HomeMy WebLinkAbout1999-05-04 - Agendas - Final f
FINAL AGENDA
FAYETTEVILLE CITY COUNCIL
MAY 4, 1999
A meeting of the Fayetteville City Council will be held on May 4, 1999 at 6:30 p.m. in Room
219 of the City Administration Building, 113 West Mountain Street, Fayetteville, Arkansas.
The following items will be considered:
• Nominating Committee Report: George Cowen for Tree & Landscape
A. CONSENT AGENDA
1. APPROVAL OF THE MINUTES: Approval of the minutes from the April 20,
1999 City Council Meeting.
2. DRAKE FIELD DELIIGIFT SHOP: Request approval of a modification to a
lease with Air Host, Inc. This modification provides for the cancellation of their
lease to operate the Deli and Gift Shop in the Drake Field terminal building. Air
Host has requested the cancellation as their customer volume has decreased with
the relocation of four of the five airlines to another airport.
3. BID 99-43: Accepting Ron Blackwell Ford as the lowest qualified bidder meeting
specifications for the purchase of 4-wheel drive utility vehicles, Bid 99-43. These
units will be utilized by the Fire Department and the Police Department.
—CIG 4. BID 99-46: Approval of bid award 99-46 for the Walker Park pavilion project to
11 Heckathorn Construction in the amount of$64,618, plus a project contingency of
$3,500 for a total of$68,118.
Z- 'j� 5. HIGHWAY 16 WEST WIDENING: Approval of a construction contract for
Highway 16 W. widening, water and sewer relocation project. Information on
contractor, cost and project contingency to be provided May 3.
6. ASSEMBLY ROAD STORM DRAINAGE: A resolution approving a contract
Cr) for Assembly Road Storm Drainage Improvements with Jerry D. Sweetser, Inc.
In the amount of$58,575.00 plus a contingency of 20.0% ($11,715.) Totaling
$70,290.00
City Council
May 4, 1999
Page 2
7. SUNBRIDGE DRIVE EXTENSION: A resolution approving a contract for
Sunbridge Drive Extension with Red Deer Inc. in the amount of$268,174.75 plus
6Lt` a contingency of 11.1% ($29,825.25) totaling $298,000. Approval of a budget
adjustment adding funds to the project and a project contingency of$19,461 is
also requested.
8. RESEARCH & TECHNOLOGY PARK: A resolution approving a contract for
Research and Technology Park for tree and shrub removal with erosion control
with Tomlinson Asphalt Co. Inc., in the amount of$31,306.00 plus a contingency
of 19.8% (6,194.00) totaling $37,500.00.
B. OLD BUSINESS
1. CHIEF EXECUTIVE OFFICER: REMOVED FROM THE AGENDA AT
THE REQUEST OF THE MAYOR. An ordinance amending Chapter 10,
General Provisions, of the Code of Fayetteville, to add Section 10.13, Chief
Executive Officer, to define miscellaneous powers and duties of the mayor. Item
was left on the second reading at the April 20, 1999 meeting.
2. ODOR CONTROL OF SEWAGE TREATMENT PLANT: A resolution
establishing odor abatement and control as a priority in the design and operation
of the City's sewage facilities.
3. WATER & SEWER TREATMENT PLANT: A resolution to exercise the
City's purchase options on three tracts of land on the west side of Fayetteville for
-r1 the construction of a new sewage treatment facility. Land tracts to be considered
are currently owned by James McClelland, H. M. and Norma Shipp, and the
Broyles Farm.
C. NEW BUSINESS
1. VA 99-4: An ordinance approving VA 99-4 vacating an alley located at 903
South Government Street as requested by the Regional National Cemetery
�T Improvement Corporation lying contiguous to the east side of Lot 10 and to the
west side of Lot 11 of the Dowell Addition.
q 2. VA 99-5: An ordinance approving VA 99-5 vacating an alley located at 898 Hill
Street as requested by the Regional National Cemetery Improvement Corporation
for that portion of a 20 foot alley lying contiguous to the west side of a part of lot
9 and all of Lots 10, 13, and 14 in the Dowell Addition.
City Council
May 4, 1999
Page 3
3. CARDINAL CAB: A resolution authorizing a Certificate of Public Convenience
and Necessity be issued to Cardinal Cab Co. of Springdale Arkansas for operating
a transportation service within the City of Fayetteville.
4. WASTEWATER TREATMENT PLANT DATA REVIEW: A resolution
.G1 authorizing a review of data related to the Paul R. Noland Wastewater Treatment
Facility by an independent engineer to determine flow processing capabilities.
r�
y
nAMIFT
RANTOR
DAVIS
MAYC)R HANNA
REYNOLDS
AT ISTIN
MAY(-)'R 14ANNA
73 Ofoll
-�
. LE
SANTOR
RT TqQFl T.
AT JSIIN
DAVILS
MAYQR HANNA
D-D .
LAP
TRI JMBO
RANTOR
AT T'qTTW
DAVIS
MAYOR 14ANNA
✓ ✓
ATNTIN
DAVIR
MAVOR HANNA
DANIEL
v
,/ ✓ ✓
r
✓ ✓
✓ ✓
✓ V600,
DAVIS
MINUTES OF A MEETING
OF THE
FAYETTEVILLE CITY COUNCIL
APRIL 20, 1999
r
A meeting of the Fayetteville City Council was held on April 20, 1999 at 6:30 p.m. in Room 219
of the City Administration Building located at 113 West Mountain Street, Fayetteville, Arkansas.
PRESENT: Mayor Hanna, Aldermen Bob Reynolds, Ron Austin, Bob Davis, Trent Trumbo,
Heather Daniel, Kevin Santos, Cyrus Young, and Kyle Russell, Planning Secretary Janet Johns
(for City Clerk Heather Woodruff), City Attorney Jerry Rose, Staff, Press and Audience.
ABSENT: City Clerk Heather Woodruff.
The follow items were considered:
ITEM ACTION TAKEN
Approval of the Minutes Approved
Arkansas Avenue Res. 55-99
Bid 99-47: Paul R. Noland Wastewater Treatment Plant Res. 56-99
Insurance Policy Renewals Res. 57-99
Historic District Commission Removed
Land Possession - Rupple Road Ord. 4157
Chief Executive Officer Left on 2111 reading
Street Name Change: Hall Avenue to Garland Avenue Res. 58-99
Cliffs Boulevard Ord. 4158
Planning Commission Appeal: Cliff s Boulevard Phase 2 Motion
Discussion of Odor Emitting Businesses No Action
1999 Water & Sewer Refunding Bonds Ord. 4159
O
MINUTES OF A MEETING
OF THE
FAYETTEVILLE CITY COUNCIL
APRIL 20, 1999
A meeting of the Fayetteville City Council was held on April 20, 1999 at 6:30 p.m. in Room 219
of the City Administration Building located at 113 West Mountain Street, Fayetteville, Arkansas.
PRESENT: Mayor Hanna, Aldermen Bob Reynolds, Ron Austin, Bob Davis, Trent Trumbo,
Heather Daniel, Kevin Santos, Cyrus Young, and Kyle Russell, Planning Secretary Janet Johns
(for City Clerk Heather Woodruff), City Attorney Jerry Rose, Staff, Press and Audience.
ABSENT: City Clerk Heather Woodruff.
CONSENT AGENDA
APPROVAL OF THE MINUTES
Approval of the minutes from the April 6, 1999 City Council meeting.
ARKANSAS AVENUE
A resolution approving a budget adjustment and authorizing the Mayor to enter into a cost-
sharing agreement with the University of Arkansas for the removal and replacement of the curbs
and gutters located on the outside of each lane of Arkansas Avenue between Dickson and Maple
Street.
RESOLUTION 55-99 AS RECORDED IN THE OFFICE OF THE CITY CLERK
BID 99-47
A resolution awarding Bid number 99-47 to the selected bidder, Multi-Craft Contractors, for the
installation of the ultraviolet disinfection system for the Paul R. Noland wastewater treatment
facility.
RESOLUTION 56-99 AS RECORDED IN THE OFFICE OF THE CITY CLERK.
INSURANCE POLICY RENEWALS: A resolution to exercise option to renew Blue
Cross/Blue Shield, U.S. Able Life, Accidental Death and Dismemberment, and Long Term
Disability Group increase in premium. Annualized total city contributions for calendar year
1999 will be approximately $184,606.
RESOLUTION 57-99 AS RECORDED IN THE OFFICE OF THE CITY CLERK.
Alderman Daniel moved to approve the consent agenda. Alderman Reynolds seconded the
motion. Upon roll call the motion carried unanimously.
City Council
April 20, 1999
Page 3
HISTORIC DISTRICT COMMISSION
An ordinance approving the amendment of Ordinance 3836 to provide for two additional
members to the Historic District Commission for a total of nine members. Item was tabled on
the first reading at the April 6, 1999 meeting..
Mayor Hanna stated the item had been tabled until the Historic District Commission could meet
again.
LAND POSSESSION: RUPPLE ROAD
Mayor Hanna introduced an ordinance authorizing the City Attorney to seek court-ordered
possession of 0.317 acre of land owned by Tony and Bobbye Hardin, located north of Mount
Comfort Road and west of Salem Road for the purpose of extending Rupple Road from Mount
Comfort road to the proposed new middle school. Ordinance should also include specific
temporary easements. Item was left on the first reading at the April 6, 1999 meeting.
Mr. Rose read the ordinance for the first time.
Alderman Trumbo stated he would like to hear from Mr. Carr from the Fayetteville School. He
asked Mr. Carr to give a history of procedure that the school board had gone through and the
public notification they had done during the planning process. He also asked him to explain the
location of the proposed road.
Mr. Carr explained they had looked at several parcels of land. They had been offered a piece of
property off Mount Comfort. There had been several public hearings on the location of the new
school. They then selected an architect to design the building to work with Rupple Road. The
school had to pay the architects additional money, so they could have the benefits of having
Rupple Road to the south. The best pick up and drop off of students was off of Rupple Road.
All of their utilities were coming off Rupple Road. Currently all the foundations were poured
and the utilities were stubbed out on the east side of the building. To change the location of the
utilities and drop-offs would be financially devastating. If they had to move the drop offs, then
the playgrounds would be reduced significantly. To move things now would be over$600,000 to
the school district.
Alderman Trumbo stated that Mr. Hardin had suggested the road be moved to the west, but it
was Alderman Trumbo's understanding that the engineering and the curvature of the road would
make it infeasible to move it to the west. He thought this was the only option available.
Mr. Carr stated their engineers and architects had looked at the site and agreed this was the best
site for the road. It was unfortunate that Mr. Hardin was not aware of this going on. They had
had several advertisements in the local paper. It would be impossible for them to make changes
at this time.
City Council
April 20, 1999
Page 4
Alderman Trumbo asked if he had exhausted all avenues rather than placing this road so close to
Mr. Hardin's house.
Mr. Carr replied they were following the Master Street Plan. All their planning had been done
around the Master Street Plan.
Ms. Laleh Amirmoez, architect for school, stated the location of the school within the property
was to take advantage of the Rupple Road access and utilities and would allow more room for
playgrounds. They could not move the building further west because of the drainage. They had
located the school the most effecient way possible.
Alderman Daniel noted the street had been on the Master Street Plan for a long time and was not
just a result of the school.
In response to questions from Mr. Austin, Mr. Carr stated the finished construction date was May
25, 2000. They intended to occupy the school that fall.
Alderman Davis stated the school would be looking at an additional cost of$650,000 if they
were to change the road at this point.
Mr. Carr stated that would be a minimum, because the utility extensions could be more.
Alderman Davis noted that Mr. Venable had estimated the relocation of the road would cost an
additional $500,000 cost to the city.
Mayor Hanna stated they could all understand Mr. Hardin's concerns. He thought they should
seriously consider moving ahead with the ordinance but broadening it to include negotiating with
Mr. Hardin to purchase his house. The fire chief thought they could use the location as a
substation in the location. Mr. Hardin had stated he would consider it as a last resort. He
thought this was a fair settlement rather than condemning the land and constructing a road thirty
to forty feet from his house.
Mr. Rose read a proposed amendment to the ordinance by adding a section 2 which would
authorize the city staff to enter negotiations for the purchase of the house and the property.
Alderman Trumbo moved to amend the ordinance. Alderman Daniel seconded the motion.
Upon roll call the motion carried unanimously.
Mr. Hardin stated that utilities and roads were two different things. He stated they could still run
the utilities through the same place. He did not see a problem with the cost of the utilities. He
thought the majority of the cost would be utilities. He had looked at the master plan of the
City Council
April 20, 1999
Page 5
school. The only thing that would have to be done would be to change the parking areas. He did
not believe there would be any additional cost to the schools.
Mr. Carr replied if they were to move they would have to construct two access roads: one for
buses and another for the parents. Two roads would wipe out their play ground area.
In response to questions from aldermen, Mr. Rose stated they were on the second reading and if
they were to pass the ordinance they would authorize him to start legal action to obtain the
smaller portion of the property. They would also be authorizing city staff to begin negotiations
to obtain the house and property.
Alderman Santos moved to suspend the rules and move to the third and final reading.
Alderman Davis seconded the motion. Upon roll call the motion carried unanimously.
Mr. Rose read the ordinance as amended for the third and final time.
Mr. Hardin asked if they would be voting on moving the road.
Mayor Hanna stated it would depend on how the council voted on this motion.
Alderman Austin explained a motion had been made on the ordinance.
Mr.Hardin disagreed with the cost estimate from Mr. Venable.
Mayor Hanna stated it was a tough decision.
Alderman Trumbo explained they had all listened to his side.
Alderman Austin pointed out the motion on the floor gave Mr. Hardin another option.
Mr. Hardin explained he had lived in this house for over 30 years and had buried a son in the
cemetary. In response to questions from Mayor Hanna, Mr. Hardin stated he only owned one
and half acres.
Mayor Hanna called for the vote. Upon roll call the motion carried by a vote of 7-1-0,
Daniels voting nay.
ORDINANCE 4157 AS RECORDED IN THE OFFICE OF THE CITY CLERK.
CHIEF EXECUTIVE OFFICER
Mayor Hanna introduced an ordinance amending Chapter 10, General Provisions, of the Code of
City Council
April 20, 1999
Page 6
Fayetteville, to add Section 10.13, Chief Executive Officer, to define miscellaneous powers and
duties of the Mayor. The item was left on the first reading at the April 6, 1999 meeting.
Mr. Rose read the ordinance for the second time.
Alderman Santos asked that the council table this item until they had more time to do research.
The only town he could find that had something like this was Los Angeles, California. They had
gone through a charter reform and the decision they had made was that the mayor should not
have the power to remove department general managers as Fayetteville had now. They had
thought it would be better if the council hired and fired the general managers. They had pointed
out that the authority of the mayor was that he was the dominant player in the city's budget and
was the political leader. He thought this would make decisions which should be made by
professional positions to be made by political appointees. He thought they should redefine the
qualification definition for department heads and let the council as a whole decide the hiring and
firing of the senior management. He read a letter from Bill Moler expressing concern of a shift
of power. He noted the mayor to override or bypass a department head. He read questions from
Mr. Moler. What were the specific needs being met by the ordinance?
Alderman Trumbo responded that it was a legal question. It was currently a mayoral decision to
hire and fire staff now. He did not feel that he as an alderman had the time to micromanage the
city's hiring and firing. The mayor was elected to make those decisions. In the past there had
been a lot of complaints about the red tape and bureaucracy they had to go through.
Alderman Santos stated he was not answering the question about the specific need that it met.
He stated the ordinance was a solution begging for a problem. He asked what the problem was.
Mr. Rose replied he had attempted to avoid having the mayor change every ordinance in the code
book that mentioned individual job titles. He mentioned that the mayor currently has the
authority to hire and fire and redesignate and restructure job positions.
Mayor Hanna stated that, in his opinion, they were creating the ordinance to clarify questions,
not to make it more complicated. Some of the things prescribed in the ordinance were state laws.
Mr. Rose explained that the state of Arkansas gave the voters and the people in each city a list of
ways in which they can be governed, such as City Manager, Mayor-Council, City Charter, or
City Administrator forms of government. The voters had chosen the Mayor-Council form of
government. In that section the law stated that the Mayor of the city shall be the chief executive
officer. As chief executive officer it generally meant that they could hire, fire and be the
supervisor of the employees. The council would hold the purse strings and the mayor would
supervise the day-to-day running and administration of the city hall. He thought the example Mr.
Santos had given was a charter form of government, where the citizens had negotiated a charter
City Council
April 20, 1999
Page 7
or contract with the government. He did not believe this ordinance would change the form of
government. The state statute would always prevail. They were operating under the Mayor-
Council form of government and they could not pass an ordinance to change that.
Alderman Santos stated he could not see the reason to pass this ordinance, because it did not
fulfill any currently need.
Alderman Young stated one of the problems of passing an ordinance was the unintended
consequences of the ordinance. He added it was harder to undo an ordinance. It was very hard
to override a veto.
Alderman Davis asked Mr. Rose some of the possible problems which could occur if they passed
the ordinance.
Mr. Rose stated he could not answer it from a legal point of view. He thought it was for the
council to discuss. If they were to have a bad mayor or council they would have bad mayors.
Alderman Trumbo stated all the time he had served on the city council he had never been
involved in the interviewing, hiring or firing of an employee.
Alderman Santos asked that they not approve this ordinance which allowed the Mayor's duly
appointed representative to serve in the positions, if the only reason they were passing the
ordinance was so they did not have to change all the job title specifications in the code book. He
stated that it did not make any sense at all, because it should be a public decision and not a
political appointment. If they defined the positions of the people making the decisions it would
be better than giving a blanket approval to reappointed anyone to those positions.
In response to questions from aldermen, Mr. Rose explained the mayor could currently do that
now.
Alderman Russell stated Section B was completely consistent with state law. Section B was
about all the power which the mayor currently has under the Mayor-Council form of
government. What he had a problem with was the unintended consequence of firing an
individual. In regards to Section A, there were sections in the code which specifically delegated
certain tasks to certain city staff members. The "and/or" gave people the option to bypass the
staff and to go straight to the mayor. He had a problem with people bypassing the steps. He had
a problem with part A and not part B of the ordinance.
Alderman Trumbo pointed out that anyone had the right to file a lawsuit for wrongful discharge.
Mayor Hanna explained his duly appointed person was the "planning director," and if they were
City Council
April 20, 1999
Page $
not available the city had a good enough staff to advise him to make a good a decision. He asked
Ms. Little how many times he had asked her to change her decision.
Ms. Little replied he had not asked her one time.
Alderman Russell replied he was not talking about Mayor Hanna, he was talking about what
would happen if they were to pass the ordinance, it would take a vote of six council members to
rescind the ordinance. He suggested the ordinance should read the Mayor's duly appointed
representative.
Mayor Hanna replied he would not have a problem. He stated he was ready to move on with the
ordinance and would support a change if he wanted to make it.
Alderman Santos moved to amend the ordinance as alderman Russell had suggested.
Alderman Young seconded the motion. Upon roll call the motion carried by a vote of 5-3,
Trumbo, Reynolds, and Austin voting nay.
Mr. Rose read the amended ordinance to read "the Mayor's duly authorized representative."
Ms. Terry Easton, citizen, stated the staff was around him to protect him with their expertise and
knowledge in different fields. If the ordinance were to pass they would open themselves up to
unfavorable opinions. She did not believe the ordinance would serve the general public.
Mr. Randy Zurcher, a resident, urged the council to vote against the ordinance.
Mr. Jeff Erf stated he had yet to hear a need for the ordinance and urged the council to vote
against it.
Mr. Glenn Sowder, an area resident, stated there were people that had a lot of time on their hands
that had good imaginations about conspiracies. He asked them to keep doing a good job.
Mr. Dan Coody, an area resident, asked if the mayor was still considering withdrawing the
ordinances. He stated many people were concerned about the "good old boy" system.
Alderman Davis stated the mayor could not change existing ordinances.
Mr. Coody stated the Mayor had stated someone would need to interpet the ordinances.
Ms. Pat Jackson, an area resident, stated the feeling in this town was that if it was a done deal,
why bother to go. She referred to Mr. Hardin's property being condemned.
City Council
April 20, 1999
Page 9
Alderman Austin replied they had gone to Mr. Hardin's property. He could see that Mr. Hardin
was proud of his home by the way he had taken care if it and the layout of the property. He
stated they had considered it more. They had authorized the staff to negotiate for the purchase of
the property. He stated it had not been a done a deal for him.
Mr. Jay Kerri, an area resident, thought this could create a dinosaur in lawsuits. He thought this
could create a lot of problems that were not a problems now.
Alderman Trumbo moved to suspend the rules and move to the third and final reading.
Alderman Santos asked the other council members if they were supporting the ordinance to
support Mayor Hanna or the ordinance.
Alderman Trumbo replied in terms of the respect of the office. Mayor Hanna would do nothing
to damage or deteriorate the office.
Alderman Santos asked Mr. Trumbo if he would still be as supportive of the ordinance if it did
not go into affect until the next mayoral election.
Alderman Trumbo stated they had looked at the proposed ordinance for three years.
Alderman Davis seconded the motion. Upon roll call the motion failed by a vote of 5-3-0,
Santos, Young, and Russell voting nay.
Mr. Rose stated the ordinance would be on the third and final reading at the next meeting.
NEW BUSINESS
STREET NAME CHANGE
A resolution changing the name of Hall Avenue (Highway 112) to Garland to make Garland
Avenue the continuous street name south from I-540 to West Maple Street.
Alderman Austin moved to approve the resolution. Alderman Russell seconded the
motion. Upon roll call the motion carried unanimously.
RESOLUTION 58-99 AS RECORDED IN THE OFFICE OF THE CITY CLERK.
CLIFFS BOULEVARD
An ordinance approving a budget adjustment, cost share and bid waiver in the amount of
City Council
April 20, 1999
Page 10
$300,129 for construction of Cliffs Boulevard Phase 2 and Happy Hollow extension south of
Cliffs Boulevard with the developers of Cliffs PUD.
Alderman Young stated he would be abstaining from the discussion and vote because he worked
for the company doing the engineering.
Mr. Rose read the ordinance for the first time.
Mr. Rose explained they would be approving the cost-share, bid waiver, budget adjustment and
the requirements for competitive bidding and everything he had just read.
Mr. Venable explained when the first phase of the Cliffs had come through, the city had
requested a boulevard be constructed and a cost share had been done in the phases completed.
He explained this was the next phase in the work.
Alderman Davis moved to suspend the rules and go to the second reading. Alderman
Daniel seconded the motion. Upon roll call the motion carried by a vote of 6-0-2, Young
and Trumbo abstaining.
Mr. Rose read the ordinance for the second time.
Alderman Austin moved to suspend the rules and move to the third and final reading.
Alderman Reynolds seconded the motion. Upon roll call the motion carried by a 6-0-2
vote,Trumbo and Young abstaining.
Mr. Rose read the ordinance for the third and final time.
Mr. Jeff Erf, an area resident, asked what the justification was for spending $300,000 for a
project that was a private development. He asked how the citizens would benefit from this.
Mayor Hanna explained the developer agreed originally to construct a two-lane road through
there. The city had requested at the time, that the road be made four lanes with a boulevard in
the middle to connect Cliff Boulevard to Happy Hollow Road to give them another connection
from Hwy. 16 to Hwy 265 to make it easier for children to get to Happy Hollow school. The
additional cost was to cover what the city had requested.
Mr. Venable stated that Mayor Hanna was correct. The Master Street Plan showed the street as a
minor arterial which went on towards the east which finally would hook up to the bypass. He
expressed concern that it would look like a private road because of the entry arches.
Mayor Hanna stated the citizens would be getting a four-lane boulevard which connected Hwy.
City Council
April 20, 1999
Page 11
265 to Happy Hollow Road.
Mr. Erf asked if part of the justification was to alleviate some of the traffic congestion on Hwy.
265. He noted Hwy. 265 was in the process of being widened. He questioned who would be
using the boulevard.
Alderman Russell wondered what the reasoning was for a four-lane road in this location.
Alderman Reynolds stated it was to bring kids to Happy Hollow School.
Alderman Santos asked if this had originated with the Master Street Plan.
Mr. Venable stated that the Master Street Plan showed the street as a minor arterial.
Alderman Santos stated a lot of planning had gone into the Master Street Plan and there had been
a lot of public input.
Mr. Erf felt it was a waste of taxpayer money.
Mr. Dan Coody asked for a point of clarification. He thought Happy Hallow was supposed to be
two-lane street.
Mr. Venable replied Happy Hollow was designated as a collector and part of it was a minor
arterial which went to the east to the bypass. They had cost-shared on the first phase and this
was the second phase. Once this was complete there would be a connection all the way through
to Happy Hollow and Hwy. 16 and Hwy. 265.
Mr. Coody stated the Master Street Plan showed a four-lane going into a two-lane which might
cause problems. He stated he preferred for Happy Hollow to be two lanes because they owned
property there. He noted Happy Hollow was not a wealthy neighborhood and a lot of people
would be losing their entire front yard and porches because of the widening. He added they did
not even have fire protection now. There was no water or sewer in the area. There was no plan
for upgrading the water and sewer when the street improvements were made. The people will be
losing their yards but they would not be gaining any city services. The city wanted developers to
upgrade the city's services.
Mayor Hanna called for the vote. Upon roll call the ordinance passed by a vote of 6-0-2,
Young and Trumbo abstaining.
ORDINANCE 4158 AS RECORDED IN THE OFFICE OF THE CITY CLERK.
City Council
April 20, 1999
Page 12
PLANNING COMMISSION APPEAL
A request for an appeal of a Planning Commission requirement for the Cliff's Phase 2
Preliminary Plat.
Mr. Venable explained this was a request from Mr. Underwood to offset some of the things the
Planning Commission had requested. At the time he was dealing with the State Highway
Department on land acquisition from the Cliffs. The Planning Commission had asked him to
donate a tract of land. The other request was the cost involved in the upgrades along Hwy. 265
in front of the Cliffs. There had been some questions along Hwy. 265. Mr. Venable had
consulted with their attorney, Mr. Jack Butts, on a possible offer. Mr. Venable and Jerry Rose
thought it was a reasonable offer.
Mr. Jack Butts explained when this item had been presented by Cliffs Limited Partnership, the
Planning Commission had approved a subdivision on a condition that a $46,000 off-site
improvement be assessed as a condition of approval. At that time they had pending from the
State of Arkansas an offer of$17,000 to buy the right-of-way. If they could have waited they
could have sold the right-of-way to the state which they needed for the widening. Before the
Planning Commission the issue had come up as to whether they could get some credit for the fact
that the Planning Commission was requiring them to forfeit the land rather than getting $17,000.
The developer was also challenging the method of calculations for the off-site improvement fees.
He asked if the city could charge any fees at all and if so how much they could charge. He had
met with Mr. Rose to try and come up with a fair proposal. The off-site improvement fees of
approximately $47,000 they were willing to pay half of it. They were asking for credit for
$8,500 for half of what the State would have paid them for the right-of-way. He felt they owed
the city $23,000 and the city owed them $8,500. They were willing to pay the city $15,212 for
off-site improvements fees. The city had came back and told them they were to pay for their
sidewalks out of the off-site fees of$3,300 for a total of$18,512 dollars.
Alderman Austin stated he appreciated the developer coming to them with a solution rather than
a problem. He thought this was a reasonable solution.
Alderman Russell asked if it was legal for them to be doing this. He stated he wanted to be fair.
He stated they were opening themselves up for a lot of people to be coming forward. If they
agreed to cut this in half they would have to agree to cut it in half for everyone.
Mr. Rose replied he had looked at the city's off-site improvements very hard after his
conversation with Mr. Butts. He thought their off-site improvement ordinance was very
enforceable. This was a rather unusual situation in which the State of Arkansas was paying
100% of state tax money for the widening of Hwy 265. The argument they were getting into was
that if they were charging the Cliff's Phase 2 development the full amount of$46,000 they would
take that money and give it to the state. They would not get to keep it. Normally when they had
City Council
April 20, 1999
Page 13
an off-site improvement ordinance the city had an out-of-pocket expense that they seek to
recover from the developer. In this situation the causation was not there. The city was not out of
any money for this transaction. It was as if they were acting as.the agent for the State. He felt
that was enough of a distinguishing situation that would allow them to enforce their off-site
improvement ordinance, but would allow compromise in this particular situation. He did not
believe they were setting a precedent. One thing that had cost the city was the sidewalks. And
the city was charging them for the sidewalks, $3,300 and would be collecting that fee.
Mr. Butt added the stipulation was that the developer would pay $15,212 as a compromise as lost
for the condemnation fee as well as a matter for the off-site improvement fee. They would also
pay for the sidewalk, not to exceed an additional $3,300.
Alderman Davis did not like the city taking a right-of-way without giving just compensation.
Mr. Butts stated every developer was obliged to give up right-of-way to the roads they were
building onto as an addition to development. He added it was a fact of life.
Alderman Davis moved to accept the settlement as outlined. Alderman Austin seconded
the motion. Upon roll call the motion carried by a vote of 6-0-2,Trumbo and Young
abstaining.
DISCUSSION OF ODOR-EMITTING BUSINESSES
A discussion of the permitting process for odor emitting business in Fayetteville, i.e. Bakery
Feeds and Hanna's Potpourri.
Mayor Hanna stated this would be a report on the city's permitting process and not a discussion.
The city attorney had advised them they did not want to discuss a specific instance they had
voted on because of the lawsuit. They would be limiting questions.
Ms. Little stated she had been asked to discuss facilities emitting odors and facilities handling
explosives. She presented a handout. She defined a conditional use, a use permitted in certain
zoning districts subject to certain conditions imposed by the Planning Commission after review
of a development plat. She thought it was important for them to notice the words that were used
in the definition. The general purpose behind a conditional use was to permit those uses. They
were not a use by right, certain businesses were not allowed to go in without review by the
Planning Commission. The Planning Commission was to assign enough conditions on those
uses that they would be compatible with the area they were attached to. Conditional uses were
not uses by right. They could not be placed in districts unless the Planning Commission decided
they could be. Th Planning Commission did not have the authority to decide what they were
going to hear. They could only hear those items that were in the chart of use permitted upon
appeal to the Planning Commission. The Planning Commission could grant the conditional use
City Council
April 20, 1999
Page 14
with conditions and safe guards which were appropriate under the chapter. They could assign
whatever conditions they thought were necessary under the chapter to make the use compatible.
The Planning Commission must decide the use was going to have general compatibility with
adjacent properties and other property in the district.
Ms. Little defined a facility emitting odors; the definition gave them the authority to look at
things that had the potential for emitting an odor. The odors that were referenced in the
ordinance suggested that the Planning Commission would be reasonably satisfied that the
permitted use would not generate generally offensive or noxious odor or create an unreasonable
hazard to the public.
The odor ordinance was not like the noise ordinance. The Planning Commission had to be
reasonably assured that the odors would not be noxious or create an unreasonable hazard to the
public. There had to be a public hearing and the building had to inspected by the fire marshall
and building inspector to ensure compliance with state code. The building had to pass inspection
before the use was permitted, and they were subject to the large scale development process.
Ms. Little read the definition for non-conforming uses. Non-conforming uses could continue,
however, they were not to encourage their survival. It was the intent that non-conforming uses
shall not be enlarged upon, expanded or extended. If it was there it could stay there. It could be
maintained but it could not be enlarged.
In response to questions from Alderman Trumbo, Ms. Little replied a facility emitting odors had
to be considered for the potential for emitting odor. If they thought there was a potential for a
plant to emit an odor then they would place that development into this process. What the
Planning Commission had to do was to add enough conditions onto permitting that facility that
the use would not be generally offensive or generate noxious odor or create a hazard to the
public. The staff did not make that decision, the Planning Commission would.
Alderman Russell clarified it was the planning director's responsibility to categorize each
applicant into a use unit. And it they fit into the use unit then it was their responsibility to send
them to the Planning Commission.
Ms. Little added when an applicant came in they consulted with staff. It was very important that
they had accurate information on what would be going on there and what equipment would be
used in the process.
Alderman Russell asked what the city would do if someone was not forthright with the
information provided. What was the next step if they started emitting odors.
Ms. Little replied only that all projects would have two public hearings with the exception of the
projects that were less than an acre. What they expected to happen was that all the information
City Council
April 20, 1999
Page 15
that was necessary surfaces at the hearings. They required representatives to come to all the
meetings. The public was invited to come to the Subdivision and the Planning Commission
meetings.
Mr. Rose stated the legal remedy was what they had approved earlier that the city would seek to
enjoin them from operating in what would be an illegal zone. Then they would have to go back
through the permitting process. The other way was to seek ways to improve the ordinance. The
State of Arkansas defined odor as an "air contaminant or air pollution." Arkansas statutes state
that it was the intent to occupy by preemption the field of control and abatement of air pollution
and contamination. No political subdivision of the state shall enact or enforce laws or ordinances
in this field. The State of Arkansas has preempted a lot of this coverage. They had discussed
this during the Ordinance Review Committee. He thought this ordinance had come up at the
time they were discussing the noise ordinance. He did not believe they could go a great deal
further than what they had already gone.
Alderman Russell stated the DEQ had determined that if a business did not need a DEQ permit,
it did not preclude the city from requiring them to go through the conditional use process as an
odor-emitting business.
In response to questions from Alderman Young, Mr. Rose stated the city could require them to
go through our conditional use process and the city could seek to enforce the conditional use.
But in terms of odor abatement they could only enforce those regulations the state had given
them.
Alderman Reynolds stated their discussion was going into a different area. Industrial Park was
what it said, I-2. He stated he lived right across the street from the Industrial Park. He stated he
had never smelled Hanna's Potpourri. He thought they would run every one off from the
Industrial Park because they had smells. He stated he would rather have the smell rather than the
noise he currently has.
Ms. Little explained the whole purpose of the conditional use was that the Planning Commission
needed to be reasonably satisfied that the permitted use would not generate general or noxious
odors.
In response to questions regarding Hanna's Potpourri, Ms. Little stated they had constructed
warehouses after this ordinance had been passed. The construction of a storage facility had
nothing to do with the manufacturing process. As far as she knew they had not expanded their
manufacturing process. They had constructed additional buildings.
Alderman Austin stated he jogged all over the town. He looked forward to the different smells
within the city. He smelled the bakery, coffee shop, flower gardens, dogs. Blind people
City Council
April 20, 1999
Page 16
experienced Fayetteville by their smells. It was not a bad thing.
Alderman Daniel stated odors were part of their experiences.
Mayor Hanna thanked Ms. Little for the report.
WATER AND SEWER PLANT
A recommendation from the Water and Sewer Committee to exercise their option to purchase the
land on the west side of town for a sewer treatment plant.
Mayor Hanna added they had a resolution concerning the odor.
Mr. Rose stated they had two resolutions prepared. One was to exercise the options on
purchasing the property. The other was to establish odor abatement and control as a priority in
the design.
Alderman Young asked where it was on the agenda.
Alderman Trumbo stated he had been under the impression that after the Water and Sewer
Committee had met that it would be on the agenda.
Alderman Young stated it was not on the agenda that was published in the paper.
The topic was taken off the agenda and placed on the next agenda.
1999 WATER AND SEWER REFUNDING BONDS
An ordinance that provides for the issuance of Water and Sewer System Refunding Revenue
Bonds, Series 1999 in the amount of$8,370,000. All costs associated with the issuance of the
bonds will be paid from bond proceeds. The refunding bonds result in an approximate savings of
$600,000 to the city.
Mr. Rose read the ordinance for the first time.
Mr. Trumbo moved to suspend the rules and go the second reading. Alderman Austin
seconded the motion. Upon roll call the motion carried 7-0-0. Alderman Daniel was absent
for the vote (she left early to catch a flight).
Alderman Austin moved to suspend the rules and move to the third and final reading.
Alderman Trumbo seconded the motion. Upon roll call the motion carried 7-0-0, Daniel
absent for vote.
4
City Council
April 20, 1999
Page 17
ORDINANCE 4159 AS RECORDED IN THE OFFICE OF THE CITY CLERK
Alderman Trumbo moved to invoke the emergency clause so that the ordinance would be
effective immediately rather than waiting the customary 30 days. Alderman Austin
seconded the motion. Upon roll call the motion carried by a vote of 7-0-0.
Meeting adjourned at 10:00 p.m.
FINAL AGENDA
FAYETTEVILLE CITY COUNCIL
MAY 4, 1999
A meeting of the Fayetteville City Council will be held on Ma-y-4, 1999 at 6:30 p.m. in Room
219 of the City Administration Building, 113 West Mountain Street, Fayetteville, Arkansas.
The following items will be considered:
• Nominating Committee Report: George Cowen for Tree& Landscape
A. CONSENT AGENDA
1. APPROVAL OF THE MINUTES: Approval of the minutes from the April 20,
1999 City Council Meeting.
2. DRAKE FIELD DELI/GIFT SHOP: Request approval of a modification to a
lease with Air Host, Inc. This modification provides for the cancellation of their
lease to operate the Deli and Gift Shop in the Drake Field terminal building. Air
Host has requested the cancellation as their customer volume has decreased with
the relocation of four of the five airlines to another airport.
3. BID 99-43: Accepting Ron Blackwell Ford as the lowest qualified bidder meeting
specifications for the purchase of 4-wheel drive utility vehicles, Bid 99-43. These
units will be utilized by the Fire Department and the Police Department.
4. BID 99-46: Approval of bid award 99-46 for the Walker Park pavilion project to
Heckathorn Construction in the amount of$64,618, plus a project contingency of
$3,500 for a total of$68,118.
5. HIGHWAY 16 WEST WIDENING: Approval of a construction contract for
Highway 16 W. widening, water and sewer relocation project. Information on
contractor, cost and project contingency to be provided May 3.
6. ASSEMBLY ROAD STORM DRAINAGE: A resolution approving a contract
for Assembly Road Storm Drainage Improvements with Jerry D. Sweetser, Inc.
In the amount of$58,575.00 plus a contingency of 20.0% ($11,715.) Totaling
$70,290.00
City Council
May 4, 1999
Page 2
7. SUNBRIDGE DRIVE EXTENSION: A resolution approving a contract for
Sunbridge Drive Extension with Red Deer Inc. in the amount of$268,174.75 plus
a contingency of 1 1.1% ($29,825.25) totaling $298,000. Approval of a budget
adjustment adding funds to the project and a project contingency of$19,461 is
also requested.
8. RESEARCH & TECHNOLOGY PARK: A resolution approving a contract for
Research and Technology Park for tree and shrub removal with erosion control
with Tomlinson Asphalt Co. Inc., in the amount of$31,306.00 plus a contingency
of 19.8% (6,194.00) totaling $37,500.00.
B. OLD BUSINESS
1. CHIEF EXECUTIVE OFFICER: REMOVED FROM THE AGENDA AT
THE REQUEST OF THE MAYOR. An ordinance amending Chapter 10,
General Provisions, of the Code of Fayetteville, to add Section 10.13, Chief
Executive Officer, to define miscellaneous powers and duties of the mayor. item
was left on the second reading at the April 20, 1999 meeting.
2. ODOR CONTROL OF SEWAGE TREATMENT PLANT: A resolution
establishing odor abatement and control as a priority in the design and operation
of the City's sewage facilities.
3. WATER& SEWER TREATMENT PLANT: A resolution to exercise the
City's purchase options on three tracts of land on the west side of Fayetteville for
the construction of a new sewage treatment facility. Land tracts to be considered
are currently owned by James McClelland, H. M. and Norma Shipp, and the
Broyles Farm.
C. NEW BUSINESS
1. VA 99-4: An ordinance approving VA 99-4 vacating an alley located at 903
South Government Street as requested by the Regional National Cemetery
Improvement Corporation lying contiguous to the east side of Lot 10 and to the
west side of Lot 11 of the Dowell Addition.
2. VA 99-5: An ordinance approving VA 99-5 vacating an alley located at 898 Hill
Street as requested by the Regional National Cemetery Improvement Corporation
for that portion of a 20 foot alley lying contiguous to the west side of a part of lot
9 and all of Lots 10, 13, and 14 in the Dowell Addition.
• 'tip '. ,
City Council
May 4, 1999
Page 3
3. CARDINAL CAB: A resolution authorizing a Certificate of Public Convenience
and Necessity be issued to Cardinal Cab Co. of Springdale Arkansas for operating
a transportation service within the City of Fayetteville.
4. WASTEWATER TREATMENT PLANT DATA REVIEW: A resolution
authorizing a review of data related to the Paul R. Noland Wastewater Treatment
Facility by an independent engineer to determine flow processing capabilities,
r
MINUTES OF A MEETING
OF THE
FAYETTEVILLE CITY COUNCIL
APRIL 20, 1999
A meeting of the Fayetteville City Council was held on April 20, 1999 at 6:30 p.m. in Room 219
of the City Administration Building located at 113 West Mountain Street, Fayetteville, Arkansas.
PRESENT: Mayor Hanna, Aldermen Bob Reynolds, Ron Austin, Bob Davis, Trent Trumbo,
Heather Daniel, Kevin Santos, Cyrus Young, and Kyle Russell, Planning Secretary Janet Johns
(for City Clerk Heather Woodruff), City Attorney Jerry Rose, Staff, Press and Audience.
ABSENT: City Clerk Heather Woodruff.
The follow items were considered:
ITEM ACTION TAKEN
Approval of the Minutes Approved
Arkansas Avenue Res. 55-99
Bid 99-47: Paul R. Noland Wastewater Treatment Plant Res. 56-99
Insurance Policy Renewals Res. 57-99
Historic District Commission Removed
Land Possession- Rupple Road Ord. 4157
Chief Executive Officer Left on 2°d reading
Street Name Change: Hall Avenue to Garland Avenue Res. 58-99
Cliffs Boulevard Ord. 4158
Planning Commission Appeal: Cliffs Boulevard Phase 2 Motion
Discussion of Odor Emitting Businesses No Action
1999 Water& Sewer Refunding Bonds Ord. 4159
TENTATIVE AGENDA
FAYETTEVILLE CITY COUNCIL
MAY 4, 1999
A. CONSENT AGENDA
1. APPROVAL OF THE MINUTES: Approval of the minutes from the April 20,
1999 City Council Meeting.
2. DRAKE FIELD DELUGIFT SHOP: Request approval of a modification to a
lease with Air Host, Inc. This modification provides for the cancellation of their
lease to operate the Deli and Gift Shop in the Drake Field terminal building. Air
Host has requested the cancellation as their customer volume has decreased with
the relocation of four of the five airlines to another airport.
3. BID 99-43: Acceptance of the lowest qualified bidder meeting specifications for
the purchase of 4-wheel drive utility vehicles, Bid 99-43, Item #1. The vendor for
this purchase will be Ron Blackwell Ford, P.O. Box 547, Bentonville, AR 72712
(Vendor 88230). These units will be utilized by the Fire Department and the
Police Department,
4. BID 99-46: Approval of bid award 99-46 for the Walker Park pavilion project.
Bid award is on Monday, April 19, at 11:30 a.m.
5. HIGHWAY 16 WEST WIDENING: Approval of the construction contract with
(info to be provided) for Highway 16 W. widening, water and sewer relocation
project in the amount of$(info to be provided), and a project contingency amount
of$(info to be provided).
6. ASSEMBLY ROAD STORM DRAINAGE: A resolution approving a contract
for Assembly Road Storm Drainage Improvements with Jerry D. Sweetser, Inc.
In the amount of$58,575.00 plus a contingency of 20.0% ($11,715.) Totaling
$70,290.00
7. SUNBRIDGE DRIVE EXTENSION: A resolution approving a contract for
Sunbridge Drive Extension with Red Deer Inc. in the amount of$268,174.75 plus
a contingency of 11.1% ($29,825.25) totaling $298,000. Approval of a budget
adjustment adding funds to the project and a project contingency of$19,461 is
also requested.
8. RESEARCH & TECHNOLOGY PARK: A resolution approving a contract for
Research and Technology Park for tree and shrub removal with erosion control
with Tomlinson Asphalt Co. Inc., in the amount of$31,306.00 plus a contingency
of 19.8% (6,194.00) totaling $37,500.00.
B. OLD BUSINESS
1. CHIEF EXECUTIVE OFFICER: An ordinance amending Chapter 10, General
Provisions, of the Code of Fayetteville, to add Section 10.13, Chief Executive
Officer, to define miscellaneous powers and duties of the mayor. Item was left on
the second reading at the April 20, 1999 meeting.
2. WATER& SEWER TREATMENT PLANT: A resolution to exercise the
City's purchase options on three tracts of land on the west side of Fayetteville for
the construction of a new sewage treatment facility. Land tracts to be considered
are currently owned by James McClelland, H. M. and Norma Shipp, and the
Broyles Farm,
3. ODOR CONTROL OF SEWAGE TREATMENT PLANT: A resolution
establishing odor abatement and control as a priority in the design and operation
of the City's sewage facilities.
C. NEW BUSINESS
1. VA 99-4: An ordinance approving VA 99-4 vacating a utility easement located at
903 South Government Street as requested by the Regional National Cemetery
Improvement Corporation lying in Lot 10 and 11 of the Dowell Addition.
2. VA 99-5: An ordinance approving VA 99-5 vacating a utility easement located at
898 Hill Street as requested by the Regional National Cemetery Improvement
Corporation for that portion of a 20 foot alley lying contiguous to the west side of
a part of lot 9 and all of lots 10, 13, and 14 in Dowells Addition.
GIFT SHOP
A.2.1
STAFF REVIEW FORM
X AGENDA REQUEST
X CONTRACT REVIEW
GRANT REVIEW
For the Fayetteville City Council meeting of May 4, 1999
FROM: _-
Dale Frederick Ai ort General Gvmt.
Namc Division Department
ACTION REQUIRED: Request approval of a Modification to a Lease with Air Host, Inc. This modification provides
for the cancellation of their lease to operate the Deli and Gift Shop in the Drake Field terminal building. Air Host has
requested the cancellation as their customer volume has decreased with the relocation of four of the five airlines to another
airport.
COST TO CITY: --
$ NIA $ NIA NIA
Cost of this Request Category/Project Budget Category/Project Name
5550 0955 4458 00 $ NIA NIA
Account Number Funds used to date Program Name
NIA $ NIA Ai ort
Project Number Remaining Balance Fund
BUD ET EVIEW: Budgeted Item Budget Adjustment
to d
w
Budget oordinator Administrative Services Director
{CONTRACT/GRANTILEASE REVIEW: GRANTING AGENCY:
.l --
Acc ntin Ma er Date C ordinato Da �-
u0mey Date
Irnal Auditor Date
Purchasing Officer Date
STAFF RECOMMENDATION: Staff recommends approval of the Lease Agreement.
--_-_-
Division Head Date Cross Reference
1 artn t it cto to New Item: Yes CNo)
Prev. Ord/Res#: Res. #126-93
Adpi[ istr v ervices Director e Orig Cont. Date: Dec. 7, 1993
71t or 6ate