HomeMy WebLinkAbout098-26 RESOLUTION1 13 West Mountain Street
Fayetteville, AR 72701
(47e) 575-8323
Resolution: 98-26
File Number: 2026-998
A RESOLUTION TO APPROVE AMENDMENT NO. 2 TO THE PROFESSIONAL ENGINEERING
SERVICES AGREEMENT WITH GARVE& LLC. IN THE AMOUNT OF $2,974,800.00 TO CONTINUE
ENGINEERING DESIGN OF MASTER-PLAN RECOMMENDED IMPROVEMENTS TO THE NOLAND
WATER RESOURCE RECOVERY FACILITY, AND TO APPROVE A BUDGET AMENDMENT
WHEREAS, the City completed a year-long master planning effort at the end of 2024 for the Noland Water Resource
Recovery Facility; and
WHEREAS, the most immediate improvements recommended by the plan were facility/equipment replacements
associated with aging and deteriorating unit treatment processes, aeration technology replacement, secondary clarifier
rehab, headworks expansion, and tertiary filtration technology changes; and
WHEREAS, the Phase I improvements are anticipated to take 5 years to implement with an estimated total cost of $98
million; and
WHEREAS, Amendment No. 2 will expand the design scope to the75o/o milestone for all components of the project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section l: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign
Amendment No. 2 to the Professional Engineering Services Agreement with Garver, LLC in the amount of
52,974,800.00 to continue engineering design of master-plan recommended improvements to the Noland Water
Resource Recovery Facility.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget amendment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on April 2l ,2026
Approved Attest:$t!,%
=oiFAYrTrrvrr,ri"i%;xN
Molly Rawn,
Page 1
Kara Paxton, City
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2026-998
A RESOLUTION TO APPROVE AMENDMENT NO. 2 TO THE PROFESSIONAL
ENGINEERING SERVICES AGREEMENT WITH GARVER, LLC. IN THE AMOUNT OF
$2,974,800.00 TO CONTINUE ENGINEERING DESIGN OF MASTER-PLAN
RECOMMENDED IMPROVEMENTS TO THE NOLAND WATER RESOURCE RECOVERY
FACILITY, AND TO APPROVE A BUDGET AMENDMENT
WHEREAS, the City completed a year-long master planning effort at the end of 2024 for the Noland
Water Resource Recovery Facility; and
WHEREAS, the most immediate improvements recommended by the plan were facility/equipment
replacements associated with aging and deteriorating unit treatment processes, aeration technology
replacement, secondary clarifier rehab, headworks expansion, and tertiary filtration technology changes;
and
WHEREAS, the Phase 1 improvements are anticipated to take 5 years to implement with an estimated
total cost of $98 million; and
WHEREAS, Amendment No. 2 will expand the design scope to the 75% milestone for all components
of the project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign Amendment No. 2 to the Professional Engineering Services Agreement with Garver, LLC in the
amount of $2,974,800.00 to continue engineering design of master-plan recommended improvements to
the Noland Water Resource Recovery Facility.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
amendment, a copy of which is attached to this Resolution.
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2026-998
MEETING OF APRIL 21, 2026
TO: Mayor Rawn and City Council
THROUGH: Keith Macedo, Chief of Staff
FROM: Tim Nyander, Utilities Director
SUBJECT: Garver, LLC - Amendment No. 2 for Noland WRRF Improvements
RECOMMENDATION:
Staff recommends approval of Amendment No. 2 to the Engineering Services Agreement with Garver, LLC in
the amount of $2,974,800.00 to continue engineering design of master-plan recommended improvements to
the Noland Water Resource Recovery Facility (WRRF), and approval of a budget amendment.
BACKGROUND:
The City completed a year-long master planning effort at the end of 2024 for the Noland WRRF, one of two
wastewater treatment plants owned by the City of Fayetteville. This master plan, completed by Garver, took a
comprehensive and in-depth look at the facility’s performance and condition, both now and into the future. The
most immediate improvements recommended by the plan were facility/equipment replacements associated
with aging and deteriorating unit treatment processes, such as new/increased influent pumping, aeration
technology replacement, secondary clarifier rehab, headworks expansion, and tertiary filtration technology
changes. The Phase 1 improvements are anticipated to take 5 years to implement, with an estimated total cost
of $98 million.
DISCUSSION:
Garver was selected (RFQ 25-01, Selection #5) to provide engineering design services for this project and will
soon be complete with 30% preliminary design effort. Amendment No. 2 will expand the design scope to the
75% milestone for all components of the project. Future amendments will be presented to complete design,
bidding, and construction services.
The not-to-exceed estimated fee for this amendment is $2,974,800.00.
BUDGET/STAFF IMPACT:
Budgeted Funds will be moved from multiple water and sewer capital projects to the WWTP Building
Improvements project to cover the cost of the engineering services.
ATTACHMENTS: 3. Staff Review Form, 4. Budget Amendment, 5. Amendment No. 2
City of Fayetteville Staff Review Form
2026-998
Item ID
4/21/2026
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Tim Nyander 4/1/2026 WASTEWATER TREATMENT (730)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Amendment No. 2 to the Engineering Services Agreement with Garver, LLC in the
amount of $2,974,800.00 to continue engineering design of master-plan recommended improvements to the
Noland Water Resource Recovery Facility (WRRF), and approval of a budget amendment.
Budget Impact:
5400.730.5800-5314.00 Water & Sewer
Account Number Fund
02032.2601 WWTP Building Improvements
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $ 4,454,066.00
Expenses (Actual+Encum)$ 2,784,260.05
Available Budget $ 1,669,805.95
Does item have a direct cost?Yes Item Cost $ 2,974,800.00
Is a Budget Amendment attached?Yes Budget Amendment $ 3,000,000.00
Remaining Budget $ 1,695,005.95
Purchase Order Number:2025-544 Previous Ordinance or Resolution #117-25
Change Order Number:2 Approval Date:
Original Contract Number:2025-25
Comments:RFQ 25-01, Selection #5
4/21/2026
City of Fayetteville, Arkansas - Budget Amendment/Adjustment
(Agenda)1 Errors
Budget Year Division
/Org2 WASTEWATER TREATMENT (730)
BA Number
2026 Requestor:Cheryl Partain
BUDGET AMENDMENT/ADJUSTMENT DESCRIPTION:
A budget amendment is needed in the Water and Sewer (2026 Bonds) project to move budgeted water and sewer funds to
the project to cover the cost for final engineering design of master plan recommended improvements to the Noland Water
Resource Facility (WRRF). Garver, LLC Amendment 2 will expand the preliminary design scope from 30% to 100%.
Budgeted funds from multiple capital projects are being moved to cover the cost until Bond funds are available.
COUNCIL DATE:4/21/2026
ITEM ID#:2026-998
Holly Black
4/1/2026 3:33 PM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.202635TOTAL--
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
5400.730.5800-5314.00 3,000,000 -02032 2601 EX Professional Services
5400.720.5700-5815.00 (1,000,000)-02017 1 EX Improvements - Sewer
5400.730.5800-5801.00 (800,000)-02069 1 EX Fixed Assets
5400.720.5600-5808.00 (1,000,000)-14010 1 EX Improvements - Water Line
5400.730.5800-5801.00 (100,000)-10027 1001 EX Fixed Assets
5400.730.5800-5818.00 (100,000)-13018 1 EX Wastewater Treatment Plant - Improvements
- -
- -
- -
- -
- -
- -
- -
- -
1 of 1
Contract Amendment No. 02 1 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
AMENDMENT TO AGREEMENT FOR PROFESSIONAL SERVICES
City of Fayetteville, Arkansas
Fayetteville, AR
Project No. W01-2401736
CONTRACT AMENDMENT NO. 02
This Contract Amendment No. 02 (“Amendment”), effective on the date last written below, shall amend
the original contract between the City of Fayetteville, Arkansas (Owner) and Garver, LLC (Garver),
dated May 6, 2025, referred to in the following paragraphs as the “Agreement.”
This Amendment adds professional services for the Fayetteville Noland Water Resource Recovery
Facility (WRRF) Phase 1 Improvements Project.
The Agreement is hereby modified as follows:
APPENDIX A – SCOPE OF SERVICES
Appendix A of the Agreement is modified as follows:
TASK 1.2 – FINAL DESIGN PROJECT MANAGEMENT AND QUALITY ASSURANCE
1.2 Garver will continue providing project management and quality assurance services for
final design services. This will include:
•Updating project work plan,
•Quality control management, coordination, and tracking
•Updating project schedule as required,
•Maintaining action item and decision logs,
•Coordinating with regulatory agencies, and stakeholders
•Conducting project team meetings,
•Conducting technical review committee meetings,
•Preparing monthly invoicing.
•Preparing biweekly progress reports.
TASK 8 – FINAL DESIGN – 75% DESIGN MILESTONE
Based upon the results of the approved preliminary design (30%) by the Owner, Garver will develop
75% level design plans, specifications, and OPCC to support design of the included elements in the
Preliminary Design (30%) listed as follows.
•New Septage Receiving and VAC Unloading Stations,
•Headworks – New Screening Building with Odor Control,
•Headworks – Grit Removal Improvements,
•New Influent Pump Station and Electrical Building,
Contract Amendment No. 02 2 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
•Biological Nutrient Removal (BNR) Trains Improvements – Diffused aeration system upgrade,
zoning and mixing improvements,
•New Blower Facility and Electrical Building,
•Secondary Clarifiers Improvements,
•New Waste Activated Sludge (WAS) and Secondary Clarifier Scum Pump Station,
•Filtration Improvements – Rehabilitation of existing sand filter complex or design of a new disk
filter facility (pending decision during the 30% workshop),
•New Ultraviolet (UV) Disinfection System with Inclined UV modules,
•Post-aeration Improvements with new Mechanical Surface Aerators,
•Sludge Holding Tank Improvements – New outdoor positive displacement blower facility
connected to a new diffused aeration system,
•New Sludge Screening System,
•Dewatering Improvements – Replacement of the existing belt filter presses with new
centrifuges and belt conveyors,
•Additional Backup Power Generator
•Ancillary site civil, yard piping, and site electrical improvements associated with the project
facilities.
8.1. Garver will lead a 50% design review workshop at the Owner’s office to solicit comments and
feedback from the Owner. Garver will provide a design update of each work area, solicit
feedback from project stakeholders, and request direction or decisions of the Owner where
required to advance the design. Decisions and actions will be documented in the meeting
minutes. There will not be formal 50% submittal package.
8.2. Garver will develop 75% Drawings, Details, Technical Specifications, and AACE Class 2 OPCC
for the project. These plans will represent a 75% level of design and will incorporate all
feedback and comments from the 50% design review workshop. The 75% plans will be
developed in accordance with applicable and appropriate code requirements. The 75%
submittal will not include “front-end” contract documents.
8.3. Garver will lead a 75% design review workshop at the Owner’s office to solicit comments and
feedback from the Owner. Garver will provide a design update of each work area, solicit
feedback from project stakeholders, and request direction or decisions of th e Owner where
required to complete the design. Decisions and actions will be documented in the meeting
minutes.
8.4. Garver will furnish OWNER, when requested, the engineering data and graphics necessary for
applications for routine permits, submittals, and approvals required by local, state, and federal
authorities, and assist Owner in consultations with appropriate authorities. Garver will
coordinate and meet with applicable regulatory agencies, which may include but are not limited
to the ADEE.
8.5. Garver will also develop the ADEE Construction Permit and Permit Modification Application,
conformed Drawings, Details, and Specifications to support design of the included elements in
the 75% Design.
Contract Amendment No. 02 3 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
8.6. Garver will provide the following deliverables:
(a)75% Drawings, Details, and Technical Specifications as a searchable and
bookmarked PDF.
(b)75% Design AACE Class 2 OPCC
(c)ADEE Construction Permit and Permit Modification Application
TASK 9 – BIOSOLIDS MASTER PLAN UPDATE`
Garver will update the City of Fayetteville Biosolids Master Plan to evaluate current biosolids
management practices, identify gaps in existing infrastructure and operations, and evaluate short -term
and long-term alternatives for biosolids processing and b eneficial reuse. The update will incorporate
changes in wastewater treatment plant loading, regulatory considerations, and operational constraints
identified since completion of the previous biosolids master planning effort.
The scope of work for this task will include the following elements:
9.1. Garver will update biosolids design criteria based on current and projected conditions, including
solids production rates from the Noland WRRF and Westside WRRF. Updated criteria will
consider current plant operations, industrial loading impacts, solids handling processes, and
future growth projections.
9.2. Garver will document a gap analysis comparing existing biosolids management capacity and
infrastructure against updated design criteria and projected biosolids production. The gap
analysis will identify deficiencies, operational risks, and capacity limitations within the curr ent
biosolids management system.
9.3. Garver will evaluate near-term improvements and operational strategies to address biosolids
management needs prior to implementation of long-term alternatives. This evaluation will
include Summarizing the impacts of anticipated industrial loading reductions at the Noland
WRRF on biosolids production and characteristics. This evaluation also includes equipment
life expectancy associated with existing biosolids processing facilities and identifying potential
constraints related to third-party agreements or disposal contracts.
9.4. Garver will evaluate long-term biosolids management alternatives for the City. Each alternative
will be developed to a conceptual planning level and will include PFDs, conceptual site layouts,
Contract Amendment No. 02 4 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
OPCC estimates, and life cycle cost (LCC) evaluations. Alternatives to be evaluated will
include:
9.4.1 Thermal heat drying at the Biosolids Management Site (BMS) to process all
solids generated at the Noland and Westside WRRFs and hauled to the BMS
site (consistent with the 2020 Biosolids Master Plan recommendation).
9.4.2 Thermal heat drying at the Noland WRRF to process biosolids generated at
Noland and biosolids hauled from the Westside WRRF.
9.4.3 Composting at the BMS site.
9.4.4 Composting at the Westside WRRF combined with thermal heat drying at the
BMS site or at the Noland WRRF.
9.5. Garver will prepare a Biosolids Master Plan Update Technical Memorandum (TM) summarizing
the findings of this task. The TM will include updated design criteria, summary of existing
conditions, gap analysis results, evaluation of short-term improvements, conceptual evaluation
of long-term alternatives, and recommendations for the City’s future biosolids management
strategy.
9.6. For all composting evaluations, Garver will coordinate up to 3 meetings with appropriate City
staff and stakeholders.
9.7. Garver will conduct a review workshop presenting the findings of the Biosolids Master Plan
update.
TASK 10 – PHYSICAL SCALE MODELING
Garver will subcontract with a specialty hydraulic modeling firm to perform physical scale model testing
of the proposed influent pump station intake structure. The model testing will be performed in
accordance with applicable Hydraulic Institute (HI) guidance and accepted industry practices for pump
station intake design. The scope of Garver’s services under this task will include the following:
10.1. Garver will provide the hydraulic modeling consultant with relevant design information
necessary to develop the physical model, including proposed pump station geometry, pump
configuration, design flow conditions, anticipated operating scenarios, and other project data
required to construct and operate the model. Garver will review the proposed testing conditions
and evaluation criteria. Garver will participate in coordination meetings with the modeling
consultant and the Owner as required to support development of the testing plan.
10.2. Garver will attend and observe the physical model testing conducted by the hydraulic
modeling consultant. Garver’s participation will include review of test conditions, observation
of model performance, and coordination with the modeling consultant regardi ng potential
design adjustments identified during testing.
10.3. Following completion of model testing, Garver will review the modeling results and
recommendations and conduct a meeting with City staff to discuss the findings and
Contract Amendment No. 02 5 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
recommended design modifications. Following Owner concurrence, Garver will incorporate
applicable modeling recommendations into the final design of the influent pump station.
TASK 11 – SUE SURVEY & COORDINATION
11.1 Garver will assist the City of Fayetteville in Subsurface Utility Exploration (SUE) services
to support final design efforts, including utility designation and location to identify and map
underground utilities that may impact the proposed improvements. This survey will be tied
to the Owner’s control network. Garver will provide approximate location of utilities that
require SUE, the Owner will provide the labor and excavation equipment to expose the
utility, Garver will provide survey services to document the location of found utilities.
Contract Amendment No. 02 6 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
EXTRA WORK
The following items are not included under this agreement but will be considered as extra work:
(a)90% and 100% Final Design and Bidding
(b)Revisions, due to changed conditions, after OWNER approval and G arver completion of
final documents.
(c)Submittals or deliverables in addition to those listed herein.
(d)Pilot testing.
(e)Independent construction materials testing outside of this contract.
(f)Video inspections and/or pipeline cleaning.
(g)Wastewater flow monitoring.
(h)Environmental Handling and Documentation, including wetlands identification or
mitigation plans or other work related to environmentally or historically (culturally)
significant items.
(i)Risk assessments and Emergency Response Plans in accordance with America’s Water
Infrastructure Act.
(j)Rate studies.
(k)Operations and maintenance services.
(l)Financial services.
(m)Receiving Stream Modeling.
(n)Any construction related services outside those specifically stated above.
Extra Work will be as directed by the Owner in writing for an additional fee as agreed upon by the
Owner and Garver.
Contract Amendment No. 02 7 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
SCHEDULE
Garver shall begin work under this agreement within ten (10) days of a Notice to Proceed and shall
complete the work in accordance with the schedule below:
Phase Description Calendar Days Anticipated
Completion Date
Task 1 – Project Management and
Quality Assurance Project Duration Completed
Task 1.1 – Preliminary Design Project
Management Preliminary Design Project Duration -
Task 1.2 – Final Design Project
Management Final Design Project Duration -
Task 2 – Submit Draft 10% Design
Report 120 days after Kickoff meeting Completed
Task 2 – 10% Design Workshop 14 days after draft 10% Design Report
Submittal Completed
Task 2 – Submit Final 10% Design
Report 14 days after 10% design workshop Completed
Task 3 – CMAR Solicitation /
Determination 90 days from NTP for this Task Completed
Task 4 – CMAR Onboarding
(REMOVED FROM AGREEMENT) 45 days from CMAR selection -
Task 5 – Preliminary Design 120 days from NTP for this Task April 21, 2026
Task 5 – Preliminary Design Workshop 14 days after Draft Preliminary Design Completed
Task 6 – Survey 90 days from NTP for this Task Completed
Task 7 – Geotechnical Investigation 90 days from NTP for this Task Completed
Task 8 – Final Design (50% Workshop) 60 days from NTP for Amendment 02 June 27, 2026
Task 8 – Final Design (75%) 120 days from NTP for Amendment 02 August 26, 2026
Task 8 – Final Design (75% Workshop) 14 days from 90% Submittal September 9, 2026
Task 9 – Biosolids Master Plan Update 100 days from NTP for Amendment 02 August 6, 2026
Task 10 – Physical Scale Modeling 120 days from NTP for Amendment 02 August 26, 2026
Task 11 – SUE Survey & Coordination 100 days from NTP for Amendment 02 August 6, 2026
Future Tasks
Task 12 – Final Design (90%) 45 days from NTP for Amendment 03 October 24, 2026
Task 12 – Final Design (90%
Workshop) 7 days from 90% Submittal October 31, 2026
Task 12 – Final Design (100%) 30 days after Owner approval of 90%
Workshop meeting minutes November 30, 2026
Task 13 – Bidding Support 75 days from 100% Submittal February 10, 2027
Task 14 – Construction Administration
Services TBD
Task 15 – Construction Observation TBD
Task 16 - Start-up Services TBD
Task 17 - Warranty Inspection Services TBD
Contract Amendment No. 02 8 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W01-2401736
APPENDIX B – SCOPE OF SERVICES
Appendix B of The Agreement is hereby modified as follows:
Appendix B
City of Fayetteville
Fayetteville Noland WRRF Phase I Improvements
FEE SUMMARY
Basic Services Section Estimated Fees
Task 1 – 10% Design Project Management $23,627.00
Task 1.1 – Preliminary Design Project Management $66,300.00
Task 1.2 – 75% Design Project Management $79,000.00
Task 2 – 10% Design $231,995.00
Task 3 – CMAR Solicitation / Determination $12,514.00
Task 4 – Special Services Requested By Owner $35,568.00
Task 5 – Preliminary Design (30%) $1,713,100.00
Task 6 – Survey $85,900.00
Task 7 – Geotechnical Coordination $56,400.00
Task 8 – Final Design – 75% Design Milestone $2,636,400.00
Task 9 – Biosolids Master Plan Update $136,500.00
Task 10 – Physical Scale modeling $92,900.00
Task 11 – SUE Survey and Coordination 30,000.00
Subtotal for 10% Design + Amendment 01 (Shaded) $2,225,404.00
Subtotal for Tasks Added via this Amendment 02 $2,974,800.00
Subtotal for Basic Services $5,200,204.00
GARVER
This Amendment may be executed in two (2) or more counterparts each of which shall be deemed an
original, but all of which together shall constitute one and the same instrument.
lN WITNESS WHEREOF, (Owner) and Garver have executed this Amendment effective as of the date
last written below.
CITY OF FAY LLE, ARKANSAS GARVER, LLC
By:By:
Signature
Name: MqllyAew!Name:T. Martin PE
Title: Mayor Title: Water Team Leader
Date' 412112026 Date: 0 4101 12026
Attest:
Clerk Sr. Project Manager, Chris Randall
Contract Amendment No. 02 9 of 9
Fayetteville Noland WRRF Phase I Improvements Garver Project No. W0 1-2401736
Y
a a
a FAYET-IEvtLLE ia
a
a
a a