A RESOLUTION TO APPROVE AMENDMENT NO. 3 TO THE PROFESSIONAL ENGINEERING
SERVICES CONTRACT WITH HAWKINS-WEIR ENGINEERS, INC. IN AN AMOUNT NOT TO EXCEED
$976,480.00 FOR CONSTRUCTION MANAGEMENT AND FIELD OBSERVATION SERVICES
ASSOCIATED WITH UTILITY RELOCATIONS ALONG HIGHWAY 112, AND TO APPROVE A BUDGET
ADJUSTMENT
WHEREAS, on June 1, 2021, the City Council passed Resolution No. 164-21 approving a Professional Engineering
Services Agreement with Hawkins-Weir Engineers, Inc. for engineering services associated with the utility relocations
along Highway 112 from Truckers Drive to Howard Nickell Road associated with Arkansas Department of
Transportation Project 040746; and
WHEREAS, Amendment No. 1 to the contract provided for costs associated with significant additional services
required during the final design phases of the project; and
WHEREAS, Amendment No. 2 provided for costs associated with re-design efforts required by ARDOT’s plan to add
another round-about to the roadway design; and
WHEREAS, Amendment No. 3 will provide funds for construction management and field observation throughout the
construction of the project, with reimbursement from ARDOT expected to cover approximately 90% of those costs.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign
Amendment No. 3 to the engineering services contract with Hawkins-Weir Engineers, Inc. in an amount not to exceed
$976,480.00 for construction management and field observation services associated with the utility relocations along
Highway 112.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on January 20, 2026
Approved: Attest:
_______________________________
Molly Rawn, Mayor
_______________________________
Kara Paxton, City Clerk Treasurer
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2025-2746
MEETING OF JANUARY 20, 2026
TO: Mayor Rawn and City Council
THROUGH: Keith Macedo, Chief of Staff
FROM: Tim Nyander, Utilities Director
SUBJECT: Hawkins-Weir Engineers, Inc. - Amendment No. 3 for Highway 112 Utility Relocations
RECOMMENDATION:
Staff recommends approval of Amendment No. 3 to the engineering services agreement with Hawkins-Weir
Engineers, Inc. for professional services associated with ArDOT Project 040746 Utility Relocations along
Highway 112 in an amount not to exceed $976,480.00, and approval of a budget adjustment.
BACKGROUND:
The Arkansas Department of Transportation has requested utility relocations to prepare for the widening of
Highway 112 from Truckers Drive to Howard Nickell Road. Amendments 1 & 2 were related to ARDOT-initiated
design changes throughout the design phase of the project.
DISCUSSION:
Amendment No. 3 will provide funds for construction management and field observation throughout the
construction duration. Per the original relocation agreement with ARDOT, this project is 90.74% reimbursable
to the City of Fayetteville.
BUDGET/STAFF IMPACT:
2026 Budgeted funds available from the Water & Sewer Relocations project will be utilized. 2026 budgeted
funds from the Sanitary Sewer Rehabilitation project and the Water System Rehabilitation and Replacement
project will be transferred to the Water and Sewer Relocations project to cover the remainder of the cost of the
project.
ATTACHMENTS: 3. Staff Review Form, 4. Budget Adjustment, 5. Amendment No. 3
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2025-2746
A RESOLUTION TO APPROVE AMENDMENT NO. 3 TO THE PROFESSIONAL
ENGINEERING SERVICES CONTRACT WITH HAWKINS-WEIR ENGINEERS, INC. IN AN
AMOUNT NOT TO EXCEED $976,480.00 FOR CONSTRUCTION MANAGEMENT AND
FIELD OBSERVATION SERVICES ASSOCIATED WITH UTILITY RELOCATIONS ALONG
HIGHWAY 112, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, on June 1, 2021, the City Council passed Resolution No. 164-21 approving a Professional
Engineering Services Agreement with Hawkins-Weir Engineers, Inc. for engineering services associated
with the utility relocations along Highway 112 from Truckers Drive to Howard Nickell Road associated
with Arkansas Department of Transportation Project 040746; and
WHEREAS, Amendment No. 1 to the contract provided for costs associated with significant additional
services required during the final design phases of the project; and
WHEREAS, Amendment No. 2 provided for costs associated with re-design efforts required by
ARDOT’s plan to add another round-about to the roadway design; and
WHEREAS, Amendment No. 3 will provide funds for construction management and field observation
throughout the construction of the project, with reimbursement from ARDOT expected to cover
approximately 90% of those costs.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign Amendment No. 3 to the engineering services contract with Hawkins-Weir Engineers, Inc. in an
amount not to exceed $976,480.00 for construction management and field observation services
associated with the utility relocations along Highway 112.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
City of Fayetteville Staff Review Form
2025-2746
Item ID
1/6/2026
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Tim Nyander 12/17/2025 WATER SEWER (720)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Amendment No. 3 to the engineering services agreement with Hawkins-Weir
Engineers, Inc. for professional services associated with ArDOT Project 040746 Utility Relocations along Highway
112 in an amount not to exceed $976,480.00, and approval of a budget adjustment.
Budget Impact:
5400.720.5600-5314.00 5400.720.5700-
5314.00 Water and Sewer
Account Number Fund
11011.2101 Water & Sewer Relocations
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $27,444,852.00
Expenses (Actual+Encum)$26,816,494.86
Available Budget $628,357.14
Does item have a direct cost?Yes Item Cost $976,480.00
Is a Budget Adjustment attached?Yes Budget Adjustment $476,480.00
$277.00 Remaining Budget $128,357.14
V20221130
Purchase Order Number:2021-418 Previous Ordinance or Resolution #218-19
Change Order Number:3 Approval Date:
Original Contract Number:2021-00000039
Comments:
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division
/Org2 WATER SEWER (720)
Adjustment Number
2026 (BY) Requestor:Cheryl Partain
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
A budget adjustment is needed in the Water/Sewer Relocations for Street Projects project to cover the cost for amendment
#3 to the engineering services agreement with Hawkins-Weir Engineers, Inc. for professional services associated with ArDOT
Project#040746 - Utility Relocations along Highway 112. Budgeted funds from the Sanitary Sewer Rehabilitation Project and
the Water System Rehabilitaton and Replacement projects will be used to fund part of the cost of this amendment.
COUNCIL DATE:1/6/2025
ITEM ID#:2025-2746
Holly Black
12/18/2025 3:19 PM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.2025125TOTAL--
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
5400.720.5600-5314.00 732,360 -11011 2101 EX Professional Services
5400.720.5700-5314.00 244,120 -11011 2101 EX Professional Services
5400.720.5600-5808.00 (500,000)-11011 1 EX Improvements - Water Line
5400.720.5700-5815.00 (119,120)-02017 1 EX Improvements - Sewer
5400.720.5600-5808.00 (357,360)-12009 1 EX Improvements - Water Line
--
--
--
--
--
--
--
--
--
--
--
--
--
1 of 1
AMENDMENT NO. 3
TO THE
AGREEMENT For PROFESSIONAL ENGINEERING SERVICES
BETWEEN
CITY OF FAYETTEVILLE, ARKANSAS
AND
HAWKINS-WEIR ENGINEERS, INC.
In accordance with the AGREEMENT For PROFESSIONAL ENGINEERING SERVICES for the
Highway 112 Utility Relocation (HW Project No. 2021048), dated June 1, 2021, between the City of
Fayetteville, Arkansas (hereinafter called Owner) and Hawkins-Weir Engineers, Inc. (hereinafter called
Engineer), Owner hereby authorizes Engineer to proceed with engineering services as modified by this
Amendment No. 3.
SECTION 1 -SCOPE OF SERVICES
1. 1 Amendment No. 3 is for Prebid and Construction Phase Services for the Highway 112 Utility
Relocation project by the Arkansas Department of Transportation (ARDOT). Additional information on
the proposed engineering services are detailed in the Engineer's attached Exhibit A -Scope of Services
dated October 24, 2025.
SECTION 2 -TIME OF SERVICE
2.1 Engineer will proceed with providing the services set f01ih herein immediately upon execution of
this Authorization by all paiiies and commencement of construction activities by ARDOT and the
Contractor.
SECTION 3 -COMPENSATION
3 .1 Owner shall compensate Engineer for providing the services set fo1ih herein in accordance with the
te1ms of the Agreement. Total payment for Scope of Services described herein shall not exceed Nine
Hundred Seventy-Six Thousand Four Hundred Eighty and 00/100 Dollars ($976,480.00) without written
approval of Owner.
2021048 Amendment 3_2025-10-24 Page 1 of2 October 24, 2025
These additional services adjust the Agreement's total not to exceed fee to $1,767,230.00, including
proposed reimbursable expenses.
Attachments: Exhibit A -Scope of Services dated October 24, 2025
Exhibit B -Fee Proposal dated October 24, 2025
Exhibit C -Standard Hourly Billing Rate Structure, effective 2025
ACCEPTED BY:
HA WK.INS-WEIR ENGINEERS, INC.
By:_�_ru)j--------=--=---------'---�--e_eh.M, __
Brett D. Peters, P.E.
President and CEO
Date: October 24, 2025
2021048 Amendment 3_2025-10-24
AUTHORIZATION BY:
CITY OF FAYETTEVILLE, ARKANSAS
By: __________ _Honorable Molly Rawn, Mayor
Date: ___________ _
Page 2 of 2 October 24, 2025
01/20/2026
Exhibit A
Scope of Services
Construction Phase Services
Highway 112 Utility Relocations
Fayetteville, Arkansas
Project No. 2021048
October 24, 2025
2021048 Exhibit A Construction Phase - Scope of Services 1
Project Description
This scope of services describes professional engineering services provided to the City of
Fayetteville for the Arkansas Highway 112 Utility Relocations Project. Hawkins-Weir Engineers
(HW) shall provide construction phase and other services as set forth below and based on a
construction contract length of 840 calendar days (28 months). Although the scope of public utility
work on this project has been incorporated into the Arkansas Department of Transportation
(ARDOT) roadway plans and specifications for Project 040746, this Amendment to the
Engineering Services Agreement for Hawkins-Weir will be for construction phase services
associated with construction of the utility improvements only. In addition, Hawkins-Weir will serve
as the liaison between ARDOT’s contractor and the City of Fayetteville. For the purposes of this
Scope of Services, “the Owner” is identified as the City of Fayetteville.
TASK 1 – Preliminary Engineering Services – Completed
TASK 2 – Final Design Phase Services – Completed
TASK 3 – Prebid Services
1. Reformat previously approved plans to match ARDOT formatting to allow incorporation of
the utility improvements into the roadway construction plans,
2. Reformat previously approved technical specifications into Special Provisions to allow
incorporation into ARDOT bidding documents,
3. Provide assistance to City of Fayetteville during easement acquisition efforts, including
participating in coordination meetings with property owners and revising easement
documents,
4. Assist ARDOT during bidding phase in interpretation of utility relocation plans and
preparation of bid addenda.
TASK 4 – Construction Phase Services – Utility Relocations
1. Participate in a preconstruction conference with ARDOT, the Owner, and Contractor,
2. Conduct pre-work coordination meetings with the Contractor and the Owner, including
concrete pre-placement (vault structures), water and sewer main tie-overs, and
connection to existing 36-in. prestressed concrete cylinder pipe (PCCP),
3. Conduct up to 12 coordination meetings with water and sewer customers, the Contractor,
and the Owner for water and sewer line tie-overs,
4. Participate in up to 56 construction progress meetings conducted by ARDOT (typically
semi-monthly), provide updates on the project status, review outstanding construction
issues, assist ARDOT in preparing meeting minutes, and advise the Owner on utility
matters,
Exhibit A
Scope of Services
Construction Phase Services
Highway 112 Utility Relocations
Fayetteville, Arkansas
Project No. 2021048
October 24, 2025
2021048 Exhibit A Construction Phase - Scope of Services 2
5. Provide full-time construction observation for a 28-month construction period for utility
relocations only,
6. Prepare, review and disseminate construction documentation including utility material
submittals, requests for information (RFIs), field change orders (FCOs), and change
orders (COs) as directed by ARDOT or the Owner,
7. Compile, review and maintain documentation for procurement of materials in accordance
with Build America, Buy America Act (BABAA) compliance,
8. Review the Contractor’s construction quantities for utilities and provide assistance to
ARDOT in processing Contractor’s monthly pay requests,
9. Conduct as-built surveys of the completed water and sewer improvements,
10. Coordinate and conduct a final inspection of utility improvements with ARDOT, Contractor,
and Owner, and prepare a punch list of deficient construction items for the Contractor to
address,
11. Prepare Record Drawings of the completed utility relocation project and provide one (1)
electronic copy for the Owner’s archives,
12. Provide documentation for ARDOT on reimbursable and betterment construction costs for
the utility relocation work,
13. Assist ARDOT in project management and contract administration.
Scope of Services Exclusions
1. This scope of services describes construction observation and construction phase
services related only to the construction of public water and sanitary sewer improvements
on the project. Hawkins-Weir will provide coordination between the City of Fayetteville,
the Contractor, and ARDOT on the utility improvements, but ARDOT will be responsible
for all other inspection and construction administration related to the roadway and storm
drainage improvements.
2. Water and sewer relocations and associated improvements are generally expected to be
completed prior to the completion of the roadway improvements. Therefore, this scope of
services assumes and the accompanying fee proposal is based on 840 days for review
and approval of utility material submittals; construction, testing, and commissioning of the
proposed utilities; and demolition and abandonment of existing utilities.
End of Scope of Services
Exhibit B
Fee Proposal Summary
Construction Phase Services
Highway 112 Utility Relocation
City of Fayetteville, Project No. 021048
October 24, 2025
TASK 3 - Prebid Services Highway 112 Utility Relocations, Fayetteville, Arkansas
Engr Engr Engr GPS Surv Const Obs CAD Tech Civil Eng Total Total
VII V II Survey Tech Surveyor III III Asst II Hours Cost
$275 $225 $150 $200 $50 $175 $115 $120 $90
1.Reformat previously approved plans to match ARDOT formatting 88 24 112 $27,080
2.Reformat previously approved specifications for ARDOT bid documents 72 4 32 108 $23,580
3.Provide assistance to City of Fayetteville during easement acquisition 24 8 8 40 $8,960
4.Assist ARDOT during bidding phase and prepare bid addenda 24 4 4 32 $7,440
TOTAL HOURS 208 4 0 0 0 8 0 36 36 292
SUBTOTAL COST: TASK 3 - PREBID SERVICES $57,200 $900 $0 $0 $0 $1,400 $0 $4,320 $3,240 $67,060
TASK 4 - Construction Phase Services - Utility Relocations Highway 112 Utility Relocations, Fayetteville, Arkansas
Engr Engr Engr GPS Surv Const Obs CAD Tech Civil Eng Total Total
VII V II Survey Tech Surveyor III III Asst II Hours Cost
$275 $225 $150 $200 $50 $175 $115 $120 $90
1.Participate in a preconstruction conference 8 4 4 4 4 24 $4,520
2.Conduct pre-work coordination meetings with Contractor and Owner (1)16 8 8 8 40 $8,120
3.Conduct up to 12 coordination meetings for utility tie-overs 24 16 16 8 64 $13,320
4.Participate in up to 56 construction progress meetings (bi-monthly)112 32 32 40 216 $46,400
5.Provide full-time construction observation for 28-mo. construction (2)16 16 400 5,824 6,256 $737,760
6.Prepare, review and disseminate submittals, RFIs, FCOs, and COs 48 8 48 40 144 $25,800
7.Compile, review and maintain BABAA documentation 8 8 40 40 96 $13,600
8.Review Contractor's monthly quantities for utilities and assist ARDOT 16 48 40 104 $15,200
9.Conduct as-built surveys of the completed water & sewer improvements 40 40 16 96 $12,800
10.Coordinate and conduct a final inspection and prepare punch list 4 4 8 4 20 $3,560
11.Prepare Record Drawings of completed utility improvments 4 16 8 40 68 $9,220
12.Prepare betterment and reimbursement documentation for ARDOT 8 4 8 20 $3,520
13.Assist ARDOT in project management and contract administration 40 40 80 $14,600
TOTAL HOURS 304 96 624 40 40 16 5,836 40 232 7,228
SUBTOTAL COST: TASK 4 - CONSTRUCTION PHASE SERVICES $83,600 $21,600 $93,600 $8,000 $2,000 $2,800 $671,140 $4,800 $20,880 $908,420
(1) "The Owner" = City of Fayetteville
(2) For Task 4 - Item 5: Construction Observer III based on 48-hours per week for 840-day construction time for utility relocations only
Reimbursable Expenses
1.Outside Services Reproduction and Printing $1,000
Total Estimated Reimbursable Expenses $1,000
Engineering Services Summary
TASK 3 - Prebid Services $67,060
TASK 4 - Construction Phase Services - Utility Relocations $908,420
Reimbursable Expenses $1,000
Total Engineering Fee (NTE)$976,480
Billing Rates (Effective 2025)
Billing Rates (Effective 2025)
2021048 Exhibit B Fee Proposal 2025-10-24\Prebid-Const Phase Fee 10-24-25 1 of 1
Hawkins-Weir Engineers, Inc.
Hourly Rate Schedule: 2025
Description Billing Rate/Hour
Engineer VII $275
Engineer VI $250
Engineer V $225
Engineer IV $200
Engineer III $175
Engineer II $150
Engineer I $125
Environmental Specialist II $130
Environmental Specialist I $110
Designer II $135
Designer I
Civil Eng Assistant II
Civil Eng. Assistant I
$100
$90
$80
CAD/BIM Modeler II $135
CAD/BIM Modeler I $100
CAD/GIS Technician III $120
CAD/GIS Technician II $95
CAD/GIS Technician I $75
Construction Manager II $140
Construction Manager I $125
Construction Observer IV $135
Construction Observer III $115
Construction Observer II $95
Construction Observer I $85
Surveyor $175
GPS Survey $200
Survey Technician $50
Business Manager $100
Graphic Designer $100
Document Processor $75
Reimbursable Expenses
Mileage $0.77/mile
Printing @ Cost
Travel @ Cost
Expert Witness Rate x 2.0
Other Direct Costs @ Cost
Notes:
1.Hourly rates may be equitably adjusted
2. Adjustment to rate schedule will not change contract lump sum or NTE amounts
3.If a conflict exists, hourly rates & reimbursable expenses will be invoiced per terms of Agreement.
Exhibit C