HomeMy WebLinkAbout110-26 RESOLUTION
Page 1
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 110-26
File Number: 2026-1350
A RESOLUTION TO AWARD RFQ #26-01, SELECTION #2 AND AUTHORIZE THE PURCHASE OF ON-
CALL SURVEYING SERVICES FROM CRAFTON TULL, HAWKINS-WEIR ENGINEERS, INC., AND
GARVER, INC. AS NEEDED THROUGH APRIL 30, 2027, WITHIN THE APPROVED BUDGET
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby awards RFQ #25-01 Selection #2 and
authorizes the purchase of on-call surveying services from Crafton Tull, Hawkings-Weir Engineers, Inc., and Garver,
Inc. for the rates attached to this Resolution and based on availability as needed through April 30, 2027, within the
approved budget.
PASSED and APPROVED on May 5, 2026
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-1350
MEETING OF MAY 5, 2026
TO: Mayor Rawn and City Council
THROUGH: Chris Brown, Public Works Director
FROM: Justin Bland, City Engineer
SUBJECT: Approval of a resolution to award RFQ 26-01, Selection #2 to Crafton Tull, Hawkins-
Weir Engineers, Inc. and Garver as primary providers based on rates provided and
availability for on-call surveying services as needed through April 30, 2027.
RECOMMENDATION:
Approval of a resolution to award RFQ 26-01, Selection #2 to Crafton Tull, Hawkins-Weir Engineers, Inc. and
Garver, Inc. as primary providers based on rates provided and availability for on-call surveying services as
needed through April 30, 2027.
BACKGROUND:
The Engineering Division has a two-person survey crew as part of the design team. The survey crew provides
surveying services to multiple City Divisions in addition to the surveys needed for the in-house projects
designed by the City engineers. As a result, the current workload for the survey crew is quite large. With the
potential for many projects to begin in 2026, additional surveying services may be required.
DISCUSSION:
An engineering selection committee selected Crafton Tull, Hawkins-Weir Engineers, Inc. and Garver to be
used for on-call surveying services for various city projects until April 30, 2027.
BUDGET/STAFF IMPACT:
Funds for the project surveying have been budgeted in various capital projects with the Sales Tax Capital
Improvements Fund, the Transportation Bond Fund, Drainage Bond Fund and the Water and Sewer Fund.
ATTACHMENTS: 3. Staff Review Form, 4. Garver Fee Sheet, 5. Crafton Tull Fee Sheet, 6. HW Fee Sheet
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-1350
A RESOLUTION TO AWARD RFQ #26-01, SELECTION #2 AND AUTHORIZE THE
PURCHASE OF ON-CALL SURVEYING SERVICES FROM CRAFTON TULL, HAWKINS-
WEIR ENGINEERS, INC., AND GARVER, INC. AS NEEDED THROUGH APRIL 30, 2027,
WITHIN THE APPROVED BUDGET
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby awards RFQ #25-01
Selection #2 and authorizes the purchase of on-call surveying services from Crafton Tull, Hawkings-
Weir Engineers, Inc., and Garver, Inc. for the rates attached to this Resolution and based on availability
as needed through April 30, 2027, within the approved budget.
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
4/10/2026
Submitted Date
No
-$
V20221130
Budgeted Item?
Does item have a direct cost?
Is a Budget Adjustment attached?
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
No
No -$
-$
Project Number
Budget Impact:
FundAccount Number
Project Title
City of Fayetteville Staff Review Form
2026-1350
Item ID
5/5/2026
City Council Meeting Date - Agenda Item Only
Approval of a resolution to award RFQ 26-01, Selection #2 to Crafton Tull, Hawkins-Weir Engineers, Inc. and Garver
as primary providers based on rates provided and availability for on-call surveying services as needed through April
30, 2027.
N/A for Non-Agenda Item
Action Recommendation:
Submitted By
Sara Combs ENGINEERING (621)
Division / Department
Comments:
Purchase Order Number:
Change Order Number:
Previous Ordinance or Resolution #
Approval Date:
Original Contract Number:
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Rates Rates
Engineers / Architects Resource Specialists
E-1 146.00$ RS-1 120.00$
E-2 171.00$ RS-2 159.00$
E-3 191.00$ RS-3 214.00$
E-4 223.00$ RS-4 309.00$
E-5 272.00$ RS-5 386.00$
E-6 333.00$ RS-6 475.00$
E-7 475.00$ RS-7 517.00$
Planners Environmental Specialists
P-1 181.00$ ES-1 119.00$
P-2 226.00$ ES-2 151.00$
P-3 270.00$ ES-3 194.00$
P-4 316.00$ ES-4 219.00$
P-5 347.00$ ES-5 277.00$
ES-6 367.00$
Designers ES-7 449.00$
D-1 135.00$ ES-8 507.00$
D-2 150.00$
D-3 186.00$ Project Controls
D-4 217.00$ PC-1 122.00$
D-5 267.00$ PC-2 163.00$
D-6 282.00$ PC-3 206.00$
PC-4 265.00$
Technicians PC-5 324.00$
T-1 110.00$ PC-6 418.00$
T-2 127.00$ PC-7 511.00$
T-3 161.00$
T-4 202.00$ Management / Administration
AM-1 86.00$
Surveyors AM-2 108.00$
S-1 67.00$ AM-3 152.00$
S-2 89.00$ AM-4 188.00$
S-3 120.00$ AM-5 242.00$
S-4 165.00$ AM-6 299.00$
S-5 216.00$ AM-7 393.00$
S-6 246.00$ M-1 574.00$
S-7 299.00$
S-8 368.00$
2-Man Crew (Survey) 253.00$
3-Man Crew (Survey) 318.00$
2-Man Crew (GPS Survey) 320.00$
3-Man Crew (GPS Survey) 388.00$
Construction Observation
C-1 126.00$
C-2 159.00$
C-3 198.00$
C-4 247.00$
C-5 305.00$
Agreement for Professional Services
Fayetteville 2026 On-Call Surveying Garver Project No. 2600000
Garver Hourly Rate Schedule: July 2026 - June 2027
Classification Classification
Exhibit B
City of Fayetteville
Fayetteville 2026 On-Call Surveying
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Effective January 1, 2026
Hourly Hourly
Category Rate Category Rate
ENGINEERING LANDSCAPE ARCHITECTURE
ENGINEERING PRINCIPAL ……....………..……………………..270$ VICE PRESIDENT OF LANDSCAPE ARCHITECTURE …..........220$
SR. ENGINEERING MANAGER ……………...……………...……240$ SR. LANDSCAPE ARCHITECTURE PROJECT MANAGER …............................................195$
ENGINEERING MANAGER ………………….……………....……..210$ LANDSCAPE ARCHITECTURE PROJECT MANAGER …..............................................................180$
SR. PROJECT ENGINEER …………………….…………...…….180$ SR. LANDSCAPE ARCHITECT ………………..…………………..170$
PROJECT ENGINEER …………………………..…………..…….160$ PROJECT LANDSCAPE ARCHITECT ………....………………..155$
ENGINEER INTERN III ………………………..………….………..145$ LANDSCAPE DESIGNER III …………………...……….................125$
ENGINEER INTERN II …………………………..………..………..135$ LANDSCAPE DESIGNER II …………………………...................115$
ENGINEER INTERN I …………………………..………….……….125$ LANDSCAPE DESIGNER I …………………………......................100$
SR. ENGINEERING DESIGNER ……………..…………..………..165$ LANDSCAPE DESIGN INTERN …………………………....................80$
ENGINEERING DESIGNER III ………………..…………..……….130$ LANDSCAPE CAD TECHNICIAN II …………………………....................85$
ENGINEERING DESIGNER II ………………..…………..………..110$ LANDSCAPE CAD TECHNICIAN I …………………………....................75$
ENGINEERING DESIGNER I …………………..………..…………100$ SURVEYING
ENGINEERING CAD TECHNICIAN III ……..……………………..95$ SURVEYING PRINCIPAL ………………………………….............250$
ENGINEERING CAD TECHNICIAN II ……….………..…………..85$ SR. SURVEYING MANAGER ………………………………..………215$
ENGINEERING CAD TECHNICIAN I ………..……….……………75$ SURVEYING MANAGER …………………………….....................190$
ENVIRONMENTAL SR. PROJECT SURVEYOR ………………………………….........165$
SR. ENVIRONMENTAL MANAGER …………….……..………….220$ PROJECT SURVEYOR ……………………………………….........145$
ENVIRONMENTAL MANAGER …………………..……........…….185$ SURVEYOR INTERN II ………………………………………..…….125$
SR. ENVIRONMENTAL SCIENTIST ……………..…...………….155$ SURVEYOR INTERN I …………………………………………..….110$
PROJECT ENVIRONMENTAL SCIENTIST ……..……........……125$ SURVEY COORDINATOR …………………………………….……120$
ENVIRONMENTAL SCIENTIST II ………………..……...……….100$ CREW CHIEF II ………………………………………………..........110$
ENVIRONMENTAL SCIENTIST I ………………..………....…….80$ CREW CHIEF I ………………………………………………….......95$
ENVIRONMENTAL FIELD TECHNICIAN …..…………………….65$ FIELD SURVEYOR III …………………………………………........85$
INSPECTION FIELD SURVEYOR II …………………………………………...…...75$
INSPECTION MANAGER …........................................................140$ FIELD SURVEYOR I ……………………………………………......65$
SR. INSPECTOR ………………………………...…..……………..120$ SURVEY CAD TECHNICIAN III ………………………………..…..110$
INSPECTOR II ………………………………...….………………….100$ SURVEY CAD TECHNICIAN II ………………………………...…..90$
INSPECTOR I …………………………………....………………….80$ SURVEY CAD TECHNICIAN I ………………………………...…….80$
UAV SERVICES GEOGRAPHIC INFORMATION SYSTEMS
UAV TEAM LEAD ………………………………...……………........125$ SR. GIS MANAGER ………………………………………………..180$
UAV PILOT ………………………………………...………………....85$ GIS MANAGER ………………………………………….....………..145$
ADMINISTRATIVE GIS ANALYST …………………...………………………....………..110$
ADMINISTRATIVE PRINCIPAL ………………...………………….240$ GIS TECHNICIAN II ……………………………………..……………85$
ADMINISTRATIVE MANAGER ………………...…………………..180$ GIS TECHNICIAN I …………………………………….…………….65$
ADMINISTRATIVE IV ………………………....……………………..120$ REIMBURSABLE EXPENSES
ADMINISTRATIVE III …………………………...…………………..95$ GPS Equipment………...….....….……............…..….....…....$35/Hour
ADMINISTRATIVE II ……………………...……...…………………..70$ Robotic Survey Equipment…….……….........…….............…$20/Hour
ADMINISTRATIVE I ……………………………...………………….55$ Bathymetric Survey Equipment …………..….................…...$35/Hour
PLANNING LiDAR Scanning Equipment …………..…..................….…..$35/Hour
PLANNING PRINCIPAL …...........................................................250$ UAV ……………………………….............……….…..…...…$1000/Unit
SR. PLANNING MANAGER …………………………………...…..220$ Job Related Mileage………...........................................…...$0.72/Mile
PLANNING MANAGER ……………………………………….........210$ Per Diem for Out of Town Crews…...…................Per GSA Allowable
SR. PLANNER …………………………………………………...…..170$ Airfare and other travel related expenses……….................….At Cost
PROJECT PLANNER …………………………………………........130$ Black and white 8.5"x11" Copies ….……......................... $0.15/sheet
PLANNER III …………………………………………………….…....120$ Color 8.5"x11" Copies …….……....……..................….…. $1.50/sheet
PLANNER II ……………………………………………………..….....110$ Photo Paper Color Plan Sheet Copies ……..................... $0.75/sq. ft.
PLANNER I ………...…………………………………………...……..100$ Reproducible Plan Copies (Vellum) …...…....................... $1.50/sq. ft
Reproducible Plan Copies (Bond) ……........................…. $0.35/sq. ft.
All rates are subject to change without notice.
Exhibit "B"
Standard Hourly Rate Schedule
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Hawkins-Weir Engineers, Inc.
Hourly Rate Schedule: 2026
Description Billing Rate/Hour
Engineer VII $275
Engineer VI $250
Engineer V $225
Engineer IV $200
Engineer III $175
Engineer II $150
Engineer I $125
Environmental Specialist II $130
Environmental Specialist I $110
$145
$135
$120
$100
$90
$150
$145
$135
$125
$135
$125
Designer III
Designer II
Designer I
Civil Eng. Assistant II
Civil Eng. Assistant I
Digital Design Manager
BIM Modeler III
BIM Modeler II
BIM Modeler I
CAD/GIS Technician III
CAD/GIS Technician II
CAD/GIS Technician I $115
Construction Manager II $150
Construction Manager I $130
Construction Observer IV $140
Construction Observer III $120
Construction Observer II $110
Construction Observer I $100
Surveyor $175
GPS Survey $200
Survey Technician $50
Business Manager $100
Graphic Designer $100
Administrative $75
Reimbursable Expenses
Mileage $0.77/mile
Printing @ Cost
Travel @ Cost
Expert Witness Rate x 2.0
Other Direct Costs @ Cost
Notes:
1.Hourly rates may be equitably adjusted
2. Adjustment to rate schedule will not change contract lump sum or NTE amounts
3.If a conflict exists, hourly rates & reimbursable expenses will be invoiced per terms of Agreement.
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370