be tested in accordance with this Specification. After the manhole rehabilitation, including curing, has been completed, then the manhole shall be tested. The test shall be conducted by the Contractor in coordination with - and at the direction of the Engineer. It is realized that there are certain conditions which will make manhole testing impractical or impossible to perform, such as excessively high sewer flows requiring bypassing of the sewerage, manholes with depths exceeding 20 feet, etc. When conditions of this nature are encountered, no testing will be required. Manhole testing shall be accomplished by an exfiltration test. All incoming and outgoing sewer lines shall be plugged and the manhole filled with water up to the corbel section. If the water loss exceeds the maximum allowable as shown below, the manhole shall have failed the test. Depth of Manhole Maximum Allowable Water Loss 0-8 feet 1 inch over 5 minutes Over 8 feet 1/8 gallon per vertical foot over 5 minutes All manholes which fail the test shall be carefully inspected to determine the problem. If the source of the problem is something other than originally specified for that manhole, then it shall be corrected following the method as prescribed in these Specifications. Additional payment shall he made to the Contractor on the basis for the method used. If the source of the problem is related to the original problem, 145-6 Section 145 Manhole Rehabilitation then it shall be corrected by the Contractor at no additional cost to the owner. 145-7 REHAB CODES: 23 & 24 TABLE 2 MANHOLES REQUIRING FRAME ADJUSTMENT AND GROUTING MANHOLE NO. STREET COVER OTHER WORK Minisystem 7 64B Lewis Avenue Field No 128 H Sunset Avenue Pavement No 198 Elmwood Avenue Pavement No Minisystem 8 40 Old Wire Rd. Easement No Minisystem 11 18 U.S. Hwys. 62 & 71 Easement No Minisystem 16 4 Poplar Street Easement No 98 Kings Drive Pavement No 145 T2-1 REHAB CODE: 25 MANHOLE NO. Minisystem 2 165 165A Minisystem 4 150 Minisystem 8 4 31 41 45 49 217 TABLE 2 (Cont.) MANHOLES REQUIRING REGROUTING FRAME TO CONE STREET COVER OTHER WORK Wesley Road Yard No Wesley Road Yard No Stanton Avenue Pavement State Hwy. 265 N. Field Old Wire Rd. (Easement) Field Between Old Wire Rd. & Strawberry Drive Yard Between Old Wire Rd. & Strawberry Drive Yard Old Wire Road Easement Ash Street (Easement) Field Minisystem 11 21 Township Road Easement 63 Villa Mobile Home Park Easement Plug Holes in Cover No No No No No No No No 145 T2-2 TABLE 2 (Conti "')'der' MANHOLES REQUIRING REGROUTING FRAME TO CONE MANHOLE NO. STREET COVER 150 College Avenue Woods Minisystem 16 REHAB CODE: 25 OTHER WORK No 27 Abshier Drive Easement No 74 Hwy. 45.(Easethent) Field No 95 Arlington Street Sidewalk No 1'45 T2-3 ■ REHAB CODE: 27 MANHOLE NO. Minisystem 2 26 91 11OA 140 145 164 Minisystem 4 TABLE 2 (Cont.) MANHOLES REQUIRING CLEANING WALLS, FILLING SMALL CRACKS AND WATERPROOFING WALLS STREET STRUCTURE DEPTH COVER OTHER WORK Fifth Street Center Street Conner Street Lafayette St. (Easement) Dickson St. Missouri Way (Easement) Brick Brick Brick Brick Brick Stone 7 Front Street Concrete 26 Harold Street Brick 142 Stanton Ave. Brick 163 Stagecoach Dr. Precast U.S. Hwy. 71 321 Bypass Precast 5' Woods No 9Pavement No 7' Pavement No ' 1 4' Yard No 4' Easement No ' 1 6' Woods No 1 8' Easement No ' 6' Easement No ' Plug Holes 5' Sidewalk in Cover 9' Yard No 1 Raise MH to ' 9' Field Above Grade 145 T2-4 REHAB CODE: 27 TABLE 2 (Cont-.) MANHOLES REQUIRING CLEANING WALLS, FILLING SMALL CRACKS AND WATERPROOFING WALLS MANHOLE NO. STREET STRUCTURE DEPTH COVER OTHER WORK Minisystem 7 24 Porter Road Brick 7' Easement No Sang Avenue 54D (Easement) Brick 5' Yard No 107 S. Maxwell Dr. Brick 6' Easement No Raise MH to Above Grade; Excavate MH/ Line Connection 111 S. Maxwell Dr. Brick 5' Easement & Repair Between Leland Avenue & Sang 154 Avenue Precast 10' Easement No Between Eva Avenue & Sang Raise MH to 164A • Avenue Precast 10' Field Above Grade 196 Cedarwood Ave. Brick 7' Easement No Between Cedar - wood Ave. & 197 Lewis Avenue Brick 4' Easement No Between Elmwood Ave. & Cedar - 199 wood Avenue Brick 8' Yard No 145 T2-5 REHAB CODE: 27 MANHOLE NO. Minisystem 8 30 33 53A 71 72 182 Minisystem 11 13 62 TABLE 2 (Cant.) MANHOLES REQUIRING CLEANING WALLS, FILLING SMALL CRACKS AND WATERPROOFING WALLS STREET STRUCTURE DEPTH COVER OTHER WORK Old Wire Road (Easement) Precast 5' Field No Old Wire Road (Easement) Precast 7' Field No Old Wire Road Precast 6' Yard No Township Road Precast 4' Yard No Township Road Precast 5' Yard No Juneway Terrace Brick 5' Pavement No U.S. Hwys. 62 & 71 Brick 8' Easement No Villa Blvd. Precast 6' Yard No 145 T2-6 REHAB CODE: 28 TABLE 2 (Conf:)4=A MANHOLES REQUIRING CLEANING WALLS, PLUGGING LARGE CRACKS AND WATERPROOFING WALLS MANHOLE NO. STREET STRUCTURE DEPTH COVER OTHER WORK Minisystem 4 60A Elizabeth Ave. Brick 9' Pavement No 92 Market Street Precast 3' Sidewalk No Minisystem 7 8 Hatfield St. Brick 6' Pavement No Repair MH/Line 167 Sang Avenue Brick 10' Pavement Connection Minisystem 8 146 Sunny Hill Dr. Brick 7' Pavement No Minisystem 11 U.S. Hwys. 12 62 & 71 Brick 96 Marie Brick 115. U.S. Hwy. 71 Brick Minisystem 16 47 Rayview Drive Brick 16' Pavement No 5' Pavement No 6' Pavement No 12' Pavement No 145 T2-7 REHAB CODE: 28 TABLE 2 (Cont.) MANHOLES REQUIRING CLEANING WALLS, PLUGGING LARGE CRACKS AND WATERPROOFING WALLS MANHOLE NO. STREET STRUCTURE DEPTH COVER OTHER WORK 50 Walnut Avenue Brick 3' Sidewalk No Between Sycamore St. & North Grout Frame 62 Lakeside Drive Brick 7' Field to Cone 145 T2-8 • REHAB CODE: 29 TABLE 2 MANHOLES REQUIRING CLEANING WALLS, PLUGGING LARGE CRACKS, AND PLASTERING AND WATERPROOFING MANHOLE NO. STREET STRUCTURE DEPTH COVER OTHER WORK Minisystem 7 26A Holly Street Brick 4' Pavement No Raise MR to 32 Porter Road Brick 4' Pavement Above Grade 44 Lawson Street Brick 7' Pavement No 51 Lawson Street Brick 7' Pavement No 52 Sang Avenue Brick 12' Pavement No Sang Avenue 59 (Easement) Brick 5' Pavement No 81 Stephens Ave. Brick 5' Pavement No 145 T2-9 I REHAB CODES: 30 & 31 ' TABLE 2 (Cont.) MANHOLES REPUIRING EXCAVATING MH/LINE CONNECTION AND REPAIRING MANHOLE NO. STREET STRUCTURE DEPTH COVER OTHER WORK Minisystem 4 Plug Holes ' 148 Stanton Ave. Brick 5' Pavement in Cover 338 Masonic Drive Precast 7' Minisystem 7 30 Porter Road Brick 4' Stephens Ave. 106 (Easement) Brick 4' 111 S. Maxwell Dr. Brick 5' 116 N. Maxwell Dr. Brick 6' 149 Lonnie Avenue Precast 6' 167 Sang Avenue Brick 10' Plug Vent , Holes in Easement MH Lid ' Pavement No 1 Yard No , Clean Walls, Fill In Small Cracks & Waterproof Walls; Raise Manhole to Easement Above Grade Pavement No Yard No , Clean Walls, ' Fill In Small Cracks & Water- ' Pavement proof Walls 1 145 T2-10 MANHOLE N0. Minisystem 2 13 REHAB CODE: 32 TABLE 2 (Cont.)`"! MANHOLES REQUIRING REPLACEMENT OF ENTIRE MANHOLE STREET DEPTH COVER OTHER WORK South Street 9' Plug Vent Holes in Pavement MH Lid 145 T2-11 MANHOLE NO. Minisystem 2 112 113 128 153 156 TABLE 2 (Cont.) MANHOLES REQUIRING RAISING STREET DEPTH COVER Dickson St. 4' Easement Dickson St. 16' Pavement Olive Avenue 5' Pavement Dickson St. (Easement) 4' Woods Dickson St. 4' Pavement Minisystem 4 32 Sheryl Avenue 7' Easement 301 Plainview Ave. 4' Field Burrell St. 302 (Easement) 8' Easement 311 Plainview Ave. 6' Easement 312 Plainview Ave. 6' Easement 321 U.S. Hwy. 71 Bypass 9' Field 145 T2-12 ■ REHAB CODES: 33-38 OTHER WORK AMOUNT 1 RAISED ' No Above Grade No 8" No 9" No Above Grade ' No 3" No Above Grade No Above Grade I No Above Grade No Above Grade No Above Grade Clean Walls, Fill In Small Cracks , & Waterproof Walls Above Grade 1 1 REHAB CODES: 33-38 t TABLE 2 (Cont.5i' MANHOLES REQUIRING RAISING MANHOLE NO. STREET DEPTH COVER OTHER WORK AMOUNT RAISED Minisystem 7 2 West End Ave. 4' Easement No Above Grade 6 Above Valley Dr. 4' Easement No Above Grade 10 Porter Road 6' Easement No Above Grade Between Holly 14 & Hatfield Sts. 8' Yard No Above Grade Between Hatfield St. & Wedington 20 Drive 4' Yard No Above Grade Between Hatfield St. & Wedington 21 Drive 4' Yard No Above Grade Between Hatfield St. & Wedington 22 Drive 5' Easement No Above Grade Between Hatfield St. & Wedington 23 Drive 4' Yard No Above Grade 25 Aberdeen Ave. 4' Easement No Above Grade 28 Sang Avenue 5' Pavement No 2" Between. Holly 41 & Lawson Sts. 4' Field No Above Grade 145 T2-13 RFHAB CODES: 33-38 MANHOLE NO 53 62 64H 83 90 111 127 139 143 156 TABLE 2 (Cont.) MANHOLES REQUIRING RAISING STREET DEPTH COVER Sang Avenue 11' Pavement Lawson Street 6' Pavement Lewis Avenue (Easement) 6' Easement No Above Grade Stephens Ave. 7' Easement No Above Grade Comfort Road 5' Pavement No 6" OTHER WORK AMOUNT RAISED No Unknown No 2" S. Maxwell Dr Sunset Ave. Wedington Dr. Oak Drive West Berry St Between Weding- ton Drive & 164A Ora Drive 202 Aberdeen Ave. Clean Walls, Fill In Small Cracks & Water- proof Walls; Excavate Mil/ Line Connec- 5' Easement tion & Repair Above Grade 5' Pavement No 2" 7' Easement No Above Grade 6' Easement No 6" 5' Easement No Above Grade Clean Walls, Fill In Small Cracks & Waterproof 0' Field Walls Above Grade 5' Field No Above Grade 145 T2-14 REHAB CODES: 33-38 t TABLE 2 (Cont. ):n;: MANHOLES REQUIRING RAISING MANHOLE NO. STREET DEPTH COVER OTHER WORK AMOUNT RAISED Between Aberdeen & Bardolier 203 Avenue 5' Field No Above Grade Between Hwy. 16 W. & Cleveland 205 Street 5' Field No Above Grade Between Hwy. 16 W. & Cleveland 206 Street 5' Field No Above Grade U.S. Hwy. 71 Bypass 210 (Easement) 5' Field No Above Grade U.S. Hwy. 71 Bypass 215 (Easement) 4' Yard No Above Grade U.S. Hwy. 71 Bypass 216 (Easement) 4' Yard No Above Grade Minisystem 8. 12 Old Wire Rd. 6' Woods No Above Grade 155 Elm Street 5' Pavement No 2" 156 Elm .Street _ 6' Easement No 2" 242 Austin Drive 8' Pavement No 2" 258 Old Wire Rd. 8' Pavement No 2" 145. T2-15 REHAB CODES: 33-38 TABLE 2 (Cont.) MANHOLES REQUIRING RAISING MANHOLE NO. STREET DEPTH COVER OTHER WORK AMOUNT RAISED Minisystem 11 22A Township Rd. 4' Woods No Above Grade 46 Peg Lane 6' Yard No Above Grade 48 Peg Lane 7' Yard No Above Grade 49 Peg Lane 6' Easement No Above Grade 59 Sierra 7' Easement No Above Grade REHAB CODES: 33-38 Minisystem 16 5 Poplar St. 8' Pavement No 3" 21 N. College Ave. 5' Easement No Above Grade 24 N. College Ave. 7' Easement No 2" 44 Walnut Avenue 6' Easement No 18" 84 E. Lakeside Dr. 12' Pavement No 2" 145 T2-16 REHAB CODE: 40 TABLE 2 (Cont.) MANHOLES REQUIRING PLUGGING OF HOLES IN COVER AND RAISING FRAME TO STREET LEVEL MANHOLE NO. STREET DEPTH COVER OTHER WORK Minisystem 2 Between Mountain 162 & Rock Sts. 3' Pavement No 145 T2-17 Section 146 Backfill.ing PLACING PIPE PROTECTION COVER AND BACKFILL 146-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all materials, labor, equipment, tools, supplies, and incidentals necessary for backfilling areas excavated during the construction of sewer pipe lines, manholes, and other appurtenances. The work shall include every item of construction necessary for a complete and acceptable installation as shown on the Plans and hereinafter specified. 146-B. MATERIALS. Crushed Stone Backfill. Crushed limestone backfill be Class SB-2, as defined in Section 306 of t1 Arkansas State Highway Department Specifications. supplier shall submit certificates stating that the accordance with these Specifications. NOTE: This at the unit price bid in the proposal, and as Measurement and Payment. (where specified) shall ie 1978 Edition of the The crushed limestone material provided is in item shall be paid for set out in Methods of 146-C. CONSTRUCTION. Areas excavated for the construction of sewer lines, manholes, fittings, and other appurtenances shall have pipe protection. cover placed, and shall be backfilled in accordance with these Specifications. 1.. Pipe Protection Cover. In all areas of sewer line construction (excluding areas of construction within and approximately perpendicular to or crossing curb and gutter, a street, or other driving surfaces) pipe protection cover consisting of good earth, sand or gravel free from large stones or organic materials shall be placed over the top of the pipe. The pipe protection cover shall be hand and/or machine placed from the springline of the pipe to a point 12 inches above the top of the pipe by the width of the trench. When sewer line construction is within and approximately perpendicular ' to.or crossing curb and gutter, a street or other driving surface, the pipe protection cover shall consist of Class SB-2 crushed stone trench backfill as. defined in Section 146-B of these Specifications. The pipe protection cover shall be placed from the springline of the pipe ' to a point 12 inches above the top of the pipe by the trench width. 2. Backfilling. After the pipe protection cover has been placed, the I trench, excavated areas around manholes, and other appurtenances shall be backfilled in accordance to the following specifications depending upon the type of area in which excavation occurs. Extra care shall be exercised around manholes to assure that the backfill material is placed evenly around the perimeter of the manhole. Manholes shall not be backfilled prior to 12 hours after the manhole forms have been removed. 146-1 aCUL1UII 14O Backfilling a. Driving Surface Crossings (Perpendicular to Centerline). In all areas where excavation crosses within the limits of any driving surface, including paved and gravel streets or roads, driveways and parking lots, the entire depth and width of the trench shall be backfilled with crushed stone trench backfill from a point 3 feet outside each edge of the driving surface. The backfill shall be compacted or allowed to settle sufficiently to assure thorough consolidation of the material prior to making the pavement repair. As the ditch settles, additional crushed stone trench backfill shall be added to bring the ditch to finished grade. The intent of these Specifications is to insure that no settlement of the trench occurs after cleanup of final repair of street surfaces. In the event such does occur, it will be the responsibility of the Contractor to repair the settled areas.Driving surface repairs shall be made in accordance with the Specifications governing the type of pavement repair to be made. b. Parallel to Driving Surfaces (Excluding State Highways). In all areas where excavation is parallel to and within the limits of any driving surface, the trench shall be backfilled with excavated material to a point 12 inches below existing surface. The top 12 inches of the trench shall be backfilled with crushed limestone trench backfill immediately upon completion of the aforementioned portions of the backfilling operation. As the ditch settles, additional crushed stone trench backfill shall be added to bring the ditch to finished grade. The intent of these Specifications is to insure that no settlement of the trench occurs after cleanup or final repair of street surfaces. In the event such does occur, it will be the responsibility of the Contractor to repair the settled areas. Driving surface repairs shall be made in accordance with the Specifications governing the type of pavement repair to be made. c. Manholes Located within Driving Surfaces. In all areas where manholes or manhole appurtenances are constructed and/or replaced within the limits of any driving surface, the entire width and depth of the excavated area shall be backfilled with crushed limestone trench backfill. The backfill shall be completed or allowed to settle sufficiently to assure thorough consolidation of the material prior to making the pavement repair. The intent of these Specifications is to insure that no settlement of the trench occurs after cleanup or final repair of street surfaces. In the event such does occur, it will be the responsibility of the Contractor to repair the settled areas. d. Lawns, Gardens and Other Well -Kept Areas. After the pipe protection cover has been placed, the trench shall then be backfilled with excavated material. Topsoil stored along the trench line shall then be replaced to a minimum depth of 6 inches over the trench and 3 inches over all damaged surfaces. In the event there is insufficient topsoil stored along the ditch line to accomplish the topsoiling requirement, then the Contractor 146-2 • section 14b Backfilling shall haul indditional topsoil,to�meet this requirement and shall do so wit$2out additional cost: to the Owner, The topsoil over the trench shall be left slightly rounded in order to allow for some settlement. It is the intent of these Specifications to insure that no settlement of the trench occurs after seeding and mulching the areas. In the event such does occur, it will be the responsibility of the Contractor to repair the settled areas. e. Mowed or CultivatedAreas(Excluding Gardens). The requirements for backfilling in these areas is identical to that specified in Section 146—C.2.d above, except that it is the intent of the Specifications to -replace the top 6 inches of the soil using the excavated topsoil, regardless of the quality of that material. Only when the Contractor allows the material excavated from the top of the trench to become mixed with the remaining excavation will he be required to haul in additional material to replace the top 6 inches. If the Contractor is required to haul in additional material, he shall haul in good grade topsoil (free of roots, weeds, clay and rocks, and from a source approved by the Engineer) and shall do so without additional cost to the Owner. f. Steep, Wooded or Rocky Areas. After the pipe protection cover has been placed, the trench shall be backfilled with excavated material. The trench shall be compacted to insure that the backfill has been thoroughly consolidated. The trench backfill material shall be left slightly rounded to allow for additional settling. g. Sidewalks. In all areas where excavation crosses or is parallel to and within the limits of a sidewalk, the trench backfilling procedure shall be as specified for backfilling "Parallel to Driving Surfaces," Section 146-C.2.b of these Specifications. h. Curb and Cutter Crossings. In all areas where excavation crosses within the limits of curb and gutter, the trench. backfilling procedure shall be as specified for backfilling "Driving Surface Crossings," Section 146-C.2.a of these Specifications. i. Parallel to Curb and Gutter. In all areas where excavation is parallel to and within the limits of existing curb and gutter, the trench backfilling procedure shall be as specified for "Backfilling, Parallel to Driving Surfaces," Section 146-C.2.b of these Specifications. 3. Cleanup. Cleanup shall be in accordance with Section 900 of these Specifications. 4. Replacement and Repair of Driving Surfaces, Sidewalks, Curb and Cutter. Replacement and repair of driving surfaces, sidewalks, and curb and gutter shall be made in accordance with Section 300 of these Specifications. 146-3 oecuon iw Manholes CAST -IN -PLACE MANHOLES 150-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all materials, labor, equipment, tools, supplies, and incidentals necessary for the construction of standard and drop cast -in -place manholes. The work shall include every item of construction necessary for a complete and acceptable installation as shown on the Plans and hereinafter specified. Precast, brick, masonry, or vitrified clay radial block manholes are not approved for use on this project. 150-B. MATERIALS. 1. Concrete; Concrete used in the construction of standard and drop cast -in -place manholes shall be in conformance with the Concrete section of these Specifications. 2. Mortar and Grout. Mortar or grout used in the construction of manholes shall be mixed in the proportion of one part of Portland cement and two parts mortar sand as defined in the Concrete section of these Specifications. The mixture shall be dry -mixed until it has a uniform color, after which water shall be added or the mixing continues until. the mortar has a consistency such that it can be easily handled and spread with a trowel. Mortar or grout that has not been used within 30 minutes after water has been added shall not be used. 3. Manholes Steps. Steps shall be 10 inches wide and shall be constructed of steel reinforced fiberglass. Manhole steps shall be Perma-Step Model 100-2 as manufactured by Utility Products, Inc., or equal. 150-C. MANHOLE CONSTRUCTION. 1. Excavation for Manholes. Excavation for manholes will be made of such dimension and depth as to allow the construction of the manhole as shown on the Plans. No extra payment shall be made for manhole excavation, and all surface removal shall be in accordance with Section 095 of these Specifications. 2. Base. The concrete base shall have a minimum thickness of 8 inches and shall be poured on undisturbed earth. The base shall be poured so that the top of the base is a minimum of 2 inches and a maximum of 4 inches below the lowest pipe inside the manhole, except when the lowest pipe can be laid continuously through the manhole, the base may be poured to a point 2 inches below the centerline of the pipe, providing this point is not above invert of other pipes entering the manhole. The base shall have a minimum diameter of 8 inches greater than the outside diameter of the finished manhole barrel. .3. Connections to Manholes. Pipe connections to manholes are a constant source of potential trouble. In order to ensure that pipe will not break immediately adjacent to the manhole, care shall be taken that excavation for the manhole bottom is limited to the area to be filled 150-1 Manholes with concrete. The Contractor shall support pipe entering the manhole ALL OF THE WAY to solid bedding by backfilling under the pipe and up to mid-springline with concrete. 4. Invert. The invert of the manhole shall be hand -placed and shaped using grout as specified. The base and barrel of the manhole shall be cleaned thoroughly prior to placement of the invert. The invert shall be shaped and smoothed so that the manhole will be self-cleaning and free of areas where solids may be deposited as sewage flows through the manhole. The entire diameter of each pipe entering the manhole barrel shall be cut smooth with the inside edge of the manhole barrel and the invert shaped throughout from all inlet pipes to the outlet pipe. 5. Manhole Barrels. The barrel forms may be set as soon as the concrete base has cured enough to support the forms. The manhole barrel shall be of such construction so that the finished manhole will have an inside diameter of 4 feet 0 inches, plus or minus one-half inch. Prior to setting the forms in place, any water that may have accumulated in the excavated area shall be pumped out and the concrete base thoroughly cleaned, if required, of dirt and debris. Before pouring of the concrete begins, a 2 inch layer of grout mixture shall be placed in the bottom of the forms. The forms shall be removed after the initial set of the concrete so that holes may be cut in the manhole barrel for the installation of pipes which are to enter the manhole at points other than adjacent to the manhole base. After these pipes have been put in place, the barrel shall be repaired using a grout mixture. If honeycombing of the barrel is found to be present after removal of the forms, they shall be repaired as directed by the Engineer. 6. Manhole Steps. Manhole steps are required in all manholes 4 feet deep or more. During the construction of each manhole, steps shall be set in place on the inside of the manhole, beginning 2 feet above the bottom and placed not more than 18 inches below the top of the manhole. These steps are to be built to the dimensions shown on the Plans. The ends shall be firmly built into the wall., allowing the steps to project 5 inches from the inside of the manhole. 7. Manhole Heights. Manholes are to be built to the existing ground surface unless otherwise noted on the Plans or directed by the Engineer. When manholes are constructed in streets, the top of the poured manhole shall be left at such an elevation so that two rings of standard brick are required to bring the manhole ring to the finished elevation. A 3 inch wide by 2 inch deep keyway shall be left in the top of the poured manhole to hold the mortar for the first ring of bricks. All brick or block shall have full mortar joints on the bottom and sides. Every joint shall be formed at one operation by placing sufficient mortar on the bed and forcing the brick or block into it. Horizontal joints shall not exceed 3/8 inch and the vertical joints on the inside of the manhole shall not exceed 1/4 inch. The brick shall 150-2 UCll1VLL 1JV Manholes be plastered on both the inside and outside with 1/2 inch of cement mortar. The plaster shall be smoothly`'l`aid, and on the inside of the manhole all rough projections shall be removed. Details for the construction of manholes are shown on the standard detail sheet of the Plans. 8. Drop Manholes. Drop manholes, unless otherwise shown on the Plans, shall be constructed at all manholes where the difference in invert elevation between incoming and outgoing sewer is 2.5 feet or more. Drop manholes shall be constructed of the same material and dimensions as are standard manholes, the only difference being in the inlet arrangements as shown on the standard detail sheet. 9. Curing. Curing compounds option of the Contractor. the Contractor to protect curing process and to prot The Engineer shall, at his periods of extreme cold or or covers may or may not be used, at the However, it will be the responsibility of the concrete to prevent cracking during the act the manhole during freezing temperatures. discretion, prohibit pouring concrete during inclement weather. 10. Backfilling. The manhole shall be backfilled evenly around its perimeter no less than 12 hours after the forms have been removed. Extra care shall be taken to compact all backfill to the top of the highest pipe entering the manhole. All backfilling shall be in accordance with Section 146 of these Specifications. 11. Watertightness. All manholes constructed shall be watertight and show no visible evidence of infiltration, and shall be tested in accordance with this Specification. After the manhole rehabilitation, including curing, has been completed, then the manhole shall be tested. The test shall be conducted by the Contractor in coordination with and at the direction. of the Engineer. It is realized that there are certain conditions which will make manhole testing impractical or impossible to perform, such as excessively high sewer flows requiring bypassing of the sewerage, manholes with depths exceeding 20 feet, etc. When conditions of this nature are encountered, no testing will be required. Manhole testing shall be accomplished by an exfiltration test. All incoming and outgoing sewer lines shall be plugged and the manhole filled with water up to the corbel section. If the water loss exceeds the maximum allowable as shown below, the manhole shall have failed the test. Depthof Manhole Maximum Allowable Water Loss 0-8 feet 1 inch over -5 minutes. Over 8 feet 1/8 gallon per vertical foot over 5 minutes All manholes which fail the test shall be repaired or a new manhole constructed at the expense of the Contractor. 150-3 Section 160 Classification of Excavated Material CLASSIFICATION OF EXCAVATED MATERIALS 160-A. CLASSIFICATION OF EXCAVATED MATERIALS. Unless specifically provided for in the Proposal and Methods of Measurement and Payment, no provision is made for classifying excavation. In certain instances, however, provision is made in the Proposal for payment for rock excavation. Most of the work is generally in an area which might be underlain with broken chert, and in some instances may be solid sections of sandstone or limestone rock. To make a distinction between what should be classified as rock is very difficult. Consequently, the pay item for rock under this contract, if provision is made for such payment, will include: 1. All rock or chert in solid layers. 2. All consolidated chert which cannot be normally excavated with a three-quarter yard backhoe without undue damage to equipment. Broken and badly weathered chert which can be readily removed will not be classified as rock. Where broken chert or rock is consolidated so that it is only removed with considerable difficulty by the use of a backhoe, or requires undue hammering with the bucket, or where heavy rippers are required, or where it is necessary that materials be blasted, it shall be classified as rock. Rock or broken chert, excavated in construction of right of way, will not be classified and paid for as rock. Measurement for rock excavation will be made on the basis of a ditch width of 16 inches greater than the outside dimensions of the pipe being laid. Rock excavated shall be measured on the job at the end of each day's operation, and the quantity of rock agreed upon between the inspector and the Contractor or the Contractor's representative shall be recorded and initialed. 160-B. PAYMENT. There shall be no pay item for rock excavation in this contract. Rock excavation shall be considered subsidiary to pipe laying. I 1 I 160-1 JCL.LSULL IUU Mandrel Test MANDREL TEST 180-A. GENERAL. The work to be included under this Section of these Specifications shall consist of providing all labor, equipment, tools, supplies, and incidentals necessary for mandrel testing all acrylonitrile-butadiene-styrene (ABS) composite sewer lines. ABS composite sewer lines shall be mandrelled in conformance with these Specifications with the following exception: any line segment which has only been partially replaced with ABS composite shall not be mandrelled. 180-B. TESTING. Flexible sewer pipes shall be mandrelled with a rigid device sized to pass 5 percent or less deflection (or deformation) of the pipe. The mandrel (go/no-go) device shall be cylindrical in shape and constructed with either 9 or 16 evenly spaced arms or prongs. Mandrels with less arms (in odd or even numbers respectively) will be rejected as not sufficiently accurate. The contact length of the mandrel's arms shall equal or exceed the nominal diameter of the sewer to be inspected. Critical mandrel dimensions shall carry a tolerance of 10.01 inch. Pipe dimensions as contained in ASTM 2680, latest revision, shall be used to compute the mandrel dimensions. Allowances for pipe wall thickness tolerances or ovality (from shipment, heat, shipping loads, poor production, etc.) shall not be deducted from the base ASTM data, but shall be counted as a part of the 5 percent or lesser deflection allowance. The mandrel shall be hand pulled by the Contractor through all sewer lines. Any sections of sewer not passing the mandrel shall be uncovered and the Contractor shall reround or replace the sewer to the satisfaction of the Engineer. These repaired sections shall be retested. The inspection shall be conducted no earlier than 30 days after reaching final trench backfill grade, provided in the opinion of the Engineer that sufficient water densification or rainfall has occurred to thoroughly settle the soil throughout the entire trench depth. If this cannot be achieved in the time after installation prior to the project completion date, then the mandrel size shall be increased to measure 1/3 less of a deflection allowance. Drawings of the mandrel with complete dimensioning shall be furnished by the Contractor to the Engineer for his approval for each diameter and specification of pipe. 180-1 Section 190 Air Testing LOW PRESSURE AIR TESTING FOR SEWER LINES 190-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all labor, equipment, tools, supplies, and incidentals necessary for low pressure air testing of all sewer lines. Sewer line segments which have been scheduled for only partial replacement shall not be air tested. 190-B. TESTING. After the sewer line has been installed and manholes constructed, the Contractor shall proceed to air test all sewer lines to determine if sewers are free of breaks or other defects which would permit excessive infiltration or exfiltration. The test shall be performed according to the provisions of ASTM C828, latest revision, and these technical Specifications. The sewer line shall be air tested prior to backfilling or reconnecting the existing service lines. On all gravity flow sewers, the Contractor shall conduct low pressure air tests of the various sections of pipe by use of equipment manufactured for this purpose. The equipment shall include a regulator to avoid overpressurizing and possibly damaging an otherwise acceptable line. The equipment used shall be identical or equal to the Air-Loc system as manufactured by Cherne Industrial, Inc., Hopkins; Minnesota. The low pressure air test shall be conducted by plugging each opening in the reach of pipe to be tested, including all service wyes, tees or saddles. All plugs shall be braced against slippage due to internal pressure, and no one shall be allowed in the manhole during the testing procedure. One of the plugs provided must have an inlet tap or other provision for connecting an air hose. After connecting the air, control equipment to the air hose, monitor the air pressure so that the internal pressure does not exceed 5.0 psig. After reaching 4.0 psig, the air supply shall be throttled to maintain between 4.0 and 3.5 psig for at least 2 minutes in order to allow equilibrium between air temperature and the pipe walls. If plugs are found to leak, the Contractor shall bleed off the air, tighten the plugs, and again begin supplying air. After the temperature has stabilized, the pressure is allowed to decrease to 3.5 psig. At 3.5 psig, the Contractor shall begin timing to determine the time required for the pressure to drop to 2.5 psig. The pipe shall be presumed free of defects if the time, in seconds, for the air pressure to decrease from 3.5 psig to 2.5 psig is greater than that shown in the table below. " Pipe Size Minimum Time Pipe Size Minimum Time (Inches) (Minutes/100 Ft.) (Inches) (Minutes/100 Ft.) I 3 0.2 21 3.6 4 0.3 27 4.2 6 0.7 30 4.8 I 8 1.2 33 5.4 10 1.5 36 6.0 12 1.8 39 6.6 18 2.1 42 7.3 190-1 Air Testing If by use of the above procedure, defective section(s) of line are found, the ' line segment shall be tested at 20 foot intervals to determine the exact location of the defect(s). Repairs shall be made in defective section(s) and the entire line segment shall then be retested. I I I 190-2 section Suu STREET OVERLAY, DRIVING SURFACE; SIDEWALK, AND_CURB AND GUTTER REPAIR 300-A. GENERAL. The work to be. included under this section of the Specifications shall consist of providing all labor, equipment, tools, supplies, and incidentals necessary for the repair of driving surfaces, curb and gutter, and sidewalks. This specification is intended for any driving surface, paved or unpaved, including but not limited to streets, roads, driveways, and parking lots. This specification does not apply to state or interstate highways, or driving surfaces within railroad rights of way unless otherwise directed by the Engineer. 300-B. MATERIALS. 1. Prime Coat. Prime coat material shall be Grade MC -30 as set forth in Table II on page 160 of the 1978 Edition of the Arkansas State Highway Department Standard Specifications. 2. Tack Coat. Tack Coat material shall be Grade SS -1, as set forth in Table III on page 161 of the 1978 Edition of the Arkansas State Highway Department Standard Specifications. 3. Hot -Mixed, Hot -Laid Asphaltic Concrete. The hot -mix. asphalt surface course shall conform in composition to the weights and gradation of Type 2 asphalt as set forth under Section 408, page 174, of the 1978 Edition of the Arkansas State Highway Department Standard Specifications, using asphalt cement viscosity grade AC -30. 4. Concrete.. Concrete shall be as defined in Section 800 of these Specifications. 5. Reinforcing Steel. Reinforcing steel shall be as defined in Section 810 of these Specifications. . 6. Crushed Stone Base. Crushed stone base shall be in conformity with the gradation and hardness requirements as set forth under Section 306 of the 1978 Edition of the Arkansas Highway Department Standard Specifications, Class SB-2. The crushed stone supplier shall submit certificates stating that the materials provided are in conformance with these specifications. 7. Curb and Gutter Joint Sealer. Curb and gutter joint sealer shall be either Type 1, Type 2, or Type 3 in accordance with Section 501 of the 1978 Edition of the Arkansas State Highway Department Standard Specifications. 300-C. MATERIALS AND CONSTRUCTION. The following Specifications are hereby referenced and made a part of these Specifications. These Specifications are contained in the "Standard Specifications for Highway Construction," Edition of 1978, published by the Arkansas State Highway Commission. The page numbers 300-1 _IC 1. L LULL JVV given below refer to pages in these "Standard Specifications for Highway Construction." These Specifications are available for inspection in the Engineer's office, or may be obtained from the Arkansas State Highway Department, Little Rock, Arkansas, and are set out below. Bituminous Pavement, Part 400 Pages Prime and Tack Coats, Section 401 . . . . . . . . . 150-153 Materials and Equipment for Bituminous Surface Courses, Section 403 . . . . . . . . . . . . 157-165 Asphaltic Concrete Hot -Mix Surface Course, Section 408 . . . . . . . . . . . . . . . . . 174-177 Materials and Equipment for Hot -Mix Bituminous Binder and Surface Courses, Section 409 . . . 177-188 Construction Methods for Hot -Mix Bituminous Binder and Surface Courses, Section 410 . . . 188-195 300-D. CONSTRUCTION. Pavement Removal, Pipe Protection Cover and Backfill. The pavement shall be removed, pipe protection cover placed, and trench backfilled in accordance with the pipe Specifications according to the type of pipe sewer being installed. All pavements which have been removed or damaged shall be repaired in accordance with these Specifications depending upon the type of pavement existing prior to construction. No payment for repair will be made for pavements damaged outside the width of allowable removal set out in Section 095 of these Specifications. a. Asphaltic Pavement Repair. After the trench has been backfilled, the trench shall be permitted to settle as set out in Section 146 of these Specifications. After this time the permanent repair shall be made as follows. The existing pavement shall be saw -cut and removed to a point 18 inches beyond the trench line limits, and brought to grade 3 inches below the top of the existing pavement. This area shall then be resurfaced by applying asphaltic cement prime coat at the rate of 0.25 gallons/square yard, followed by a minimum of 3 inches of hot -mixed, hot -laid asphaltic concrete, laid to an elevation matching the existing finished grade. The hot -mixed, hot -laid asphaltic concrete shall be compacted to 92 percent of theoretical density. One nuclear densometer test per asphaltic patch or repair shall be performed. The asphaltic pavement repair shall be deemed acceptable by the Engineer upon a passing nuclear densometer test at a location as directed by the Engineer. The cost of determining the compacted density shall be at the expense of the Contractor. 300-2 Section 300 Any unacceptable patch or repair shall be recompacted and retested at the Contractor's expense. b. Concrete Pavement and Asphaltic Overlaid Concrete Pavement Repair. After the trench has been backfilled, the trench shall be permitted to settle as set out in Section 146 of these Specifications. The trench area and an area 12 inches either side of the trench shall be brought to a grade 8 inches below the top of the existing concrete pavement. One-half (1/2) inch diameter reinforcing steel shall be drilled and grouted into the existing pavement at 12 inch centers both ways. Concrete shall then be poured into the excavated area to an elevation matching the existing finished grade, and troweled or brushed to match the existing finish. If the existing surface is a bituminous overlay, lamp black shall be mixed into the top 1 inch of the concrete to match the color of the surrounding pavement. c. Unpaved Driving Surface Repair. After the trench has been. backfilled and allowed to settle as set out in Section 146 of these Specifications, the surface shall be brought to the existing grade with additional crushed stone base. 2. Pavement Overlay. Some streets may require an overlay. Streets shall be overlaid only as shown on the Plans. Payment for street overlays shall be made under the appropriate items as set out in the Methods of Measurement and Payment. a: Surface Preparation. Excavated areas within the limits of sewer line construction shall be backfilled in accordance with the pipe specifications.. All areas within the limits of the street overlay which show evidence of chuck holes, cracks, etc. shall be repaired and patched with an asphalt mixture. After the Contractor has completed all patching required, the surface shall be thoroughly cleaned and swept with power brooms. When the surface is distorted, construction of leveling courses or leveling wedges shall be required to restore proper line and cross-section. Leveling wedges are patches, of asphalt hot mix used to level sags and depressions in existing old pavement prior to the overlay operation. b. Tack and Prime Coats. (1) Prime Coat. Prior to the placement of the asphaltic overlay a prime coat shall be applied to areas within the limits of the pavement removal at the rate of 0.25 gallons per square yard. This item shall be considered subsidiary to asphalt concrete hot -mix surface course. 300-3 VG.L 1Vll JlV (2) Tack Coat. Prior to the placement of the asphaltic overlay a tack coat shall be applied to the existing pavement at the rate of 0.10 gallons per square yard. This item shall be considered subsidiary to asphaltic concrete hot -mix surface course. c. Asphaltic Concrete Hot -Mix Surface Course. A laver of asphaltic concrete of the thickness as shown on the Plans or directed by the Engineer, shall be placed on all street areas to be paved or overlaid, as shown on the Plans. The asphalt shall be placed by a self-propelled asphalt laying machine equipped with an adjustable vibrating screed, and of such size as will permit the laying of one-half street width during each pass of the machine. Asphalt placement shall be in accordance with Section 300-C of these Specifications. Where possible the entire width shall be overlaid with one pass, thereby eliminating the longitudinal joint. The finished bituminous course shall be compacted to not less than 92 percent of theoretical density. A mix design shall be submitted to the Engineer for approval prior to use of any materials. Approximately one nuclear densometer test per 300 Linear Feet of asphaltic overlay shall be performed, but in no case shall less than 2 tests be conducted per overlay. The asphaltic pavement repair shall be deemed acceptable by the Engineer upon passing nuclear densometer tests at locations directed by the Engineer. The cost of determing the compacted density shall be at the expense of the Contractor. Any unacceptable overlaid area shall be recompacted and retested at the Contractor's expense. 3 Curb and Cutter Repair. The Plans show the location of curb and gutter to be replaced. The curb and gutter shall be constructed on previously placed trench backfill material. Expansion joints shall be made at drop inlets (if required), radius points and at intervals not greater than 50 feet along the curb line. The joint shall not be less than one-half inch thick and shall be filled with joint filler neatly trimmed to match the cross section of the curb and gutter. Contraction joints shall be either formed or sawed at a spacing of not more than 10 feet to a depth of 1' inches. All joints shall be filled with an approved joint filler and sealed. The concrete shall be placed on subgrade that has been watered down, and shall be vibrated and spaded until the mortar is evenly spread. The surface shall be finished smooth with rounded corners. The curing of the concrete shall be controlled and the concrete protected in accordance with the prevailing weather conditions at the time of the pour. Concrete will not be poured when the outside temperature is below 40° F. within four hours after the last batch is poured. 300-4 Section 300 When the curb and gut1er4,have_ cured,1;the,Contractor will shape the area behind the curb to th', existing finishedTgrade. Extreme care shall be exercised to avoid damage to the curb and gutter during the backfill operation.. Any such damage will be replaced at the Contractor's expense. 4. Sidewalk Repair. The Plans show the locations of sidewalks to be repaired. The sidewalk shall be placed on trench backfill material as previously specified. The concrete shall be placed on subgrade that has been watered down, and shall be vibrated and spaded until the mortar is evenly spread. the surface shall be finished smooth with rounded corners. The curing of the concrete shall be controlled and the concrete protected in accordance with the prevailing weather conditions at the time of the pour. Concrete will not be poured when the outside temperature is below 40° F. within four hours after the last batch is poured. Nonreinforced Portland cement concrete sidewalks shall be constructed at the locations shown on the Plans. The sidewalks shall be constructed to the width as required to•match the existing sidewalk. The thickness shall be a minimum of 4 inches, and contraction joints shall be either formed or sawed at a spacing of not more than 5 feet 0 inches. Redwood expansion joints shall be placed at no greater than 30 foot intervals. Expansion joints shall be placed between the sides of the walks and adjacent curb pavement or other structures. This space shall be filled with approved joint sealer. The finish shall be a light broom finish. 5. Barricades, Guards and Safety Provisions. To protect persons from injury and to avoid property damage, adequate barricades, construction signs, torches,, red lanterns and guards as required shall be placed and maintained during the progress of the construction work and until it is safe for traffic to use the highway. All material piles, equipment and pipe which may serve as obstructions to traffic shall be enclosed by fences or barricades and shall be protected by proper lights when the visibility is poor. Execution of all safety precautions set forth in the Special Conditions is the sole responsibility of the Contractor. 6. Maintenance of Traffic and Closing of Streets. The Contractor shall carry on the work in a manner which will cause the least interruption to traffic, and may close to trough travel not more than two consecutive blocks, including the cross street intersected. Where traffic must cross open trenches, the Contractor shall provide suitable bridges at street intersections and driveways. The Contractor shall post suitable signs indicating that a street is closed and necessary detour signs for a proper maintenance of traffic. 7. Piling Excavated Material for Reuse. All excavated material which is to be reused shall be piled in a manner that will not endanger the work and that will avoid obstructing sidewalks and driveways. Hydrants under 300-5 ucl WLI JVV . pressure, valve pit covers, valve boxes, curb stop boxes, fire and police call boxes, or other utility controls shall be left unobstructed and accessible until the work is completed. Gutters shall be kept clear or other satisfactory provisions made for street drainage, and natural water courses shall not be obstructed. 8. Removal of Excess Material. All excess excavated material shall be loaded in trucks during the excavating operation, hauled from the job site and disposed of at the option of the Contractor. 9. Cleanup. Cleanup of areas behind the curb and gutter and around sidewalks shall be in accordance with Section 900 of these Specifications. ' 300-6 Section 500 Point Repairs POINT REPAIRS, 500-A. GENERAL. The work to be included under this section of the Specifications shall consist of providing all materials, labor, equipment, tools, supplies, bypass pumping, and incidentals necessary to plug or repair existing sewer line segments and appurtenances. 500-B. CLASSIFICATION OF POINT REPAIRS. Point repairs shall include such repairs as are generally set out in Tab].e 3 below, and hereinafter specified. Also listed in Table 3 is the related point repair rehabilitation code as referenced on the Plans and in these Specifications, and the primary bid item(s) under which payment will be made as set out in the Methods of Measurement and Payment. Rehabilitation Method Plug Overflow at Exit Excavate and Repair Faulty Main Line Tap Under Easement TABLE 3 Rehabilitation Code 1 18 Bid Items 1 Excavate and Repair Faulty Main 19 Line Tap Under Pavement The line segments upon which point repair rehabilitation work is required are set out in tabular form in Table 4 at the end of this section of the Specifications. ' 500-C. MATERIALS. 1. Crushed Limestone. Crushed limestone trench backfill (where specified) ' shall be Class SB-2, as defined in Section 306 of the 1978 Edition of the Arkansas State Highway Department Specifications. Note: This item shall be paid for at the unit price bid in the proposal, and as set out in the Methods of Measurement and Payment. ' 2. Concrete. Concrete shall be as defined in Section 800 of these Specifications. ' 3. Sewer Pipe and Appurtenances. All sewer pipe, fittings, joints, lubricant, bedding and backfill gravel shall be in conformance to the ' Pipe Specifications, depending upon the type of pipe used. 500-D. CONSTRUCTION. Methods for performing each of the Rehabilitation Methods contained in Section 500-B above are set out as follows. 1 500-1 Point Repairs 1. General Construction. I a. Flow Control and Bypass Pumping. All flow control and bypass pumping as necessary shall be provided by the Contractor. All bypass pumping required during construction shall be in accordance with Section 090 of these Specifications. There is no separate pay item for bypass pumping and bypass pumping, as necessary, shall be considered subsidiary to the rehabilitation method employed. b. Surface Removal. Surface removal shall be in accordance with Section 095 of these Specifications. There is no separate pay item for the removal of existing cover or excavation, and any such removal or excavation shall be considered subsidiary to the rehabilitation method employed. c. Driving Surface, Sidewalk, and Curb and Gutter Repair. After the proposed manhole rehabilitation has been completed, all paved and unpaved driving surfaces, driveways, parking lots, sidewalks, and curb and gutter shall be repaired as set out in Section 300 of these Specifications. Payment for the different types of surface repairs shall be made to the Contractor as set out in the Methods of Measurement and Payment except that damage to any groundcover, driving surface, sidewalk or curb and gutter while performing manhole rehabilitation under Rehabilitation Code I shall be considered non -essential, and the Contractor shall be responsible for repairing any damaged areas at his own expense. d. Cleanup. After the proposed manhole rehabilitation has been completed, the Contractor shall clean up the area in accordance with Section 900 of these Specifications. Payment for cleanup shall be made to the Contractor as set out in the Methods of Measurement and Payment section of these Specifications except that damage to any surface while performing manhole rehabilitation under Rehabilitation Codes 27, 28, 29 or 40 shall be considered non -essential, and the Contractor shall be responsible for repairing damaged areas at his own expense. 2. Plug Overflows at Exit (Rehabilitation Code No. 1). Overflows and bypasses exist at lift stations and manholes. The Contractor shall be responsible for making a watertight repair at the overflow or bypass outlet at the locations shown or. the Plans and as hereinafter specified. The overflow line shall be thoroughly cleaned at the inlet point for a distance of 24 inches down the overflow line. A watertight concrete plug shall then be poured down the overflow line for a distance of 12 inches. NO OVERFLOWS SHALL BE PLUGGED UNTIL EVERY OTHER ITEP1 OF CONSTRUCTION AND REHABILITATION HAS BEEN COMPLETED UNDER THIS CONTRACT. 3. Excavation and Repair of Faulty Main Line Taps (Rehabilitation Codes 18 and 19). The Contractor shall be responsible for repairing the point where the service line connects with the main line. 500-2 Section 500 Point Repairs Main line tap repairssare.indicated, 4n;Table 4 at the end of these Specifications. Some of these line segments have not been previously televised to locate the exact point(s) requiring repairs. On these segments, the line shall be cleaned and televised to find the exact point of repair, as determined by the Engineer. After the point has been established, the repair shall be initiated. The Contractor shall be responsible for repairing the main line tap so that no possible infiltration or inflow may be created. a. Trench Preparation. All trench preparation and construction shall be made in accordancewith the detail sheet of the Plans and Pipe Specifications Section 100-C.4 of these Specifications except that the trench shall be excavated to a depth so that a concrete collar may be placed in conformance to the dimensions as shown on the Plans. b. Repair of the Main Line Tap Connection. . The main line tap connection shall be externally sealed with "Ram -Neck" flexible ' plastic material, or equal. The sewer line and service line are to be cleaned with a wire brush to remove any dirt, mud, or other debris from the lines. An unreinforced concrete collar shall then be poured so as to encase the main sewer line and service line, I. and shall extend a minimum of 6 inches above, below, and on both sides of the main line and service line. The encasement shall extend a distance of 12 inches from the point of connection of the ' service line and main line along the service line, and a distance of 12 inches along the main line on both sides of the service line. I c. Pipe Protection Cover and Backfilling. After the initial set of the concrete encasement, pipe protection cover and backfill shall be placed in accordance with Section 146 of these Specifications. I I I I I I 500-3 REHAB CODE: 1 TABLE 4 MAINLINES REQUIRING PLUGGING OF OVERFLOW LINE OTHER NUMBER STREET COVER WORK Minisystem 2 2/3 Seventh Street Field No Minisystem 8 PS6/Creek State Hwy. 265 N. Yard No REHABILITATION METHOD AND LOCATION Plug Overflow at Exit Plug Overflow at Exit 500 T4-1 REHAB CODES: 18 & 19 TABLE 4 (Cont.) MAINLINES REOUIRING TAP REPAIRS LINE NO. TELEVISED REHABILITATION SIZE/LENGTH OTHER DURING METHOD AND MATERIAL STREET DEPTH COVER WORK SURVEY LOCATION Minisystem 2 9/10 2 Main Line Tap 8'/335' East Repairs at 225' Clay Avenue 10 Pavement No Yes & 293' from MR 10 30/31 South Main Line Tap 12'/110' College Repair at 102' Clay Avenue 4' Pavement No Yes From WI 31 71/72 Main Line Tap 10"/408' Mill Repair at 233' Clay Avenue 6' Pavement No Yes From MM 72 Minisystem 7 64/117 Main Line Tap 6"/345' Lewis Repair at 196' Clay Avenue 8' Pavement No Yes From MH 117 64E/64F Main Line Tap 6"/293' Lewis Repair at 107' Clay Avenue 9' Easement No Yes From MN 64F 160/161 Wedington Main Line Tap 8"/315' Drive Repair at 150' Clay (Easement) 6' Yard No Yes From MM 161 166/167 2 Main Line Tap B"/272' Sang Repairs at 28' & Clay Avenue 9' Pavement No Yes 231' From MIT 167 5O0 T4-2 Section 800 Concrete 800-A. GENERAL. This item shall consist of forms, providing all labor, equipment, tools, supplies, and incidentals necessary for the construction of concrete structures, tanks, bridges, culverts and miscellaneous work, including the concrete portions of steel, timber, stone masonry and composite structures, prepared and constructed in accordance with these Specifications, and conforming to the lines, grades, dimensions, and designs shown on the Plans. Concrete shall consist of an approved Portland cement, a fine aggregate, a coarse aggregate, and water mixed in the proportions specified. Air entrainment shall be accomplished by the addition of an air -entraining agent to the mixing water. The various materials entering into the composition of the concrete shall be such as will satisfy the requirements specified into this section. 800-B. MATERIALS. The materials used shall conform to the requirements as set out herein. No materials shall be used containing foreign matter, frost, or lumps or crusts of hardened substances. The gradation of the aggregate shall be determined by laboratory methods with sieves having square openings. The Contractor or producer shall use the size, length and character of screen and method of crushing and screening that is best suited to produce the different sizes of aggregate required. 1. Water. All water used in mixing or curing shall be clean and free from injurious amounts of oil, salt, or other deleterious substances. Where the source of water is relatively shallow, it shall be obtained at such a depth, and the intake so enclosed as to exclude silt, mud, grass or other foreign materials. ' 2. Cement. Portland cement shall conform to the requirements of the current A.A.S.H.O. Specifications, Designation M 85, for Portland cement. Unless otherwise provided, Type I shall be furnished. Only one brand of ' any one type of cement shall be used on the contract except by written permission of the Engineer. The Contractor may use, subject to the approval of the Engineer, Type 'III, a high early strength Portland cement. When a type of cement not specified on the Plans or in the Specifications ' is permitted by the Engineer, any additional cost shall be assumed by the Contractor. ' 3. Air -Entraining Agent. The air -entraining agent shall comply with the requirements of Standard Specifications of Air -Entraining. Admixtures for Concrete, A.A.S.H.O. Designation M-154, and shall be added to the mixing ' water in solution. The Contractor shall submit evidence based on tests made in a recognized laboratory to show that the air -entraining admixture conforms to the requirements of the latest revision A.A..S.H.O. M-154 (ASTM C206) for seven and 28 •day compressive and flexural strengths and ' resistance to freezing and thawings, except as provided in the following paragraph. Tests for bleeding, bond strength and volume change will not be required. A "recognized" laboratory is any State Highway, Bureau of 1 800-1 Concrete Public Roads or cement concrete laboratory Cement Reference Laboratory of the National may be made upon samples taken from a Contractor for use on the project or upon sai by the manufacturer as representative of the regularly inspected by the Bureau of Standards. Tests quantity submitted by the aples submitted and certified admixture to be supplied. An exception to the requirements in the preceding paragraph is the case of admixtures which are manufactured by neutralizing Vinsol resin with caustic soda (sodium hydroxide). When the Contractor proposes to use such an admixture he shall submit a certification concerning the admixture in the following form: "This is to certify that the product (trade name) as manufactured and sold by the (company) is an aqueous solution of Vinsol resin that has been neutralized with sodium hydroxide. The ratio of sodium hydroxide to Vinsol resin is one part of sodium hydroxide to (number) parts of Vinsol resin. The percentage of solids based on the residue dried at 105° C. is (number). No other additive or chemical agent is present in this solution." When the Contractor proposes to use an air -entraining admixture which has been previously approved, he shall submit a certification stating that the admixture is the same as that previously approved. If an admixture offered for use is essentially the same (with only minor difference in concentration) as another previously approved material, a certification will be required stating that the produce is essentially the same as the approved admixture and that no other admixture or chemical agent is present. Either prior to or at any time during construction the Engineer may require that the admixture selected by the Contractor be further tested to determine its effect upon the strength of the concrete. When so tested, seven-day compressive strength of concrete made with the cement and aggregates in the proportions to be used in the work and containing the admixture under test in an amount sufficient to produce 5 percent ±1 percent entrained air in the plastic concrete shall be not less than 88 percent of the strength of concrete made with the sane materials and with the same cement content and consistency but without the admixture. The percentage reduction in strength shall be calculated from the average strength of at least five standard 6 inch by 12 inch cylinders of each type of concrete. Specimens shall be made and cured in the laboratory in accordance with the requirements of the latest revision of the A.A.S.H.O. T-126 (ASTM C 192) and shall be tested in accordance with the requirements of the latest revision of A.A.S.H.O. T-22 (ASTM C 39). The percentage of entrained air shall be determined in accordance with the requirements of the latest revision of A.A.S.H.O. T-152 (ASTM C 231). Cement furnished in sacks shall weigh not less than 94 pounds net per sack, the use of cement salvaged from used or discarded sacks will not be allowed, nor will the mixing or alternate use of different brands of 800-2 Section 800 Concrete cement be permitted•.%:.*Cement placed-.,,inr°storage shall be suitably protected. Any retrogr sign in quality "'occurring during the storage period will be cause for rejection. If the cement furnished shows erratic behavior under the field conditions incident to the pouring and placing of the concrete, or in regard to the strength of the finished product, or in the time of the initial or final set, the Contractor will at once, without notice from the Engineer, cease the use of that brand of cement and furnish cement of such properties as to ensure work of a quality satisfactory to the Engineer. 4.. Coarse Aggregate. The coarse aggregate shall consist of crushed stone or gravel. A coarse aggregate consisting of a combination of crushed stone and gravel shall be used only when specifically approved by the Engineer. Crushed stone shall consist of clean, tough, durable fragments of rock of uniform quality. The stone shall have a percent of wear or not more than 40 (Los Angeles test) and when subjected to five cycles of the soundness test (Sodium Sulphate), shall have a loss not to exceed 12 percent. Gravel shall consist of clean, hard, durable, uncoated pebbles, crushed or uncrushed, having a percent of wear of not more than 40 (Los Angeles test) A.A.S.H.O. Designation T-96. When tested by laboratory methods the amount of deleterious substances ' will not exceed the following limits: Maximum Permissible ' Percentage by Weight Removed by decantation -------------------- 1% I Coal and signite-- 0.25% Clay lumps 0.25% - Soft fragments _____ 5% Total deleterious substances -----------5% ' Coarse aggregate size shall be reasonably well graded from coarse to fine and shall conform to the following grading requirements: Class A(AE) Concrete: Retained on 1-1/4" sieve ------------------ 0% ' Retained on 3/4" sieve -------------------- 20-65% Retained on 3/8" sieve 70-90% Retained on No. 4 sieve ------------------- 95-100% ' Coarse aggregate from any one source shall not vary as to maximum size and shall be uniform to a reasonable degree in gradation with the t representative sample submitted by the Contractor, with the further provision the aggregate furnished from any one source having a variation in fineness modulus greater than 20 points either way from the fineness modulus of the representative sample submitted by the Contractor will not be accepted under the Specifications. 800-3 Concrete 5. Fine Aggregate. The fine aggregate shall consist of clean, hard, durable particles of natural sand or other approved inert material with similar characteristics. The amount of deleterious substances shall not exceed the following limits: Maximum Permissible Percentage by Weight Removed by decantation Clay lumps ----------- Coal and lignite ----- Soft and flaky particles 2% 0.50% 0.25% 2% The fine aggregate shall be free from injurious amounts of organic impurities and shall pass the mortar strength test as specified in the following: When the fine aggregate is mixed with Portland cement in the proportion of one part of cement to three parts of fine aggregate, the tensile strength compared to standard Ottawa sand mortar specimens made with the same cement of the same proportions and consistency shall not be less than 100 percent at seven and 28 days, Fine aggregate shall be reasonable well graded from coarse to fine, and shall conform to the following grading requirements: Total retained on 3/8" sieve --------------- 0% Total retained on No. 4 sieve -------------- 0-5% Total retained on No. 8 sieve -------------- 5-30% Total retained on No. 16 sieve ------------- 20-55% Total retained on No. 30 sieve ------------ 40-80% Total retained on No. 50 sieve ------------- 70-95% Total retained on No. 100 sieve ------------ 95-100% 6. Mortar Sand. Fine aggregate from any one source shall be uniform to a reasonable degree in gradation with the representative sample submitted by the Contractor, with the further provision that aggregate supplied from any one source having a variation in fineness modulus greater than 20 points either way from the fineness modulus of the representative sample submitted by the Contractor will not be accepted. Mortar sand, when specified, shall meet the following gradations: Passing No. 8 sieve ------------------------ 100% Passing No. 50 sieve -----------------------15-40% Passing No. 100 sieve ------------------- 0-10% 7. Joint Fillers. The material for filling and sealing joints shall comply with the Specifications for one or more of the following types, a. Preformed Joint Fillers. Preformed joint filler, bituminous type, shall meet the requirements of the current A.S.T.M. Specifications, Designation D 994 (A.A.S.H.O. Designation M-33). 800-4 Section 800 Concrete 1. Preformed•expansion :joint filler;,•non;extiuding and resilient types, shall meet the'Y' requirements of the current A.A.S.H.O. Specifications, Designation M-153, except that all materials shall require a load of at least 100 pounds per square inch for compression to 50 percent of original thickness. Unless otherwise designated on the Plans or in the Detailed Specifications, Type III filler shall be used: b. Poured Joint Filler. Poured prepared mixture of asphalt and shall be diatomaceous earth. 7 and shall not foam when heated application, 400° to 485° F. following requirements: Joint filler shall consist of a mineral filler. The mineral filler he mixture shall be free from water to the proper temperature range for It shall also comply with the Specific Gravity at 77° - Softening Point -------------------- Penetration at 77° F. 100 gm. 5 sec. - Penetration at 32° F. 200 gm. 1 min. - Penetration at 115° F. 50 gm. 5 sec. - Flash Point ------------------------ Ash-------------------------------- Settlement Ration ------------------ Ductility at 77° F. ------------=---- Flow at 140° F. -------------------- 1.02 min. 183° F. to 200° F.. 68 to 88 38 min. 160 max. 550° F. min. 8% min. 1.02 max. 5 min. 0.5 cm. max. 8. Water Stops. Synthetic rubber and metal water stops shall conform to the requirements of the Specifications covering Reinforcing Steel as hereinafter set out. 800-C. CLASSES OF CONCRETE, PROPORTIONING AND CONSISTENCY. 1. Class A(AE) Concrete. All concrete provided shall be Class A(AE) concrete and shall be i-n conformance with the Specifications. 2. Proportioning. The concrete mixture shall be proportioned as so to secure a workable and durable concrete, as hereinafter specified. Class A(AE) Concrete Designated Size of Coarse Aggregate - 114" to Minimum Cement Factor --------------- 6 Bags Maximum Net Water Content per Bag (94 lbs.) of cement -------- 5½ gal Range in Slump =--------------------- 2 to 4 Air Content (Range) ----------------- 4 to 6 No. 4 Square Openings per Cubic Yard Ions inches percent. The Contractor shall -provide laboratory design mixes for approval by the Engineer. The concrete materials shall be proportioned as determined by the Engineer using the Absolute Volumes method in accordance with- the requirements for each class specified above. It is the intent of the U 800-5 Concrete above limits to produce a concrete with a minimum 28 day compressive strength of 3,000 pounds per square inch. The compressive strength will be determined from testing cylinders which have been sampled from concrete used in the structure, cured under the same conditions as the structure, made and compression tested in accordance with the current American Association of State Highway Officials Specifications, Designation T-23, covering the testing of molded cylinders. If the strength required for the class of concrete being produced is not secured with the minimum cement content specified, additional cement shall be used at the Contractor's expense. When the Contractor proposes to use a new source of material which has not been proven by past experience, he shall submit samples sufficiently in advance so that trial mixes can be prepared and the concrete tested as provided above. The air entrainment shall be accomplished by adding to the mixing water the proper amount of air -entraining agent in solution. The Engineer shall determine by means of trial batches on the project the amount of admixture required to produce an air content within the range specified. The mixer shall be equipped with a suitable automatic dispenser for adding to the mixing water the desired amount of air -entraining agent. The dispenser shall be constructed and connected so that the Inspector can make ready determination of the amount of air -entraining admixture entering the mixing water. 3. Consistency. Concrete shall have a consistency such that it will be workable in the required position. It shall be of such a consistency that it will flow around reinforcing steel but individual particles of the coarse aggregate when isolated shall show a coating of mortar containing its proportionate amount of sand. The consistency of concrete shall be gauged by the ability of the equipment to properly place it and not by the difficulty in mixing or transporting. The quantity of mixing water shall be determined by the Engineer in accordance with Section 800-A.2 above and shall not be varied without his consent. In general, the slump for concrete, placed by the usual methods or by the vibration method, shall comply with the requirements of Section 800-C above, unless otherwise authorized by the Engineer. 800-D. SAMPLING AND TESTING. Compliance with the requirements shown in Section 800-C above shall be determined in accordance with the current methods of the American Association of State Highway Officials. During the progress of the work, concrete test cylinders or beams will be made by the Engineer and tested for compressive strength or modulus of rupture for the purpose of checking the field control of the quality of the concrete. The cost of working, transporting, testing and all other costs associated with sampling and testing will be borne by the Contractor. 800-E. HANDLING AND STORAGE OF MATERIALS. The handling and storage of concrete aggregates shall be such as to prevent segregation and the admixture 800-6 Section 800 Concrete of foreign materials. The yEngineer may require -that the aggregates be stored on suitable platforms. Coarse and fine aggregates shall be stored in separate stockpiles sufficiently removed from each other to prevent the material at the edge of the piles from becoming intermixed. The location of stockpiles shall be satisfactory to the Engineer. All cement shall be stored in suitable weatherproof buildings which will protect the cement from dampness. Provision for storage shall be ample and the shipments of cement as received shall be separately stored in such a manner as to provide easy access for the identification and inspection of each shipment. Stored cement shall meet the test requirements at any time after storage when a retest is ordered by the Engineer. On small jobs, storage in the open may be permitted by written authorization from the Engineer, in which case a raised platform and ample waterproof covering shall be provided. Copies of cement records shall be furnished the Engineer, showing in such detail as he may reasonably require, the quantity used during the day or run at each part of the work. Cement held in storage for a period of over three months, or cement which, for any reason, the Engineer may suspect of being damaged, shall be subject to a retest before being used on the work. ' 800-F. MEASUREMENT OF MATERIALS. Materials shall be measured by weighing, except as otherwise specified or where other methods are specifically authorized by the Engineer. The apparatus provided for weighing the t aggregates and cement shall be suitably designed and constructed for this purpose. Each size of aggregate and the cement shall be weighed separately. The accuracy of all weighing devices shall be such that successive quantities ' can be measured to within 1 percent of the desired amount. Cement in standard packages (sack) need not be weighed, but bulk cement shall be weighed. The mixing.water shall be measured by volume or by weight. The water measuring device shall be susceptible of control accurate to plus or minus 1/2 percent ' of the capacity of the tank. All measuring devices shall be subject to approval. ' Where volumetric measurements are authorized by the Engineer for projects where the amount of concrete is small, the weight proportions shall be converted to equivalent volumetric proportions. In such cases, suitable allowance shall be made for variations in the moisture condition of the ' aggregate, including the bulking effect in the fine aggregate. When the aggregates contain more water than the quantity necessary to produce ' a saturated surface -dry condition as contemplated in Section 3 above, representative samples shall be taken and the moisture content determined for each kind of aggregate. ' When sack cement is used, the quantities of aggregates for each batch shall be exactly sufficient for one or more full sacks of cement and no batch requiring fractional sacks of cement will be permitted. 1 1 800-7 I Concrete 800-G. MIXING CONCRETE. I 1. Ready -Mixed Concrete. The use of ready -mixed concrete will be permitted as approved by the Engineer. If the use of ready -mixed concrete is permitted, all provisions set out heretofore for site -mixed concrete shall be observed except as herein modified. When the specified slump is 3 inches or less, the tolerance shall be plus or minus 1/2 inch. When the specified slump is greater than 3 inches, the tolerance shall be plus or minus 1 inch. Ready -mixed concrete shall be understood to mean any concrete which is proportioned and mixed in a central plant and hauled to the work site in agitator trucks of approved type, or in non -agitating equipment when approved by the Engineer; or concrete which is proportioned in a central plant and mixed in approved transit mix trucks en route to the site of the work; or mixed completely in a truck mixer at the point of delivery following the addition of mixing water. Mixer may be stationary mixers or truck mixers. Agitators may be truck mixers or truck agitators. Each mixer and agitator shall have attached thereto, in a prominent place, a metal plate on which is plainly marked for the various uses for which the equipment is designed, the capacity of the drum container in terms of volume of mixed concrete and the speed of rotation of the mixing drum and blades. The truck mixer, when loaded to manufacturer's rated capacity, which shall not exceed 57-1/2 percent of the volume of the drum of the mixer, shall be capable of combining the ingredients of the concrete within the specified time into a thoroughly mixed and uniform mass and of discharging the concrete with a satisfactory degree of uniformity. The agitator, when loaded to manufacturer's rated capacity, which shall not exceed 80 percent of the volume of the drum and of the agitator, shall be capable of maintaining the mixed concrete in a thoroughly mixed and uniform mass and of discharging the concrete with a satisfactory degree of uniformity. Mixers and agitators shall be operated within the limits of capacity and speed of rotation designed by the manufacturer of the equipment. Units designated as agitators shall not be used in connection with truck mixing. When a stationary mixer is used for the complete mixing of the concrete, the mixing time shall be the same and the mixer and mixer operation shall comply substantially with the provision set out herein for site -mixed concrete. When a truck mixer is used for complete mixing, each batch of concrete shall be mixed not less than 70 nor more than 100 revolutions of the drum or blades at the rate of rotation designated by the manufacturer of the equipment as mixing speed. Additional mixing, if any, shall be at the speed designated by the manufacturer of the equipment as agitating speed. 800-8 Section 800 Concrete When a truck mixer is, -used for transpdriing concrete which has been completely mixed in a stationary mixer, mixing during transportation shall be at the speed designated by the manufacturer of the equipment as agitation speed, and the volume of the batch shall not exceed 80 percent of the gross drum volume. Concrete shall be delivered to the site of the work and discharged from the truck mixer or agitator into the forms complete within 1-1/2 hours after the introduction of the mixing water to the cement and aggregates except that in hot weather, or under other conditions contributing to quick stiffening of the concrete, the maximum allowable time may be reduced by the Engineer. Each batch shall be accompanied by a time slip issued at the batching plant bearing the time of departure. Slump tests shall be made from time to time of individual samples taken at the beginning, midpoint and end of the load. If these slumps vary by more than the tolerances specified above, the mixer or agitator shall not be used unless the condition is corrected. Mixers and agitators shall be examined daily for changes in condition due to the accumulation of hard concrete or mortar or wear of blades. The pickup and throw -over blades shall be replaced when any part of section is worn 1 inch or more below the original height of the manufacturer's design. A copy of the manufacturer's design, showing dimensions and arrangement of blades, shall be available at all times. The concrete, when discharged, shall be of the consistency and workability required for the job without the use of additional mixing water. The rate •of discharge shall be controlled by the speed of rotation of drums in the discharge direction with the discharge gate fully open. Unless otherwise approved by the Engineers, the mixed concrete shall not be less than 50°F, and not more than 90°F at the time of placing. , When approved i.n writing by the Engineer, central -mixed concrete which is designed for the purpose may be transported in approved non -agitating equipment. Bodies of this equipment shall be smooth, watertight., metal containers, equipped with gates that will permit control of the discharge of the concrete. Covers shall be provided for protection against the weather. The concrete shall be delivered to the site of the work in,a thoroughly mixed and uniform mass and discharged with a satisfactory degree of uniformity. Placement in forms shall be completed within 30 minutes after introduction of the mixing water to the cement and aggregates. If the concrete furnished shows erratic behavior under the field conditions, or in regard to strength of the finished product as shown by beams or cylinder tests or in the time of initial or final set, the Contractor will, at once, without notice from the Engineer, cease the use of ready -mixed concrete until such corrections in procedure are made as to ensure work of a quality satisfactory to the Engineer. 800-9 Concrete The organization supplying concrete shall have sufficient plant capacity and transporting apparatus to ensure continuous delivery at the rate required. The rate of delivery of concrete during concreting operations shall be such as to provide for the proper handling, placing and finishing of the concrete. The rates shall be such that the interval between batches shall not exceed 20 minutes. The methods of delivering and handling the concrete shall be such as will facilitate placing with the minimum of rehandling and without damage to the structure of the concrete. 2. Hand Mixing. When hand mixing is authorized it shall he done on a watertight platform and in such a manner as to ensure a uniform distribution of the materials throughout the mass. Mixing shall be continued until a homogeneous mixture of the required consistency is obtained. 3. Retempering. The concrete shall be mixed only in such quantities as are required for immediate use and any which has developed initial set shall not be used. Concrete which has partially hardened shall not be retempered or remixed. 800-H. HANDLING AND PLACING CONCRETE. General. In preparation for the placing of concrete, all sawdust, chips, and other construction debris and extraneous matter shall be removed from the interior of forms. Struts, stays and braces, serving temporarily to hold the forms in correct shape and alignment, pending the placing of concrete at their locations, shall be removed when the concrete placing has reached an elevation rendering their service unnecessary, and these temporary members shall be entirely removed from the forms and not buried in the concrete. All concrete shall be placed before it has taken its initial set. Concrete shall be placed so as to avoid segregation of the materials and the displacement of the reinforcement. The use of long troughs, chutes and pipes for convening the concrete from the mixer to the forms shall be permitted only on written authorization from the Engineer. In case an inferior quality of concrete is produced by the use of such conveyors, the Engineer may order discontinuance of their use and the substitution of a satisfactory method of placing. Open troughs and chutes shall be of metal or metal lined. Where steep slopes are required, the chutes shall be equipped with baffles or be in short lengths that reverse the direction of movement. All chutes, troughs, and pipe shall be kept clean and free from coatings of hardened concrete by thoroughly flushing with water after each run; water used for flushing shall be discharged clear of the structure. When placing operations would involve dropping the concrete more than 5 feet, it shall be deposited through sheet petal or other approved pipes. As far as practicable, the pipes shall be kept full of concrete during placing and their lower ends shall be kept buried in the newly placed concrete. After initial 800-10 Section 800 Concrete set of the concrete, the forms shall not be. jarred and no strain shall be placed on the ends of reinforcing bars which project. All concrete, during and immediately after depositing, shall be thoroughly compacted. The compaction shall be done by mechanical vibration subject to the following provisions: 1. The vibration shall be internal unless special authorization of other methods is given by the Engineer or as provided herein. 2. Vibrators shall be of a type and design approved by the Engineer.. They shall be capable of transmitting vibration to the concrete at frequencies of not less than 4,500 impulses per minute. 3. The intensity of vibration shall be such as to visibly affect a mass of concrete of 1 inch slump over a radius of at least 18 inches. 4.. The Contractor shall provide a sufficient number of vibrators to properly compact each batch immediately after it is placed in the forms. 5. Vibrators shall be manipulated so as to thoroughly work the concrete around the reinforcement and imbedded fixtures and into the corners and angles of the forms. Vibration shall be freshly deposited withdrawn out of sufficient duration shall not be contit be continued at any are formed. applied at the point of deposit and in the area of concrete. The vibrators shall be inserted and the concrete slowly. The vibration shall be of and intensity to thoroughly compact the concrete, but cued so as to cause segregation. Vibration shall not one point to the extent that localized areas of grout Application of vibrators shall be at points uniformly spaced and not farther apart than twice the radius over which the vibration is visibly effective. 6. Vibration shall not be applied directly or through the reinforcement to sections or layers of concrete which have hardened to the degree that the concrete ceases to be plastic under vibration. It shall not be used to make concrete flow in the forms over distances so great as to cause segregation, and vibration shall not be used to transport concrete in the forms. 7. Vibration shall be supplemented by such spading as is necessary to ensure smooth surfaces and dense concrete, along form surfaces and in corners and locations impossible to reach with the vibrators. 8. The provisions of this article shall apply to precast piling, concrete cribbing and other precast members except that, if approved by the Engineer, the manufacturer's methods of vibration may be used. Concrete shall be placed in horizontal layers not more than 12 inches thick except as hereinafter provided. When less than a complete layer is placed in 800-11 Concrete one operation, it shall be terminated in a vertical bulkhead. Each layer shall be placed and compacted before the preceding batch has taken initial set to prevent injury to the green concrete and avoid surfaces of separation between the batches. Each layer shall be compacted so as to avoid the formation of a construction joint with a preceding layer which has not taken initial set. When the placing of concrete is temporarily discontinued, the concrete, after becoming firm enough to retain its form, shall be cleaned of laitance and other objectionable material to a sufficient depth to expose sound concrete. To avoid visible joints as far as possible upon exposed faces, the top surface of the concrete adjacent to the forms shall be smoothed with a trowel. There a "feather edge" might be produced at a construction joint, as the sloped top surface of wingwall, an insert form work shall be used to produce a blocked out portion in the preceding layer which shall produce an edge thickness of not less than 6 inches in the succeeding layer. Work shall not be discontinued within 18 inches of the top of any face, unless provision has been made for a coping less than 18 inches thick, in which case, if permitted by the Engineer, the construction joint may be made at the underside of the coping. Immediately following accumulations of mortar forms shall be removed. the unset concrete. concrete becoming set, concrete -steel bond at reinforcing steel. the discontinuance of placing concrete, all splashed upon the reinforced steel and the surface of Dried mortar chips and dust shall not be puddled into If the accumulations are not removed prior to the care shall be exercised not to injure or break the and near the surface of the concrete when cleaning 800-I. DEPOSITING CONCRETE UNDER WATER. Concrete shall not be deposited in water except with the approval of the Engineer, and under his immediate supervision; and in this case, the method of placing shall be as hereinafter designated. Concrete deposited in water shall be seal concrete. To prevent segregation, it shall be carefully placed in a compact mass, in its final position, by means of a tremie, a bottom dump bucket or other approved method, and shall not be disturbed after being deposited. Still water shall be maintained at the point of deposit and the forms under water shall be watertight. For parts of structures under water, when possible, concrete seals shall he placed continuously from start to finish. The surface of the concrete shall be kept as nearly horizontal as practicable at all times. To ensure thorough bonding, each succeeding layer of seal shall be placed before the preceding layer has taken initial set. A tremie shall consist of a tube having a diameter of not less than 10 inches, constructed in sections having flanged couplings fitted with gaskets. The tremies shall be supported so as to permit free movement of the discharge end over the entire top surface of the work and so as to permit rapid lowering when necessary to retard or stop the flow of concrete. The discharge end shall be closed at the start of work so as to prevent water entering the tube and shall be ertirely sealed at all times. The tremie tube shall be kept full 800-12 Section 800 Concrete ;y to the bottom of the hoppertiWhen a batch is duped into the hopper, the flow of concrete shall be induce'd*'by slightly' raising the discharge end, always keeping it in the deposited concrete. The flow shall be continuous until the work is completed. Depositing of concrete by the drop bottom bucket method shall conform to the following specification. The top of the bucket shall be open. the bottom door shall open freely and outward when tripping. The bucket shall be completely filled and slowly lowered to avoid backwash. It shall not be dumped until it rests on the surface upon which the concrete is to be deposifed and when discharged, shall be withdrawn slowly until well above the concrete. The slump of concrete shall be maintained between 4 and 8 inches. Unwatering may proceed when the concrete seal is sufficiently hard and strong. All laitance or other unsatisfactory materials shall be removed from the exposed surface by scraping, chipping or other means which will not injure the surface of the concrete. 800-J. CONSTRUCTION JOINTS. 1. General. Construction joints shall be made only where located on Plans or shown in. the pouring schedule, unless otherwise approved by the Engineer. If not detailed on the Plans, or in the case of emergency, construction joints shall be placed as directed by the Engineer. Shear keys or inclined reinforcement shall be used where necessary to transmit -shear or bond the two sections together. 2. Bonding. Before depositing new concrete on or against concrete which has hardened, the forms shallbe retightened. The surface of the hardened concrete shall be roughened as required by the Engineer in a manner that will not leave loosened particles or aggregates or damaged concrete at the. surface. It shall be thoroughly cleaned of foreign matter and laitance, and saturated with water. To ensure an excess of mortar at the juncture of the hardened and the newly deposited concrete, the cleaned and saturated surfaces, including vertical and inclined surfaces, shall 'first be thoroughly covered with a coating of mortar or neat cement grout against which the new concrete shall be placed before the grout has attained its initial set. The placing of concrete shall be carried continuously from joint to joint. The face edges of all joints which are exposed to view shall be carefully finished true to line and elevation. 800-K. FALSEWORK AND CENTERING. Unless otherwise provided, detailed Plans 1 for falsework or centering shall be supplied to the Engineer on request; but, in no case shall the Contractor be relieved of responsibility for results obtained by the use of these Plans. ' For designing falsework and centering, a weight of 150 pounds per cubic foot shall •be • assumed for green concrete.. All falsework shall be designed and constructed to provide the necessary rigidity and to support the loads without i 800-13 Concrete appreciable settlement or deformation. The Engineer may require the Contractor to employ screw jacks or hardwood wedges to take up any settlement in the formwork either before or during the placing of concrete. Falsework which cannot be founded on a satisfactory footing shall be supported on piling which shall be spaced, driven and removed in a manner approved by the Engineer. Falsework shall be set to give the finished structure the camber specified or indicated on the Plans. Arch centering shall be constructed according to centering plans approved by the Engineer. Provision shall be made by means of suitable wedges, sand boxes or other devices for the gradual lowering of centers, and rendering the arch self-supporting. When directed, centering shall be placed upon approved jacks in order to take up and correct any slight settlement which may occur after the placing has begun. 800-L. FOUNDATION PITS AND FORMS. All foundation pits and forms shall be inspected and approved by the Engineer prior to placing any part of the structure and the methods employed in performing the work and all equipment, tools and machinery used for handling materials and executing any part of the work shall be subject to the approval of the Engineer. All equipment, tools and machinery used must be maintained in a satisfactory working condition. Forms shall conform to the shape, lines and dimensions of the concrete as called for on the Plans. All plane form surfaces shall be constructed so that the finished concrete surfaces will be true planes, free from waves and irregularities. Lumber used in forms for exposed surfaces shall be straight, dressed to uniform width and thickness and shall be free from loose knots or other defects. Joints in forms shall be horizontal or vertical. For unexposed surfaces, undressed lumber may be used. Lumber once used in forms shall have nails withdrawn and surfaces to be in contact with the concrete thoroughly cleaned before being used again. Forms shall be substantial and sufficiently tight to prevent leakage of mortar. They shall be properly braced or tied together in such a manner that they will maintain their original position and shape under the superimposed loads and the fluid pressure of the concrete. If adequate foundations for shores cannot be secured, trussed supports shall be provided. Where required by the Detailed Specifications, concrete shall be poured against waterproofed Douglas fir plywood, or waterproofed tempered hardpressed fiberboard, of a make and quality approved by the Engineer, and installed in strict conformity to the manufacturer's specifications. Forms used for backing up and otherwise supporting form lining shall have a flat surface but need not be tight. At the top of all walls or other surfaces which are to be finished to a true line, the top of the form shall be brought to a true line and grade so that the surface may be finished by means of a float or template resting on the top edge of the form. Forms, on one side of the wall at least, shall not extend over horizontal construction joints. 800-14 Section dUU Concrete Flat steel bars or rods .unless otherwise authorized, shall be used for internal form ties. They 'shall be provided with lugs,nuts, cones or other approved devices, which will serve as spreaders or form spacers, and the ties shall have sufficient mechanical strength, stiffness and rigidity to hold the forms in proper position, spacing and alignment. The ties shall be of such design that the body of the tie will remain embedded in the concrete, with the ends of the ties not closer than 1/2 inch from the outer concrete surfaces. The ends of the embedded portion of the tie shall be provided with holes, corrugations, hooks, or other approved type of mortar clinch, and these ends shall be protected from the concrete by means of cone shaped shields of sufficient depth to provide adequate anchorage for the cement mortar plugs which shall be placed in the holes left by these shields. Wire form ties will be permitted only on light and unimportant work and with the approval of the Engineer. They shall not be used through surfaces where discoloration would be objectionable, wire ties, where used, must not be tightened by twisting, but shall be tightened by means of wedges placed outside the forms. No more initial stress is to be placed in the wire tie than is necessary to remove all slack. Shores supporting successive stories shall be placed directly over those below or so designated that the load will be transmitted directly to them. Forms shall be set.to line and grade and so constructed and fastened as to provide and maintain true lines. Special care shall be used to prevent bulging. The forms for all walls should be such as to allow continuous pouring from the bottom to the top of the wall. Unless otherwise specified, suitable moulding or bevel strips shall be placed in the angles of forms to round or bevel the edges of the concrete. Bevel ' strips on the exposed corners of beams and girders shall be carried to within 1 foot of the face of the beam support. Bevel strips on the exposed corners of columns shall be carried to within 1 foot of their intersection with the edge of a beam or girder of the same width as the column. If the column is ' from 2 to 6 inches wider than the largest beam or girder it supports, the bevel strips shall extend to within 2 inches of the bottom of the girder. If the column is'� inches or more wider than the largest beam it supports, the bevel strips shall, continue to within 1 foot of the bottom of the slab above the beam. Bevel strips on columns shall stop at a point 16 inches above the floor. The ends of all triangle bevel strips which do not extend the full length of the corners they occupy shall be cut off on an angle of 45°. Unless otherwise authorized by the Engineer, the inside of forms shall be coated with non -staining paraffin oil, or other approved material, applied ' before the reinforcement 'is placed, and all surplus oil removed from the surface of the forms by thorough wiping with soft absorbent cloths. ' Temporary openings shall be placed at the bottom of the column and wall forms, and at other points where necessary to facilitate cleaning and inspection immediately. before depositing concrete. I. Forms shall not be disturbed until the concrete has adequately hardened. Shoring shall not be removed until the member has acquired sufficient strength to support its weight and the load upon it. Members subject to additional 1 800-15 Concrete loads during construction shall be adequately shored to support both the ' member and construction loads in such a manner as will protect the member from damage by the loads; this shoring shall not be removed until the member has acquired sufficient strength to support safely its weight and the load upon it. The following table gives the minimum time which shall elapse between the time of placing the concrete and the removal of forms at various average temperatures. ' Class of Work Above 60° 500 to 600 40° to 50° Below 40° ' Walls in Mass Work I day 2 days 5 days Not until tests ' have been made indicating concrete is set. Thin Walls - 12 inches 2 days 4 days 7 days or less in thickness Columns - if girders are shored Bottom forms of slabs (5 feet or less span) 3 days 5 days 10 days I 4 days 8 days 14 days I Bottom forms of beams 14 days and girders (less than 14 inch span) 20 days 28 days If high early strength cement is used these periods may be reduced as directed by the Engineer. When field operations are controlled by beam or cylinder tests, the removal of forms, supports and housing, and the discontinuance of heating and curing may be begun when the concrete is found to have a modulus of rupture of not less than 600 pounds per square inch or a compressive strength of 3,000 pounds per square inch, provided further that in no case shall supports be removed in less than seven days after pouring the concrete. The beams of cylinders shall be cured under conditions which are not more favorable than the most unfavorable conditions for the portions of the concrete which they represent. Form work in buildings should be so designed that the column forms may be removed without in any way disturbing the supports of the beams or girders, in order than any defect in the column may be detected and remedied before any load is placed on the column. Dimensions of all forms shall be carefully checked by the Contractor and the Engineer after they are erected and before the concrete is placed. The Contractor will be held responsible for the accuracy of all construction. 800-16 aecuon out) Concrete 800-M. FINISHING CONCRETE. Face forms shall be removed as soon as practicable in order to facilitate .finishingX7hjthe concrete surfaces. Care shall be. taken to avoid roughening or injuring corners, and to keep all edges sharp. Immediately after the forms are removed, any fins or other projections shall be carefully removed, rough spots in the faces of the walls and any broken corners or edges shall be repaired and all bolt holes shall be plugged and entirely filled with mortar containing one part by volume of cement and two parts by volume of sand screened over a No. 8 screen. Pointing shall be brought smooth with the surface by means of a wooden float. A steel trowel shall not be used to finish the surface. Plastering will not be permitted. All concrete which, upon removal of the forms, is found to be porous or "honeycombed" shall be immediately cut out and removed entirely from the body of the concrete. The parts removed shall extend not less than l inch back of the reinforcement steel where such steel is present in the concrete face which is being repaired, removing sound concrete, if necessary, to obtain this depth. If reinforcement steel is not present, the parts removed shall extend into the concrete not less than 3 inches and the opening dovetailed in such a manner that the new concrete filling will be securely anchored. In replacing concrete so removed, forms shall be built with a spout or hopper outside the concrete surface, which shall be filled with fresh concrete to a point not less than 12 inches above the top of the hole caused by removing the porous concrete. The fresh concrete shall be properly bonded to the old concrete surfaces, as hereinbefore specified, and shall be well puddled. The hopper shall be removed after the concrete has hardened and within 24 hours after the concrete is placed, the excess concrete carefully cut away, and the surface pointed and rubbed smooth. Concrete used in replacing porous concrete shall be protected from premature drying as hereinafter specified. After the pointing has set sufficiently to permit it, all exposed surfaces shall be thoroughly wetted and rubbed with a medium carborundum stone followed by a second rubbing with a fine carborundum stone to obtain an entire surface of a smooth texture and uniformity in color. A cement wash or plaster coat shall not be used. If honeycombing is determined to be excessive by the Engineer, the Contractor shall remove and replace such at his own expense. Specific exceptions to rubbing of exposed concrete may be made in the Detailed Specifications or on the Plans. Particular attention is called to the fact that the tops of all walls shall be finished true to line and grade and shall be troweled smooth. Floors, sidewalks, and other exposed wearing surfaces which require finishing shall be poured against carefully set screeds and troweled smooth with power operated trowels. 800-17 Concrete Excess water shall be drained away or otherwise removed. The final finish with a steel trowel shall not be made until the cement has acquired its initial set. No more troweling shall be done than is necessary to obtain a smooth surface. At the option of the Engineer, the top surfaces of walks may be finished with a light broom or brush and an edging tool instead of a trowel. Sidewalks shall be laid out in blocks with an approved grooving tool as shown on the Plans or as directed by the Engineer. Care must be taken to avoid drawing an excess of cement to the surface of floors or walks. Dry cement or a dry mixture of cement and sand shall not be sprinkled directly on the surface. Floors shall be marked at the direction of the Engineer. Care shall be taken that all floor surfaces drain properly and that the grooving tool does not raise the surface of the floor and form pockets which do not drain. Floors requiring a mortar wearing coat will be so indicated on the Plans and shall be finished as specified. 800-N. CONCRETING IN COLD WEATHER. No concrete shall be placed when the air temperature is below 35° F., unless provision is made for heating the ingredients and for enclosing the concrete and heating the enclosures. No concrete shall be placed when the weather reports indicate air temperatures below 32° F. during the succeeding five days unless provision is made for enclosing the concrete and heating the enclosure. When concrete is placed at air temperature below 35° F., the ingredients shall be heated so that the temperature of the concrete when placed shall be not less than 60° F. The concrete shall be enclosed immediately after placing and the concrete and air in the enclosure kept above 50° F. for a period of five days. When dry heat is used, means of maintaining atmospheric moisture shall be provided. If wet steam is used for heating, the time may be reduced to a minimum of 48 hours provided that the temperature of the concrete and the air in the enclosure is held above 78° F. If protected in this manner, the concrete shall be covered with cotton mats or three thicknesses of 9 ounce burlap after the enclosure is removed and the covering shall remain in place for a total period of five days after placing the concrete. 800-0. CURING CONCRETE FOR STRUCTURES. Membrane curing compound solution shall not be used on surfaces to be rubbed or painted. These surfaces shall be cured with cotton mats or burlap blankets, as provided for below. White pigmented membrane curing solution may be used for curing concrete in all minor drainage structures and the substructures of major structures except for precast piling and substructures of grade separation structures including railroad underpasses. All of the concrete in substructures for grade separation structures, superstructures of major structures and precast piling shall be cured with wet cotton mats or wet burlap blankets. The membrane curing solution shall comply with the requirements of A.A.S.H.O. Designation M-148. The cotton mats shall comply with the requirements of A.A.S.H.O. Designation M-73. The burlap blankets shall he made of jute and manila fibers and shall weigh not less than 9 ounces per square yard of single thickness. 800-18 section ouu Concrete When membrane curing is used, the exposed concret°e shall be thoroughly sealed immediately after the free! water has left 3the%Psurface. The concrete• inside the forms shall be sealed immediately after the. forms are removed and necessary finishing has been done. The solution shall be applied in one or two separate applications. If the solution is applied in two increments, the second application shall follow the first application in 30 minutes. The Contractor shall provide satisfactory equipment and means to properly control and assure the direct application of the curing solution on the concrete surface so as to result in a uniform coverage at the rate of one gallon for each 200 square feet of area. If rain falls on the newly coated concrete before the film has dried sufficiently to resist damage or if the film is damaged in any other manner, a new coat of the solution shall be applied to the affected portions equal in curing value to that above specified. When curing with cotton mats or burlap blankets is required, the exposed concrete immediately after finishing shall be covered with wet cotton mats or two thicknesses of wet burlap blankets. The cotton mats or burlap blankets shall be kept continuously and thoroughly wet•for a period of not less than five days after the concrete was placed. 800-P. EXPANSION AND FIXED JOINTS. All joints shall be constructed according to details shown on the Plans. Ii. Open Joints. Open joints shall be placed in the locations shown on the Plans and shall be constructed by the insertion and subsequent removal.of a wood strip, metal plate or other approved material. The insertion and removal of the template shall be accomplished without chipping or ' breaking the corners of the concrete. Reinforcement shall not extend across an open joint unless so specified on the Plans. 2. Filled Joints. Poured expansion joints shall be constructed similar to • open joints. When premolded types are specified, the filler shall be placed and held in correct position as the concrete on one side of the joint is placed. When the form is removed, the concrete on the other side shall be placed. Premolded material shall be anchored to the concrete on one side of the joint by means of copper wire not lighter than 12 gage, so as to retain the filler in proper position. Water stops shall be carefully placed as shown on the Plans. Care shall be exercised in the construction of filled joints to ensure that the concrete sections are completely separated by the joint material. 3. Steel Joints. The plates, angles or other structural shapes shall be accurately shaped, at the shop, to conform to the sections of the concrete floor. The fabrication and painting shall conform to the requirements of these Specifications covering those items. When called for on the Plans or in the Detailed Specifications, the material shall be galvanized in lieu of painting. 4. Water Stops and Flashing. Copper water stops and flashing shall conform to the Specifications for Copper Sheet, Strip and Plate of the A.A.S.H.O. 800-19 Concrete Designation M 138. Type ETP shall be used unless otherwise specified. Sheets shall be 16 ounces per square foot unless otherwise specified. The sheet copper in each joint shall be continuous, separate pieces being connected by thoroughly workmanlike soldered joints to form a complete watertight unit. 5. Rubber Water Stops. Rubber water stops shall conform to the details shown on the Plans and to the following Specifications. Rubber water stops shall be formed from synthetic rubber made exclusively from neoprene, reinforcing carbon black, zinc oxide, polymerization agents, and softeners. This compound shall contain not less than 70 percent by volume of neoprene. The tensile strength shall not be less than 2,750 pounds per square inch with an elongation at breaking of 600 percent. The Shore Durometer indication (hardness) shall be between 50 and 60. After seven days in air at 158° (±2°) F., or after four days in oxygen at 158° (±1°) F. and 300 pounds per square inch pressure, the tensile strength shall be not less than 65 percent of the original. The water stops shall be formed with an integral cross section in suitable molds, so as to produce a uniform section with a permissible variation in dimension of 1/32 inch plus or minus. No splices will be permitted in straight strips. Strips and special connection pieces shall be well cured in a manner such that any cross section shall be dense, homogeneous, and free from all porosity. All junctions in the special connection pieces shall be full molded. During the vulcanizing period, the joints shall be securely held by suitable clamps. The material at the splices shall be dense and homogeneous throughout the cross section. Water stops shall be installed and held in proper position during construction in accordance with the details shown on the Plans. 800-20 aeccion oiu Reinforcing Steel REINFORCING STEEL; ar, 810-A. GENERAL. Under this item, reinforcing steel and miscellaneous metallic material of the quality, type, size. and quantity designated shall be furnished and placed in concrete structures in accordance with these Specifications and in conformity with the details shown on the Plans. 810-B. MATERIALS. 1. Bar Reinforcement. Bar reinforcing for concrete shall conform to requirements of the current Specifications for Billet Steel Bars, A.A.S.H.O. Designation M 31, or to the current Specifications for Rail Steel Bars, Designation M 42 of the A.A.S.H.O. Specifications for High Materials with the following restrictions applying to both kinds. a. All bars shall be of the deformed type conforming to the current Specifications of the A.A.S.H.O. Designation M 137, unless otherwise specified. b. The use of cold twisted bars will not be permitted. c. Steel for all bars shall be made by the open-hearth process, unless otherwise called for in the Detailed Specifications or on the Plans. d. Structural grade billet steel bars may be permitted only when the Plans were prepared based upon 18,000 pounds per square inch design strength for reinforcing steel, or when at the expense of the Contractor, an additional amount of steel, in the proportion of the design stress to 18,000 pounds per square inch, is. provided. 2. Wire and Wire Mesh. Wire shall conform to the current Specifications for Cold -Drawn Steel Wire for Concrete Reinforcement of the A.A.S.H.O. Specifications for Highway Materials, Designation M 32. Wire mesh, when used as reinforcement in concrete, shall conform to the Specifications for Welded Steel Wire Fabric for Concrete Reinforcement of the A.A.S.H.O. Specifications for Highway Materials, Designation M 55. 3. Bar Mat Reinforcement. Bar mat reinforcement for concrete shall conform to the Specifications for Fabricated Steel Bar or Rod Mats for Concrete Reinforcement of the A.A.S.H.O. Specifications for Highway Materials, Designation M 54. 4. Structural Shapes. Structural shapes used as reinforcement in concrete shall conform to the requirements for structural steel, A.S.T.M. Standards. 5. Wrought Iron. (Plates, shapes and bars.) Wrought iron shall conform to the. requirements of the A.S.T.M. Standards A 42 for Wrought Iron Plates, A 207 for Rolled Wrought Iron Shapes and Bars, or A 72 for Welded Wrought Iron Pipe. 810-1 Reinforcing Steel 810-C. ORDER LISTS. Before ordering material, all order lists and bending diagrams shall be furnished by the Contractor for approval of the Engineer, and no materials shall be ordered until such lists and bending diagrams have been approved. The approval of order lists and bending diagrams by the Engineer shall in no way relieve the Contractor of responsibility for the correctness of such lists and diagrams. Any expense incident to the revision of material furnished in accordance with such lists and diagrams to make it comply with the design drawings shall be borne by the Contractor. Unless otherwise noted, all dimensions relating to reinforcing steel are to center of bars. ' 810-D. PROTECTION OF MATERIAL. Steel reinforcement shall be protected at all times from injury. When placed in the work, it shall be free from dirt, detrimental scale, paint, oil and other foreign substances. However, when steel has, on its surface, detrimental rust, loose scale and dust which is easily removable, it may be cleaned by a satisfactory method, if approved by the Engineer. ' 810-E. FABRICATION. Bent bar reinforcement shall be sold bent to the shapes shown on the Plans, and unless otherwise provided on the Plans or by authorization, bends shall be made in accordance with the following requirements. Stirrups and tie bars shall be bent around a pin having a diameter not less than three times the minimum thickness of the bar. Bends for other bars shall be made around a pin having a diameter not less than six times the minimum thickness except for bars larger than 1 inch, in which case the bends shall be made around a pin of eight bar diameters. Bar reinforcement shall be shipped in standard bundles, tagged and marked in accordance with the Code of Standard Practice of the Concrete Reinforcement Steel Institute. 810-F. PLACING AND FASTENING. All steel reinforcement shall be accurately placed in the positions shown on the Plans and firmly held during the placing and setting of concrete. When placed in the work, it shall be free from dirt, detrimental rust, loose scale, paint, oil or other foreign material. Bars shall be tied at all intersections except where spacing is less than 1 foot in each direction when alternate intersections shall be tied. Distances from the forms shall be maintained by means of stays, blocks, ties, hangers, or other approved supports, except that reinforcing i superstructure shall be supported by approved metal chairs and bar supports. Blocks for holding reinforcement from contact with the forms shall be precast mortar blocks of approved shape and dimensions or approved metal chairs. Metal chairs which are in contact with the exterior surface of the concrete shall be galvanized. Layers of bars shall be separated by metal bar supports or by other equally suitable devices. The use of pebbles, pieces of broken stone or brick, metal pipe and wooden blocks shall not be permitted. Reinforcement in any member shall be placed and then inspected and approved by the Engineer before the placing of concrete begins. Concrete placed in violation of this provision may be rejected and removal required. I I 1l 810-2 becrion oiu Reinforcing Steel If fabric reinforcement is.,shipped in rolls,..it shall be straightened into flat sheet before placing. >k`=° ` q Water stops shall be furnished and placed as shown on the Plans. Where splicing is necessary, joints shall be welded or soldered to form continuous watertight joints. 810-G. SPLICING. All reinforcement shall be furnished in the full lengths indicated on the Plans. Splicing of bars, except where shown on the Plans, will not be permitted without the written approval of the Engineer. Splices shall be staggered as far as possible. Unless otherwise shown on the Plans, bars shall be lapped 40 diameters to make the splice. In lapped splices, the bars shall be placed in contact and wired together in such a manner as to maintain the minimum distance to the surface of the concrete shown on the Plans. Welding of reinforcing steel shall be done only if detailed on the Plans or if authorization is made by the Engineer in writing. Welding shall conform to the current Specifications for Welded Highway and Railway Bridges of the American Welding Society.' 810-H.. LAPPING. Sheets of mesh or bar mat reinforcement shall overlap each other sufficiently .to maintain a uniform strength and shall be securely fastened at the ends and edges.. The edge lap shall not be less than one mesh in width. 810-I. SUBSTITUTIONS. Substitution of bars which differ in size from.that shown on the Plans will be permitted only with specific authorization by the Engineer. If steel is substituted, it shall have an area equivalent to the design area or larger. 810—J. METHOD OF MEASUREMENT. Reinforcing steel, placed and accepted in concrete for structures will' be measured in pounds based on the -total computed weight for the sizes and lengths of bars, mesh or mats as shown on the Plans or authorized. The weight of mesh will be computed from the theoretical weight of plain wire. If the weight per square foot is given on the Plans, that weight shall be used. The weight of plain or deformed bars or bar mat will be computed from the theoretical weight of plain round or square bars of the same nominal size as shown on the following table. 810-3 Reinforcing Steel Number Size Size Weight Pounds Round Bars Square Bars Per Foot 2 1/4" 0.167 3 3/8" 0.376 4 1/2" 0.668 5 5/8" 1.043 6 3/4" 1.502 7 7/8" 2.044 8 1" 2.670 9 1" 3.400 10 1-1/8" 4.303 11 1-1/4" 5.313 The weight of all reinforcement used in railings, when they are paid for on a linear foot basis, shall not be included. The weight of reinforcement in precast piles and other items where reinforcement is included in the contract price for the item shall not be included. No allowance will be made for clips, wire, separators, wire supports, and other material used in fastening the reinforcing in place. If bars are substituted upon the Contractor's request, and as a result, more steel is used than specified, only the amount specified shall be included. When laps are made for splices, other than those shown on the Plans, for the convenience of the Contractor, the extra steel shall not be included. 810-K. BASIS OF PAYMENT. Unless otherwise set out in the Methods of Measurement and Payment section of these Specifications, reinforcing steel placed and accepted in concrete for structures and measured as provided above shall be paid for at the contract unit price per pound bid for "Reinforcing Steel." which price shall be full compensation for furnishing, blending, fabricating and placing the reinforcement placed in concrete, and for all tools, labor, equipment and incidentals necessary to complete the work. Clips, metal spacers, bar supports, ties, wire or other material used for fastening reinforcement in place will not be paid for directly but will be considered subsidiary to the item of Reinforcing Steel. Note: There shall be no special pay item for reinforcing steel in this contract, and reinforcing steel used in concrete pavement repair, pipe supports, or other structures shall be considered subsidiary to such pavement repair or placement of concrete. 810-4 bection vuu P. Cleanup PIPELINE tx CLEANUP 900-A. GENERAL. Cleanup shall be considered an important part of this project, and adequate equipment and qualified personnel shall be applied to this phase of the work from the very beginning of the project. There are generally four classifications of cleanup to be used on this project, as set out below. Class I Cleanup. Areas of construction within lawns, gardens, or other well -kept areas, including street rights of way that are kept as lawns by adjacent landowners. Class II Cleanup. Areas of construction within fields, meadows and street rights of way which are mowed or cultivated (gardens excepted). Class III Cleanup. Areas of construction that are heavily brushed or wooded, steep rocky slopes, or other areas where it is not practical for the area to be cultivated. Special Cleanup.. Unless otherwise noted under Section 900-B.4 of these Specifications, no special cleanup will be required. 900-B. METHOD OF CLEANUP. The method of cleanup for each of the classes defined in Section 900-A of these Specifications shall be as set out below. ' 1. Class I Cleanup - Lawns, Gardens, Etc. The trench shall be backfilled in accordance with the pipe specifications. After the topsoil has been spread over the damaged areas, the Contractor shall proceed immediately to hand rake the entire construction area to remove all rock 1 inch or larger in diameter. Debris of every type shall be removed and all damaged tree limbs shall be pruned. After the area has been raked and ' accepted by the Engineer, the area shall be seeded at the rate of 0.15 pounds per 100 square feet, using the following seed mixture (percent expressed in terms of weight). •' Lawn Fescue 30% Blue Grass 30% Rye Grass (Annual) 30% ' White Clover (Common) 10% During or after seeding is complete, all areas shall be covered with 10-20-10. fertilizer at the rate of 500 pounds per acre, or approximately one pound per 100 square feet. No watering will be required. 1 Straw mulch consisting of good grade clean straw, free of weeds or seed and of a quality approved by the Engineer prior to use, shall be placed over seeded areas and shall be uniformly spread so as to provide a thickness of approximately 2 inches when first spread. Where the existing ground cover does not contain any of the grasses as set out in the seed mixture above (Bermuda grass, Zoysia, etc.), the 1 900-1 P. Cleanup Contractor shall be responsible for cutting, removing and stockpiling the existing sod on the job site. After constructing the sewer line, reconnecting the existing service lines, and backfilling the trench, the sod shall be replaced to a condition equal to or better than that prior to construction. In the event that insufficient sod has been stored, or sod has been lost or destroyed, the Contractor shall be responsible for providing and installing new ground cover of the existing type to complete the cleanup. 2. Class II Cleanup - Fields, Meadows, Etc. The trench shall be backfilled in accordance with the pipe specifications. After the backfill is completed and the surface over the trench left slightly rounded, the area shall be machine raked to remove all rock I inch or larger in diameter from the finished surface. All excess excavated material shall be removed from the site, including hand raking excess material which has accumulated around fence posts, trees, mailboxes, etc. All areas which have been disturbed, such as that caused by equipment tracks, shall be carefully backfilled and repaired as though it were a part of the actual trench excavation. Seeding and fertilizing of these areas is required using the same mixture and rates as set out for Class I cleanup. 3. Class III Cleanup - Steep, Wooded or Rocky Areas. The trench shall be backfilled in accordance with the pipe specifications. After the trench backfill is complete, all damaged brush of every type shall be cut just below ground surface and all damaged limbs shall be trimmed. All brush and debris shall be disposed of by the Contractor and the entire area shall be machine raked to remove all rock from the finished surface which is 2 inches or larger in diameter. When directed by the Engineer, the area of the trench line shall then be seeded at the rate of 0.15 pounds per 100 square feet using the same seed mixture as set out under Class I cleanup, except that tall fescue (Kentucky 31) shall be used in place of lawn fescue. 4. Special Cleanup. No special cleanup will be required on this project. 5. All Areas. All work within the construction area shall be cleaned up to the satisfaction of the Owner and the Engineer. In general, all rocks, trash, or rubbish of any nature shall be removed from the site of the work. During construction, the Contractor shall at all times keep work areas in a clean, neat and workmanlike condition. Excess pipe, excavation, brush and materials of construction shall be removed and disposed of as the work progresses. In built-up areas, including lawns, the job site shall be cleaned up immediately behind construction. Streets and driveways blocked by excess materials after basic construction is completed will not be tolerated. If the trench should settle while the Contractor is still on the job or within one year of the project completion date, the Contractor shall make the required repairs at no additional cost to the Owner in accordance with the continuing responsibility provisions of these Specifications. 900-2 section 9UU P. Cleanup 6. Payment. There is no.special pay item fprcleanup. Cleanup should be a,, considered subsidiary ?Wlsewer lines. " 1` Sewer lines will be included on partial payment estimates only when every item of work required to construct each individual sewer line segment has been completed, including reconnection of existing services, trench backfill, cleanup, topsoiling, fertilizing, seeding and mulching. (Seeding, fertilizing and mulching shall only be done between the months of March through October.) When seeding, fertilizing and mulching cannot be completed (during the months of November through February), an additional 10 percent retainage on work under these bid items shall be withheld until completion. 900-3 Section 995 FINAL INSPECTION The final estimate will be prepared and approved for final payment upon completion of the work after a final inspection of the work has been made. This inspection shall be made by the Engineer or his chief assistant, the Contractor or one of the principal owners of the contracting firm, and a representative of the Owner. The final acceptance of the job and the payment of the Contractor in full will not reduce the continuing responsibility of the Contractor as set out in these Specifications. 995-1 VCCl1V,L LVVV METHODS OF MEASUREMENT AND PAYMENT I Methods of measurement and payment as set out in the Specifications covering the various items of construction are hereby clarified and superseded as set out herein. Wherever they are not clarified or superseded herein, methods of payment as provided in the Specifications shall prevail. Payment for all work under this contract shall be made at the unit prices bid under the various items of the Proposal as hereinafter set out. Bid Items 1, 2, 3, 4 and 5 - Sewer Lines Payment •for the size •and type of sewer line will be made at the unit price bid per linear foot, complete in -place, for sewer line segments scheduled to be replaced. The unit prices bid shall include any necessary clearing, tree or brush disposal, stripping and stockpiling of topsoil, trenching, bypass pumping as required, removal of all existing sewer lines in place, furnishing, installing and bedding the new sewer lines with 4 inches of SB-2, protective cover as required, testing, trench backfill and cleanup, and every item of work required to install the sewer pipe in a trench 0 to 6 feet deep. Additional compensation will be made only for those items of work specifically set out in the Proposal. Should any defective pipe be uncovered during the performance of rehabilitation under Rehabilitation Codes 18, 19, 30 or 31 (Bid Items 11 and 14), outside the limits of repair, payment for replacement of this defective pipe will be made under this item at the direction of the Engineer. ' Measurement will be in accordance with the final lengths of pipe installed, without deductions for service line connections or manholes. Final lengths of pipe installed will be determined from survey notes and inspection reports made by the Engineer in the course of setting construction. survey stakes. Sewer lines will be included on partial payment estimates only when every item of work required to construct each individual sewer line segment has been completed, including reconnection of existing services, trench backfill, cleanup, topsoiling, fertilizing, seeding and mulching. (Seeding, fertilizing and mulching shall only be done between the months of March through October.) When seeding, fertilizing and mulching cannot be completed (during the months of November through February), an additional 10 percent retainage on work under these bid items shall be withheld until completion. Bid Items 6, 7, 8 and 9 -. Extra Depth Trench Payment for extra depth trench shall be made for gravity sewer lines and in accordance with the unit prices bid per linear foot for each of the various items. The depth of the trench is hereby defined as the distance from the invert of the sewer line as constructed to the ground 1000-1 directly above the pipe centerline. The linear feet to be paid for under each item shall be determined by plotting the ground surface and the invert elevation of the sewer line as constructed. By using these plotting procedures, the Engineer will determine the final quantity to be paid for under each item, without deduction for manholes. Example: If the ditch plots to be 7 feet 6 inches, payment will be made under the 6 foot to 8 foot classification. If the ditch plots to be 9 feet 6 inches, payment will be made under the 8 foot to 10 foot classification, with no payment being made for the 6 foot to 8 foot classification. No payment for extra depth trench shall be made in connection with sewer service line reconnections. Bid Item 10 - Plug Sewer Overflow or Bypass Lines Payment for the plugging of sewer overflow or bypass lines shall be made in accordance with the unit price bid for each sewer overflow or bypass line plugged. The location for these overflows or bypass lines are as shown on the Plans and set out in the Specifications. The unit price bid shall include all necessary excavation, cleaning, furnishing and placing concrete in the overflow or bypass line, backfill, and cleanup for a complete, acceptable job. Bid Item 11 - Main Line Tap Repairs Payment for each main line tap repair shall be made at the unit price bid for each tap repair. The unit prices bid shall include all necessary excavation, trench preparation, and backfill and cleanup. Concrete encasement shall be paid for under Item 21 of the Proposal. Should any defective pipe be uncovered outside the limits of the proposed repair, additional payment for replacement of this pipe will be made under Items 1 through 5, and 6 through 9, as applicable, at the direction of the Engineer. Note: Abandonment. If a decision is made by the Engineer in the field that a repair to the line will not sufficiently correct the problem, or the Contractor excavates at the required location and does not find the source of the problem, then the Engineer shall verify and declare the point repair to be abandoned and the hole backfilled. Payment for abandonment will be made under Bid Item 23. No additional payment will be made for a main line tap repair. Bid Item 12 - Adjustment and/or Grouting Manhole Ring to Cone Payment for adjustment and grouting of existing manhole rings to cones ' shall be made in accordance with the unit price bid for each manhole ring adjusted and grouted at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials necessary to adiust and grout the manhole ring to the cone. Surface repair immediately adjacent to the adjusted manhole ring shall be paid for under other appropriate items of the bid, i.e., SB-2 crushed stone backfill, concrete or asphalt pavement repair, etc. 1000-2 Section 1000 Bid Item 13 - Cleaning;; Patching and Filling Cracks, and, Waterproofing Manholes Payment for cleaning, patching and filling cracks, and waterproofing manholes shall be made in accordance with the unit price bid for each manhole cleaned, patched and waterproofed at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials required to clean, patch and waterproof and test the manholes as specified. Bid Item 14 - Repair Manhole/Sewer Line Connections Payment for repair of manhole/sewer line connections will be made in accordance with the unit price bid for each manhole/sewer line connection repaired at the locations shown on the Plans and set out in the Specifications or, as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials to perform the repairs as specified. Also included in the price bid will be all necessary excavation, repair, pipe, couplings, etc. Concrete for pipe encasement or repair of manhole, SB-2 for backfill and surface repair will be paid for under other appropriate items of the bid. Should any defective pipe be uncovered outside the limits of the proposed repair, additional payment for replacement of this pipe will be made under Items 1 through'5, and 6 through 9, as applicable, at the direction of the Engineer. Note: Abandonment. If a decision is made by the Engineer in the field that a repair to the line will not sufficiently correct the problem, or the Contractor excavates at the required location and does not find the source of the problem, then the Engineer shall verify and declare the manhole/sewer line connection to be abandoned and the hole backfilled. Payment for abandonment will be made under Bid Item 23. No additional payment will be made for a manhole/sewer line connection repair. • ' Bid Item 15 - Raising Manholes Payment for raising manholes will be made at the unit price bid for each manhole raised at the locations shown on the Plans and set out in ' the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials to excavate, raise the manhole to the desired elevation (either at or above the existing grade, as directed by the Engineer), backfill and clean up the area as specified. Surface repair immediately adjacent to the manhole shall be paid for under other appropriate items of the bid, i.e., SB-2 crushed stone backfill, concrete or asphal.t pavement repair, etc. Bid Item 16 Plug Vent }toles and Raise Casting to Street Level ' Payment for this item will be made at the unit price bid for both raising the manhole and plugging the vent holes in the manhole lid at the locations shown on the Plans and set out in the Specifications. 1000-3 The unit price bid shall include all necessary materials, labor and , equipment to excavate, raise the manhole to the desired elevation (either at or above grade, as directed by the Engineer), plug the vent ' holes as specified, backfill and clean up the area as specified. Surface repair immediately adjacent to the manhole shall be paid for under other appropriate items of the bid, i.e., SB-2 crushed stone backfill, concrete or asphaltic pavement repair, etc. Bid Item 17 - Manhole Replacement Payment for manhole replacement will be made in accordance with the unit price bid for each manhole replaced at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials for excavation, bypass pump removal and disposal of existing manhole, construction of new manhole at the same grade and location, backfill and cleanup of the site. Also included are the furnishing and installation of new manhole steps, ring and lid as specified. Surface repair immediately adjacent to the manhole shall be paid for under other appropriate items of the bid, i.e., SB-2 crushed stone backfill, concrete or asphalt pavement repair, etc. Bid Item 18 - SB-2 Crushed Stone Backfill Payment for placement and compaction of SB-2 crushed stone backfill will be made in accordance with the unit price bid for each ton of material installed at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials to furnish, install and compact the SB-2 crushed stone used as trench backfill under driveways and pavements, as directed by the Engineer. However, no payment will be made under this item for SB-2 crushed stone used for pipe bedding. Measurement shall be by certified scale weight tickets furnished and initialed by the Engineer's representative at the location the material is to be used. Bid Item 19 - Hot -Mixed, Hot -Laid Asphalt Concrete Pavement Repair (3 Inch Minimum Thickness) Payment for placement and compaction of hot -mixed, hot -laid asphalt concrete will be made at the unit price bid for each square yard of material placed at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials to prepare the suhgrade, furnish and place prime or tack coat, and placement of a minimum of 3 inches thickness of asphalt concrete as specified. The unit of measurement shall be the nearest one -tenth of a square yard, on areas as directed by the Engineer. 1000-4 Section 1000 Bid Item 20 - Concrete for Pavement, Driveway and Sidewalk Repair Payment for placement of concrete for pavement or driveway repair shall be made at the unit price bid for each square yard of reinforced concrete pavement, placed at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and materials in the preparation of the subgrade, forming, expansion and contraction joints, reinforcing, furnishing and placement of concrete (thickness as shown on the Plans), finishing, curing, cleanup and all other related items of work as required. The unit of measurement shall be the nearest one -tenth of a square yard, placed on areas as directed by the Engineer. Bid Item 21 - Concrete for Pipe Encasement or Cover, and Pipe Anchor Payment for concrete used for pipe encasement and cover or pipe anchors shall be made in accordance with the unit price bid per cubic yard placed at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall include all necessary labor, equipment and material necessary to place the concrete as specified. The unit of measurement will be by delivery tickets furnished and initialed by the Engineer's representative, at the location the material is to be used. Bid Item 22 - Topsoiling, Fertilizing, Seeding and Mulching Payment for the furnishing and placement of 3 inches of topsoil (where required), fertilizing, seeding and straw mulching will be made in accordance with the unit price bid per square yard at the locations shown on the Plans and set out in the Specifications, or as directed by the Engineer. The unit price bid shall be full compensation for all necessary labor, equipment and materials to complete the work as specified. The unit of measurement shall be the nearest square yard, placed as directed by the Engineer. Bid Item 23 Abandonment of Main Line Tap or Manhole/Sewer Line Connection Repair If a decision is made by the Engineer in the field that a main line tap repair or repair to the manhole/sewer line connection will not ie sufficntly correct the problem, or the Contractor excavates at the required location and does not find the source of the problem, then the Engineer shall verify and declare the repair to be abandoned and the hole backfilled. Payment for abandonment will be made, and shall include excavation, backfill, and cleanup, Where required, payment for SB-2 crushed limestone backfill, concrete, asphalt or concrete pavement or sidewalk repair, topsoiling, seeding, fertilizing and mulching will be made under other bid items. 1 1000-5 Bid Item 24 - Sewer Service Line Reconnections I Payment for sewer service line reconnections shall be made at the unit price bid per reconnection. The unit price shall include any necessary clearing, tree or brush disposal, stripping and stockpiling of topsoil, surface removal, trenching and extra depth trench, disconnecting and temporary plugging of existing service line connections, furnishing, installing and bedding the sewer service line with 4 inches of SB-2, protective cover as required, providing and installing any straight or transition couplings and every item of work required to reconnect the existing service line toe sewer service wye. Additional compensation will be made only for those items of work specifically set out in the Proposal. 1 1 1 1 1 1000-6