HomeMy WebLinkAbout109-83 RESOLUTION•
RESOLUTION NO. 109-83
A RESOLUTION AUTHORIZING A CHANGE ORDER IN THE
CITY'S CONTRACT WITH BRAUN EXCAVATING COMPANY
FOR SANITARY SEWER SYSTEM REHABILITATION AND
RECONSTRUCTION TO PROVIDE FOR THE REROUTING OF
A SEWER LINE SFGMFNT AT EASTC.,LAFAYETTE STREET
AND'DOGWOOD LANE. 4
4
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSA•S: ' ••
That the Mayor and City 'Clerk are hereby authorized and
directed to execute the' change order.'attached hereto, marked
.-Exhibit ',A" and made a part hereof.
PASSED AND APPROVED this 20th day of September , 1983.
r.
M=.f
"t!k .j:Nx
r•
'.
By:
ST:
•
APPROVED:
By:�/C1ea / giZtA
Mayor
Change Order No,..2
SANITARY SEWER SYSTEM REHABILITATION
AND RECONSTRUCTION
Minisystems 2, 4, 7, 8, 11 and 16
City of Fayetteville, Arkansas
Plans No. Fy-116
Dated April, 1983
The contract dated June 29, 1983, between the City of Fayetteville, Arkansas,
and Braun Excavating Company of Seymour, Missouri, is hereby changed as follows:
1. Change the alignmentand grade on Segment 2-9 from that shown on the
original plans to the alignment and grade shown on the attached plan and
profile (Attachment No. 1).
2. Construct two new manholes at the locations and to the depths shown on the
attached plan and profile. The manhole specification is attached
(Attachment No. 2).
Manholes 2/3/1 and PS6/Creek/1 (Mainlines Requiring Plugging of Overflows -
Rehab Code 1) are hereby deleted from the contract.
4. Provide and place native stone riprap
an aid to erosion control as required
at the unit price set out below for
Engineer to be hauled in and placed.
along Segments 16-2, 2-2 and 2-4 as
Payment for this item will be made
native stone as required by the
5. The contract shall be extended six (6) calendar days,changing the date of
completion of construction to October 17, 1983.
6. Change estimated quantities for Bid Items No. 2, 10, 18 and 19 and add Bid
Items No. 25 (construct new manhole 0'-6' in depth) and 26 (native stone
riprap) to the contract as follows:
Bid Item
No.
2. ADD 12 L.F. 6" Ductile Iron Pipe Sewer @ $21.58/L.F. ...
10. DEDUCT 2 Each Plug Sewer Overflow or Bypass Line
@ $53.30/Each
18. ADD 15 Tons SB -2 Crushed Stone Backfill @ $9-.00/Ton
19. ADD 60 S.Y. HMAC Pavement Repair @ $27.00/S.Y.
25. ADD 2 Each Manholes 0'-6' @ $700.00/Ea
26. ADD 90 S.Y. Native Stone Riprap @ $13.50/S.Y
Net Addition, This Change Order
$ 258.96
(106.60)
135.00
1,620.00
1,400.00
1,215.00
$ 4,522.36
Total Contract Price, Including Change Orders No.
EXHIBIT A
1 and No. 2
$206,266.06
All other provisions of the contract remain in force.
Approved this
T / R.k day of `-S7" "`.k..l , 1983.
ENGINEER: McGoodwin, Williams and Yates, Inc.
Jer
chards Pro3 nager
lir
CONTRACTOR: Braun Excavating Company, Inc.
d Braun 'resident
APPROVED: City of Fayetteville, Arkansas
.01kwaie
Donald R., Bunn, City Engineer
e) —
PFW
bhp, M ,. tfi;:i , \
f 2e'ut
h;A • o+27-Cot417T.
i pew MAUHOLb
Gxicir I5° RGP ��
�u�v�6r_P OT
x
eKI°Tr, 1.4-1 2/140
5T3, 2+00 TI E
5/1. 4c ;xl'ir. Mi.
7
5ECMEMT ?-c,
4414-e I"
F:K. FY, 1o1 f2(4`.7. 7.33
STh • I+02 -COW•411
�? N
MANHOLE.:
.17 -rt r7"Dt,P
�
C�nl=k ` ,-
C #-
I Jr
-4.
10
0
.._ - .. Oho__ ______-
IO
100
400 t00
McGoodwin, Williams and Yates, Inc.
Consulting Engineers
nLLacl,menC NO. G
Section 150
Manholes
CAST -IN-PLACE MANHOLES
150-A. GENERAL. The work to be included under this section of the
specifications shall consist of providing all materials, labor, equipment,
tools, supplies, and incidentals necessary for the construction of standard
and drop cast -in-place manholes. The work shall include every item of
construction necessary for a complete and acceptable installation as shown
on the Plans and hereinafter specified. Precast, brick, masonry, or
vitrified clay radial block manholes are not approved for use on this
project.
150-B. MATERIALS.
1. Concrete. Concrete used in the construction of standard and drop
cast -in-place manholes shall be in conformance with the Concrete
Section of these. Specifications.
2. Mortar and Grout. Mortar or grout used in the construction of manholes
shall be mixed in the proportion of one part of Portland cement and two
parts mortar sand as defined in the Concrete Section of these
Specifications. The mixture shall be dry -mixed until it has a uniform
color, after which water shall be added or the mixing continues until
the mortar has a consistency such that it can be easily handled and
spread with a trowel. Mortar or grout that has not been used within
30 minutes after water has been added shall not be used.
3. Manhole Rings and Lids. All castings for manhole frames, covers and
other purposes must be of tough gray iron, free from cracks, holes,
swells and cold shuts, shall be of workmanlike finish, and shall
conform to the Plans. The quality shall be such that a blow from a
hammer will produce an indentation on a rectangular edge of the casting
without flaking the metal. Before leaving the foundry, all castings
shall be thoroughly cleaned and subjected to a hammer inspection.
Manhole rings and lids shall have a combined weight of not less than
350 pounds and shall be in accordance with the dimensions shown on the
Plans. The manhole lids shall be of solid construction without any
openings of_any type except two pick holes which shall be located on
directly opposite sides of the manhole lid. The pick holes shall be of
such design that when the lid is in place, there is not a clear opening
into the manhole.
Manholes Steps. Steps shall be 10 inches wide and shall be constructed
of steel reinforced fiberglass. Manhole steps shall be equal and
similar in design to Perma-Step Model 100-2 as manufactured by Utility
Products, Inc., or equal.
150-C. MANHOLE CONSTRUCTION.
1. Excavation for Manholes. Excavation for manholes will be made of such
dimension and depth as to allow the construction of the manhole as
150-1
•
•
nL LeleautLL P40. L
Section 150
Manholes
shown on the Plans. No extra payment shall be made for manhole
excavation, and all surface removal shall be in accordance with
Section 095 of these Specifications.
2. Base. The concrete base shall have a minimum thickness of 8 inches and
shall be poured on undisturbed earth. The base shall be poured so that
the top of the base is a minimum of 2 inches and a maximum of 4 inches
below the lowest pipe inside the manhole, except when the lowest pipe
can be laid continuously through the manhole, the base may be poured to
a point 2 inches below the centerline of the pipe, providing this point
is not above invert of other pipes entering the manhole. The base
shall have a minimum diameter of 8 inches greater than the outside
diameter of the finished manhole barrel.
3. Connections to Manholes. Pipe connections to manholes are a constant
source of potential trouble. In order to ensure that pipe will not
break immediately adjacent to the manhole, care shall be taken that
excavation for the manhole bottom is limited to the area to be filled
with concrete. The Contractor shall support pipe entering the manhole
ALL OF THE WAY to solid bedding by backfilling under the pipe and up to
mid-springline with concrete.
4. Invert. The invert of the manhole shall be hand -placed and shaped
using grout as specified. The base and barrel of the manhole shall be
cleaned thoroughly prior to placement of the invert. The invert shall
be shaped and smoothed so that the manhole will be self-cleaning and
free of areas where solids may be deposited as sewage flows through the
manhole. The entire diameter of each pipe entering the manhole barrel
shall be cut smooth with the inside edge of the manhole barrel and the
invert shaped throughout from all inlet pipes to the outlet pipe.
5. Manhole Barrels. The barrel forms may be set as soon as the concrete
base has cured enough to support the forms. The manhole barrel shall
be of such construction so that the finished manhole will have an
inside diameter of 4 feet 0 inches, plus or minus one-half inch.
Prior to setting the forms in place, any water that may have
accumulated in the excavated area shall be pumped out and the concrete
base thoroughly cleaned, if required, of dirt and debris.
Before pouring of the concrete begins, a 2 inch layer of grout mixture
shall be placed in the bottom of the forms.
The forms shall be removedafter the initial set of the concrete so
that holes may be cut in the manhole barrel for the installation of
pipes which are to enter the manhole at points other than adjacent to
the manhole base. After these pipes have been put in place, the barrel
shall be repaired using a grout mixture. If honeycombing of the barrel
is found to be present after removal of the forms, they shall be
repaired as directed by the Engineer.
150-2
nLLOCIWltllll. INU. G•
Section 150
Manholes
6. Manhole Steps. Manhole steps are required in all manholes 4 feet deep
or more. During the construction of each manhole, steps shall be set
in place on the inside of the manhole, beginning 2 feet above the
bottom and placed not more than 18 inches below the top of the manhole.
These steps areto be built to the dimensions shown on the Plans. The
ends shall be firmly built into the wall, allowing the steps to project
5 inches from the inside of the manhole.
7.. Manhole Heights. Manholes are to be built to the existing ground,
surface unless otherwise noted on the Plans or directed by the
Engineer. When manholes are constructed in streets, the top of the
poured manhole shall be left at such an elevation so that two rings of
standard brick are required to bring the manhole ring to the finished
elevation. A 3 inch wide by 2: inch deep keyway shall be left in the
top of the poured manhole to hold the mortar for the first ring of
bricks. All brick or block shall have full mortar joints on the bottom
and sides. Every joint shall be formed at one operation by placing
sufficient mortar on the bed and forcing the brick or block into it.
Horizontal joints shall not exceed 3/8 inch and the vertical points on
the inside of the manhole shall not exceed 1/4 inch. The brick shall
be plastered on both the inside and outside with 1/2 inch of cement
mortar. The plaster shall be smoothly laid, and on the inside of the
manhole all rough projections shall be removed. Details for the
construction of manholes are shown on the standard detail sheet of the
Plans.
8. Drop Manholes. Drop manholes, unless otherwise shown on the Plans,
shall be constructed at all manholes where the difference in invert
elevation between incoming and outgoingsewer is 2.5 feet or more.
Drop manholes shall be constructed of the same material and dimensions
as are standard manholes, the only difference being in the inlet
arrangements as shown on the standard detail sheet.
Curing. Curing compounds or covers may or may 'not be used at the
option of the Contractor. However, it will be the responsibility of
the Contractor to protect the concrete to prevent cracking during the
curing process and to protect the manhole during freezing temperatures.
The Engineer shall, at hisdiscretion, prohibit pouring concrete during
periods of extreme cold or inclement weather.
10. Backfilling. The manhole shall be backfilled evenly around its
perimeter no less than 12 hours after the forms have been removed.
Extra care shall be taken to compact all .backfill to the top of the
highest pipe entering the manhole. All backfilling shall be in
accordance with Section 146 of these Specifications..
150-3