HomeMy WebLinkAbout1994-10-13 - Minutes•
•
•
MINUTES OF A SUBDIVISION COMMITTEE MEETING
A meeting of the Fayetteville Subdivision Committee was held on Thursday,
October 13, 1994 at 10:30 a.m., in Room 326 of the City Administration
Building, 113 West Mountain Street, Fayetteville, Arkansas.
MEMBERS PRESENT: Kenneth Pummill, Chuck Mickley and Tom Suchecki
OTHERS PRESENT:
Alett Little, Tim Conklin, Don Bunn, Jerry Kelso,
Mel Milholland, Bill Rudasill, Laleh Amirmoez,
Neal Albright, Al Harris, Dave Jorgensen, and
others
PRELIMINARY PLAT - KANTZ PLACE
E. J. BALL - N OF HWY 45, W OF HWY 265
The next item was a preliminary plat for Kantz Place submitted by Crafton, Tull
& Associates, Inc. on behalf of E. J. Ball for property located north of Highway
45, west of Highway 265. The property is zoned C-2, Thoroughfare Commercial, and
contains 15.22 acres with 7 proposed lots.
Mr. Conklin stated the utility company representatives had asked for a 20 -foot
utility easement along the north side of the property. He requested the setback
be shown as a building setback and utility easement.
Mr. Jerry Kelso, Crafton, Tull & Associates, agreed and advised he would place
the setbacks in his legend rather than drawn on the plat.
MOTION
Mr. Suchecki moved to forward the plat to the Planning Commission.
Mr. Pummill seconded the motion.
• Subdivision Committee
October 13, 1994
Page 2
•
•
FINAL PLAT - OWL CREEK
MIKE PENNINGTON - E OF DOUBLE SPRINGS, S OF HWY 16
The first item was a final plat for Owl Creek Subdivision submitted by Mel
Milholland on behalf of Mike Pennington for property located east of Double
Springs Road, south of Highway 16. The property is zoned R-1, Low Density
Residential, and contains 10.22 acres with 33 proposed lots.
In response to a question from Mr. Conklin, Mr. Milholland stated cable would be
installed at the time of development.
MOTION
Mr. Suchecki moved to forward the plat to the Planning Commission.
Mr. Pummill seconded the motion.
• Subdivision Committee
October 13, 1994
Page 3
•
•
PRELIMINARY PLAT - CRYSTAL SPRINGS, PHASE II
JED DEVELOPMENT - E OF SALEM, N OF MT. COMFORT
The next item was a preliminary plat for Crystal Springs, Phase II, submitted by
Mel Milholland on behalf of JED Development for property located east of Salem
Road, north of Mt. Comfort. The property is zoned R-1, Low Density Residential,
and contains 35.32 acres with 104 proposed lots.
Mr. Milholland advised there was a problem with the sidewalk crossing the berm.
He explained the ponds would be in the way of the sidewalk but the developer
preferred to move the ponds down into the flood plain area, leaving more space
for the sidewalk.
Me. Little stated that would be fine. She further stated staff had decided the
ponds would need to be maintained by the City.
Mr. Milholland agreed.
Mr. Bunn advised they would need an easement or deed for access to the ponds.
He further noted they would need a fence. He stated they would work out the
details on the location of the fence.
Ms. Little reminded Mr. Milholland there had been discussion at the plat review
meeting regarding the flood plain land. She asked if a decision had been made.
Mr. Milholland stated the developer was discussing the matter with the Parks
Department but an agreement had not been reached.
Ms. Little stated that, if the property were to be park land, they might consider
access for the residents of Crystal Springs.
Mr. Milholland stated the developer had suggested the city provide a walkway.
Ms. Little stated that, since they did not know the outcome of the land, they
could not make any plans for it.
Mr. Bunn suggested access between lots 164 and 165; between 171 and 172; and
between 179 and 180. He further stated he had received a number of calls
regarding a tie -through from the subject subdivision over to Dean Solomon Road.
He pointed out the golf course went to the northeast corner of the subdivision.
He advised they had provided an access to the north at that point which would
provide for a tie -through. He stated staff was not asking that the road go
straight through the golf course.
MOTION
Mr. Sickle moved to forward the plat to the Planning Commission.
Mr. Suchecki seconded the motion.
• Subdivision Committee
October 13, 1994
Page 4
•
•
FINAL PLAT - THE MASTERS
DEE & DALLAS WRIGHT AND ELDON & DRYDEN PENCE- S OF COUNTRY CLUB, E OF S. COLLEGE
The next item was a final plat for The Masters submitted by Bill Rudasill on
behalf of Dee and Dallas Wright and Eldon and Dryden Pence for property located
south of Country Club Drive, east of South College. The property is zoned R-1,
Low Density Residential, and contains 20 acres with 15 proposed lots.
In response to a question from Mr. Conklin, Mr. Rudasill assured him he had
worked out the drainage easements with Randy Allen, Street Department.
Mr. Conklin advised the Subdivision Committee the developer was asking the
sidewalks be placed one foot behind the curb rather than four feet due to the
terrain.
Mr. Rudasill advised they would be installing the cable at time of development.
MOTION
Mr. Suchecki moved to forward the plat to the Planning Commission.
Mr. Nickle seconded the motion.
•
•
•
•
Subdivision Committee
October 13, 1994
Page 5
LARGE SCALE DEVELOPMENT - CHEROKEE VILLAGE SHOPPING CENTER
KEITH CHARLEY - SOUTHEAST CORNER OF HWY 45 AND HWY 265
The next item was a large scale development for Cherokee Village Shopping Center
presented by Laleh Amirmoez, Hailey & Associates, on behalf of Keith Cearley, for
property located at the southeast corner of Highway 45 and Highway 265. The
property is zoned C-2, Thoroughfare Commercial, and contains 14.74 acres.
Mr. Nickle asked about the adjacent zoning.
Mr. Bunn advised there was R -O and R-2 property adjacent to the subject tract.
In response to a question from Mr. Nickle, Mr. Bunn stated staff had been on-site
but had not reviewed the property for sight distances. He went on to say he
believed the sight distances would be adequate at all shown entrances/ exits.
He stated drainage from the southern area of the tract drained across Highway 265
to the west and then went into another drainage ditch which went north, crossing
Highway 265 again. He further stated that, from the northern portion of the
site, drainage crossed under Highway 45 and went to the north. He explained the
preliminary drainage plan submitted on this project indicated all three drainage
structures under the highways were nearing capacity. He further advised he
believed their figures were conservative. He noted he would receive a more
detailed drainage report covering routing the flows. He explained that, after
reviewing the more detailed report, a decision would be made regarding detention
on site might be required. He stated there were two areas which would work for
detention: one at the southwest corner and the other was near the northeast
corner. He advised that, if detention on site was required, the developer would
be asked to reduce the quantity of flows to pre -development levels.
Mr. Bunn also pointed out there was some mini -storage units on the bank of the
stream. He explained those units were to be above the 100 -Year level but he did
not know if they were or not. He further stated that, since they were in
existence, they did have to be protected from additional flows generated by the
subject site. He further noted the Highway Department would also have to be
involved. He explained the detailed report would need to be submitted prior to
any work being done on the site.
Mr. George Faucette asked why the current developer would be responsible for
protecting the mini -storage units if they were not constructed above the 100 Year
Flood Plain.
Ms. Little reminded the Subcommittee the flood plain had not been shown on the
FEMA map and they had a difficult time in determining the exact location.
Mr. Bunn advised the engineer for the mini -storage units had done an in-depth
study and certified as to the location of the buildings. He further stated that,
since the buildings were existing, he believed those buildings had to be
protected.
There was discussion as to alternative drainage paths.
Ms. Little stated staff had been contacted by Mr. Purtle, an adjoining property
owner, regarding access. She asked if one area on the plat was access from the
west into the shopping center or if it was planned for the internal roadway.
Ms. Amirmoez advised part of the entry into Mr. Purtle's property was on Mr.
Cearley's property. She explained they were proposing to widen that entry to
reduce the impact of vehicles coming into the drive. She further stated they
• Subdivision Committee
October 13, 1994
Page 6
were also proposing a stack space next to the highway so vehicles had room to
pull off before turning.
Mr. Bunn suggested Ms. Amirmoez contact Mr. Purtle and see if a solution could
be worked out.
Me. Little explained Mr. Purtle was concerned vehicles would cut across his
property to avoid the stop light.
Mr. Faucette pointed out it was doubtful people would use that property to cut
across since there was a main entrance onto Highway 45.
Ms. Little asked if the southernmost entrance was intended as ingress/egress.
Ms. Amirmoez stated it was intended as a one-way service road.
Mr. Nickle asked the square footage of the proposed buildings.
Ms. Amirmoez advised the buildings would be 132,000 square feet. She further
noted they were showing 657 parking spaces (656 spaces required). She stated
they were attempting to provide landscaping to break up the large parking lot
but, if she added any more landscaping, she would lose parking spaces. She asked
if she could get a waiver from the required number of parking spaces.
All of the Subcommittee members stated they believed that would be possible since
they would prefer the landscaping.
• Ms. Amirmoez pointed out the existing trees and the proposed trees on the plat.
•
In response to a question from Mr. Nickle, Ms. Amirmoez stated they had not
completed a lighting plan. She advised they did plan to landscape the hillside
and place a sign at that location.
Ms. Little asked that Ms. Amirmoez review signage with the Inspection Department.
Ms. Amirmoez also advised she had contacted Cheryl Zotti, Solid Waste Department,
and they were working on dumpster sites. She further advised she had contacted
the Highway Department regarding the access points to the development.
Ms. Little advised they would also need to have all drainage plans approved by
the Highway Department.
An adjoining property owner stated he was happy to learn the City would be
reviewing drainage plans. He advised there was an existing drainage problem.
He also requested the developer not do major excavations from the hillside for
aesthetic reasons. He further expressed the hope there would be good control on
litter after the development was completed.
In response to a question from Mr. Conklin, Mr. Faucette stated John and Frances
Stokes owned the property immediately to the east. He advised he believed their
lot depth was 250 feet. He stated they were discussing a joint access but
nothing had been decided.
MOTION
Mr. Nickle moved to forward the plat to the Planning Commission.
Mr. Suchecki seconded the motion.
• Subdivision Committee
October 13, 1994
Page 7
•
•
LARGE SCALE DEVELOPMENT - RIDOUT LUMBER
RIDOUT CONTRACTOR OUTLET - W OF GREGG, N OF POPLAR
The next item was a large scale development for Ridout Lumber presented by Neal
Albright on behalf of Ridout Contractor Outlet for property located wet of Gregg,
north of Poplar. The property is zoned I-1, Heavy Commercial - Light Industrial,
and contains 4.68 acres.
Ms. Little advised staff had worked with the developers of the subject project
in terms of connection to Old Gregg Road (also called Shady Street from the
south). She explained staff had originally thought there should be a connection
but found access to the south was blocked. She pointed out the existing access
easement to the south and advised staff was asking for a 25 -foot access easement
from the subject tract with a 25 -foot building setback. She stated there were
no plans to extend the street at this time and pointed out exiting trees which
would act as a screen.
She further stated the developer had asked specifically for clearing of the
railroad right-of-way on the west side. She stated staff had recommended as many
trees as possible be left. She explained the building would be 10 feet high and
the railroad sat up 6 to 8 feet. She further noted the second building (a
warehouse) would be 24 feet in height with the signage on the side of the
building.
Ms. Little also noted they planned on fencing the site and staff hoped to
minimize the amount of fencing along the railroad right-of-way. She suggested
using the backs of the buildings for the security. She advised that issue had
not been fully decided.
She stated the developer had also requested clearing the railroad right-of-way
on the east side. She advised staff had not given permission for that clearing
at this time because there would not be a visibility problem. She further noted
the developer had requested a parking waiver since this would be a contractor
sales outlet. She stated staff did support the parking waiver.
In response to a question from Mr. Nickle, Mr. Albright advised there was a lot
between the subject tract and the county property.
A Ridout representative stated they just wanted to clean up the east side of the
railroad right-of-way but leave the trees. They presented pictures of the area
together with a rendition of the proposed buildings.
Mr. Suchecki stated he believed a compromise could be reached. He suggested
clearing out the thickets and then perhaps it would be easier to see what trees
needed to be saved.
Mr. Bunn stated the drainage went to the west, under the railroad and then
generally flowing to the northwest portion of the property. He stated he did not
anticipate any drainage problems.
In response to a question from Ms. Little, the Ridout representative advised the
structure would be metal with a front facade.
MOTION
Mr. Suchecki moved to forward the plat to the Planning Commission.
Mr. Nickle seconded the motion.
•
•
•
•
Subdivision Committee
October 13, 1994
Page 8
LARGE SCALE DEVELOPMENT - STERLING ANDERS
STERLING ANDERS - W OF SHILOH, S OF POINT WEST STREET
The next item was a large scale development for Sterling Anders submitted by
Harry Gray (represented by Al Harris) for property located west of Shiloh, south
of Point West. The property is zoned I-1, Heavy Commercial - Light Industrial,
and contains 1.13 acres.
In response to a question from Ms. Little, Mr. Harris advised the easements were
in place from the subdivision plat.
Mr. Conklin asked if the fire chief had approved the location of the fire
hydrant.
Mr. Harris advise he had.
Mr. Conklin requested
Shiloh Drive be noted
Ms. Little requested a
explained that would
ordinance.
the right-of-way from the centerlines of Point West and
on the plat.
notation be made on the plat that the site was clear. She
then meet the requirements of the tree preservation
MOTION
Mr. Nickle moved to forward the plat to the Planning Commission.
Mr. Suchecki seconded the motion.
• Subdivision Committee
October 13, 1994
Page 9
•
•
FINAL PLAT — PINS VALLEY, PHASE III
BMP DEVELOPMENT - S OF NT. COMFORT, W OF PORTER
The next item was a final plat for Pine Valley, Phase III submitted by Harry Gray
(represented by Al Harris) on behalf of BMP Development for property located
south of Mt. Comfort Road, west of Porter Road. The property is zoned R-2,
Medium Density Residential, and contains 8.7 acres with 26 proposed lots.
Ms. Little stated the preliminary plat of the subject subdivision had just been
approved at the last Planning Commission meeting.
Mr. Bunn explained the developer had submitted a preliminary plat earlier but had
changed the layout so staff had requested the preliminary plat be resubmitted.
Ms. Little advised a barricade would need to be placed at the end of Marigold
Street. She requested a notation be made on the plat that separate grading
permits would be required for lots 41 through 46 since those lots were partially
located within the area designated as the 100 -Year Flood Plain.
MOTION
Mr. Nickle moved to forward the plat to the Planning Commission.
Mr. Suchecki seconded the motion.
•
•
•
Subdivision Committee
October 13, 1994
Page 10
PRELIMINARY PLAT - KEE CORNER SUBDIVISION
LARGE SCALE DEVELOPMENT - REE CORNER PLAZA
KIRK ELSASS - S OF ZION, W OF HWY 265
The next items were a preliminary plat and large scale development for Kee Corner
submitted by Dave Jorgensen on behalf of Kirk Elsass for property located south
of Zion Road, west of Highway 265. The property is zoned C-1, Neighborhood
Commercial, and contains 3.82 acres with 4 proposed lots.
Ms. Little advise the Subcommittee the developer had spent a great deal of time
on the subject plat with reference to curb cuts. She explained originally there
was a curb cut very near the intersection which had now been moved back to line
up with Hillside. She further noted they had moved a curb cut on Zion Road to
line up with the Athletic Club directly across the street. She pointed out that
gave the development a shared access between lots 2 and 3 with a reciprocal
access to lot 4. She went on to Bay Lot 4 was planned to come through separately
as a gas station/convenience store.
Ms. Little further noted Micki Harrington had contacted the planning office
stating she wanted no curb cuts across from Hillside Terrace.
Mr. Jorgensen advised it was not the best intersection but it was the best they
could come up with. He stated the owner wanted some type of access for lots 3
and 4 from Highway 265. He further stated this development would be very similar
to the development at the southeast corner of Township and Gregg.
There was further discussion regarding the access to Highway 265. Ms. Little
suggested contacting the highway department regarding a left -turn lane onto
Hillside Terrace from the north.
MOTION
Mr. Nickle moved to forward the plat to the Planning Commission.
Mr. Suchecki seconded the motion.
The meeting adjourned at 11:45 a.m.