HomeMy WebLinkAbout205-26 RESOLUTIONDocusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 205-26
File Number: 2026-2926
A RESOLUTION TO APPROVE CHANGE ORDER NO. 4 TO THE CONTRACT WITH LEGACY
CONSTRUCTION MANAGEMENT IN THE AMOUNT OF $42,738.14 FOR ADDITIONAL SERVICES
RELATED TO CONSTRUCTION AT UNDERWOOD PARK, AND TO APPROVE AN ADDITIONAL
PROJECT CONTINGENCY IN THE AMOUNT OF $63,000.00
WHEREAS, on July 15, 2025, City Council approved Resolution 162-25 that authorized a contract with Legacy
Construction Management for construction at Underwood Park; and
WHEREAS, Change Order No. 4 includes additional fine grading and spreading topsoil in the greenspace, a sanitary
sewer line invert change where it connects to the manhole, additional irrigation lines and boxes with hose bibbs at the
pickleball court area for the plantings south of the courts, charges from Ozarks Electric to connect to electric service,
and the removal of an existing asphalt path.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 4 to the
contract with Legacy construction Management in the amount of $42,738.14 for construction at Underwood Park and
further approves an additional project contingency in the amount of $63,000.00.
PASSED and APPROVED on September 15, 2026
Approved:
Molly Rawn, Mayor
N�����RK T RF���/i
Attest:`QjY
v: FAYETTEVILLE-�=
ro
•q 5��
Kara Paxton, City Clerk TreasuTN
�9s•:4kgNSP;•
111111
Page 1
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
Na) CITY OF
�. FAYETTEVILLE
ARKANSAS
MEETING OF SEPTEMBER 15, 2026
CITY COUNCIL MEMO
2026-2926
TO: Mayor Rawn and City Council
THROUGH: Alison Jumper, Director of Parks, Natural Resources and Cultural Affairs
Ted Jack, Park Planning Superintendent
Jennifer Walker, Chief of Staff
FROM: Melissa Evans, Park Planner
SUBJECT: Underwood Community Park Phase 1 Improvements Change Order # 4
RECOMMENDATION:
Staff recommends approving Change Order # 4 with Legacy Construction Management Inc. for
Underwood Park Phase 1 Construction in the amount of $42,738.14, approving 31 additional days, and
$63,000.00 in additional contingency.
BACKGROUND:
Bid 25-38 for improvements to Underwood Park Phase 1 was approved at City Council July 15, 2025
(2025-1034) in the amount of $3,628,930.66. Construction for Phase 1 includes three pavilions, a
restroom, parking, utilities, a playground, sidewalks, pickleball courts and a basketball court. Change
Order # 1 was for a rock dam addition, B-stone for the restroom and pavilion areas, and geogrid for the
pickleball areas in the amount of $22,231.27. Twenty-eight additional days were added to the schedule
due to delays in starting the project that were beyond the contractor's control. Total contract cost with
Change Order # 1 was $3,651,161.93. Change Order #2 was for drainage and elevation revisions,
additional supervisory time, additional conduit, pavilion lightning protection, concrete bases for donated
sculptures and a backwater valve for the restroom in the amount of $172,552.27. Thirty-three additional
days were added to the schedule for the changes. Total contract cost with Change Order # 2 was
$3,823,714.20. Change Order #3 was for additional playground surfacing and additional handrails for the
tree deck in the amount of $49,795.20. Total contract cost with Change Order # 3 was $3,873,509.40.
DISCUSSION:
Work for Change Order # 4 includes additional fine grading and spreading topsoil in the greenspace, a
sanitary sewer line invert change where it connects to the manhole, additional irrigation lines and boxes
with hose bibbs at the pickleball court area for the plantings south of the courts, charges from Ozarks
Electric to connect to electric service, and the removal of an existing asphalt path where the "American
Dog" statue is located. The work is more clearly defined in the Change Order documents.
BUDGET/STAFF IMPACT:
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
Funding for the change order is below. After Change Order # 4, $63,000.00 will remain in contingency and
the construction contract will increase to $3,916,247.54.
GL ACCOUNT
PROJECT
AMOUNT
2250.520.9256-5806.00
46050.7570
$5,421.26
4805.860.7570-5806.00
46050.7570
$37,316.88
TOTAL
$42,738.14
ATTACHMENTS: 3. Staff Review Form, 4. 2026.08.25_Underwood Park —Change Order 004 EDG APP
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
City of Fayetteville, Arkansas 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
Legislation Text
File #: 2026-2926
A RESOLUTION TO APPROVE CHANGE ORDER NO. 4 TO THE CONTRACT WITH
LEGACY CONSTRUCTION MANAGEMENT IN THE AMOUNT OF $42,738.14 FOR
ADDITIONAL SERVICES RELATED TO CONSTRUCTION AT UNDERWOOD PARK, AND
TO APPROVE AN ADDITIONAL PROJECT CONTINGENCY IN THE AMOUNT OF
$63,000.00
WHEREAS, on July 15, 2025, City Council approved Resolution 162-25 that authorized a contract with
Legacy Construction Management for construction at Underwood Park; and
WHEREAS, Change Order No. 4 includes additional fine grading and spreading topsoil in the
greenspace, a sanitary sewer line invert change where it connects to the manhole, additional irrigation
lines and boxes with hose bibbs at the pickleball court area for the plantings south of the courts, charges
from Ozarks Electric to connect to electric service, and the removal of an existing asphalt path.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 4 to the contract with Legacy construction Management in the amount of $42,738.14 for
construction at Underwood Park and further approves an additional project contingency in the amount of
$63,000.00.
Page 1
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
City of Fayetteville Staff Review Form
2026-2926
Item ID
9/15/2026
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
Melissa Evans 8/25/2026 PARKS & RECREATION (520)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approving Change Order # 4 with Legacy Construction Management Inc. for Underwood Park
Phase 1 Construction in the amount of $42,738.14, approving 31 additional days, and $57,261.86 in additional
contingency.
Budget Impact:
4805.860.7570-5806.00
Parks Projects 2024 Bonds
Account Number Fund
46050.7570 Park Projects (2019/2022/2024 Bonds),
Underwood Improvements
Project Number
Budgeted Item? Yes
Does item have a direct cost? Yes
Is a Budget Adjustment attached? No
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$
9,284,288.00
$
8,124,055.04
$ 1,160,232.96
$
42,738.14
1,117,494.82
V20221130
Purchase Order Number: 2025-00000754 Previous Ordinance or Resolution # Res. 162-25
Change Order Number:
Original Contract Number:
Comments:
#4
2025-1034
Approval Date:
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
AIA
Document G701"- 2017
Change Order
PROJECT: (Name and address} CONTRACT INFORMATION:
CHANGE ORDER INFORMATION:
Underwood Park -Phase 1 Contract For: Construction Bid 25-38
Change Order Number: 004
Dean Solomon Road Date: lfl-27-2025
Date: 08-20-2026
Fayetteville, AR 72704
OWNER: (Name and address] ARCHITECT: (Name and address)
CONTRACTOR: ('frame and address)
City of Fayetteville Ecological Design Group, LLC
Legacy Construction Management. Inc.
113 W. Mountain 216 W. Birch Street
3733 Wildcat Creek Blvd.
Fayetteville, AR 72701 Rogers, AR 72756
Fayetteville, AR 72704
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon
adjustments attributable to executed Construction Change Directives.)
Refer to the attached Change Order #4 Narrative for a detailed description. This Change Order is the second half of the additional
work caused by ASN VASI#2 and adds other work directed by Park. Planning.
The original Contract Sum was
$ 3,628,930.66
The net change by previously authorized Change Orders
$ 244,579.74
The Contract Sum prior to this Change Order was
$ 3,873,509.40
The Contract Sum will be increased by this Change Order in the amount of
$ 42,738.14
The new Contract Sum including this Change Order will be
$ 3,916,247.54
The Contract Time will be increased by Thirty -One (31) days
The new date of Substantial Completion will be 10-16-2026
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price; or the Contract Time,
that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Ovvner and
Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
cam-
ARCHITECT (Sig- na1 e) CONTRACTOR (Signature) OWNER (Signature)
BY: Caleb Posey, PE BY: Jeffrey Kearns, PM BY: Molly Rawn, Mayor
(Printed name, title, and license (Printed name and title) (Printed name and title)
number frequiredj
08/25/2026
Dare
August 24th, 2026
Date
09/15/2026
Date
ALA Document G701 — 2017. Copyright 01979, 1987, 2000, 2001 and 2017. All rights reserved. "The American Institute of Architects; 'American Institute of
Architects," "AIA," the AIA Logo, and "AIA Contract Documents' are trademarks of The American Institute of Architects. This draft was produced at 20-59-02 CDT
on 08/2412026 under Subscription No.20250118434 which expires on 04112/2027, is not for resale, is licensed for one-time use only, and may only be used in
accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfu@_aiacontracts.com.
User Notes: (6a875d901e4d916d2bac7772)
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
LEM
L E G A C Y
CONSTRUCTION MANAGEMENT
August 24th, 2026
Mrs. Melissa Evans, PLA, ASLA
Park Planner II
City of Fayetteville, Arkansas
Re: Underwood Park Phase 1
2837 N. Deane Solomon Road
Fayetteville, AR 72704
Sub: Change Order Request #4: Non -Priority List Narrative
Dear Mrs. Evans:
Email: mevans@fayetteville-ar.gov
Change Order #2 at Underwood Park was approved by Mayor Rawn on July 27, 2026. As you'll recall, Change
Order #2 addressed critical path activities caused in the ASI#1 and ASI#2 design updates along with a portion
of the project extension needs. Per the "Key Takeaways", non -critical activities and an updated schedule
evaluation would be forthcoming in a separate change order request. This is [t]hat change order request.
As narrated below and outlined on the spreadsheet snapshot, we respectfully request your approval of the
remaining ASI#1/ASI#2 changes along with a few other items that we have been asked to provide since.
Helpful Terms
Item ##: Refers to line items 1-8 shown on the outline snapshot below
Bid Item: Refers to the contracted elements of the job with agreed unit values.
Item 1 and Item 2 were non -critical path activities relating to "bid item" 6.7 and 6.8 of the original bid
form, respectively. Each "bid item" showed a value of 11,486 square yards. The actual value,
calculated using the ASI#2 updates, is 13,188 square yards. This is an increase of 1,702 square yards
of additional "Greenspace" work to be performed for each category. The agreed unit price was used
to calculate each "bid items" increase in value.
Item 3 describes another non -critical path activity modified in ASI#2. This item was originally
considered added scope but has been "zeroed out" as the cost to perform this activity will be covered
by a prorated value of bid item 10.24 scope that was ultimately not required... namely the exterior drop.
The new work involved reworking the SS trench and adding a new 4" backwater valve.
Legacy Construction Management, Inc
3733 Wildcat Creek Blvd.
Fayetteville, AR 72704
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 EBEFD
L E G A C Y
CONSTRUCTION MANAGEMENT
Item 4 adds new irrigation along the south end of the Pickleball Court area in Zone 4. This "system"
was not shown on the original construction documents. It also doesn't tie back to previously agreed
unit costs as this portion of the job has long since been completed. The cost shown for this item
covers all materials, labor and remobilization that were necessary to tie into existing lines.
Item 5 covers service fees Legacy Construction paid to Ozark Electric for the city. The construction
documents [and Bid Item 5.2] required Legacy to prepare [trench] the service line for primary electrical
service to be installed by Ozark Electric. After the fee is paid and Legacy's electrical work has been
inspected, OE takes over. They size the wire and conduit, set a transformer and connect our work to
their components inside the transformer.
Item 6 covers the cost to remove additional asphalt paving near the new "dog" statue. This area fell
outside the boundaries of our contracted scope of work. It required remobilizing labor and equipment
after the playground area had already been completed.
Item 7 and Item 8 are the last of the drainage changes associated with ASI#1 and ASI#2. ASI#1 added
two PC Headwalls [Item 7] whereas later, ASI#2 deleted the one near the Pickleball Court area.
Underwood Park -Phase 1
Summary of Changes - COR#004
SECONDARY LIST
Item Bid Item
Ref:
Description
Qty
UOM
Unit Price
Total
1
6.7
ASI#1
Fine Grade at Disturbed Greenspace
1702
SY
$ 1.68 $
2,859.36
2
6.8
ASI41
Spread 4' Topsoil from On -Site Stockpile in Disturbed Greenspace
1702
SY
$ 2.55 $
4,340.10
3
10.24
EDG
4' Sewer Line Invert Change
1
LS
$ - $
-
4
New
City
Add additional irrigation boxes w/hose bibs at Pickleball Court area
1
LS
$ 5,680.00 $
5,680.00
5
New
City
Legacy paid Ozark Electric to run primary connection
1
LS
$ 6,322.62 $
6,322.62
6
New
City
Remove Asphalt at Statue - Gall PC0014
1
LS
$ 1,156.23 $
1,156.23
7
New
ASI#1
Added PC Headwall from original list
2
EA
$ 2,000.00 $
4,000.00
8
New
ASI#2
Deleted one of the two PC Headwall[above] at Pickleball Court
-1
EA
$ 2,000.00 $
(2,000.00)
Subtotal $
22,358.31
Fees at SO% $
2,235.83
Subtotal $
24,594.14
570.29
31 GC Days $
17,678.99
0.011
Bond $
465.00
TotaICOR#2 $
42,738.14
The extension in time for this request is in addition to the previously approved Change Order #2. Although the
ASI#1 and ASI#2 changes took many months to redesign and approve, Legacy minimized much of the down
time by refocusing efforts on items unaffected by the drainage changes.
Respectfully submitted,
:A'W'g-lm
Jeffrey Kearns, Project Manager
Legacy Construction Management, Inc.
Legacy Construction Management, Inc
3733 Wildcat Creek Blvd.
Fayetteville, AR 72704
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
HDI CONTRACTORS
SERVING ALL OF ARKANSAS
1073 W Bowen Blvd
Fayetteville, AR 72703
Office 417-720-4766
Jacob's Cell: 479-466-6920
August 13th, 2026
RE: Underwood Park Additional Irrigation Boxes and Hose Bibs
PLUMBING PROPOSAL:
We furnish and install two additional irrigation boxes with hose bibs per detail for the sum of
BREAKDOWN
• 340 1" PVC @ $1.00 per foot $340
• Fittings and tracer wire $340
• Irrigation boxes and hose bibs $250 each $500
• Labor 2 man 30 hours @ $75 per hour $4,500
TOTAL $5,680
Notes:
If you have questions please call our estimator, Jacob Brewer, at 479-466-6920.
Contractors License # 0007240427 Plumbing License # MP6128 Electrical License # M2744
Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
1 �
14A, -m
� r
e i 1
� I
o 1
1
c➢ 1
T i 1
1
—---- 1 z i
�Tl
��l� iI
���
1�I
= a
UNDERWOOD PARK
e
Fayetteville, Arkansas
g
M
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
ozarks
ELECTRIC
COOPERATIVE NUN-
-
July 29, 2026
Dear Member,
Our records indicate you have a work order that has been on hold for 60 days or longer. In order to
prevent a backlog of work orders, we do not hold a work order longer than 90 days if there has been no
contact from the members. Details of the work order are below, and copies of the needed paperwork
--are enclosed:
• Work order: 3820451
• Invoice amount: $6,322.62
• Easement: N/A
If you plan to proceed with this job, please contact the Work Order Process Clerk at 479-684-4979 or our
Member Relations Department at 800-521-6144 to extend the waiting period beyond the 90 days. If no
contact has been made within 30 days from the date on this letter, the work order will be canceled, as
of 9/1/2026.
If the job is canceled and you wish to have the work done later, please contact our Member Relations
Department at 800-521-6144 to start a new work order.
Sincerely,
Celeste Sifuentes
Work Order Process Clerk
Ozarks Electric Cooperative
Enclosure
PO Box 848 1 Fayetteville, AR 72702 1 800.521.6144 1 www.ozarksecc.com
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
Ozarks
ELECTRIC
COOPERATIVE �►
POUox848 i Payettev-Ae.AR72702 i 800.521.6144 woNma[f45eCccom,
LEGACY CONSTRUCTION MANAGEMENT
STEVE COLLIER
3733 WILDCAT CREEK BLVD
FAYETTEVILLE AR 72704-8590
INVOICE:
Invoice Date:
Terms:
Due Date:
Amount Due:
45647
05/28/2026
Due In 30 Days
06/27/2026
$ 6,322.62
Account: 21350
Description: WORK ORDER 3820451 - AID TO CONSTRUCTION CHARGES Page 1 of 1
DESCRIPTION
QUANTITY
UOM
UNIT PRICE
AMOUNT
TAX
AID TO CONSTRUCTION
1.000
EA
6,322,6200
6,322.62
MESSAGES
Subtotal: $ 6,322.62
Tax: $ 0.00
Total: $ 6,322.62
Amount Paid: $ 0.00
Amount Due: $ 6,322.62
ozarks
ELECTRIC
COOPERATIVE r`
PO 8(w. 848 - `rayeltev!iie. AR 72702 i 800.52151,44 7 wwvr.6zery tccom
Account: 21350
Invoice: 45647
Due Date: 06/27/2026
Amount Due: $ 6,322.62
Amount Of Payment:
Remit To:
LEGACY CONSTRUCTION MANAGEMENT OZARKS ELECTRIC COOPERATIVE
STEVE COLLIER P.O. BOX 848
3733 WILDCAT CREEK BLVD FAYETTEVILLE AR 72702-0848
FAYETTEVILLE AR 72704-8590
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 EBEFD
08/05/2026 Ozarks Electric Cooperative
Aid to Construction
6,322.62
Checking Invoice 45647 Account: 21350
LEGACY CONSTRUCTION MANAGEMENT, INC.
ARKANSAS DISTRICT OFFICE
Ozarks
PO Box 848
Fayetteville, AR 72702
(800)521-6144
Journal: 344247 Date: Aug 06, 2026
Set: 0 Time: 08:03;21 AM
Legacy Construction Management
MISCELLANEOUS RECEIVABLE
Invoice; 45647 6322.62
Total To -Be -Paid: 6322.62
--------------
6294 CHECK IN OFFICE; 6322.62
Total Paid: 6322.62
--------------
Change Due: 0.00
--T -8561 8-0
THANK YOU FOR YOUR PAYMENT
SIONAIURE
6,322.62
6294
Rzr u,. ceissoc¢ze
Docusign Envelope ID: 4119F2C6-911 F-8E7A-8147-A511541 E8EFD
Gall Excavation, Inc.
PO Bo 682
Rogers, AR 72757
479.925.1175
License: 0152110526
Pricing Breakout
Order# : PCO 014
Order Date: 7.27.26
To: Legacy Const Management Project: Underwood Park - Phase 1
788 N. Old Missouri Rd. Deane Solomon Rd
Springdale, AR 72764 Fayetteville, AR 72704
The asphalt path to the set of the playground area is a want by Park to be removed however this area was not called out to be
demoed and per Wayne, there will be no updated drawings to show this
Description of Work Amount
Includes:
2501fx5ft of asphalt path demo, requested by Park
Approx. 29 cy of asphalt path demo $1,116.A3
If concrete gets poured and area is diffcult to access ,
Excludes:
Negative changes will lower the overall contract Requested Amount of Change $ 3,656.23
price requiring no additional payment by owner.