HomeMy WebLinkAbout22-80 RESOLUTION•
RESOLUTION NO. ot;"SD
A RESOLUTION AUTHORIZING THE MAYOR AND CITY CLERK TO
EXECUTE A CHANGE ORDER IN THE CITY'S CONTRACT WITH JERRY D.
SWEETSER INC. FOR THE INSTALLATION OF CONCRETE CURB AND
GUTTER, DROP INLETS, AND A SIDEWALK AT THE NEW AIRPORT
TERMINAL BUILDING.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
That the Mayor and City Clerk are hereby authorized and
directed to execute a change order in the City's contract
with Jerry D. Sweetser, Inc., for the installation of concrete
curb and gutter, drop inlets, and a sidewalk at the new
airport terminal building. A copy of the change order
authorized for execution hereby is attached hereto and
marked Exhibit "A" and made a part hereof.
PASSED AND APPROVED this i" day of � (2hC.A.— , 1980.
4.
-V ATTEST::{
-7w
, own
Pa, CITY/ LERK
(SEAL)
APPROVED*
MICROFILMED
•
•
CHANGE ORDER
PROJECT: Change Order No. 3
Airport Improvements to Drake Field Contract Section II
Fayetteville, Arkansas
OWNER:
City of Fayetteville
P.O. Drawer F
Fayetteville, Arkansas 72701
CONTRACTOR:
Jerry D. Sweetser, Inc.
P.O. Box 579
Fayetteville, Arkansas 72701
,
•
Job No. 77-183
DATE: February 20, 1980
Contract Date: April 13, 1979
FAA ADAP Project No.: 6-05-0020-06
(Non Participating)
PROJECT DESCRIPTION
Concrete Paving, Concrete
Drainage for New Terminal
Facility.
CHANGES TO BE MADE
Add Items II -4, II -8 and II -14, concrete curb and gutter, curb Inlets
and 5 ft. sidewalk, respectively, for the public and rental car parking
lots which were deleted by Deductive Alternate Nos. 1 and 2.
Contract
Changes
Bid
Item
No.
Original
Estimated
Quantity
Contract Revised
Unit Estimated
Price Quantity
1. A. II -4 4246 L.F. $ 3.75
2. A. II -8 1 EA. $800.00
3. A. II -14 27.2 S.Y. 13.50
Original
Estimated
Cost
8806 L.F. $15,922.50
5 EA. $ 800.00
47.8 S.Y. $ 367.20
$17,089.70
Original Contract Price
Increase in Contract Price
Page 1 of 2
EiA;b; 4 /7
New Contract Price
Revised
Estimated
Cost
$33,022.50
$ 4,000.00
$ 645.30
$37,667.80
$437,085.93
$ 20,578.10
$457,664.03
r
c
THE AFOREMENTIONED CHANGE, AND WORK AFFECTED THEREBY, IS SUBJECT TO ALL
CONTRACT STIPULATIONS AND COVENANTS.
ISSUED FOR REASONS INDICATED ABOVE:
ACCEPTED BY CITY OF FAYETTEVILLE:
ACCEPTED BY JERRY D. SWEETSER, INC.
ACCEPTED BY FEDERAL AVIATION
ADMINISTRATION:
CONDITIONS OF SATISFACTION:
McCLELLAND CONSULTING ENGINEERS, INC.
gineer)
S i .'ture
Titl i
gnature (�
Title
2-ol7-30
Date
Airport District Office
Date
This confirms our satisfaction, however the
increased contract price is ineligible for
Federal participation as stated in our letter
of March 17, 1980 to Mr. Wayne Jones.