HomeMy WebLinkAbout90-97 RESOLUTION RESOLUTION NO. 9 0-9 7
SCAN FD
A RESOLUTION APPROVING CHANGE ORDER NO. 1 TO THE
ENGINEERING CONTRACT WITH RJN GROUP, INC. IN THE
AMOUNT OF $192,415 FOR SANITARY SEWER
REHABILITATION.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1. That the City Council hereby approves Change Order No. 1 to the engineering
contract with RJN Group,Inc. in the amount of$192,415 for sanitary sewer rehabilitation. A copy
of the change order is attached hereto marked Exhibit "A" and made a part hereof.
PASSED AND APPROVED this 16th day of September , 1997.
" r_E C i, APPROVED:
LPf..,,
f !"' �-ti, ' ` By:
,rr. • , * F ed Hanna, Mayor
ATTE•� .
B 4-04
Traci Paul, City Clerk
•4: • 4. y %fi)
L
Amendment No. 1 EXHIBIT A
WHEREAS, on the third day of December 1996 the City of
Fayetteville, Arkansas and RJN Group, Inc . made and entered into
a contract for Engineering Services related to sewer improvements
in the White River and Illinois River Watersheds and
WHEREAS, the Wastewater Collection System Master Plan
recently completed for the City of Fayetteville identified
several sewer segments in Basin 9 of the Illinois River Watershed
requiring capacity improvements to prevent sanitary sewer
overflows . The City of Fayetteville desires to proceed with
these improvements in conjunction with currently scheduled
improvements in Basin 9, the engineering services for the
original agreement may be modified to include these improvement .
WHEREAS, the City of Fayetteville and RJN Group, Inc .
desire to amend said Contract, so as to include therein the
necessary scope of work;
NOW THEREFORE, KNOW
ALL MEN BY THESE PRESENTS :
That the City of Fayetteville, a municipal corporation
situated in Washington County, Arkansas, hereinafter called
"City" and RJN Group, Inc . , hereinafter called "Engineer" , hereby
make and enter into the following agreement :
The December 3, 1996 contract between the City of
Fayetteville and RJN Group, Inc . is hereby amended to include
additional services required to provide final engineering design,
bidding services, and resident engineering services for the Basin
8 and Basin 9 sewers listed in Table 1, attached hereto and made
part of this Amendment No. 1 . A separate set of construction
documents will be provided. The contract entered into on
December 3, 1996 is hereby amended by increasing the cost not-
to-exceed ceiling in Section V, Fees and Payment to $627, 648 . A
revised schedule, Exhibit B, and Exhibit C is also attached
hereto and made part of this agreement . Also included is final
engineering design and resident engineering sercices for manhole
and sewer line rehabilitation on the University of Arkansas
campus . A total of 200 manholes are included. Sewer lines
scheduled for rehabilitation are given in Table 2 and Table 3 .
All other provisions, covenants, recitals, terms and
conditions of the Contract, which are not expressly amended
herein, shall remain in full force and effect .
June 23, 1997 -1-
IN WITNESS WHEREOF, the parties hereby have executed this agreement in
triplicate originals on this date, the /(ofA day of S cp f. , 1911.
RUN GROUP, INC. CITY OF FAYETTEVILLE
Firm Name
itaii41 .-.
Signt4 Signature
Regional Vice President Mayor
Title Title
ATTEST lr:d/'GA) ATTEST 4iiiieli . >Q6
c.;•1-y G/e.rls
,, ,;,etc 4► . -4 ..r.., r •0
\l1 1► ', :.. `, ,ij ':/t'
711 3 i
June 23, 1997 -2- CADATAWwrwancarrn,MPAYensIMs.,uu
•
EXHIBIT B
REVISED
AUTHORIZATION PROGRESS AND COMPLETION
The City and ENGINEER agree that the project is planned
to be completed according to the schedule below with anticipated
approval of Amendment in September 1997 .
Major Tasks Completion Date
Draft Manhole Rehabilitation Plans/Specs February 1997
Final Manhole Rehabilitation Plans/Specs September 1997
Draft Sewer Line Replacement/Repair Plans/Specs February 1998
Final Sewer Line Replacement/Repair Plans/Specs March 1998
Draft Sewer Lining Plans/Specifications September 1997
Final Sewer Lining Plans/Specifications October 1997
Bidding and Award
Manhole Rehabilitation October 1997
Sewer Line Replacement/Repair April 1998
Sewer Lining November 1997
Construction
Manhole Rehabilitation Winter 1997
Sewer Line Replacement/Repair Summer 1998
Sewer Lining Winter 1997
The ENGINEER shall employ manpower and other resources and use
professional skill and diligence to meet the schedule; however, he
shall not be responsible for schedule delays resulting from
conditions beyond his control . With mutual agreement, the City and
the ENGINEER may modify the project schedule during the course of
the project and if such modifications affect the ENGINEER' s
compensation, it shall be modified accordingly, subject to City
Council approval .
For Special Services, the authorization by the City shall be in
writing and shall include the definition of the services to be
provided, the schedule for commencing and completing the services
and the basis for compensation therefore, all as agreed upon by the
City and ENGINEER in writing.
June 23, 1997 B-1
•
EXHIBIT C
REVISED
SUMMARY OF COST
City of Fayetteville
Illinois River and White River Watersheds
Sewer Improvements
Unit
Task Description Cost Cost
Engineering Design. Bidding and Resident Engineering
I . Final Engineering Design
A. Project Administration LS $ 10, 000
B. Basic Design Services LS 163 , 980
B. 1 Basic Design Services Basin 8 & 9 LS 68, 200
B.2 Manhole Rehab Design (U of A) LS 10, 025
B.3 Sewer Replacement/Point Repairs LS 21, 850
U of A
C. Additional Services (if required)
1 . Geotechnical Investigation $300/EA 600
(2 Borings)
2 . Easement Survey $350/EA 1, 750
(5 Easements)
3 . Railroad and State Permits LS 2, 000
4 . Cleaning and Televising $3 .50/LF 7, 228
(2, 065 LF)
D. Bidding Assistance
1 . Manhole Rehabilitation LS 5, 290
2 . Sewer Line Rehabilitation LS 5, 870
3 . Sewer Lining LS 5, 870
II . Resident Engineering
A. Manhole Construction (City) T&M1' 125, 420
(Based on 1, 640 inspector manhours)
B. Sewer Line Construction/Repairs T&M1/ 49, 355
(Based on 490 inspector manhours)
C. Sewer Lining T&M1/ 57, 870
(Based on 620 inspector manhours)
D. Basin 8 and 9 Sewer Improvements T&MIJ 51, 240
(Based on 600 inspector manhours)
E. Manhole Construction (U of A) T&M1' 27, 060
F. Sewer Line Construction Repairs T&M1' 14, 040
(U of A)
Total Cost Not-to-Exceed $627, 648
June 23, 1997 C-1
•
REVISED
EXHIBIT:C (Cont . )
Unit
Task Description Cost Cost
Optional Services
I . Cleaning Program
A. Prepare Bidding Documents LS $ 8, 600
B. Bidding Assistance LS 2, 200
C. Cleaning Observation T&M1' 17. 640
$28, 440
1/ To be performed on a time and expense basis . Personnel charge
out rates are Principal ($113/hr) , Senior Engineer ($90/hr) ,
Project Engineer ($65/hr) , Resident Project Representative
($50/hr) , Draftsperson ($55/hr) , Construction Resident
Engineer ($65/hr) , Field Survey Leader ($40/hr) , Field
Technician ($30/hr) , Office/Clerical ($33/hr) , Field Manager
($55/hr) .
June 23, 1997 C-2
•
Table 1
Required
Upstream Downstream Diameter Length Capacity
Manhole Manhole (in) (lf) (gpd)
I-(08)001 I-(06)042 15 128 10,861,783
I-(08)002 I-(08)001 15 392 2,545,986
I-(08)003 I-(08)105 15 113 2,052,800
I-(08)038 I-(08)002 15 8 2,138,050
I-(08)051 I-(08)038 15 391 2,138,050
I-(08)055 I-(08)051 15 183 2,028,332
I-(08)062 I-(08)055 15 280 2,028,332
I-(08)063 I-(08)062 15 200 2,342,116
I-(08)066 I-(08)063 15 38 2,342,116
I-(08)071 I-(08)066 15 70 2,342,116
I-(08)072 I-(08)071 15 145 2,138,050
I-(08)076 I-(08)072 15 88 2,138,050
I-(08)077 I-(08)076 15 135 2,342,116
I-(08)078 I-(08)077 15 43 2,028,332
I-(08)105 I-(08)002 15 53 2,052,800
I-(09)001 I-(08)078 15 342 2,028,332
I-(09)002 I-(09)001 15 161 2,028,332
I-(09)087 I-(09)086 15 361 2,508,909
I-(09)088 I-(09)087 15 434 2,482,349
I-(09)089 I-(09)088 15 384 1,979,285
I-(09)090 I-(09)089 15 170 3,688,988
I-(09)091 I-(09)090 15 39 2,396,143
I-(09)092 I-(09)091 15 40 1,690,277
I-(09)093 I-(09)092 15 401 1,711,776
I-(09)096 I-(09)093 15 347 1,492,046
I-(09)097 I-(09)096 15 237 1,761,784
I-(09)098 I-(09)097 15 7 1,400,382
I-(09)099 I-(09)098 15 129 1,629,693
I-(09)105 I-(09)104 12 240 2,933,885
June 23, 1997 C:(DATA\VVPWQ!\CCNTAAC WAYFn8111S .AM1
Table 2
SUMMARY OF RECOMMENDED
POINT REPAIRS
Estimated
Construction
Cost
Segment Diameter Repair Location ($)
(18A)023-(18A)022 12 0+70 - 0+90v 4,000
(18A)089-(18A)046 6 0+00 - 0+70v 6,000
(13B)011-(13B)010 10 0+05 - 0+15v 4,000
(13B)011-(13B)010 10 0+05 - 0+85v 4,500
(13B)012-(13B)011 10 0+05 - 0+10v 3,500
(13B)012-(13B)011 10 0+85 - 1+00v 4,000
(13B)012-(13B)011 10 1+65 - 1+7521 4,000
(13B)085-(13B)084 8 0+10 - 0+20v 4,000
(13B)119-(13B)118 6 0+00 - 0+8021 6,500
Total 40,500
1/ Stationing is from upstream manhole.
2/ Stationing is from downstream manhole.
June 23, 1997 CADATAMYVRAO0NTRACIWAYHRHMJ!SI.AM1
Table 3
RECOMMENDED COMPLETE REPLACEMENT BASED
ON MAINTENANCE DEFECTS AND I/I REMOVAL
Estimated
Existing Replacement Construction
Diameter DiameterU Length Cost
Line Segment (in) (in) elf) ($)
(18A)018-(18A)072 12 12 113 9,605
(18A)024-(18A)023 12 12 90 7,650
(18A)071-(18A)017 12 12 150 12,750
(18A)072-(18A)017 10 10 109 8,720
(18A)075-(18A)069 6 8 61 4,575
(13B)031-(13B)030 10 10 205 16,400
(13B)034-(13B)032 8 8 80 6,000
(13B)037-(13B)174 8 8 170 12,750
(13B)049-(13B)179 8 8 195 14,625
(13B)151-(13B)150 8 8 270 20,250
(13B)206-(13B)205 6 8 255 19,125
Total 1,698 119,700
1/ During final design, replacement diameter should be verified based on projected loading.
2/ Unit costs used for each pipe diameter are $75/1f for 8", $80/lf for 10", and $85/lf for 12".
June 23, 1997 ckoArAwnve eorrrxkmmreneussA.,wi