Resolution: 147-26
File Number: 2026-1796
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL ENGINEERING
SERVICES AGREEMENT WITH HAWKINS-WEIR ENGINEERS, INC. IN AN AMOUNT NOT TO
EXCEED $195,220.00 FOR ADDITIONAL SERVICES ASSOCIATED WITH THE NOLAND WATER
RESOURCE RECOVERY FACILITY PRIMARY SWITCHGEAR IMPROVEMENTS PROJECT.
WHEREAS, the primary electrical feed to the Noland Water Resource Recovery Facility (WRRF) has been identified
as a concern for reliability of keeping the plant in power continuously, primarily due to the arrangement of high-voltage
breakers and the WRRF’s tie in to both grid-power and standby generator power; and
WHEREAS, design and bidding are complete, and the project is ready to move into construction, and this amendment
provides for additional services including project administration, construction observation, engineering oversight, final
inspections and system start-up.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign
Amendment No. 1 with Hawkins-Weir Engineers, Inc. in an amount not to exceed $195,220.00 for additional services
associated with the Noland Water Resource Recovery Facility Primary Switchgear Improvements Project.
PASSED and APPROVED on June 16, 2026
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-1796
MEETING OF JUNE 16, 2026
TO: Mayor Rawn and City Council
THROUGH: Keith Macedo, Chief of Staff
FROM: Tim Nyander, Utilities Director
SUBJECT: Hawkins-Weir Engineers, Inc. - Amendment No. 1 for Noland WWTP Switchgear
RECOMMENDATION:
Staff recommends approval of Amendment No. 1 to the engineering services agreement with Hawkins-Weir
Engineers, Inc. for professional services associated with the Noland WRRF Primary Switchgear Improvements
Project in an amount not to exceed $195,220.00.
BACKGROUND:
The primary electrical feed to the Noland Water Resource Recovery Facility (WRRF) has been identified as a
concern for reliability of keeping the plant in-power continuously. This is primarily due to the arrangement of
high voltage breakers and the WRRF’s tie-in to both grid-power and standby generator power. Hawkins-Weir
Engineers was selected via RFQ# 24-01, Selection #8 to provide these professional services.
DISCUSSION:
The Noland WRRF Primary Switchgear Improvements Project began with a non-agenda agreement with
Hawkins-Weir in the amount of $19,900.00. Resolution 179-24 approved what the City referred to as
"Amendment No. 1" at the time, but it was actually a new agreement for Noland Switchgear engineering
services in the amount of $155,500.00 to bring the project to 100% design and bidding.
Design and bidding are complete, and the project is ready to move into construction. This proposed
amendment in the amount of $195,220.00 will be Amendment No. 1 to provide necessary funds for Hawkins-
Weir to be involved with project administration, construction observation, engineering oversight, final
inspections and system start-up.
Staff recommends approval of Amendment No. 1 to the engineering services agreement with Hawkins-Weir
Engineers, Inc. for professional services associated with the Noland WRRF Primary Switchgear Improvements
Project in an amount not to exceed $195,220.00.
BUDGET/STAFF IMPACT:
Funds are available in the WWTP Building Improvements account.
ATTACHMENTS: 3. Staff Review Form, 4. Amendment No. 1
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-1796
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL
ENGINEERING SERVICES AGREEMENT WITH HAWKINS-WEIR ENGINEERS, INC. IN
AN AMOUNT NOT TO EXCEED $195,220.00 FOR ADDITIONAL SERVICES ASSOCIATED
WITH THE NOLAND WATER RESOURCE RECOVERY FACILITY PRIMARY
SWITCHGEAR IMPROVEMENTS PROJECT.
WHEREAS, the primary electrical feed to the Noland Water Resource Recovery Facility (WRRF) has
been identified as a concern for reliability of keeping the plant in power continuously, primarily due to
the arrangement of high-voltage breakers and the WRRF’s tie in to both grid-power and standby
generator power; and
WHEREAS, design and bidding are complete, and the project is ready to move into construction, and
this amendment provides for additional services including project administration, construction
observation, engineering oversight, final inspections and system start-up.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign Amendment No. 1 with Hawkins-Weir Engineers, Inc. in an amount not to exceed $195,220.00 for
additional services associated with the Noland Water Resource Recovery Facility Primary Switchgear
Improvements Project.
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
City of Fayetteville Staff Review Form
2026-1796
Item ID
6/16/2026
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Tim Nyander 5/21/2026 WASTEWATER TREATMENT (730)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Amendment No. 1 to the engineering services agreement with Hawkins-Weir
Engineers, Inc. for professional services associated with the Noland WRRF Primary Switchgear Improvements
Project in an amount not to exceed $195,220.00.
Budget Impact:
540.730.5800-5314.00 Water & Sewer
Account Number Fund
02032.1 WWTP Building Improvements
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $7,454,066.00
Expenses (Actual+Encum)$7,114,976.45
Available Budget $339,089.55
Does item have a direct cost?Yes Item Cost $195,220.00
Is a Budget Amendment attached?No Budget Amendment $-
Remaining Budget $143,869.55
Purchase Order Number:2023-521 Previous Ordinance or Resolution #179-24
Change Order Number:1 Approval Date:
Original Contract Number:2024-00000036
Comments:
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
Amendment No. 1 Page 1 of 2 May 4, 2026
AMENDMENT NO. 1
TO THE
AGREEMENT For PROFESSIONAL ENGINEERING SERVICES
BETWEEN
CITY OF FAYETTEVILLE, ARKANSAS
AND
HAWKINS-WEIR ENGINEERS, INC.
In accordance with the AGREEMENT For PROFESSIONAL ENGINEERING SERVICES for the Noland
WWTP Switchgear Replacement (HW Project No. 2023055), dated July 2, 2024, between the City of
Fayetteville, Arkansas (hereinafter called Owner) and Hawkins-Weir Engineers, Inc. (hereinafter called
Engineer), Owner hereby authorizes Engineer to proceed with engineering services as modified by this
Amendment No. 1.
SECTION 1 – SCOPE OF SERVICES
1.1 Amendment No. 1 is for construction phase services for the Noland WWTP Switchgear
Replacement associated with Owner’s Project No. 26-30. Services are detailed in the Engineer’s attached
Scope of Services dated May 4, 2026.
SECTION 2 – TIME OF SERVICE
2.1 The scope of services as defined above is based on addressing the defined services within a 270-
calendar day construction Contract Time in 2026 for the Owner’s Project No. 26-30. Engineer will proceed
with providing the services set forth herein immediately upon execution of this Authorization by all parties.
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
SECTION 3 - COMPENSATION 3 .1 Owner shall compensate Engineer for providing the services set forth herein in accordance with the terms of the Agreement. Total payment for Scope of Services described herein shall not exceed One Hundred Ninety-Five Thousand Two Hundred Twenty and 00/100 Dollars ($195,220.00) without written approval of Owner. These additional services adjust the Agreement's not to exceed fee to $336,220.00,and adjusts the not to exceed reimbursable expenses to $14,500.00 for a total not to exceed fee of $350,720.00. Attachments: Scope of Services dated May 4, 2026 Fee Proposal dated May 4, 2026 2026 Standard Hourly Billing Rate Structure Certificate of Liability Insurance (2 Pages) ACCEPTED BY: HAWKINS-WEIR ENGINEERS, INC. By:�K-�cCa.v,....'�:sa::::iv1connick, P.E. Secretary Date: __ 5------=-( ,_4_(�------
Amendment No. l
AUTHORIZATION BY: CITY OF FAYETTEVILLE, ARKANSAS By: __________ _ Honorable Molly Rawn, Mayor Date: ___________ _ Page 2 of2 May 4, 2026 06/16/2026Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
2023055\Appendix A Scope of Services 050426.docx Page 1 of 1
Appendix A
Scope of Services
Amendment No. 1
Noland WWTP Switchgear Replacement
City of Fayetteville, Arkansas
HW Project No. 2023055
May 4, 2026
Hawkins-Weir Engineers, Inc. (HW) proposes to provide the following construction phase
services for the Noland WWTP Switchgear Replacement project:
Task Description
D. Construction Phase – Noland WWTP Switchgear Replacement
1. Conduct Pre-Construction Conference with the Owner and Contractor
a. Field Survey to reestablish control monumentation
2. Provide periodic observation during construction(1)
3. Conduct up to two (2) progress meetings
4. Prepare, review, and coordinate the dissemination of construction documentation
including material submittals, testing results, field orders, and change orders as directed
by the Owner
5. Review the Contractor’s constructed quantities and prepare monthly pay requests for the
Owner’s approval
6. Conduct as-built surveys of completed improvements
7. Participate in Factory Witness Test at Caterpillar in Alpharetta, Georgia, coordinate and
assist with switchgear startup testing on site
8. Coordinate and conduct a final inspection with the Contractor and the Owner, and
prepare a punch list of deficient construction items for the Contractor to address
9. Prepare Record Drawings of the completed project and provide one (1) reproducible
hard copy and one (1) electronic copy for the Owner’s archives
(1) Based on a 270-calendar day Contract Time (240-calendar days until Substantial
Completion). Periodic construction observation is based on 8-hours per day
(Monday through Friday) during the construction of the below grade improvements
(assumed at 30-calendar days) and approximately 2-hours per day (Monday through
Friday) for the remaining site construction period (assumed 240-calendar days)
through Final Completion date for the Construction Observer.
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
Amendment No. 1 - Fee Proposal
Noland WWTP Switchgear Improvements
City of Fayetteville, Arkansas
Project No. 2023055
May 4, 2026
D.Construction Phase - Noland WWTP Switchgear Replacement
Engr Engr Engr Observer Surveyor Tech BIM GPS Admin.Total Total
VII VI I III III III Survey Hours Cost
$275 $250 $125 $120 $175 $135 $135 $200 $75
1.6 10 4 2 2 24 $5,040
a)Field survey to reestablish control monumentation 4 4 8 $1,500
2.40 40 40 500 620 $86,000
3.Conduct up to two (2) progress meetings 8 8 8 4 6 34 $6,130
4.16 46 24 8 8 16 118 $22,140
5.20 40 8 68 $16,100
6.4 8 4 4 20 $3,460
7.120 60 180 $40,500
8.4 8 4 4 4 24 $4,380
9.6 4 4 8 16 4 4 46 $7,470
TOTAL HOURS =220 160 140 530 8 8 24 12 40 1,142
SUBTOTAL COST =$60,500 $40,000 $17,500 $63,600 $1,400 $1,080 $3,240 $2,400 $3,000 ----------->$192,720
E.Reimbursable Expenses
Total
1.$2,500
$2,500
Engineering Services Summary
D.Construction Phase - Noland WWTP Switchgear Replacement $192,720
E.$2,500
Total Engineering Fee - Not To Exceed $195,220
Reimbursable Expenses
Task
Conduct Pre-Construction Conference with the Owner and Contractor
Provide periodic observation during construction (1)
Prepare, review, and coordinate the dissemination of construction
documentation including material submittals, testing results, field orders,
and change orders as directed by the Owner
Review the Contractor’s constructed quantities and prepare monthly pay
requests for the Owner’s approval
Conduct as-built surveys of completed improvements
Coordinate and conduct a final inspection with the Contractor and the
Owner, and prepare a punch list of deficient construction items for the
Contractor to address
Prepare record drawings of the completed project and provide one (1)
reproducible hard copy and one (1) electronic copy for the Owner’s
archives
(1) Based on a 270-calendar day Contract Time (240-calendar days until substantial completion).
Periodic construction observation is based on 8-hours per day (Monday through Friday) during the construction of the below grade improvements
through final completion date for the Construction Observer.
Item Description
Caterpillar Factory Test
Participate in Factory Witness Test at Caterpillar in Alpharetta, Georgia,
coordinate and assist with switchgear startup testing on site
Travel for Factory Witness Test (HW Personnel only)
(assumed at 30-calendar days) and approximately 2-hours per day (Monday through Friday) for the remaining site construction period (assumed 240-calendar days)
2023055\Scope of Services and Fee Proposal -Noland WWTF Switchgear Construction Management 050426.xlsx
Docusign Envelope ID: 37324E2B-84DA-8EF6-838D-EC29D8403816
Hawkins-Weir Engineers, Inc.
Hourly Rate Schedule: 2026
Description Billing Rate/Hour
Engineer VII $275
Engineer VI $250
Engineer V $225
Engineer IV $200
Engineer III $175
Engineer II $150
Engineer I $125
Environmental Specialist II $130
Environmental Specialist I $110
$145
$135
$120
$100
$90
$150
$145
$135
$125
$135
$125
Designer III
Designer II
Designer I
Civil Eng. Assistant I
Civil Eng. Assistant II
Digital Design Manager
BIM Modeler III
BIM Modeler II
BIM Modeler I
CAD/GIS Technician III
CAD/GIS Technician II
CAD/GIS Technician I $115
Construction Manager II $150
Construction Manager I $130
Construction Observer IV $140
Construction Observer III $120
Construction Observer II $110
Construction Observer I $100
Surveyor $175
GPS Survey $200
Survey Technician $50
Business Manager $100
Graphic Designer $100
Administrative $75
Reimbursable Expenses
Mileage $0.77/mile
Printing @ Cost
Travel @ Cost
Expert Witness Rate x 2.0
Other Direct Costs @ Cost
Notes:
1.Hourly rates may be equitably adjusted
2. Adjustment to rate schedule will not change contract lump sum or NTE amounts
3.If a conflict exists, hourly rates & reimbursable expenses will be invoiced per terms of Agreement.