HomeMy WebLinkAbout1983-05-19 Minutes1
O
Q
MINUTES OF A BOARD OF DIRECTORS MEETING
A special meeting of the Board of Directors of the City of
Fayetteville was held at 3:30 p.m., on May 19,, 1983, in Room 107 of
the Continuing Education Building,'Fayetteville, Arkansas.
PRESENT.
Osborne,
Mcwethy,
Mayor Noland, Directors Bumpass, Johnson, Lancaster
and Sharp; City Manager Grimes, Assistant City Manager
and City Clerk Kelly; members of the press and audience.
ABSENT: Director Orton
CALL TO ORDER
Mayor Noland called the meeting to order and asked for a
moment of respectful silence.
PRESENTATIONS/WASTEWATER TREATMENT PLANT
Mayor Noland stated that the purpose of this meeting was to
have presentations on the wastewater management alternatives and
sewage treatment alternatives that the City of Fayetteville may
consider.
Mayor Noland asked Dr. Cliff Thompson, of CH2M Hill to address
the Board regarding their proposals, to be followed by a period
of questions.
Dr. Cliff Thompson Addressed the Board
Dr. Thompson stated that the purpose of this meeting was to
discuss the objectives which his firm would like to see
accomplished. He stated that CH2M Hill began working for the City
of Fayetteville in April, 1983, to amend the 201 Facility Plan of
the City of Fayetteville. In beginning this work, CH2M Hill con-
sidered two alternatives
There have been several delays, one of which was the sewer
moratorium to be imposed on the City of Fayetteville unless cer-
tain things were done. The City has to show cause why the mora-
torium should not be placed into effect. Their total effort to
react to the concerns which were raised as a result of that pro-
posed moratorium were required.
43
43.1
43.2
43.3
43.4
43.5
43.6
43.7
43.8
44
44.1
The second delay was the addition of two possible additional
alternatives that came to light in reacting to the show -cause
hearing for the moratorium, and in reaction to the possibility of
getting some additional funds not thought available originally.
Statements Supporting Need for Progress
44.2 Dr. Thompson stated that if the Step ILI Grant Application
is not in by June, 1984, the City will lose 1984 funding. In
order to get a Step III grant application, the plans and specifi-
cations have to be essentially complete, so only two more months
remain to agree upon a plan, to redo the 201, in addition to the
public hearing process It is, therefore, critical that a desi-
sion be made.
44.3 A second, equally important, reason why a decision should be
made is the underlying reasons behind the proposed sewer ban.
One of those is that the City doesn't have a plan that everyone
feels is supported and would be implemented. CH2M Hill feels
that there is a reasonable chance that after this discussion, the
City will get the support of most of the people that would be
affected by the long-range plan. He felt that this was extremely
important when the City and CH2M Hill goes to the May 27, 1983
meeting to talk about why the proposed sewer ban should be
lifted. The City needs to have a united, single plan, indicating
specifically what it plans to do and the schedule under which
they plan to implement it, as well as the costs to be proposed.
Then the City can turn to the Commission for their support in the
city's efforts to alleviate the wastewater problem in
Fayetteville. He reiterated the fact that this impetus would
help them make decisions. He hoped that during the presentation
the City will reach a point where they can decide what the
wastewater treatment alternative would be, and what the sludge
management alternative might be, in order to complete the 201
Facility Plan amendments.
Plans That Have Been Reviewed
44.4 As part of the 201 Plan the firm looked at the use of the
existing facilities, as they are, to optimize them so that they
could meet environmental needs. They decided this would not
work. The City does have to go to a much higher degree of
treatment than the current plant will provide. So this option
would be out. It was decided that the City could not meet the
twenty year plan through the small systems.
44.5 He stated that the original aspect of Fayetteville and
Springdale joined together would be discussed in some detail.
1
1
Under this plan, Springdale and Fayetteville would go
together and treat their waste to secondary levels, 30 parts of
BOD, 30 parts of solids. Then the combined waste would be
discharged into the Arkansas River Basin. This was looked at and
was kept in the group to be assessed, even though its cost was
considerably higher. If there is some funding available, that
funding would bring this alternative into the same economic
range, in comparison with some of the lesser cost alternatives.
Dr. Thompson stated that treatment and reuse for cooling
10 water, as well as slow rate land application were rejected
because of cost. The only money that would be available for slow
O rate land application would be EPA funds, and the cost was con-
_) sidered excessive,: particularly compared to some of the other
Q alternatives.
White River Total Discharge
This plan would treat all the wastewater to a discharge
limit of 5 ppm BOD, 5ppm Solids, 2 ppm Ammonia, 1 ppm Phosphorus,
and is the least costly of all the alternatives These costs
include sludge costs,all the line work costs, rehabilitation
costs, and it is essentially $22 million capital costs, and $35
million present worth costs. The firm recognizes in doing this
that they cannot meet a dissolved oxygen of 6 in the White River.
We would have to prove that this would have no detrimental
effects to the downstream water.
45
45.1
45.2
45.3
This is the least costly alternative, yet it is questionable 45.4
in regard to environmental considerations.
Two Plant Split Flow
As said in other meetings, this plan is ruled out on the 45.5
basis of cost.
Fayetteville Only Arkansas River
This plan would be where Fayetteville would treat its 45.6
wastewater to a 30-30 effluent and pump this to the Arkansas
River. It would be at a considerably higher cost, but it was
left in as one of the four systems to be evaluated and to be
costed out. They did this for two reasons: one, because there
may be some funding that we are not currently aware of, and two,
the firm wants the Board to know what the cost impacts would be,
so that they can make their decision.
White River Split Flow
Under this alternative, all the wastewater would be treated 45.7
at one plant, and split the effluent -- part going to the
46
46.1 Illinois Basin, via Mud Creek, and part going to the White River.
This plant would be designed to meet discharge limit of
5-5-2-1.
46.2 It will have a slightly higher cost --capital costs of $24
million and operating costs of $1 379 000 per year
Overland Flow Alternative
•
46.3 The revised wintertime permit requires that the system meet
the BOD of 5, and phosphorus of 1 in the wintertime. Dr.
Thompson stated that this is a new limit that has been placed
that overland flow system cannot meet - it is one, however, that
the AWT plant can meet, without a significant cost impact.
46.4 On the basis of wintertime permit limits, the Overland Flow
option had to be ruled out.
46.5 Project Manager, Richard Hirsekorn, addressed the Board to
discuss the four options being considered, which are Regional
Arkansas River (Fayetteville and Springdale), White River Total
Discharge, and White River Split Flow.
Hirsekorn Presentation
46.6 Mr. Hirsekorn stated that the first part of any of the four
alternatives would be getting the wastewater to the plant site.
All four of the alternatives have streamed down to have common
collection system improvements. Both in terms of inflow rehabi-
litation to remove the extraneous stormwater from the system, and
in the lift station interceptor collector improvements. He
stated the four different alternatives are referring to two
variations each of two separate alternatives.
White River
46.7 There are two methods that would meet the discharge limits
of 5 ppm BOD, 5 ppm Solids, 2 ppm Ammonia, and 1 ppm Phosphorus.
46.8 1. Total Discharge - This basically consists of a biologi-
cal phosphorus removal plant, plus filtration, with total
discharge to the White River. In this plan optimum use is made
of the facilities at the existing treatment plant site. The
existing headworks are upgraded and expanded: the existing pri-
mary clarifiers are upgraded; the two new parts to be added are
anerobic and inoxic basins because varying degrees of depletion
of oxygen are essential to the treatment process. This would
create the ability to remove the phosphorus, which makes it dif-
ferent from the existing plant. The existing oxic or aerated
basins would be upgraded and new ones added, as well as upgrading
the existing final clarifiers or settling basins, and adding two
or more to compliment those for future use.
Effluent filtration would be added to bring the solids down
to the required limits. With effluent storage provided, so that
during any possible periods of plant non-compliance, for short,
temporary periods of time, they will have the ability to store
the treated effluent, and then recycle it back into the plant
when it can be handled. The total discharge is to the White
River. The problem with that is that the dissolved oxygen stan-
dard is not met.
White River Split Flow Discharge
Mr. Hirsekorn stated that this process is identical as far
0 as the treatment process itself is concerned. The only dif-
ference is that this would include an effluent pumping station
Q and a force main which should pump a portion of the effluent to
Mud Creek, which flows to Clear Creek, and into the Illinois
Q River. The quality of the effluent is the same. The main dif-
ference is that there is flow split --a portion to the White River
and a portion to the Illinois River. CH2M Hill felt this is the
most viable treatment option to meet the 5-5-2-1 permit limita-
tions that have been mandated by the State.
1
The principal advantage of this plan, from a discharge
standpoint, is that not only does it alleviate the problem of not
being able to meet the 6 ppm DO standard on the White River, but
also the portion of the flow that goes into the Mud Creek area,
there is approximately 150 feet of drop through a good tumbling
creekbed which provides a good, natural means of reaerating the
discharge. It will essentially prevent any deleterious effects
that could be experienced from the discharge of the wastewater
into the other area in question, which is a flat, slow moving
stream.
Arkansas River (Regionalization), Springdale and
Fayetteville Together, Or Fayetteville Alone
With the two cities combined, the Springdale wastewater
treatment plant effluent would have pumped, via pump station and
force main, to a combination point with the Fayetteville
effluent. The pipeline would carry both effluents and go to two
booster pump stations and a storage commune located several
miles away at the top of the hills over which the effluent would
have to travel to get to the Arkansas River. One the way down to
the river, it would pass through two power generating stations
prior to discharge which would recover some of the power that was
used to pump the effluent to that point.
47
47.1
47.2
47.3
47.4
The principal advantage of the Arkansas River alternative is 47.5
that the advanced wastewater treatment level (the stringent
treatment level) that is provided by the plants previously
discussed is not required. It would not have the advanced
nutrient removal that is being proposed for the White River.
48
48.1 Common Elements of the Two Plans
The treatement level that is provided by the two alternatives
that have been discussed involves several more treatment units
which were located in this area. The upgrade of the Fayetteville
plant would be much less extensive, about half the cost to pro-
vide additional capacity in the future at the secondary treatment
levels that are currently being provided. The principal disad-
vantage of this alternative is simply the cost. Approximately 56
miles of large diameter pipeline would be required to reach the
Arkansas River.
48.2 The Fayetteville -only discharge to the Arkansas River
requires basically the same treatment plant improvements. At
secondary treatment levels the same additional elements, pumping
stations, and storage lagoon at the top to even out the peaks
and flows, and to provide a steady flow to the power generating
stations down to the Arkansas River are needed. This would be
approximately 45 miles of pipeline. The principal disadvantage
is the cost associated with the pipeline effort all the way to
the Arkansas River.
Summary of the Four Alternatives
48.3 The two alternatives that deal with the White River
(advanced wastewater treatment plant) are: (1) total discharge
to the White River - this process poses difficulty in meeting
dissolved oxygen standards but is the most cost efficient; (2)
White River split flow discharge - this offers an affordable and
an environmentally acceptable solution.
48.4 Arkansas River discharge alternative (Springdale and
Fayetteville) - this encompasses secondary treatment levels, less
stringent treatment, less work at the current plant, but a much
more expensive pipeline effort.
48.5 Arkansas River discharge alternative (Fayetteville only) -
same as both Fayetteville and Springdale alternative.
Summary of Most Cost Effective Alternatives
48.6 The White River is the most cost effective followed by the
White River split flow. The Arkansas River alternatives are con-
siderably more, anywhere from two to two and one-half times more,
in costs alone. The operational costs vary slightly. When
calculating the present worth cost, the alternatives are still
ranked in the same order.
48.7 Dr. Thompson stated that one point which should be made on
the costs is that all the work will assume the $15 million
federal grant throughout. With that in mind, he felt it was
1
important to remember that with the White River split flow, all
of the costs for the pump stations, about $ 1,100,000.00, would be
100% City money. Therefore, the EPA would not likely participate
in that activity.
Alternatives Dealing with Sludge Management
Dr. Thompson stated that in all the prior presentations, it
had been obvious that sludge has not been looked at in sufficient
detail. The comments that CH2M Hill and others have made are
that the current sludge watering operation is expensive. The
current disposal process is not acceptable from an environmental
standpoint. He felt that there was enough money to be saved in
0 operation to perhaps offset any capital costs.
QThe alternatives that were rejected because of cost included
composting and burning the sludge in reuse incinerator. The
four alternatives that were discussed were all within a cost
range comparable to the city's current operation. Under the
current operations, the sludge is dewatered, stabilized with the
lime, which is useful in the watering process, with very high
chemical, operational and maintenance costs. The current cost
for the maintenance and the operation for sludge dewatering is
$ 470,000 per year plus the capital costs of upgrading for future
use. This makes its present worth cost about $4.8 million.
Sludge Maintenance Alternatives
Lime Stabilization - According to the regulations, there are
two methods to stabilize sludge in order to apply it to land:
(1) Add enough lime to bring the ph to 12.0, and (2) biologically
digest the sludge through aerobic digestion.
There are essentially four alternatives that use these
concepts. First, stabilize the sludge to be able to spray for
treatment on land The problem associated with lime stabiliza-
tion is that the calcium used in the laboratory would present
management problems in terms of the sludge spray tool. Second,
digestion of the sludge, biologically, to take it from an
unstable organic material to a stable organic material. After
digestion, the sludge would be pumped to an application site in
the proximity of the existing plant and would be applied. This
has a present worth cost of about $5.9 million, as opposed to
present worth cost currently of $5 million. Third, use lime to
stabilize the water and allow it to be used for public use. This
method is acceptable and will meet all the guidelines and
requirements, but it requires a lot of land to stabilize the
sludge. The fourth process is the digestion of the sludge to
dewater it and make it available for public use.
49
49.1
49.2
49.3
49.4
49.5
This has the highest present worth cost of all the alter- 49.6
natives. Some people are unwilling to use the sludge The firm
50
50.1 feels, however, that based on their experience in a number of
locations, that this really isn't a problem that would be dif-
ficult to overcome. It would, however, require an educational
program, and a program on the city's part, to make sure that the
sludge is properly applied and managed. CH2M Hill tends to favor
the digestion liquid land application on the City site. There
was general discussion on how this plan would be used on dif-
ferent types of soil.
50.2 CH2M Hill developed a concept to cost out and determine the
cost to aerobically digest the sludge at the plant and pump it
through spray irrigation into the five spray areas. This repre-
sents disposal technique which is essentially land application.
From a cost standpoint, we have assumed that the City would own
it and lease it out to a farmer. Under this system, the value of
the crops produced could offset the maintenance costs and some of
the fuel costs to maintain the site. CH2M Hill favors this
method primarily because the City would have control of the
sludge operation.
50.3 The costs of this method are present worth costs of $5.9
million and current present worth costs of $44.8 million.
To Put All Four Plans Into Perspective
50.4 Assuming that $15 million federal grant money is available,
the relative costs are as follows for the different alternatives:
50.5 White River total discharge would require about $7.7 million
of City money; White River split flow would require about $9.2
million of City money, regional Arkansas River would require
$25.8 million of City money; and Fayetteville only Arkansas River
would require about $38.6 million of City money.
50.6 State funding covers only 25% of plant costs for line work
and EPA states their funding only covers those facilities that
are deemed necessary to protect water quality. CH2M Hill
believes $15 million would be maximum funding. If they assume
that the State would reduce their funds because the line work was
greater than 25% of the treatment work, then it would slightly
affect the city's share for the White River total discharge. All
these assume the same amount of rehabilitation, the same amount
of interceptor work, the same sludge option.
Comparison of Annual Revenue Requirements for 1987 with 1982
50.7 All of these capital costs have been upgraded to current
costs. White River total discharge would require from $3.5 to
$6.6 million in revenue to implement; White River split flow
would require from $3.5 to $7 million in revenue to implement;
Regional Arkansas River would require from $3.5 to $9 7 million
1
1
in revenue to implement; Fayetteville only Arkansas River would
require from $3.5 to $11.9 million in revenue to implement.
CH2M Hill had essentially used Black and Veatch's figures to
compute these revenues.
Dr. Thompson concluded that any one of the four alternatives,
from an environmental or from a technical standpoint, would be
implementable depending on what the City would be willing to pay
for these plans.
ID Mayor Noland stated he felt the total discharge to the White
River could be eliminated because it was too costly.
51
51.4
0Director Lancaster, seconded by Director Bumpass, made a 51.5
motion to eliminate the alternative of total discharge to the
White River. Upon roll call, the motion passed by a vote of 6-0,
Q with Director Orton being absent for this vote.
Mayor Noland submitted a letter prepared by Director Orton in 51.6
which she stated agreement with either of these alternatives.
Mayor Noland felt, that based on her letter, she would have had
some objection to eliminating the total White River discharge at
least at this point. It was her feeling that either of these
alternatives would probably be satisfactory.
1
1
Mayor Noland then opened discussion to Arkansas River alter- 51.7
native and White River split flow.
A speaker from the audience addressed the Board and stated
that he had never heard discussion concerning the White River
split flow.
In explanation, Dr. Thompson stated that the proposed con-
cent was to return the water to the watershed that it was
generated from. The split would be about 55% back to the
Illinois; 45% to the White River. He stated that at an earlier
meeting, discussions were held with the property owners that
would be affected by discharge to Mud Creek. Dr. Thompson felt
that the flooding problem could be handled and that CH2M Hill
expects the permit to dictate how they would manage this flow
split.
Peggy Treber stated that Dr. Thompson had mentioned a possi-
bility of funds that had not earlier been thought available and
asked about these funds.
Dr. Thompson stated that he had no basis to assume that
there were any funds Because of the enormous amount of interest
in the Arkansas River alternative, there had been interest at the
State and Federal level. If such funding could be made available,
51.8
51.9
51.10
51.11
52
52.1 these alternatives would become more practical from an economic
standpoint.
52.2 Scott Van Laningham asked whether CH2M Hill had figured what
would happen to the Arkansas River Regional Plan if Rogers were
included Dr. Thompson stated that this had not been done.
52.3 Wilson Kimbrough stated that the split flow plan to the
Illinois was considered at some previous time. He asked why this
plan was being considered now when it was thought to be
inappropriate earlier. There was general discussion about the
plan and why it was being considered at this time.
52.4 Wilson Kimbrough asked Dr. Thompson to characterize the
impact of the plan on wells in the Clear Creek area.
52.5 Dr. Thompson stated that it has been modeled. He stated
that at a certain point that essentially the characteristics have
been lost. At this point it becomes a resource rather than a
liability, from a pure water standpoint. He added that realisti-
cally the summertime was when it would be expected to have the
worst problems, but he did not anticipate any problems.
52.6 Director Sharp stated that the operation costs would be fan-
tastic if the wastewater is treated to 5-5-2-1 and then pumped to
the Arkansas River.
52.7 Dr. Thompson continued that if
Board, within about 30-45 days they
amendments to the 201 Facility plan
30 days after that a public hearing
this plan was selected by the
would have completed the
, submit it to the state, and
would be held.
52.8 A speaker from the audience stated
his property are used by his cattle and
He fears that it won't be acceptable in
having a plan come out in the paper one day, and the next day,
you read between the lines, and he called the City Manager's
office today and found out that there was a meeting.
that the wells he has on
are acceptable water now.
the future. He resents
52.9 Ron Bumpass asked if the State would test the resident's
water and determine the impact or if there would be an impact
from this plan when the permit from EPA was applied for.
52.10 Dr. Thompson replied that the area would be tested. There
was general discussion regarding this system.
52.11 Bill Martin, Fayetteville, a resident on 45 East, addressed
the Board. Mud Creek enters the city on his property. He
attended the meeting this afternoon and the representative of the
city informed him and the people at that meeting that the water
going into Mud Creek will be of superior quality to the water
that's in Mud Creek. He felt this was conceivably the best
1
1
1
1
•
solution that is available to us If this proposal is accepted,
then he hopes that the City will go to bat for the citizens in
all the steps along the line. If that plant is built and does
not function properly, then he feels the City has a solemn obli-
gation to the citizens to close the plant.
53
53.1
Mayor Noland stated the City would attempt to work in this 53.2
direction.
A member of the audience expressed her concern about wells 53.3
1.11 in the area becoming polluted.
0 In response to her question, Dr. Thompson stated that if 53.4
there is concern the waste will affect anything, it can be
turned off at anytime in a short time period.
Q The question was asked about who invited the landowners to 53.5
the meetings.
Mr. Grimes stated that he met with and contacted as many of
the property owners up and down Mud Creek within the city limits
as he could within the time that he had.
53.6
A comment was made that Mud Creek is currently polluted. 53.7
Mr. Grimes stated the City had a problem with a stretch of
sewer main along Mud Creek, west of Hwy 71. It's a relatively
new main and an electrolosis problem is causing its break. We're
replacing 1500 feet of line. He felt this was where a lot of
that problem was coming from.
As a representative of Mud Creek property owners,
an audience member was wondering about the flooding. He
suggested cleaning out the Mud Creek channel in preparation of
this project.
53.8
53.9
Director Osborne stated he felt that someday a regional plan 53.10
would be developed.
Dr. Thompson stated that CH2M Hill had tried to point out
through this presentation that so many of the elements of the
plans are common to all four plans. A regional plan sometime in
the future would certainly be compatible if there was a reaso-
nable plan. Money has been budgeted to do some channelization of
Mud Creek.
Director Lancaster stated that he was sorry the City had not
heard from Springdale. He would have liked to have received some
feedback on our extension because their permit is coming up right
away.
53.11
53.12
54
54.1 Dr. Mitchell addressed the Board. He felt the decision was
whether or not to go with one plant or two plants for the split
flow plan. He outlined the manner in which the plant would
operate and to what capacity the effluent would be processed.
54.2 The cost to build the plant on the west side is $ 8,600,000
and a similar $750,000 for the plant upgrading on the east side.
The sludge handling facilities on the east side or existing plant
would be sufficient to handle the production without any
upgrading.
54.3 Mayor Noland stated that the Board was simply trying to
determine the best method for all the people at the most advan-
tageous cost.
54.4 Dr. Murray stated that most of the comments go back basi-
cally to operations. It seems the City of Fayetteville can do
one thing. He felt the superintendent of the plant and the City
Engineer should be under the Civil Service Commission. He felt
the responsibility for the fish kills belonged to the operators
of the plant and not always with soup companies.
54.5 A speaker stated that the City has qualified, competent
people working on the plant.
54.6 Director Lancaster, seconded by Director Johnson, made a
motion to approve the Mud Creek design. Upon roll call, the
motion passed unanimously.
Sludge Disposal Option
54.7 Mayor Noland stated that he thought, based on what Dr.
Thompson stated and after reading the report, he would prefer the
digestion land application option which would involve a capital
cost of about $4 million and the acquisition of land to enable us
to implement the land application.
54.8 Director Sharp, seconded by Director Johnson, made a motion
for Dr. Thompson's recommendations to be accepted. Upon roll
call, the motion passed unanimously
ADJOURNMENT
54.9 There being no further discussion, the meeting adjourned.
1
1