RESOLUTION NO. 11-19
A RESOLUTION AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE
CHANGE ORDER NUMBER THREE WITH HECKATHORN CONSTRUCTION COMPANY
FOR AN EXPANSION TO THE FAYETTEVILLE YOUTH CENTER.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
That the Mayor and City Clerk are hereby authorized and
directed to execute a change order number three with Heckathorn
Construction Company for an expansion to the Fayetteville Youth
Center. A copy of the change order authorized for execution
hereby is attached hereto marked Exhibit "A" and made a part
hereof.
PASSED AND APPROVED this
1979.
ATTEST:
day of
APPROVED:
I
'MAYOR
MiCROFII(LMED
DATE 3 1919
REEL
CHANGE"
ORDER
AIA DOCUMENT G701
•
OWNER
ARCHITECT
CONTRACTOR
FIELD
OTHER
(7--75
EXHIBit ::(A
PROJECT: AN ADDITION TO FAYETTEVILLE BOYS CLUB CHANGE ORDER NUMBER: 3
(name, address) AND YOUTH CENTER
915 California Drive, Fayetteville, AR 72701
TO (Contractor)
rHeckathorn Construction Company
1880 Birch
Fayetteville, Arkansas 72701
L J
ARCHITECT'S PROJECT NO: 78-A-15
77-195
CONTRACT FOR:
CONTRACT DATE:
You are directed to make the following changes in this Contract:
1. a.
February 14, 1979
To remove and replace concrete floor for new concession room and hallway to
existing building due to excessive settlement of existing floor in this
area,
ADD. . . .$ 621.00
b. To replace the west wall of the hallway for a distance of 16 feet with a
new 8" concrete block wall. The existing wall was unstable when two new
door openings were installed. ADD. . . .$ 677.00
To reroute gas line to existing building in the ceiling and removing
gas line from hallway.
ADD. . . .$ 432.00
fPIN D. To install a concrete walk and steps for the east entrance on the first
floor. The existing asphalt pavement had been removed during the relo-
cation of gas, water and sewer lines. ADD. . . .$ 637.00
TOTAL ADDITION. . . .$2,367.00
The original Contract Sum was
Net change by previous Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be (increased) (1) O by this Change Order .
The new Contract Sum including this Change Order will be
The Contract Time will be Er ) (decrrnsed) (unchanged) by
The Date of Completion as of the date of this Change Order therefore is
A JOINT VENTURE:
Fletcher, Miller, Dean , LR
Heckathorn Construction Co.
linie land Consulting Engineers 1880A
ABirch
CAddress P. 0. Box 1229 Address
Fa ettev e R 72711 FayetteeevilleAR 72701
BY 17 . 0' _ / L BY 4�i /J i�.v✓'^"r,CGw.
DATE
R /3 -
DATE g (3-7 `r
$ 564,622.00
$ 4,956.00
$ 559,666.00
3 2,367.00
$ 562,033.00
( ) Days.
•
•
•
•
City of Fayetteville
OWNER
P. 0. Drawer F
Address
Fayettev
ille, AR 72701
BY
DATE /-./
ATTEST
-7
Cia`ir Clerk
AMA DOCUMENT G701 • CHANGE ORDER • APRIL 1970 EDITION • AIA® • ® 1970 • THE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW, WASHINGTON, D.C. 20006
ONE PAGE