HomeMy WebLinkAboutOrdinance 4198 ORDINANCE NO.4198 AN ORDINANCE APPROVING A COST SHARE AGREEMENT, IN AN AMOUNT NOT TO EXCEED $80,477, FOR CONSTRUCTION OF SERENITY WAY AS A 36 FOOT "COLLECTOR" STREET WITHIN THE SERENITY PLACE PUD SUBDIVISION, WITH TIM REYNOLDS/PRESTIGE PROPERTIES DEVELOPMENT AND CONSTRUCTION; APPROVAL OF A BUDGET ADJUSTMENT; AND WAIVING THE REQUIREMENTS OF COMPETITIVE BIDDING BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1. That a cost share agreement is hereby approved, in an amount not to exceed $80,477, for construction of Serenity Way as a 36 foot "Collector" street within the Serenity Place PUD Subdivision, with Tim Reynolds/Prestige Properties Development and Construction. A copy of the cost share agreement is attached hereto as Exhibit "A" and made a part hereof. Sestion2. That a budget adjustment is hereby approved. A copy of the budget adjustment is attached hereto as Exhibit `B" and made a part hereof. Section 3. That the City Council hereby waives the requirements of competitive bidding for the construction of Serenity Way within the Serenity Place PUD Subdivision that the City hereby agrees to cost-share in, for the reason that said requirements are neither practical nor feasible. Tim Reynolds/ Prestige Properties Development and Construction, is the developer of Serenity Place PUD Subdivision, and will be providing all labor, materials, and equipment for construction of the road. PASSED AND APPROVED this 2nd day of November , 1999. APPROVED./ By: reed Hanna, Mayor ATTEST: pFeath,, er Woodruff, City Cie � � rtV . FAYETTEVILLE EXHIBIT A THE CITY OF FAYETTEVILLE, ARKANSAS October 7, 1999 Mr. Tim Reynolds Prestige Properties Development and Construction P.O. Box 1766 Fayetteville, Arkansas 72702 Re: Proposed cost-share for Serenity Way from a "Local" 28 ft. street to a "Collector" 36 ft. street within the Serenity Place PUD Subdivision. Dear Sir, This letter shall serve as the formal agreement to be presented to the City Council for consideration for the City of Fayetteville to participate in a cost share to pay for the difference in actual construction costs only to construct Serenity Way as a collector street in lieu of a local 28 ft. street and in accordance with the Master Street Plan and the conditions of approval from the Planning Commission on May 11 , 1998. As designed by your engineer, ESI, Serenity Way extends approximately 1 ,350 feet west of Salem Road to a proposed intersection with Rupple Road extension as planned by the City. Your engineer, ESI, by facsimile memo dated August 30, 1999 has estimated the costs of Serenity as a local street at $ 143,258.25 and as a collector street at $223,735 .25 . The estimated difference is $80,477.00 The agenda request proposed to forward to the City Council for consideration is based upon the estimated difference of $80,477.00 as furnished by your engineer. If the cost-share is approved by the Mayor and the City Council, the City agrees to pay the actual and verified construction (only) cost difference to construct Serenity way as a collector in lieu of a local street up to a maximum cost of $80,477.00 as estimated by your engineer. If your future and actual bid prices exceed the estimate furnished by your engineer, then the cost- share agreement shall be required to be reevaluated and re-approved by the Mayor and/or City Council as appropriate prior to construction. Page 1 of 2 113WESTMOUNTAIN 72701 501521 -7700 FAX 501 575-8257 If the Mayor and/or City Council do not agree with the requested cost-share then you will only be required to construct Serenity as a local street, yet dedicate the right-of-way for a future collector street. Mr. Tim Reynolds/Prestige Properties and your contractor further agree to construct the public improvements, including the street construction, in compliance with all City Standards and regulations. Mr. Tim Reynolds/Prestige Properties and your engineer, ESI, further agree to provide the necessary and normal design, project management, inspection and testing as necessary for a complete and accepted public street. It is understood that the contract for construction is between Mr. Tim Reynolds/Prestige Properties and your contractor and that the City has no contractual obligation with your contractor. The City's only obligation shall be to participate in a cost share not-to-exceed $80,477.00 based upon actual construction (only) costs (without reevaluation and re-approval by the Mayor and/or City Council). It is further understood that upon final acceptance of the new City street, Mr. Tim Reynolds/Prestige Properties will provide to the City a copy of the invoices, quantities and records from your contractor and/or engineer and also a completed lien waiver executed by your contractor. The City will strive to make payment to Mr. Tim Reynolds/Prestige Properties within thirty (30) days after receipt of the invoices but cannot guarantee the thirty day schedule. Please note: This is a request for approval of a cost share only. The Mayor and/or City Council will not consider the proposed cost share for approval without a formal agreement signed in advance by you. Do not proceed with the proposed street construction unless/until the proposed cost share is approved by the City Council and a copy signed by the Mayor is furnished to you. If you agree with these provisions please sign the three original letters in the space provided and return all three to me. I will proceed to schedule this on the next available City Council Agenda. Should you need any additional information please call me at 575-8208. Thank you, Jim Beavers, P.E. City Engineer Approved City of Fayetteville Tim Reynolds Fred Hanna, Mayor Prestige Properties Development and Construction certified mail Page 2 of 2 STAFF REVIEW FORM X AGENDA REQUEST CONTRACT REVIEW GRANT REVIEW For the Fayetteville City Council meeting of November 2, 1999 FROM: Ron Petrie En ineering Public Works Name Dwisinn Department ACTION REQUIRED: Approval of a budget adjustment, cost share, and bid waiver in the amount of $80,477.00 with the developer of the Serenity Place PUD, Tim Reynolds/Prestige Properties, for the construction cost difference to construct Serenity Way to collector street standards in lieu of a local street. COST TO CITY: $ 80,477.00 (Estimated) $ 230,024.00 Street Im rovements Cost of is Request Categ�ject u g� t et Category roject Name 4470-9470-5809.00 $ 157,024.00 Cost Share Account Number Fun Use To Date Program Name 98033-0020 1 73 000.00 Sales Tax Project Number Remaining Balance Fun BUDGET REVIEW: X Budgeted Item X Budget Adjustment Attached K $inti Manager A mi istratrve Services Director CONTRACT/GRANT/LEASE REVIEW: GRANTING AGE a /3- 1A1 AA Accoun a� er ate na u or ate 7 /% Crfy tto a ate AD oor matoratS e U to - I4 - Purchasing Officer Date STAFF RECOMMENDATION: Approval of action items listed above. to - u - 99 tart on Hea Date Cross Reference New Item: Yes x No ment ' ector Date S. �G Prev Ord/Res #: mimstr a Servi�fes- DDnecttor Date Ong Contract Date: Mayor Date Page 2 STAFF REVIEW FORM Description Serenity Way Cost Share Meeting Date November 2, 1999 Comments: Reference Comments: Budget Coordinator Accounting Manager City Attorney Purchasing Officer ADA Coordinator Internal Auditor FAYETTEVILLE THE CITY OF FAYETTEVILLE, ARKANSAS DEPARTMENTAL CORRESPONDENCE To: Mr. Fred Hanna, Mayor Thru: Charles Venable, PW Director 94 Don Bunn, Asst. PW. Director Jim Beavers, City Engineer 6 From: Ron Petrie, Staff Engineer tsf' Date: October 7, 1999 Re: Agenda Request - City Council Meeting on November 2, 1999 Proposed Budget Adjustment, Bid Waiver, and Cost-Share in the amount of $80,477.00 with the developers of Serenity Place PUD for the construction of Serenity Way. The Preliminary Plat for the Serenity Place PUD was approved by the Planning Commission on May 13, 1998. The approval included constructing Serenity Way as a collector street in conformance with the Master Street Plan. The approval also stated that " ... the construction of Serenity Way as a collector is subject to the City Council approving a cost share agreement with Prestige Properties Development, Inc. If such agreement were to fail, the developer must construct Serenity Way as a 28' residential street." Therefore, the City is requested to pay the difference to construct Serenity Way to collector street standards (36' in width) in lieu of a local street (28' in width). Engineering Services Incorporated have estimated these costs as follows: City $ 805477.00 Developer $ 1439258.25 Total $223,735 .25 Based upon the information provided by the Budget & Research Division, there is a remaining balance of $73,000.00 in the Street Improvements Cost Share Account. A Budget Adjustment of $7,477.00 is attached recommending funding of the cost share. Mr. Fred Hanna, Mayor October 7, 1999 Page Two (2) The final costs to the City will be based upon actual costs as documented by Engineering Services Incorporated subject to review by the City and may, or may not exceed the Engineer's estimate. However, the City's share will not exceed the estimated costs without additional authorization. Enclosures: Budget Adjustment Vicinity Map Construction Drawing Cost Estimate from ESI Cost-Share Agreement with Prestige Properties Purchase Requisition d a OO wzz oar a a a n r a s s t jE { zy zrr PROJECT ® ® LOCATION g �� M'/t WJ�V 1 M 31 aAll, a a Sell 7 CEO n q u a e l—1 VICINITY MAP , FUTURE MINOR ARTERIAL — RUPPLE ROAD " N 1 '34'08" E — 991 . 20' i c oil �Ygo 4w , 1 4 vu • � " Ff • Y ' � �----- - -- -- -WIT- of ; 1. a e e A iii A ', wC fli sn IN �� :. � ::b ,;iy rm _ a fl ilKO fla. O flq Q 6a OKI' Yi ��S `.,A ;i. lit .rr.. _ A ( - a\ ti ,l O 1�•� ' a; - r , per;'" A \ � . -', � 1 it 31 In to It es 4c IN- g• \ j R i y �•i.'d O s i w e m . _ r : , ,/hd. .....F yYa.w �[ ®m„ti C ; �• � •' '� ss.'� i : 'w`a w,a 'r. yaa 7 O No IN It NI I Pis / S \ s>� n r 1 211 At - ° .-- J110 40 . IINx i iiO Ali O ei ® 9i . O �ae SYI:A silly ® % O i.l. Y � , no IN M d• OWN —now O� ' \ /� L7IN p • Fi - 1: 1. Art* � aosocoqr r u,GJ'•T 'r NIM. + .� .._ '4� It W? .= - - ( SAILNflDAD — —r— Oct - 06 - 99' 09 : 46A Engineering Services , Inc 501 - 751 - 8746 P . 02 ENGINEER'S PRELIMINARY STATEMENT OF PROBABLE CONSTRUCTION COSTS SERENITY WAY - SERENITY PLACE SUBDIVISION FAYETTEVILLE, ARKANSAS - REVISED OCTOBER 6, 1999 SERENITY WAYAS A COLLECTOR: Item Unit Total Quantity Description Price Amount 1 2,450 C.Y. Excavation & Grading 5.25 12,862.50 2 2,450 C.Y. Tap Soil Stripping & Stockpiling 3.00 7,350.00 3 5,025 S.Y. Lime Stabilization (10" Depth) 6.50 32,662.50 4 5,025 S.Y. Asphalt (4" Binder) 8.50 422712.50 5 5,025 S.Y. Asphalt (2" Surface) 4.45 22,361 .25 6 6,275 S.Y. Class 7 Base Material (6" Thick) 3.86 24,221 .50 7 2,890 L.F. Curb & Gutter 8.50 24,565.00 8 2,300 L.F. Sidewalk (6') 15.00 34,500.00 9 1 L.S. Bonds 21500.00 2,500.00 TOTAL STREET IMPROVEMENTS $203,735.25 CONSTRUCTION CONTINGENCY $20,000.00 TOTAL AS COLLECTOR $223,735.25 SERENITY WAYAS A LOCAL STREET: Unit Total Item Quantity Description Price Amount 1 2, 100 C.Y. Excavation & Grading 5.25 11 ,025.00 2 1 ,950 C.Y. Top Soil Stripping & Stockpiling 3.00 52850.00 3 3,775 S.Y. Lime Stabilization (10" Depth) 6.50 24,537.50 4 3,775 S.Y. Asphalt (3" Surface) 868 25 21700 5 3,775 S.Y. Class 7 Base Material (8" Thick) 5.15 19,441 .25 6 2,875 L.F. Curb & Ginter 6.50 180687.50 7 2,300 L.F. Sidewalk (4') 10.00 23,000.00 8 1 L.S. Bonds 11500.00 1 ,500.00 TOTAL STREET IMPROVEMENTS $129,258.25 CONSTRUCTION CONTINGENCY $14,000.00 TOTAL AS LOCAL STREET $1439258.25 DIFFERENCE $80,477.00 FAYETTEVILLE THE CITY OF FAYETTEVILLE, ARKANSAS October 7, 1999 Mr. Tim Reynolds Prestige Properties Development and Construction P.O. Box 1766 Fayetteville, Arkansas 72702 Re: Proposed cost-share for Serenity Way from a "Local' 28 ft. street to a "Collector" 36 ft. street within the Serenity Place PUD Subdivision. Dear Sir, This letter shall serve as the formal agreement to be presented to the City Council for consideration for the City of Fayetteville to participate in a cost share to pay for the difference in actual construction costs only to construct Serenity Way as a collector street in lieu of a local 28 ft. street and in accordance with the Master Street Plan and the conditions of approval from the Planning Commission on May 11 , 1998. As designed by your engineer, ESI, Serenity Way extends approximately 1 ,350 feet west of Salem Road to a proposed intersection with Rupple Road extension as planned by the City. Your engineer, ESI, by facsimile memo dated August 30, 1999 has estimated the costs of Serenity as a local street at $ 143,258.25 and as a collector street at $223,735 .25 . The estimated difference is $80,477.00 The agenda request proposed to forward to the City Council for consideration is based upon the estimated difference of $80,477.00 as furnished by your engineer. If the cost-share is approved by the Mayor and the City Council, the City agrees to pay the actual and verified construction (only) cost difference to construct Serenity way as a collector in lieu of a local street up to a maximum cost of $80,477.00 as estimated by your engineer. If your future and actual bid prices exceed the estimate furnished by your engineer, then the cost- share agreement shall be required to be reevaluated and re-approved by the Mayor and/or City Council as appropriate prior to construction. Page 1 of 2 113 WEST MOUNTAIN 72701 501 521 -7700 FAX 501 575-8257 If the Mayor and/or City Council do not agree with the requested cost-share then you will only be required to construct Serenity as a local street, yet dedicate the right-of-way for a future collector street. Mr. Tim Reynolds/Prestige Properties and your contractor further agree to construct the public improvements, including the street construction, in compliance with all City Standards and regulations. Mr. Tim Reynolds/Prestige Properties and your engineer, ESI, further agree to provide the necessary and normal design, project management, inspection and testing as necessary for a complete and accepted public street. It is understood that the contract for construction is between Mr. Tim Reynolds/Prestige Properties and your contractor and that the City has no contractual obligation with your contractor. The City's only obligation shall be to participate in a cost share not-to-exceed $80,477.00 based upon actual construction (only) costs (without reevaluation and re-approval by the Mayor and/or City Council). It is further understood that upon final acceptance of the new City street, Mr. Tim Reynolds/Prestige Properties will provide to the City a copy of the invoices, quantities and records from your contractor and/or engineer and also a completed lien waiver executed by your contractor. The City will strive to make payment to Mr. Tim Reynolds/Prestige Properties within thirty (30) days after receipt of the invoices but cannot guarantee the thirty day schedule. Please note: This is a request for approval of a cost share only. The Mayor and/or City Council will not consider the proposed cost share for approval without a formal agreement signed in advance by you. Do not proceed with the proposed street construction unless/until the proposed cost share is approved by the City Council and a copy signed by the Mayor is famished to you. If you agree with these provisions please sign the three original letters in the space provided and return all three to me. I will proceed to schedule this on the next available City Council Agenda. Should you need any additional information please call me at 575-8208. Thank you, Jim Beavers, P.E. City Engineer Approved City of Fayetteville Tim Reynolds Fred Hanna, Mayor Prestige Properties Development and Construction certified mail Page 2 of 2