Resolution: 262-25
File Number: 2025-2272
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH GREATER PRODUCTIONS, LLC
IN THE AMOUNT OF $871,026.00 FOR THE GREENWAY TRAIL CONNECTION ASSOCIATED WITH
THE PARK HOTEL PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, on November 1, 2022, City Council passed Resolution 256-22 authorizing a letter of intent defining
development agreement terms with Reindl Properties for a Public Private Partnership to develop a mixed-use building
that included the cost of bicycle and pedestrian infrastructure improvements; and
WHEREAS, on November 7, 2023, City Council passed Resolution 251-23 authorizing a real estate purchase contract
with Reindl Properties for the sale of property in the Civic Plaza which provided that the City and Reindl would
coordinate the design of bicycle, pedestrian, automotive, and landscape infrastructure on all sides of the building and
pay a pro rata share of the costs; and
WHEREAS, this project represents the final connection of the Greenway Trail within the Ramble Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign a cost
share agreement with Greater Productions, LLC in the amount of $871,026.00 for construction of the Greenway Trail
Connection associated with the Park Hotel Project.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on November 18, 2025
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2025-2272
MEETING OF NOVEMBER 18, 2025
TO: Mayor Rawn and City Council
THRU: Steven Dotson, Chief Financial Officer
FROM: Waylon Abernathy, Bond Projects & Construction Director
SUBJECT: Cost Share Agreement with Greater Productions LLC for Greenway Trail
Construction and approval of a Budget Adjustment.
RECOMMENDATION:
Approve the Cost Share Agreement with Greater Productions, LLC in the amount of $871,026 for the City’s
portion of the Greenway Trail Connection, in coordination with the Park Hotel Project construction at the south
end of the Upper Ramble, and approve the associated Budget Adjustment.
BACKGROUND:
Resolution 256-22 authorized the mayor to sign a letter of intent defining development agreement terms with
Reindl Properties for a Public Private Partnership to develop a mixed-use building. Included in that letter is the
language that the cost of bicycle and pedestrian infrastructure improvements will be in an agreement for the
cost shares and will be a condition of the real estate contract.
Resolution 251-23 authorized the real estate contract that included specific terms of the agreement. That
contract includes terms: Buyer and Seller will coordinate design consultants on designing bicycle, pedestrian,
automotive, and landscape infrastructure on all sides of the Building. The amount of the costs of those
improvements and an agreement as to which costs will be paid by Seller and which will be paid by Buyer are a
condition of this Contract and a condition of Closing. Once the costs for these improvements are established,
Buyer and Seller agree to pay their pro-rata share of such costs.
Resolution 46-24 authorized a Budget Adjustment transferring the land proceeds funds into the Upper Ramble
Project Account.
DISCUSSION:
This project represents the final connection of the Greenway Trail within the Ramble Project. The original
design of the Upper Ramble included this link to ensure uninterrupted trail access for cyclists, scooter users,
and runners. It also provides an alternate route for trail users during Plaza activities or closures.
This agreement outlines the cost responsibilities of both the City and the Developer, as required by the
resolution. A detailed scope of work, including associated costs, is provided in the attached agreement.
Additional railroad requirements are included, such as maintaining $4 million in liability insurance and
implementing specialized shoring methods to avoid impacts to the railroad right-of-way.
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
BUDGET/STAFF IMPACT:
The funding will be from Arts Corridor Bond, Trails Bond, and Land Sale Proceeds.
ACCOUNT PROJECT AMOUNT
4703.860.7800-5814.05 46030.7800 145,159.00
4708.860.7800-5804.00 46080.7800 355,196.00
4470.140.8900-5804.00 46080.7800 370,671.00
TOTAL 871,026.00
ATTACHMENTS: 3. Staff Review Form, 4. Budget Adjustment, 5. Cost Share Agreement Trail Greater
Productions, 6. 20251020R2 Exhibit trail Metro & Park Hotel City purchase
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2025-2272
A RESOLUTION TO APPROVE A COST SHARE AGREEMENT WITH GREATER
PRODUCTIONS, LLC IN THE AMOUNT OF $871,026.00 FOR THE GREENWAY TRAIL
CONNECTION ASSOCIATED WITH THE PARK HOTEL PROJECT, AND TO APPROVE A
BUDGET ADJUSTMENT
WHEREAS, on November 1, 2022, City Council passed Resolution 256-22 authorizing a letter of intent
defining development agreement terms with Reindl Properties for a Public Private Partnership to
develop a mixed-use building that included the cost of bicycle and pedestrian infrastructure
improvements; and
WHEREAS, on November 7, 2023, City Council passed Resolution 251-23 authorizing a real estate
purchase contract with Reindl Properties for the sale of property in the Civic Plaza which provided that
the City and Reindl would coordinate the design of bicycle, pedestrian, automotive, and landscape
infrastructure on all sides of the building and pay a pro rata share of the costs; and
WHEREAS, this project represents the final connection of the Greenway Trail within the Ramble
Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign a cost share agreement with Greater Productions, LLC in the amount of $871,026.00 for
construction of the Greenway Trail Connection associated with the Park Hotel Project.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
City of Fayetteville Staff Review Form
2025-2272
Item ID
11/18/2025
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Wade Abernathy 10/21/2025 CHIEF FINANCIAL OFFICER (110)
Submitted By Submitted Date Division / Department
Action Recommendation:
Approval of the Cost Share Agreement with Greater Productions LLC in the amount of $871,026 for the City's
portion of the Greenway Trail Connection in coordination with the Park Hotel project construction on the South
end of the Upper Ramble and approval of a budget adjustment.
Budget Impact:
4470.140.8900-5804.00
4703.860.7800-5814.05
4708.860.7800-5804.00
Sales Tax Capital Improvements
Trails Bonds
Arts Corridor Bonds
Account Number Fund
46030.7800
46080.7800
Trails Bond Projects - Arts Corridor Impr
Arts Corridor Bond Projects - Arts Corridor Impr
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $15,285,896.00
Expenses (Actual+Encum)$13,791,234.88
Available Budget $1,494,661.12
Does item have a direct cost?Yes Item Cost $871,026.00
Is a Budget Adjustment attached?Yes Budget Adjustment $221,400.00
$261.00 Remaining Budget $845,035.12
V20221130
Purchase Order Number:Previous Ordinance or Resolution #
Change Order Number:Approval Date:
Original Contract Number:
Comments:
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division
/Org2 CHIEF FINANCIAL OFFICER (110)
Adjustment Number
2025 Requestor:Wade Abernathy
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Approval of the Cost Share Agreement with Greater Productions LLC in the amount of $871,026 for the City's portion of the
Greenway Trail Connection in coordination with the Park Hotel project construction on the South end of the Upper Ramble
and approval of a budget adjustment.
COUNCIL DATE:11/18/2025
ITEM ID#:2025-2272
Holly Black
10/29/2025 9:02 AM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.20251027TOTAL221,400 221,400
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
4703.860.7800-5814.05 73,198 -46030 7800 EX Improvements - Trails
4703.860.7000-4707.47 -73,198 46030 7000 RE Interest - 2022 Project Funds
4708.860.7800-5804.00 148,202 -46080 7800 EX Building Costs
4708.860.7000-4707.47 -148,202 46080 7000 RE Interest - 2022 Project Funds
--
--
--
--
--
--
--
--
--
--
--
--
--
--
1 of 1
Page 1 of 2
AGREEMENT FOR COST SHARE
OF GREENWAY TRAIL REALIGNMENT COSTS
This Agreement, made and entered into on this 20 day of October 2025, by and between the City
of Fayetteville, Arkansas (“City”) and Greater Productions, LLC (with related entities The Park Hotel, LLC,
and Reindl Properties, Inc) (“Owner”) for the construction of a portion of the Greenway Trail (“Project”),
witnesseth:
WHEREAS, Owner is currently constructing the rerouting and realigning the Greenway Trail,
parking for the Metro District and a hotel at 510 W. Spring Street; and
WHEREAS, Owner will be constructing these improvements through a grading permit issued by
the City and the quote for construction for the trail component is attached hereto as a schedule of values
Exhibit A and made a part hereof; and
NOW, THEREFORE, the City of Fayetteville, Arkansas and Greater Production, LLC agree as
follows:
1.The City agrees to:
A.Reimburse Owner an estimated $871,026 which represents 100% of the cost of the trail
work describe in Exhibit “A”, attached.
B.The schedule of values is an estimate and does not include unforeseen scope that could
be encounter during the construction of this work. The City will consider, on a case-by-
case basis, reimbursement for any additional costs to rectify the unforeseen or out of
scope additions to the project within any project contingency approved by the City.
C.Payments due to Owner, shall be remitted within fifteen (15) calendar days after receipt
of valid invoices, and pending successful inspection and acceptance of the phased
completed work by the City. The Owner is anticipating providing invoices a minimum
of one per month.
D.Authorize the construction of the trail on behalf of the City within the railroad easement
or right of way along the adjacent property owned by the Owner. The City has retained
all necessary rights, approvals, and agreements to access and granting the Owner this
ability to construct on the railroad property.
2.Owner agrees to:
A.Provide the necessary and normal project management, inspection, and testing as
necessary to complete the work shown on Exhibit “A”, in accordance with the City of
Fayetteville Standard Specifications, and City Standard Details, both of which are
available at http://www.fayetteville-ar.gov/445/Engineering-Specs-Details.
B.Construct the Project in accordance with the design approved by the City.
C.Pay for the Project with reimbursement of the cost by the City.
3.It is further understood that the contract for construction is between Owner and their
Contractor and that the City has no contractual obligation with either the Contractor or any
agent for Owner. The City’s only obligation shall be to participate in this agreement and pay
100% of the cost as defined in the schedule of values, plus any project contingency approved
by the City for the Project.
SCHEDULE OF VALUES EXHIBIT A APPLICATION NO:
PROJECT:Metro / Park Hotel - Trail APPLCATION DATE:
19-Sep-25 ADDRESS:510 W. Spring Street, Fayetteville, AR PERIOD TO:
REVISED 2 - 20 October 2025
A B C D E F G H
item number discription of work scheduled value materials stored (not
in D or E0
total complete and
stored (D+E+F)%balance to finish (C-G)
from previous
application D+E this period
HARD COST
1 General Conditions -$
Utilities - MH Backhole: 8 January 2025
2 Demo retaining wall 2,200$ -$
3 Water main and supply 75,812$
4 Gas main and supply - Black Hills -$
5 Storm water sewer 31,062$
6 Electric main and supply 22,397$
7 Electrical supply to Park 31,500$
8 Communications - AT&T / COX -$
9 Survey 2,244$
10 Erosion control 1,386$
11
Soldier Pile and Lagging Wall - Railroad -
Foundation Specialties 81,814$
Demo/Fill/Paving - S&K Dirtworks
12 Demo trees, asphault, base, retaining, sidewalks 41,210$
13 Construction entrance 1,485$
14 Silt Fencing and Tree Protection 968$
15 Cut 2,041$
16 Import Fill 6,377$
17 Export spoils 3,061$
18 Curb & Gutter 2,558$
19 Ribbon Curb -$
20 12' wide trail (4,800sf) - new easement 52,800$
21 12' wide trail (1,327sf) - railroad 14,597$
22 Colored Concrete -$
23 Intergral Colored Concrete -$
24 HD Concrete -$
25 HD Asphault -$
26 Regular Asphault -$
Scope A- Retaining Walls/Pavers - Elite Advance
Construction
27 Retaining wall A - Redi-rock 33,913$
28 Retaining wall B - cast-in-place conc.8,200$
29 Retaining wall c - cast-in-place conc.7,248$
30 Keystone Pavers 40,725$
Scope B- Retaining Walls/Pavers Railroad - Elite
Advance Construction
31 Retaining wall - Redi-rock 79,135$
32 Keystone Pavers 13,575$
33 Electrical 7,000$
34 Lights and poles 56,390$
35 Pole bases 7,500$
36
Guardrailing - Razorbak Ironworks (6 May
2025)14,000$
SOFT COST
Design and Administration
37 Landscape Architecture - NBW LA (9,991)$
Civil Engineering - Primm / Olsson
38 Base design 28,958$
39 CA and Observations 2,471$
40 Geo-technical Testing - UES 3,300$
41
Onsite Resident Project Representative - Olsson
Engineering 6,681$
42
Quality Assurance and Testing - Olsson
Engineering 17,848$
43 Project contingency 29,000$
44 Construction / Project Management Fee 145,171$
Insurance
45 $1M Gen Liability 1,970$
46 $4M Excess Liability 4,420$
47 Bonding -$
871,026$ -$ -$ -$ -$ -$
work completed
COST SHARE AGREEMENT - TRAIL
Two Trout, LLC
Project Development 1 of 3
Project Name: Metro / Park Hotel Parking and Trail
Cost Model
Development Budget
Date: 27 May 2025 - REVISED 2 - 20 October 2025
Cost Code Cost of Work Owner City
Hard Costs
10 Land / Acquisition
-100 Land
20 Construction
20-10 Construction
-100 Sitework
Utilities - MH Backhole: 8 January 2025
Demo retaining wall 21,875$ 19,675$ 2,200$ 10.06%
Water main and supply 229,732$ 153,920$ 75,812$
*The total city amount per the
development agreement is 50% of the
total ($114,866) The difference
($39,054) to be addressed. represents
potential of unforeseen conditions are
excluded. i.e. rock excavation
Gas main and supply - Black Hills -$ -$
Storm water sewer 94,128$ 63,066$ 31,062$
Electric main and supply 67,871$ 45,474$ 22,397$
Electrical supply to Park 31,500$ -$ 31,500$
Communications - AT&T / COX -$ -$
Survey 6,800$ 4,556$ 2,244$
Erosion control 4,200$ 2,814$ 1,386$
Soldier Pile and Lagging Wall - Railroad - Foundation Specialties 81,814$ -$ 81,814$
Demo/Fill/Paving - S&K Dirtworks
Demo trees, asphault, base, retaining, sidewalks 124,878.00$ 83,668$ 41,210$
Construction entrance 4,500.00$ 3,015$ 1,485$
Silt Fencing and Tree Protection 2,934.00$ 1,966$ 968$
Cut 6,184.00$ 4,143$ 2,041$
Import Fill 19,325.00$ 12,948$ 6,377$
Export spoils 9,276.00$ 6,215$ 3,061$
Curb & Gutter 7,751.00$ 5,193$ 2,558$
Ribbon Curb 2,226.00$ 2,226$ -$
12' wide trail (4,800sf) - new easement 52,800.00$ -$ 52,800$
12' wide trail (1,327sf) - railroad 14,597.00$ -$ 14,597$
Colored Concrete 54,060.00$ 54,060$ -$
Intergral Colored Concrete 99,400.00$ 99,400$ -$
HD Concrete 99,030.00$ 99,030$ -$
$ 530,901.00
COST SHARE AGREEMENT - TRAIL
Two Trout, LLC
Project Development 2 of 3
Project Name: Metro / Park Hotel Parking and Trail
Cost Model
Development Budget
Date: 27 May 2025 - REVISED 2 - 20 October 2025
HD Asphault 21,912.00$ 21,912$ -$
Regular Asphault 12,028.00$ 12,028$ -$
Scope A- Retaining Walls/Pavers - Elite Advance Construction
Retaining wall A - Redi-rock 33,913.00$ -$ 33,913$
Retaining wall B - cast-in-place conc.16,400.00$ 8,200$ 8,200$
Retaining wall c - cast-in-place conc.14,495.00$ 7,248$ 7,248$
Keystone Pavers 40,725.00$ -$ 40,725$
Scope B- Retaining Walls/Pavers Railroad - Elite Advance Construction
Retaining wall - Redi-rock 79,135.00$ -$ 79,135$
Keystone Pavers 13,575.00$ -$ 13,575$
Electrical 7,000.00$ -$ 7,000$
Lights and poles 56,390.00$ -$ 56,390$ 5 poles
Pole bases 7,500$ -$ 7,500$
Guardrailing - Razorbak Ironworks (6 May 2025)70 lf 14,000$ -$ 14,000$
SUBTOTAL HARD COSTS 1,351,954$ 710,756$ 641,198$
COST SHARE AGREEMENT - TRAIL
Two Trout, LLC
Project Development 3 of 3
Project Name: Metro / Park Hotel Parking and Trail
Cost Model
Development Budget
Date: 27 May 2025 - REVISED 2 - 20 October 2025
Soft Costs 20%199,550$ 130,302$ 49,266$
20-30 Design and Administration
-110 Landscape Architecture - NBW LA 19,982$ hrly / nte 9,991$ (9,991)$
50/50 split with the city - City has paid
NBW
-130 Civil Engineerting - Prism / Olsson
Base design 87,750$ 58,793$ 28,958$ 76/33 split
CA and Observations 7,488$ 5,017$ 2,471$
76/33 split (Also split with the off-site
work)
20-40 Construction Consultants
-200 Geo-technical Testing - UES 10,000$ 6,700$ 3,300$ 76/33 split
-600 Onsite Resident Project Representative - Olsson Engineering 20,245$ 13,564$ 6,681$ 76/33 split
-600 Quality Assurance and Testing - Olsson Engineering 54,085$ 36,237$ 17,848$ 76/33 split
20-50 Contingency
-100 Project Contingency 3.6%49,000$ 20,000$ 29,000$
-200 Soft Cost Contingency 6.0%12,000$ 12,000$ -$
40 Development and Management
40-10 Construction / Project Management Fee 20%322,501$ 174,612$ 145,172$
40-60 Development Expenses
-400 Insurance - 12 month term
$1M Gen Liability 3,940$ 1,970$ 1,970$
$4M Excess Liability 4,420$ 4,420$ Excess due to railroad requirement
-400 Bonding (base on value of City construction)-$ -$ 100%
SUBTOTAL SOFT COSTS 591,410$ 338,883$ 229,828$
USES
TOTAL COSTS 1,943,364$ 1,049,639$ 871,026$ 894,180$
(23,154)$
SOURCES
Metro / Park Hotel (South Hotel)1,049,639$ 54%
City of Fayetteville 871,026$ 45%