Resolution: 135-26
File Number: 2026-1741
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL SERVICES CONTRACT
WITH GARVER, LLC FOR ADDITIONAL SERVICES RELATED TO THE LAKE SEQUOYAH BRIDGE
REHABILITATION PROJECT
WHEREAS, on February 1, 2022, the City Council passed Resolution 27-22 approving a professional engineering
services agreement with Garver, LLC in the amount of $75,300.00 for the design of improvements to address
maintenance issues associated with the East Lake Sequoyah Drive Bridge, which appears to have been in place since at
least 1980 according to aerial photography; and
WHEREAS, the Arkansas Department of Transportation, which inspects the bridge annually, has advised that the
bridge needs several routine and important maintenance repairs; and
WHEREAS, Amendment No. 1 to the Professional Services Agreement includes a study of bridge repair options with
cost analysis, lead paint testing, and the addition of Construction Phase Services.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign
Amendment No. 1 to the Professional Services Contract with Garver, LLC for a study of bridge repair options with cost
analysis, lead paint testing, and construction phase services associated with the Lake Sequoyah Bridge Rehabilitation
Project.
PASSED and APPROVED on June 2, 2026
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-1741
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL SERVICES
CONTRACT WITH GARVER, LLC FOR ADDITIONAL SERVICES RELATED TO THE
LAKE SEQUOYAH BRIDGE REHABILITATION PROJECT
WHEREAS, on February 1, 2022, the City Council passed Resolution 27-22 approving a professional
engineering services agreement with Garver, LLC in the amount of $75,300.00 for the design of
improvements to address maintenance issues associated with the East Lake Sequoyah Drive Bridge,
which appears to have been in place since at least 1980 according to aerial photography; and
WHEREAS, the Arkansas Department of Transportation, which inspects the bridge annually, has
advised that the bridge needs several routine and important maintenance repairs; and
WHEREAS, Amendment No. 1 to the Professional Services Agreement includes a study of bridge
repair options with cost analysis, lead paint testing, and the addition of Construction Phase Services.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign Amendment No. 1 to the Professional Services Contract with Garver, LLC for a study of bridge
repair options with cost analysis, lead paint testing, and construction phase services associated with the
Lake Sequoyah Bridge Rehabilitation Project.
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Comments:
Purchase Order Number:
Change Order Number:
Previous Ordinance or Resolution #
Approval Date:
Original Contract Number:
46020.7230.2601
Project Number
Budget Impact:
Bridge Impr-Lake Sequoyah Bridge
Fund
Street Bond Projects4702.860.7230-5860.02
Account Number
Project Title
City of Fayetteville Staff Review Form
2026-1741
Item ID
6/2/2026
City Council Meeting Date - Agenda Item Only
Staff recommends approval of Amendment 1 with Garver, LLC to add scope of services to the project including a
study of bridge repair options with cost analysis, lead paint testing, and the addition of Construction Phase Services.
The Maximum Not to Exceed Amount will be increased by $83,585.
N/A for Non-Agenda Item
Action Recommendation:
Submitted By
Amanda Swope STORMWATER MANAGEMENT (740)
Division / Department
5/5/2026
Submitted Date
Yes
83,585.00$
83,585.00$
V20221130
Budgeted Item?
Does item have a direct cost?
Is a Budget Adjustment attached?
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
782,805.00$
699,220.00$
Yes
No
-$
6/2/2026
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-1741
MEETING OF JUNE 2, 2026
TO: Mayor Rawn and City Council
THROUGH: Chris Brown, Public Works Director
FROM: Amanda Swope, Project Manager
Alan Pugh, Stormwater Manager
SUBJECT:
Approval of Amendment 1 with Garver, LLC to add scope of services to the project
including a study of bridge repair options with cost analysis, lead paint testing, and
the addition of Construction Phase Services. The Maximum Not to Exceed Amount
will be increased by $83,585.
RECOMMENDATION:
Staff recommends approval of Amendment 1 with Garver, LLC to add scope of services to the project including
a study of bridge repair options with cost analysis, lead paint testing, and the addition of Construction Phase
Services. The Maximum Not to Exceed Amount will be increased by $83,585.
BACKGROUND:
The Lake Sequoyah bridge appears to have been in place since at least 1980 according to aerial photography.
This bridge receives annual inspections from ARDOT similarly to all bridges within the area. The bridge needs
several routine and important maintenance repairs according to ARDOT. These are specialty repairs that are
not within the expertise of City staff; therefore a contractor is needed to complete the repairs.
DISCUSSION:
This amendment updates the previous original contract between the City of Fayetteville and Garver, LLC dated
February 01, 2022. Added services to this agreement include a study of bridge repair options with cost
analysis, lead paint testing, and the addition of Construction Phase Services.
BUDGET/STAFF IMPACT:
Funds for this project will be from the Sales Tax Capital Improvement Fund and from the 2024 Transportation
Bond Funds.
ATTACHMENTS: 3. Staff Review Form, 4. 2026-04-30 Lake Sequoyah Contract Amendment No. 1-Garver
Signed
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Contract Amendment No. 1 1 of 3
Lake Sequoyah Bridge Rehabilitation Garver Project No. 15047010
AMENDMENT TO AGREEMENT FOR PROFESSIONAL SERVICES
City of Fayetteville
Fayetteville, AR
Project No. 15047010
CONTRACT AMENDMENT NO. 1
This Contract Amendment No. 1, effective on the date last written below, shall amend the original
contract between the City of Fayetteville (Owner) and GARVER, LLC (GARVER), dated February 01,
2022, referred to in the following paragraphs as the original contract.
This Contract Amendment No. 1 adds professional services for the:
Lake Sequoyah Bridge Rehabilitation project. Generally, Amendment No. 1 will add scope of
services to the project including a study of bridge repair options with cost analysis, lead paint testing,
and the addition of Construction Phase Services.
The original contract is hereby modified as follows:
APPENDIX A – SCOPE OF SERVICES
The following items will be added to Section 2.7. Final Design of the original contract SCOPE OF
SERVICES:
2.7 Garver will perform a study of bridge repair alternatives that evaluates the following options:
•Partial deck repairs
•Full deck replacement
•Full bridge reconstruction
A construction cost estimate for each alternative will be developed to compare and analyze each
alternative for short-term and long-term feasibility.
Garver will revise the plans, specifications, and quantities three (3) times to accommodate the
changes for the three re-biddings of the project.
Garver will add four (4) additional site visits including: lead based paint testing site visit and one (1)
site visit prior to adjusting the plans for each rebidding.
Section 2.9 Bidding will be modified to allow for the project to bid on four (4) separate occasions.
Section 2.10 Construction Phase Services of the original contract SCOPE OF SERVICES will be
removed and replaced with the following items:
During the construction phase of work, Garver will accomplish the following:
A. Issue a Notice to Proceed letter to the Contractor and attend preconstruction meeting.
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Contract Amendment No. 1 2 of 3
Lake Sequoyah Bridge Rehabilitation Garver Project No. 15047010
B. Evaluate and respond to construction material submittals and shop drawings. Corrections or
comments made by Garver on the shop drawings during this review will not relieve Contractor
from compliance with requirements of the drawings and specifications. The check will only be for
review of general conformance with the design concept of the project and general compliance with
the information given in the contract documents. The Contractor will be responsible for confirming
and correlating all quantities and dimensions, selecting fabrication processes and techniques of
construction, coordinating his work with that of all other trades, and performing his work in a safe
and satisfactory manner. Garver’s review shall not constitute approval of safety precautions or
constitute approval of construction means, methods, techniques, sequences, procedures, or
assembly of various components. When certification of performance characteristics of
materials, systems or equipment is required by the Contract Documents, either directly or
implied for a complete and workable system, Garver shall be entitled to rely upon such
submittal or implied certification to establish that the materials, systems or equipment will meet
the performance criteria required by the Contract Documents.
C. Issue instructions to the Contractor on behalf of the Owner and issue necessary clarifications
(respond to RFIs) regarding the construction contract documents.
D. Review the progress payment request received from the Contractor and make a
recommendation to the Owner regarding payment. Garver’s recommendation for payment
shall not be a representation that Garver has made exhaustive or continuous inspections to (1)
check the quality or exact quantities of the Work; (2) to review billings from Subcontractors and
material suppliers to substantiate the Contractor’s right to payment; or (3) to ascertain how the
Contractor has used money previously paid to the Contractor.
E. When requested by the Contactor or City, provide on-site recommendations on the extent and
type of deck repairs and joint armor replacement. Construction engineering and inspection will
be performed on an on-call basis and will be capped at a total of 120 hours.
F. When authorized by the Owner, prepare change orders for changes in the work from that
originally provided for in the construction contract documents. If redesign or substantial
engineering or surveying is required in the preparation of these change order documents, the
Owner will pay Garver an additional fee to be agreed upon by the Owner and Garver.
G. Participate in final project inspection, prepare punch list, review final project closing documents,
and review the final pay request.
Section 2.13 Lead Based Paint Testing will be added to the original contract SCOPE OF SERVICES
with the following items:
The services of Snyder Environmental shall be retained to perform a Lead Based Paint (LBP)
inspection of the bridge. Snyder Environmental shall complete an LBP inspection utilizing XRF (x-ray
fluorescence) on site by a ADEQ certified inspector. Snyder Environmental will provide a written
report detaining the findings of the inspection and offering recommendations for handling any
identified LBP.
APPENDIX B – GARVER FEE SPREADSHEETS
The Maximum Not to Exceed Amount will be increased $83,585 from $75,300 to $158,885 as shown
on the attached Appendix B Fee Summary Sheet – Amendment No. 1.
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Molly Rawn
Mayor
6/2/2026
Kara Paxton-City Clerk Treasurer
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Appendix B
Title I Service Estimated Fees No. 1 Fees Totals
Environmental Handling / Documentation
Conceptual Design $ 14,490.00
Final Design $ 46,430.00 $ 31,000.00
Bidding Services
Subtotal for Title I Service $ 75,300.00 $ 40,885.00 $ 116,185.00
Title II Service
Estimated Fees No. 1 Fees Totals
Construction Phase Services $ 42,700.00 $ 42,700.00
Subtotal for Title II Service
Total All Services 75,300.00$ 83,585.00$ 158,885.00$
L:\2015\15047010 - Lake Sequoyah Bridge Improvements\Contracts\Client\Draft\Amendment No. 1 - CPS\2026-04-30 Appendix B - Amendment No, 1
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Appendix B
City of Fayetteville
Lake Sequoyah Bridge Rehabilitation
FINAL DESIGN
WORK TASK DESCRIPTION E-6 E-5 E-4 E-3 E-2 E-1 T-3
$342.00 $278.00 $229.00 $196.00 $162.00 $147.00 $157.00
hr hr hr hr hr hr hr
1.Structural Engineering
Bridge Repair Alternative Study
Develop Alternatives (3)24 24
Alternative 8 16
Coordination/Meetings with City 2 16
Rebid #1 8 4
Rebid #2 14 4 6
Rebid #3 14 4 6
Subtotal - Structural Engineering 2 14 70 0 48 0 16
Hours 2 14 70 0 48 0 16
Salary Costs $684.00 $3,892.00 $16,030.00 $0.00 $7,776.00 $0.00 $2,512.00
SUBTOTAL - SALARIES: $30,894.00
DIRECT NON-LABOR EXPENSES
Travel Costs $106.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES:$106.00
SUBTOTAL:$31,000.00
SUBCONSULTANTS FEE:$0.00
TOTAL FEE:$31,000.00
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Appendix B
City of Fayetteville
Lake Sequoyah Bridge Rehabilitation
BIDDING
WORK TASK DESCRIPTION E-6 E-5 E-4 E-3 E-2 E-1 T-3
$342.00 $278.00 $229.00 $196.00 $162.00 $147.00 $157.00
hr hr hr hr hr hr hr
1. Civil Engineering
Addendums/RFIs 4
Pre-Bid Meeting and Preparation 3 3
Bid Opening 1 1
Prepare bid tabulation 1
Evaluate bids and recommend award 1
Prepare construction contracts 1 3
Subtotal - Civil Engineering 0 0 11 4 0 3 0
2.Structural Engineering
Addendums/RFIs 4
Rebid #1 4
Rebid #2 4
Rebid #3 4
Subtotal - Structural Engineering 0 4 12 0 0 0 0
Hours 0 4 23 4 0 3 0
Salary Costs $0.00 $1,112.00 $5,267.00 $784.00 $0.00 $441.00 $0.00
SUBTOTAL - SALARIES: $7,604.00
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $46.00
Postage/Freight/Courier $0.00
Travel Costs $50.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $96.00
TOTAL FEE: $7,700.00
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F
Appendix B
City of Fayetteville
Lake Sequoyah Bridge Rehabilitation
CONSTRUCTION PHASE SERVICES
WORK TASK DESCRIPTION E-6 E-5 E-4 E-3 E-2 E-1 C-3
$342.00 $278.00 $229.00 $196.00 $162.00 $147.00 $193.00
hr hr hr hr hr hr hr
1. Civil Engineering
Preconstruction Meeting 2
Progress Meetings with Contractor/City 12
Monthly Pay Requests 6 6
Construction Engineering and Inspection 2 2
Response to Inquiries 2
Final Project Inspection and Punchlist 2
Subtotal - Civil Engineering 0 24 0 10 0 0 0
2.Structural Engineering
Preconstruction Meeting 2
Shop Drawings/Material Submittals 12
Construction Engineering and Inspection 60 60
Response to Inquiries 2
Final Project Inspection and Punchlist 2
Subtotal - Structural Engineering 0 78 0 0 0 0 60
Hours 0 102 0 10 0 0 60
Salary Costs $0.00 $28,356.00 $0.00 $1,960.00 $0.00 $0.00 $11,580.00
SUBTOTAL - SALARIES: $41,896.00
DIRECT NON-LABOR EXPENSES
Travel Costs $804.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $804.00
SUBTOTAL: $42,700.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $42,700.00
Docusign Envelope ID: 56E3B042-A1E5-86AB-8350-9E8FDA398C3F