HomeMy WebLinkAbout111-26 RESOLUTION
Page 1
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 111-26
File Number: 2026-1383
A RESOLUTION TO AMEND THE PROFESSIONAL ENGINEERING SERVICES CONTRACT WITH
GARVER, LLC FOR ADDITIONAL DESIGN SERVICES IN THE AMOUNT OF $88,050.00 TO CONTINUE
ENGINEERING DESIGN ON THE PLAINVIEW AND ROLLING HILLS EXTENSION PROJECT
WHEREAS, a 2019 bond program project to connect Appleby Drive, Rolling Hills Drive, and Plainview Avenue
through the Fiesta Square Shopping Center was stalled due to property acquisition issues; and
WHEREAS, the project was modified to remove the southern portion of the project and a contract amendment is
intended to provide funds for the additional design services associated with the modification.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign an
Amendment to the Professional Engineering Services Contract with Garver, LLC in the amount of $88,050.00 for
additional engineering design services associated with the Plainview and Rolling Hills Extension Project.
PASSED and APPROVED on May 5, 2026
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-1383
MEETING OF MAY 5, 2026
TO: Mayor Rawn and City Council
THROUGH: Chris Brown, Public Works Director
Keith Macedo, Chief of Staff
FROM: Justin Bland, City Engineer
SUBJECT: Plainview Avenue/Rolling Hills Connection – Contract Amendment with Garver
RECOMMENDATION:
Staff recommends approval of a design contract Amendment with Garver in the amount of $88,050 for
additional design services on the Plainview and Rolling Hills Extension Project.
BACKGROUND:
This is a 2019 bond program project that was originally intended to connect Appleby Drive, Rolling Hills Drive,
and Plainview Avenue through the Fiesta Square Shopping Center. The project was stalled due to property
acquisition issues and was modified to remove the southern portion of the project. Design of the project has
begun moving forward, and construction is planned for later this year.
DISCUSSION:
The project revisions have resulted in additional design efforts by Garver. They have provided a proposed
contract amendment in the amount of $88,050 for these additional design services. Detail of this amendment is
attached.
BUDGET/STAFF IMPACT:
These fees will be paid from the 2019 bond program funds.
ATTACHMENTS: 3. Staff Review Form, 4. Appendix A - Garver Scope of Services- Amend #1
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-1383
A RESOLUTION TO AMEND THE PROFESSIONAL ENGINEERING SERVICES
CONTRACT WITH GARVER, LLC FOR ADDITIONAL DESIGN SERVICES IN THE
AMOUNT OF $88,050.00 TO CONTINUE ENGINEERING DESIGN ON THE PLAINVIEW
AND ROLLING HILLS EXTENSION PROJECT
WHEREAS, a 2019 bond program project to connect Appleby Drive, Rolling Hills Drive, and
Plainview Avenue through the Fiesta Square Shopping Center was stalled due to property acquisition
issues; and
WHEREAS, the project was modified to remove the southern portion of the project and a contract
amendment is intended to provide funds for the additional design services associated with the
modification.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign an Amendment to the Professional Engineering Services Contract with Garver, LLC in the amount
of $88,050.00 for additional engineering design services associated with the Plainview and Rolling Hills
Extension Project.
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Comments:
Purchase Order Number:
Change Order Number:
Previous Ordinance or Resolution #158-20
Approval Date:
Original Contract Number:
46020.7221.1000
Project Number
Budget Impact:
Appleby/Rolling Hills/Plainview Connection
Fund
4602 - Streets Project 2019 Bonds4602.860.7221-5860.02
Account Number
Project Title
City of Fayetteville Staff Review Form
2026-1383
Legistar File ID
5/5/2026
City Council Meeting Date - Agenda Item Only
Staff recommends approval of a design contract Amendment with Garver in the amount of $88,050 for additional
design services on the Plainview and Rolling Hills Extension Project.
N/A for Non-Agenda Item
Action Recommendation:
Submitted By
Sara Combs ENGINEERING (621)
Division / Department
4/15/2026
Submitted Date
Yes
207,581.55$
88,050.00$
Must Attach Completed Budget Adjustment!
V20180321
Budgeted Item?
Does item have a cost?
Budget Adjustment Attached?
Current Budget
Funds Obligated
Current Balance
Item Cost
Budget Adjustment
Remaining Budget
1,394,635.00$
1,187,053.45$
Yes
No -$
119,531.55$
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Appendix A- Scope of Services
Amend. No. 1 1 of 2 Plainview Avenue Extension
APPENDIX A – SCOPE OF SERVICES
AMENDMENT NO. 1
1. General
Generally, the scope of services includes revising final plans and property acquisition documents as
required to redesign the roundabout as a mini-roundabout at the intersection of the existing Fiesta
Square entrance with the new roadway. The revisions also include changing the alignment of the
proposed Plainview Avenue and adding a right turn lane between the proposed mini-roundabout and
the College Avenue intersection. These changes will result in updated designs for roadway,
landscaping, electrical, traffic signal, water and sewer relocations, and preparation of revised property
acquisition documents
The following Section 11 – Final Design for Amendment No. 1 shall be added to the previously
approved Section 11 – Final Design.
11. Final Design
11.1. Signalization Design
The revised signal design and plans will include the following:
• A dedicated right turn only lane to turn southbound onto College Ave. from new roadway
to roundabout
• Signal pole layout revision for poles B & C (pedestrian pushbuttons) for ADA compliance
• Verify proper signal head alignment
• Updates to Detector Chart, Interval Chart, and Phasing
• Quantity Updates
• 90% plan submittal for client review and comment then Final Revised Plans
11.2. Mini-Roundabout Final Design (90% & 100%)
Garver will revise the Final Design plans to incorporate the changes to the alignment and roundabout.
During the final design phase of the project, Garver will conduct final designs to prepare construction
plans and specifications, for one construction contract, including final construction details and
quantities, special provisions, and opinion of probable construction cost. Garver will also provide final
coordination with Owner, make any needed plan changes as a result of the final review comments
and/or special easement acquisition considerations, and prepare the construction documents as
required to advertise for bids.
The following design items shall be revised:
• Horizontal and Vertical Alignments
• Roadway Model
• Drainage Design
• Lighting Layout
The following plan sheets shall be revised:
• Typical Sections
• Maintenance of Traffic Plans
• Pavement Marking and Striping Plans
• Demolition Plans
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Appendix A- Scope of Services
Amend. No. 1 2 of 2 Plainview Avenue Extension
• Cross Sections
• Drainage Plans and Profiles
• Survey Control Plans
• Roundabout Layout Plans
• Roundabout Grading Plans
• Erosion Control Plans
• Landscaping Plans
11.3. Utility Potholing (Crossland)
Garver will subcontract with Crossland Heavy Construction to perform subsurface potholing for up to
eight (8) locations to develop accurate locations and depth information for underground utilities and
confirm conflicts and required utility relocations.
11.4. Water and Sewer Plans
Garver will revise water and sewer line design per previous City comments and from the findings of the
utility potholing. Water/Sewer plan and profile sheets will be revised as required to accommodate
changes to design.
The following Section 12 – Property Acquisition Documents for Amendment No. 1 shall be
added to the previously approved Section 12 - Property Acquisition Documents.
12. Property Acquisition Documents
Revised Property Acquisition Documents
Garver will develop updated individual tract maps with description of temporary and permanent
acquisition for each property affected by the changes to the roadway alignment and roundabout. The
Owner will provide a standard easement acquisition document or “go-by” example for use by Garver.
The fee for providing property acquisition documentation is based on permanent right of way and
temporary construction easements for no more than 3 properties.
Garver will stake ROW/easements up to one (1) time as requested by the City.
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Exhibit B - Amendment No. 1
City of Fayetteville
Plainview Avenue Extension
FEE SUMMARY
Title I Service
Original
Estimated Fees
Amendment No. 1
Estimated Fees
Total Estimated
Fees
Geotechnical Services (Terracon)5,400.00$ 5,400.00$
Record Research 5,400.00$ 5,400.00$
Utility Markings (ARKUPS)400.00$ 400.00$
Environmental Handling/Documentation 2,800.00$ 2,800.00$
Traffic Studies 19,700.00$ 19,700.00$
H&H Study 23,650.00$ 23,650.00$
Signalization Design 28,260.00$ $ 9,100.00 37,360.00$
Surveys 49,870.00$ 49,870.00$
Conceptual Design 66,820.00$ 66,820.00$
Preliminary Design 87,850.00$ 87,850.00$
Preliminary Design - Electrical 9,000.00$ 9,000.00$
Final Design 77,100.00$ 77,100.00$
Final Design - Electrical 5,120.00$ 5,120.00$
Property Acquisition Documents 16,450.00$ $ 9,000.00 25,450.00$
Bidding Services 4,830.00$ 4,830.00$
Mini- Roundabout Final Design (90%/100%) $ 35,200.00 35,200.00$
Final Design - Water & Sewer Relocations $ 24,750.00 24,750.00$
Utility Potholing (Subconsultant) $ 10,000.00 10,000.00$
Subtotal for Title I Service 402,650.00$ 88,050.00$ 490,700.00$
Title II Service
Original
Estimated Fees
Amendment No. 1
Estimated Fees
Total Estimated
Fees
Construction Phase Services -$ -$ -$
Subtotal for Title II Service -$ -$ -$
Total All Services 402,650.00$ 88,050.00$ 490,700.00$
L:\2020\20T21040 - Fayetteville Plainview Avenue Extension\Contracts\Client\Draft\Amendment No. 1\2026-03-06 Exhibit B - Garver Fee Spreadsheet - Amend #1
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Exhibit B - Amendment No. 1
City of Fayetteville
Plainview Avenue Extension
REVISED SIGNALIZATION DESIGN
WORK TASK DESCRIPTION E-6 E-5 E-3 E-1 T-1
$320.00 $261.00 $183.00 $140.00 $105.00
hr hr hr hr hr
1. Phase
Pedestrain Push Button Pole Layout Revision 2 4
Verify signal head alignment 2 2 2
Detector Chart, Interval Chart, and Phasing Updates 2 8 4
Quantity Revisions 1 2 2
90% Revised Plans Submittal Review Comments 2 2 4
Final Revised Plans 2 2 4 2
QA/QC 1 1
Subtotal - Phase 1 12 12 20 6
Hours 1 12 12 20 6
Salary Costs $320.00 $3,132.00 $2,196.00 $2,800.00 $630.00
SUBTOTAL - SALARIES: $9,078.00
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $22.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $22.00
SUBTOTAL: $9,100.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $9,100.00
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Exhibit B - Amendment No. 1
City of Fayetteville
Plainview Avenue Extension
PROPERTY ACQUISITION DOCUMENTS
WORK TASK DESCRIPTION E-1 S-5 S-2 2-Man Crew (Survey) 2-Man Crew (GPS Survey)
$140.00 $207.00 $85.00 $243.00 $307.00
hr hr hr hr hr
1. Acquisition Documents
Coordination and Administration 1 1
Permanent Right-of-Way Acquisition Documents 4 8
Temporary Construction Easements 4 8
Stake Proposed Easement (Maximum 6-Parcels)8 6 8
Subtotal - Acquisition Documents 1 17 16 6 8
Hours 1 17 16 6 8
Salary Costs $140.00 $3,519.00 $1,360.00 $1,458.00 $2,456.00
SUBTOTAL - SALARIES: $8,933.00
DIRECT NON-LABOR EXPENSES
Travel Costs $67.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $67.00
SUBTOTAL: $9,000.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $9,000.00
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Exhibit B - Amendment No. 1
City of Fayetteville
Plainview Avenue Extension
MINI- ROUNDABOUT FINAL DESIGN (90%/100%)
WORK TASK DESCRIPTION E-5 E-2 E-1 T-2 E-4 E-1 P-2
$261.00 $164.00 $140.00 $122.00 $214.00 $140.00 $217.00
hr hr hr hr hr hr hr
1. Project Management
Administration and Coordination 4
Subtotal - Project Management 4 0 0 0 0 0 0
2. Civil Engineering
Revise Horizontal and Vertical Alignments 1 4
Revise Roadway Model 1 4
Revise Drainage Design 1 4
Revise Typical Sections 1 4 4
Revise Maintenance of Traffic Plans 2 4 4
Revise Pavement Marking and Striping Plans 2 4 2
Revise Demolition Plans 2 2 2
Revise Cross Sections 1 4 4
Revise Drainage Plan and Profiles 1 6 4
Revise Survey Control Plans 1 2 2
Revise Driveway Plans 1 2 2
Revise Roundabout Layout Plans 4 4 4
Revise Roundabout Grading Plans 4 6 4
Revise Erosion Control Plans 2 4 4
Revise Landscaping Plans 2 20
Coordination with Utility Companies 2 4
Coordination and Meetings with Owner 2 2
Coordination with Property Owners 2 2
SWPPP/Coordination with DEQ 1 6 6
Specifications/Contract Documents 6 4 1 1
Quantities 4 8 1
Opinion of Probable Construction Cost 4 4 1
Quality Control Review 4 2
Address City Comments on 90%8 8 8
Subtotal - Civil Engineering 8 53 82 50 5 23 6
Hours 12 53 82 50 5 23 6
Salary Costs $3,132.00 $8,692.00 $11,480.00 $6,100.00 $1,070.00 $3,220.00 $1,302.00
SUBTOTAL - SALARIES: $34,996.00
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $204.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $204.00
SUBTOTAL: $35,200.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $35,200.00
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Exhibit B - Amendment No. 1
City of Fayetteville
Plainview Avenue Extension
FINAL DESIGN - WATER & SEWER RELOCATIONS
WORK TASK DESCRIPTION E-5 E-4 E-1 T-2
$261.00 $214.00 $140.00 $122.00
hr hr hr hr
2. Civil Engineering
Revise Water Line Horizontal Alignments 8 12
Revise Sewer Line Horizontal Alignments 8 12
Plan & Profile Sheets 8 30 16
Detail Sheets 1 2
ADH Permitting 4 8
Coordination with Utility Companies 2
Coordination and Meetings with Owner 6
Submittals to Owner 2 2
Measurement and Payment Specs 8
Quantities 1 6
Opinion of Probable Construction Cost 4
Quality Control Review 4
Subtotal - Civil Engineering 4 52 72 16
Hours 4 52 72 16
Salary Costs $1,044.00 $11,128.00 $10,080.00 $1,952.00
SUBTOTAL - SALARIES: $24,204.00
DIRECT NON-LABOR EXPENSES
Document Printing/Reproduction/Assembly $31.00
ADH Permitting $515.00
SUBTOTAL - DIRECT NON-LABOR EXPENSES: $546.00
SUBTOTAL: $24,750.00
SUBCONSULTANTS FEE: $0.00
TOTAL FEE: $24,750.00
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370