HomeMy WebLinkAbout195-26 RESOLUTION
Page 1
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 195-26
File Number: 2026-2813
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE CONTRACT WITH NABHOLZ
CONSTRUCTION CORPORATION IN THE AMOUNT OF $687,340.18 FOR WORK RELATED TO THE
WATER AND SEWER RELOCATIONS ALONG MARTIN LUTHER KING, JR. BOULEVARD, AND TO
APPROVE A BUDGET AMENDMENT
WHEREAS, in April 2025, the City Council approved Res. 101-25 which authorized a contract with Nabholz
Construction for the relocation of water and sewer utilities impacting ARDOT’s road widening project along Martin
Luther King, Jr. Boulevard and the Highway 62/I-49 Interchange and the project is substantially complete, with only
final cleanup and closeout documentation processes remaining; and
WHEREAS, Change Order No. 3 includes costs incurred by restoring private parking lots and drive aisles that failed
significantly more than anticipated during construction.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 3 to the
contract with Nabholz Construction Corporation, a copy of which is attached to this Resolution, in the amount of
$687,340.18 for the additional work related to the water and sewer relocations along Martin Luther King, Jr. Boulevard
and the Highway 62/I-49 Interchange.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget amendment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on September 1, 2026
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-2813
MEETING OF SEPTEMBER 1, 2026
TO: Mayor Rawn and City Council
THROUGH: Keith Macedo, Chief Information Officer
FROM: Tim Nyander, Utilities Director
SUBJECT: Nabholz Construction Corp. - Change Order No. 3 for the I-49 & MLK Utility
Relocations Phase II Project
RECOMMENDATION:
Staff recommends approval of Change Order No. 3 to the contract with Nabholz Construction Corp. which will
increase the contract amount by $687,340.18 for the relocation of water and sewer utilities impacting ARDOT’s
road widening project along MLK and the HWY-62/I-49 Interchange., and approval of a budget amendment.
BACKGROUND:
In April 2025, the City Council approved a contract with Nabholz Construction (Res. 101-25) for the relocation
of water and sewer utilities impacting ARDOT’s road widening project along MLK and the HWY-62/I-49
Interchange. This project is substantially complete, with only final cleanup and closeout documentation
processes remaining. Change Order No. 1 was previously approved for realignment during construction of an
8-inch diameter waterline due to ongoing easement negotiations after start of construction. Change Order No.
2 was previously approved for connection of water and sewer services at Centennial Bank. These services
were not in the locations assumed, and significant re-routing was necessary on the bank property.
DISCUSSION:
Change Order No. 3 is necessary for costs incurred by restoring private parking lots and drive aisles that failed
significantly more than anticipated during construction. Much of this project required installation of new water
and sewer lines in newly acquired public easements through private parking lots due to lack of room by the
widened ARDOT right of way. The bid documents specified quantities of rock backfill, asphalt paving, concrete
paving, and concrete curb/gutter based on typical trenching widths and the assumption that these areas would
not substantially degrade during construction. However, many of these parking lots failed significantly during
construction, requiring excess quantities to be used in repair and reconstruction activities after the utilities were
installed. The project did realize other cost savings and scope reductions, but in net the end-of-project
reconciliation will require a change order.
Based on previous project change orders, the remaining funds from the original project contingency is
$356,785.80. Once this contingency is utilized, additional funds must be approved by the City Council. This
change order will require an additional $330,554.38 beyond the original contingency. Based on the Relocation
Agreement for this project, ARDOT will be responsible for 72.54% of this cost and the City 27.46%, or
$90,770.23.
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
Furthermore, the overall Relocation Agreement with ARDOT will reconcile below its original estimate. Based
on the most recent Change Order No. 5 of the ARDOT Relocation Agreement (total project cost of
$25,294,663.64) the project is expected to reconcile ‘under budget’ by approximately $850,000.00 through a
subsequent reconciliation change order.
BUDGET/STAFF IMPACT:
Previously approved contingency funds are available in the amount of $356,785.80. A budget amendment is
attached to move the remaining amount of $330,554.38 from within the Easements account of the same
project to cover the cost of Change Order No. 3.
ATTACHMENTS: 3. Staff Review Form, 4. Budget Adjustment, 5. Change Order No. 3
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-2813
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE CONTRACT WITH
NABHOLZ CONSTRUCTION CORPORATION IN THE AMOUNT OF $687,340.18 FOR
WORK RELATED TO THE WATER AND SEWER RELOCATIONS ALONG MARTIN
LUTHER KING, JR. BOULEVARD, AND TO APPROVE A BUDGET AMENDMENT
WHEREAS, in April 2025, the City Council approved Res. 101-25 which authorized a contract with
Nabholz Construction for the relocation of water and sewer utilities impacting ARDOT’s road widening
project along Martin Luther King, Jr. Boulevard and the Highway 62/I-49 Interchange and the project is
substantially complete, with only final cleanup and closeout documentation processes remaining; and
WHEREAS, Change Order No. 3 includes costs incurred by restoring private parking lots and drive
aisles that failed significantly more than anticipated during construction.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 3 to the contract with Nabholz Construction Corporation, a copy of which is attached to this
Resolution, in the amount of $687,340.18 for the additional work related to the water and sewer
relocations along Martin Luther King, Jr. Boulevard and the Highway 62/I-49 Interchange.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
amendment, a copy of which is attached to this Resolution.
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
City of Fayetteville Staff Review Form
2026-2813
Item ID
9/1/2026
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Tim Nyander 8/13/2026 WATER SEWER (720)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order No. 3 to the contract with Nabholz Construction Corp. which will
increase the contract amount by $687,340.18 for the relocation of water and sewer utilities impacting ARDOT’s
road widening project along MLK and the HWY-62/I-49 Interchange., and approval of a budget amendment.
Budget Impact:
5400.720.5600-5808.00
5400.720.5700-5815.00 Water & Sewer
Account Number Fund
11011.2301 Water & Sewer Relocations - I-49 & Hwy 62
(MLK) Interchange
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $ 13,032,537.00
Expenses (Actual+Encum)$ 12,675,750.22
Available Budget $356,786.78
Does item have a direct cost?Yes Item Cost $687,340.18
Is a Budget Amendment attached?Yes Budget Amendment $330,555.00
$302.00 Remaining Budget $1.60
Purchase Order Number:2025-542 Previous Ordinance or Resolution #101-25
Change Order Number:3 Approval Date:
Original Contract Number:2025-24
Comments:
9/01/2026
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
City of Fayetteville, Arkansas - Budget Amendment/Adjustment
(Agenda)
Budget Year Division
/Org2 WATER SEWER (720)
BA Number
2026 Requestor:Cheryl Partain
BUDGET AMENDMENT/ADJUSTMENT DESCRIPTION:
Staff recommends approval of Change Order No. 3 to the contract with Nabholz Construction Corp. which will increase the
contract amount by $687,340.18 for the relocation of water and sewer utilities impacting ARDOT’s road widening project
along MLK and the HWY-62/I-49 Interchange., and approval of a budget amendment.
COUNCIL DATE:9/1/2026
ITEM ID#:2026-2813
Holly Black
8/13/2026 1:35 PM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.2026714TOTAL--
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
5400.720.5700-5815.00 539,769 -11011 2301 EX Improvements - Sewer
5400.720.5600-5808.00 147,572 -11011 2301 EX Improvements - Water Line
5400.720.5700-5911.99 (76,602)-11011 2301 EX Contingency - Capital Project
5400.720.5600-5911.99 (280,184)-11011 2301 EX Contingency - Capital Project
5400.720.5600-5810.00 (330,555)-11011 2301 EX Easements
--
--
--
--
--
--
--
--
--
--
--
--
1 of 1
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
CHANGE ORDER
Contract Title:
Date of Issuance:
ORDINANCE/RESOLUTION:
Effective:
The Original Contract is changed as follows:
Bid Bid Previous Unit Contract Revised Revised Original Revised
Item Item Estimated of Unit Estimated Unit Estimated Estimated
No.Description Quantity Measure Price Quantity Price Cost Cost
1.1 Bonds and Insurance 1 LS 219,000.00$ 1 219,000.00$ 219,000.00$
1 LS 644,000.00$ 1 644,000.00$ 644,000.00$
1 LS 18,600.00$ 1.2916667 18,600.00$ 24,025.00$
1.4 Maintenance of Traffic - City Streets & Private Access 1 LS 234,810.00$ 1 234,810.00$ 234,810.00$
1 LS 356,340.00$ 1 356,340.00$ 356,340.00$
1 LS 127,650.00$ 1 127,650.00$ 127,650.00$
1 LS 76,500.00$ 1 76,500.00$ 76,500.00$
1 LS 595,400.00$ 1 595,400.00$ 595,400.00$
1 LS 35,050.00$ 1 35,050.00$ 35,050.00$
1 LS 151,800.00$ 1 151,800.00$ 151,800.00$
1 LS 17,614.00$ 0 17,614.00$ -$
2.1 Pipe Casing - 12" Steel (Bored)140 LF 1,107.00$ 135 154,980.00$ 149,445.00$
150 LF 222.00$ 149 33,300.00$ 33,078.00$
415 LF 668.00$ 430 277,220.00$ 287,240.00$
50 LF 205.00$ 40 10,250.00$ 8,200.00$
565 LF 1,048.00$ 740 592,120.00$ 775,520.00$
40 LF 236.50$ 80 9,460.00$ 18,920.00$
30 LF 1,800.00$ 30 54,000.00$ 54,000.00$
175 LF 2,640.00$ 175 462,000.00$ 462,000.00$
55 LF 503.00$ 25 27,665.00$ 12,575.00$
230 LF 2,115.00$ 150 486,450.00$ 317,250.00$
200 LF 3,120.00$ 70.18 624,000.00$ 218,961.60$
180 LF 3,550.00$ 150 639,000.00$ 532,500.00$
3.1 Pre-CCTV Sanitary Sewer Mains (6"-15")1170 LF 10.00$ 1363 11,700.00$ 13,630.00$
505 LF 19.50$ 409.5 9,847.50$ 7,985.25$
120 LF 32.50$ 283.3 3,900.00$ 9,207.25$
345 LF 27.50$ 357.1 9,487.50$ 9,820.25$
595 LF 53.50$ 660.7 31,832.50$ 35,347.45$
260 LF 96.00$ 0 24,960.00$ -$
565 LF 88.00$ 933.57 49,720.00$ 82,154.16$
3.8 615 LF 105.00$ 662.78 64,575.00$ 69,591.90$
3.9 Deep 160 LF 250.00$ 90.85 40,000.00$ 22,712.50$
1820 LF 7.60$ 1697.6 13,832.00$ 12,901.76$
5 EA 118.00$ 5 590.00$ 590.00$
19 EA 7,000.00$ 17 133,000.00$ 119,000.00$
73 VF 760.00$ 62.58 55,480.00$ 47,560.80$
4 EA 8,200.00$ 2 32,800.00$ 16,400.00$
30 VF 950.00$ 9.67 28,500.00$ 9,186.50$
6 VF 375.00$ 6 2,250.00$ 2,250.00$
9 EA 2,020.00$ 10 18,180.00$ 20,200.00$
3.18 Sanitary Sewer Mains)124 VF 570.00$ 55 70,680.00$ 31,350.00$
1 EA 4,490.00$ 1 4,490.00$ 4,490.00$
1 EA 1,700.00$ 1 1,700.00$ 1,700.00$
1 EA 1,730.00$ 1 1,730.00$ 1,730.00$
5 EA 4,485.00$ 5 22,425.00$ 22,425.00$
365 LF 28.00$ 365 10,220.00$ 10,220.00$
545 LF 30.00$ 595 16,350.00$ 17,850.00$
240 LF 57.00$ 0 13,680.00$ -$
55 LF 60.00$ 145 3,300.00$ 8,700.00$
1 EA 900.00$ 1 900.00$ 900.00$
August 4, 2026
Res. 101-25
April 15, 2025
Bid 25-29, Construction, Utility Relocations for I-
49/MLK Interchange
To Contractor: Nabholz Construction, Inc.
Change Order No. 3
Page 1 of 3
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
3.28 Reinstate Existing Sewer Service Line 15 EA 2,380.00$ 11 35,700.00$ 26,180.00$
180 LF 67.00$ 279 12,060.00$ 18,693.00$
632 LF 89.00$ 628 56,248.00$ 55,892.00$
1 EA 2,225.00$ 1 2,225.00$ 2,225.00$
25 VF 1,600.00$ 1 40,000.00$ 1,600.00$
1 EA 28,000.00$ 1 28,000.00$ 28,000.00$
4.1 Rock Excavation 500 CY 10.00$ 24.33 5,000.00$ 243.30$
7400 CY 75.00$ 10125 555,000.00$ 759,375.00$
100 CY 10.50$ 100 1,050.00$ 1,050.00$
2200 SY 195.00$ 3901.2 429,000.00$ 760,734.00$
1800 LF 56.00$ 4163.33 100,800.00$ 233,146.48$
4.6 Thickness)2100 SY 154.00$ 5090.72 323,400.00$ 783,970.88$
4.7 (6")225 SY 119.00$ 360 26,775.00$ 42,840.00$
3 EA 170.00$ 1 510.00$ 170.00$
5.1 14)25 LF 58.00$ 25 1,450.00$ 1,450.00$
5.2 14)20 LF 81.00$ 10 1,620.00$ 810.00$
5.3 14)3500 LF 108.00$ 3500 378,000.00$ 378,000.00$
4400 LF 256.00$ 4400 1,126,400.00$ 1,126,400.00$
355 LF 415.00$ 357 147,325.00$ 148,155.00$
5.6 Coated 20 LF 675.00$ 20 13,500.00$ 13,500.00$
5.7 Coated 920 LF 885.00$ 965 814,200.00$ 854,025.00$
48000 LBS 24.50$ 49525 1,176,000.00$ 1,213,362.50$
8 EA 3,670.00$ 10 29,360.00$ 36,700.00$
2 EA 13,750.00$ 2 27,500.00$ 27,500.00$
2 EA 4,290.00$ 4 8,580.00$ 17,160.00$
1 EA 6,190.00$ 2 6,190.00$ 12,380.00$
1 EA 11,670.00$ 1 11,670.00$ 11,670.00$
2 EA 14,230.00$ 2 28,460.00$ 28,460.00$
1 EA 2,640.00$ 1 2,640.00$ 2,640.00$
2 EA 6,405.00$ 5 12,810.00$ 32,025.00$
5 EA 8,930.00$ 4 44,650.00$ 35,720.00$
1 EA 9,210.00$ 1 9,210.00$ 9,210.00$
3 EA 14,970.00$ 3 44,910.00$ 44,910.00$
1 EA 13,980.00$ 2 13,980.00$ 27,960.00$
5.21 Dechlorination 1 EA 19,300.00$ 1 19,300.00$ 19,300.00$
5.22 30"x 30" Tapping Sleeve and Valve Box (Install Only)1 EA 25,200.00$ 1 25,200.00$ 25,200.00$
5.23 36"x 36" Tapping Sleeve and Valve Box (Install Only)1 EA 28,500.00$ 1 28,500.00$ 28,500.00$
5.24 M103)1 EA 110,000.00$ 1 110,000.00$ 110,000.00$
5.25 M104)1 EA 124,000.00$ 1 124,000.00$ 124,000.00$
15 EA 15,600.00$ 18 234,000.00$ 280,800.00$
7 EA 2,090.00$ 7 14,630.00$ 14,630.00$
3 EA 2,840.00$ 3 8,520.00$ 8,520.00$
9 EA 4,440.00$ 10 39,960.00$ 44,400.00$
4 EA 5,450.00$ 3 21,800.00$ 16,350.00$
3 EA 20,000.00$ 3 60,000.00$ 60,000.00$
1 EA 25,000.00$ 1 25,000.00$ 25,000.00$
1750 LF 6.70$ 0 11,725.00$ -$
1240 LF 10.30$ 1162 12,772.00$ 11,968.60$
1525 LF 13.10$ 2170 19,977.50$ 28,427.00$
520 LF 56.00$ 626 29,120.00$ 35,056.00$
405 LF 80.00$ 404 32,400.00$ 32,320.00$
215 LF 42.50$ 110 9,137.50$ 4,675.00$
2460 LF 59.50$ 2112 146,370.00$ 125,664.00$
20 LF 84.00$ 10 1,680.00$ 840.00$
575 CY 602.00$ 575 346,150.00$ 346,150.00$
2 EA 26,700.00$ 2.5 53,400.00$ 66,750.00$
5.44 Bio Outside Wrap)4800 LF 10.00$ 4800 48,000.00$ 48,000.00$
Page 2 of 3
Docusign Envelope ID: 63870A09-A886-82E7-82C6-0235D745C978
5.45 Bio Outside Wrap)920 LF 15.00$ 985 13,800.00$ 14,775.00$
12 EA 120.00$ 12 1,440.00$ 1,440.00$
5.47 (Install only for Valve)2 EA 16,200.00$ 2 32,400.00$ 32,400.00$
110 LF 73.00$ 110 8,030.00$ 8,030.00$
1540 LF 83.00$ 1540 127,820.00$ 127,820.00$
225 EA 133.00$ 225 29,925.00$ 29,925.00$
9 EA 2,250.00$ 12 20,250.00$ 27,000.00$
2 EA 3,485.00$ 3 6,970.00$ 10,455.00$
14 EA 2,675.00$ 10 37,450.00$ 26,750.00$
3 EA 7,955.00$ 3 23,865.00$ 23,865.00$
6.1 Install Modular Wall 40 LF 316.00$ 12 12,640.00$ 3,792.00$
30 LF 158.00$ 30 4,740.00$ 4,740.00$
10 LF 187.00$ 7.5 1,870.00$ 1,402.50$
32 LF 204.00$ 55 6,528.00$ 11,220.00$
10 LF 470.00$ 10 4,700.00$ 4,700.00$
205 SY 120.00$ 205 24,600.00$ 24,600.00$
20 CY 105.00$ 77 2,100.00$ 8,085.00$
6.8 Boxes 2 EA 7,735.00$ 3 15,470.00$ 23,205.00$
7.1 Pipe)152 LF 69.00$ 444 10,488.00$ 30,636.00$
7.2 Vinyl)10 LF 69.00$ 136 690.00$ 9,384.00$
4 EA 175.00$ 8 700.00$ 1,400.00$
8 EA 1,750.00$ 8 14,000.00$ 14,000.00$
1000 SY 9.00$ 1280 9,000.00$ 11,520.00$
9000 SY 11.00$ 9000 99,000.00$ 99,000.00$
Summation of Cost 13,967,679.50$ 14,655,019.68$
The Contract is changed as follows for Change Order #1:
Bid Bid Previous Unit Contract Revised Revised Original Revised
Item Item Estimated of Unit Estimated Unit Estimated Estimated
No.Description Quantity Measure Price Quantity Price Cost Cost
1 6th Street Shoppes Temporary Access Road (Cooper
0
LS
73,350.00$
1
73350 73,350.00$
2 Big O Tires Tree Removal 0 LS 39,000.00$ 1 39000 39,000.00$
3 Big O Tires Block Delivery Off Site 0 LS 3,600.00$ 1 3600 3,600.00$
Summation of Cost -$ 115,950.00$
The Contract is changed as follows for Change Order #2:
Bid Bid Previous Unit Contract Revised Revised Original Revised
Item Item Estimated of Unit Estimated Unit Estimated Estimated
No.Description Quantity Measure Price Quantity Price Cost Cost
1 Vac Truck for Potholing 0 LS 5,000.00$ 1 5000 5,000.00$
2 Centennial Bank Bore for Sewer Service (4" PVC)0 LF 168.30$ 70 168.3 11,781.00$
3 Centennial Bank Bore for Water Service (2" PVC)0 LF 74.88$ 70 74.88 5,241.60$
4 0 LF 74.88$ 70 74.88 5,241.60$
Summation of Cost -$ 27,264.20$
Not valid until signed by the Owner
The original Contract Price was 13,967,679.50$
Net change by previously authorized change orders 143,214.20$
The Contract Price prior to this Change Order was 14,110,893.70$
The Contract Price will increase by 687,340.18$
The new Contract Price including this Change Order will be 14,798,233.88$
The Contract Time(s) will increase by 142 calendar days
Required dates of Completion as of the date of this Change Order therefore are:
Substantial Completion 11/20/2026
Final Completion 12/20/2026
Nabholz Construction, Inc.CITY OF FAYETTEVILLE
BY DATE BY DATE
NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have been authorized by Work Change Directives not incorporated in this or
Page 3 of 3
8/12/2026 9/1/2026