Resolution: 228-25
File Number: 2025-1850
A RESOLUTION TO APPROVE A SUPPLEMENTAL AGREEMENT LETTER WITH THE ARKANSAS
DEPARTMENT OF TRANSPORTATION AND THE NORTHWEST ARKANSAS REGIONAL PLANNING
COMMISSION FOR AN ADDITIONAL $500,000.00 IN FEDERAL AID FUNDING THROUGH THE
CARBON REDUCTION PROGRAM FOR THE RUPPLE ROAD TRAIL LIGHTING PROJECT, AND TO
APPROVE A BUDGET ADJUSTMENT
WHEREAS, on December 4, 2024, City Council passed Resolution 288-24 accepting $315,193.00 in federal-aid funds
through the Northwest Arkansas Regional Planning Commission Carbon Reduction Program for installations of
lighting along the Rupple Road Trail from MLK Jr. Boulevard to Persimmon Street; and
WHEREAS, this supplemental agreement will serve as an amendment to the original agreement, providing an
additional $500,000.00 in federal aid funding for the project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign a
Supplemental Agreement letter with the Arkansas Department of Transportation and the Northwest Arkansas Regional
Planning Commission for an additional $500,000.00 in Federal-aid funding through the Carbon Reduction Program for
the Rupple Road Trail Lighting project, and further authorizes Mayor Rawn to sign any additional grant related
documents necessary to implement the project.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on October 7, 2025
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2025-1850
MEETING OF OCTOBER 7, 2025
TO: Mayor Rawn and City Council
THRU: Keith Macedo, Chief of Staff
Chris Brown, Public Works Director
FROM: Matt Mihalevich, Active Transportation Manager
SUBJECT: ARDOT Supplemental Agreement Letter - Rupple Road Trail Lighting
RECOMMENDATION:
Staff recommends approval of a supplemental agreement letter with the Arkansas Department of
Transportation and the Northwest Arkansas Regional Planning Commission for an additional $500,000.00 in
Federal-aid funding through the Carbon Reduction Program for the Rupple Road Trail Lighting project and
approval of a budget adjustment to recognize this revenue and authorize the Mayor to sign additional grant
related documents as necessary to implement the project.
BACKGROUND:
The City of Fayetteville has received a total of $815,193.00 in federal-aid funding from the Arkansas
Department of Transportation through the Northwest Arkansas Regional Planning Commission – Carbon
Reduction Program for the installation of lighting along Rupple Road from Hwy 62 (MLK Jr. Blvd.) to
Persimmon Street. The funding was awarded in two funding cycles:
• June 2024: $315,193 (recognized by resolution 288-24)
• June 2025: $500,000
Resolution 288-24 previously recognized the original $315,193 federal grant award and approved the
Agreement of Understanding with ARDOT. The attached supplemental Agreement letter serves as an
amendment to the original agreement, providing an additional $500,000 in federal aid funding for the project.
DISCUSSION:
The Rupple Road Trail Lighting Project will install new lighting along 1.8 miles of Rupple Road, from Martin
Luther King Jr. Boulevard to Persimmon Street. Lighting will be placed in the median to illuminate both the
roadway and the adjacent trail, including the three roundabouts along this corridor.
This project responds to significant community interest and supports the City’s broader goals for active
transportation and carbon reduction. By improving visibility and safety, the lighting will help extend trail use into
evening hours, allowing more residents to walk, bike, or roll as a reliable and sustainable transportation option.
The project is currently 90% designed and has received environmental clearance. It is expected to go to bid in
late 2025, with construction beginning in early 2026.
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
BUDGET/STAFF IMPACT:
City staff has generated a cost estimate for $1,018,991 for the Rupple Rd. lighting project. Resolution 288-24
recognized the original $315,193 in federal aid funding and allocated the 20 percent local match of $78,798.
This request will recognize the additional $500,000 in federal aid funding and allocate the 20 percent local
match of $125,000 from the 2022 Transportation bond funds.
ATTACHMENTS: 3. Staff Review Form, 4. Budget Adjustment, 5. NWARPC Signed - 040967 CRP AOU letter
- Rupple Trail Lighting $500k, 6. Rupple Trail Lighting Location Map
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2025-1850
A RESOLUTION TO APPROVE A SUPPLEMENTAL AGREEMENT LETTER WITH THE
ARKANSAS DEPARTMENT OF TRANSPORTATION AND THE NORTHWEST ARKANSAS
REGIONAL PLANNING COMMISSION FOR AN ADDITIONAL $500,000.00 IN FEDERAL
AID FUNDING THROUGH THE CARBON REDUCTION PROGRAM FOR THE RUPPLE
ROAD TRAIL LIGHTING PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, on December 4, 2024, City Council passed Resolution 288-24 accepting $315,193.00 in
federal-aid funds through the Northwest Arkansas Regional Planning Commission Carbon Reduction
Program for installations of lighting along the Rupple Road Trail from MLK Jr. Boulevard to
Persimmon Street; and
WHEREAS, this supplemental agreement will serve as an amendment to the original agreement,
providing an additional $500,000.00 in federal aid funding for the project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign a Supplemental Agreement letter with the Arkansas Department of Transportation and the
Northwest Arkansas Regional Planning Commission for an additional $500,000.00 in Federal-aid
funding through the Carbon Reduction Program for the Rupple Road Trail Lighting project, and further
authorizes Mayor Rawn to sign any additional grant related documents necessary to implement the
project.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
City of Fayetteville Staff Review Form
2025-1847
Item ID
October 7th, 2025
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Matt Mihalevich 9/17/2025 ENGINEERING (621)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of a supplemental agreement letter with the Arkansas Department of Transportation
and the Northwest Arkansas Regional Planning Commission for an additional $500,000.00 in Federal-aid funding
through the Carbon Reduction Program for the Rupple Road Trail Lighting project and approval of a budget
adjustment to recognize this revenue and authorize the Mayor to sign additional grant related documents as
necessary to implement the project.
Budget Impact:
4601.860.7237-5814.05
4702.860.7237-5814.05
Bond Program Grant Matching
Streets Projects 2022 Bonds
Account Number Fund
46020.7237.2304 Streets Projects Bonds -
Transportation Impr, Rupple Rd Lighting
Project Number Project Title
Budgeted Item?No Total Amended Budget $-
Expenses (Actual+Encum)$-
Available Budget $-
Does item have a direct cost?No Item Cost $-
Is a Budget Adjustment attached?Yes Budget Adjustment $625,000.00
$316.00 Remaining Budget $625,000.00
V20221130
Purchase Order Number:Previous Ordinance or Resolution #288-24
Change Order Number:Approval Date:
Original Contract Number:
Comments:
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division
/Org2 ENGINEERING (621)
Adjustment Number
2025 Requestor:Matt Mihalevich
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Staff recommends approval of a supplemental agreement letter with the Arkansas Department of Transportation and the
Northwest Arkansas Regional Planning Commission for an additional $500,000.00 in Federal-aid funding through the Carbon
Reduction Program for the Rupple Road Trail Lighting project and approval of a budget adjustment to recognize this revenue
and authorize the Mayor to sign additional grant related documents as necessary to implement the project.
COUNCIL DATE:10/7/2025
ITEM ID#:2025-1850
Holly Black
9/18/2025 10:51 AM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.2025826TOTAL500,000 500,000
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
4601.860.7237-4309.00 -500,000 46020 7237.2304 RE Federal Grants - Capital
4601.860.7237-5814.05 500,000 -46020 7237.2304 EX Improvements - Trails
4702.860.7237-5814.05 125,000 -46020 7237.2304 EX Improvements - Trails
4702.860.7999-5899.00 (125,000)-46020 7999 EX Unallocated - Budget
--
--
--
--
--
--
--
--
--
--
--
--
--
--
1 of 1
City of Fayetteville, AR
Legend
Proposed Trail Lighting (1.8 Miles)
Existing 12' Wide Concrete Trail
Proposed Trail lighting Along 1.8 Miles of Existing Trail 111 Lights Proposed
0 500 1,000 1,500 2,000250Feet
F
Rupple Road TrailProposed Trail Lighting
Fayetteville Vicinity Map
RazorbackRegional
Greenway
Rupple Road Trail
Sloan Brook VillageNeighborhood(Under Construction)
Proposed LED Trail lights
Existing Rupple Road Trail (1.8 Miles)
Walnut Crossing Neighborhood
^_
Rupple Road Trail