Resolution: 107-26
File Number: 2026-1257
A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 WITH SOUTHERN BROTHERS
CONSTRUCTION IN THE AMOUNT OF $37,950.00 FOR ADDITIONAL CONCRETE WORK ON THE
RECYCLING AND TRASH COLLECTIONS COMPOST PAD
WHEREAS, on January 6, 2026, City Council approved Resolution 19-26 authorizing a contract with Southern
Brothers Construction for concrete repairs to the Recycling and Trash Collections compost pad and recycling
processing facility baler pit; and
WHEREAS, during demolition of the compost pad, it was discovered that the existing concrete was thicker than
anticipated, and other field conditions resulted in unanticipated work for the contractor; and
WHEREAS, Change Order No. 1 will provide for additional concrete paving and concrete repairs.
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign Change
Order No. 1 to the contract with Southern Brothers Construction in the amount of $37,950.00 for additional concrete
work on the Recycling and Trash Collections compost pad.
PASSED and APPROVED on May 5, 2026
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-1257
MEETING OF MAY 5, 2026
TO: Mayor Rawn and City Council
THROUGH: Keith Macedo, Chief of Staff
FROM: Peter Nierengarten, Environmental Director
SUBJECT: Approval of a reconciliation change order with Southern Brothers Construction
RECOMMENDATION:
Staff recommends the approval of a reconciliation change order with Southern Brothers Construction in the
amount of $37,950 for additional concrete work on the Recycling and Trash Collections compost pad
BACKGROUND:
On January 6, 2026, the Fayetteville City Council approved a contract (Resolution 19-26) with Southern
Brothers Construction in the amount of $233,068.18, for concrete repairs to the Recycling and Trash
Collections compost pad and recycling processing facility baler pit.
DISCUSSION:
During demolition of the compost pad, it was discovered that the existing concrete was thicker than anticipated
– the plans showed 6” of existing concrete but the actual field conditions were 8” - 10” of concrete. Discovery
of this additional concrete depth and other unknown field conditions resulted in unanticipated work for the
contractor:
• Provide & place additional 2" of concrete paving
• Additional concrete paving area
• Added cost to cut out existing concrete footing discovered under the middle of the pad
• Added cost for concrete repairs along the edge of the paving due to flaking and minor blemishes
The attached reconciliation change order accounts for the cost of these additional quantities and changes the
total contract price to $271,018.18.
BUDGET/STAFF IMPACT:
The cost of the change order will be paid for using the remaining contingency in this project and previously
budgeted project funds.
ATTACHMENTS: 3. Staff Review Form, 4. Transfer Station PCCO#1_For Signature
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-1257
A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 WITH SOUTHERN BROTHERS
CONSTRUCTION IN THE AMOUNT OF $37,950.00 FOR ADDITIONAL CONCRETE WORK
ON THE RECYCLING AND TRASH COLLECTIONS COMPOST PAD
WHEREAS, on January 6, 2026, City Council approved Resolution 19-26 authorizing a contract with
Southern Brothers Construction for concrete repairs to the Recycling and Trash Collections compost pad
and recycling processing facility baler pit; and
WHEREAS, during demolition of the compost pad, it was discovered that the existing concrete was
thicker than anticipated, and other field conditions resulted in unanticipated work for the contractor; and
WHEREAS, Change Order No. 1 will provide for additional concrete paving and concrete repairs.
NOW, THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign Change Order No. 1 to the contract with Southern Brothers Construction in the amount of
$37,950.00 for additional concrete work on the Recycling and Trash Collections compost pad.
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Comments:
2026-00000266Purchase Order Number:
Change Order Number:1
Previous Ordinance or Resolution #19-26
Approval Date:1/6/2026
Original Contract Number:
20006.1
Project Number
Budget Impact:
RTC - Compost Site Improvements
Fund
Recycling and Trash Collections5500.750.5080-5816.00
Account Number
Project Title
City of Fayetteville Staff Review Form
2026-1257
Item ID
5/5/2026
City Council Meeting Date - Agenda Item Only
Approve a reconciliation change order with Southern Brothers Construction in the amount of $37.950 for additional
concrete work on the Recycling and Trash Collections compost pad repairs
N/A for Non-Agenda Item
Action Recommendation:
Submitted By
Peter Nierengarten RECYCLING/TRASH COLLECTION (750)
Division / Department
4/2/2026
Submitted Date
Yes
445,421.13$
37,950.00$
Budgeted Item?
Does item have a direct cost?
Is a Budget Amendment attached?
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Amendment
Remaining Budget
675,873.00$
230,451.87$
Yes
No
407,471.13$
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
Southern Brothers Construction, LLC
2156 E Emma Ave, Suite C
Springdale, Arkansas 72764
Phone: (479) 313-7120
Project: 26.002.000 - Fayetteville Transfer Station
Prime Contract Change Order #001: CE #002 - Additional 2" of Concrete
Paving
TO:City of Fayetteville
113 West Mountain Street
Fayetteville, Arkansas 72701
FROM:Southern Brothers Construction, LLC
2156 E Emma St, Suite C
Springdale, Arkansas 72764
DATE CREATED:4/02/2026 CREATED BY:Mike Manthei (Southern Brothers
Construction, LLC)
CONTRACT STATUS:Pending - Revised REVISION:0
DESIGNATED REVIEWER:REVIEWED BY:
DUE DATE:REVIEW DATE:
INVOICED DATE:PAID DATE:
SCHEDULE IMPACT:EXECUTED:No
REVISED SUBSTANTIAL
COMPLETION DATE:
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR:1:Fayetteville Transfer Station Improvements TOTAL AMOUNT:$37,950.00
DESCRIPTION:
CE #002 - Additional 2" of Concrete Paving
Cost associated with additional concrete scope due to unforeseen items, further scope requested by the city, etc.
•Provide & place additional 2" of concrete paving at the Compost Facility due to existing conditions. Documents show 6" concrete. Actual field
condition is 8-10".
•Additional concrete paving at section panels that city added at time of site walk.
•Cost to cut out existing concrete discovered in middle of the pad.
•Cost for concrete repairs along the edge of the paving due to flaking and minor blemishes
ATTACHMENTS:
Transfer Station Subgrade Demo.pdf, Transfer Station Additonal R&R.pdf, Transfer Station - Additional 2'' Concrete Rev.pdf, Transfer Station Demoliton
Rev.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #Title Schedule Impact Amount
001 CE #002 - Additional 2" of Concrete Paving $37,950.00
Total: $37,950.00
CHANGE ORDER LINE ITEMS:
PCO # 001: CE #002 - Additional 2" of Concrete Paving
#Budget Code Description Amount
1 32-321313.S Site Paving Concrete ADD 2" Concrete Paving $7,700.00
2 02-024119.S Sawcut & Remove Existing Compost
Pad Additional Demo $1,300.00
3 02-024119.S Sawcut & Remove Existing Compost
Pad Additional Concrete Section $3,500.00
4 02-024119.S Sawcut & Remove Existing Compost
Pad Additional Concrete Discovered $22,000.00
5 01-007233.O Contractor/GC Fee.Other OH&P $3,450.00
Grand Total:$37,950.00
Southern Brothers Construction, LLC Page 1 of 2 Printed On: 4/2/2026 01:28 PM
PCCO #001
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370
The original (Contract Sum)$233,068.18
Net change by previously authorized Change Orders $0.00
The contract sum prior to this Change Order was $233,068.18
The contract sum would be changed by this Change Order in the amount of $37,950.00
The new contract sum including this Change Order will be $271,018.18
The contract time will not be changed by this Change Order.
Matt Loos (Olsson)City of Fayetteville Southern Brothers Construction, LLC
3537 North Steele Blvd. Suite 310 113 West Mountain Street 2156 E Emma St, Suite C
Fayetteville, Arkansas 72703 Fayetteville, Arkansas 72701 Springdale, Arkansas 72764
ProcoreArchitectSignHere ProcoreArchitectSignedDate ProcoreOwnerSignHere ProcoreGeneralContractorSignHere ProcoreGeneralContractorSignedDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
Southern Brothers Construction, LLC Page 2 of 2 Printed On: 4/2/2026 01:28 PM
PCCO #001
4/2/202604/02/2026 05/05/2026
Molly Rawn, Mayor
Docusign Envelope ID: 53AFC179-D95E-8C7C-816A-763379733370