Resolution: 212-25
File Number: 2025-1521
A RESOLUTION TO APPROVE AMENDMENT #1 TO THE COST SHARE AGREEMENT WITH
GREATER PRODUCTIONS, LLC IN THE AMOUNT OF $160,729.00 FOR THE INSTALLATION OF
SANITARY SEWER AND STORM DRAINAGE UPGRADES TO SERVE THE PARK HOTEL AND OTHER
DOWNTOWN DEVELOPMENTS, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, on February 18, 2025, City Council passed Resolution 56-25 approving a cost share agreement with
Greater Productions, LLC for the installation of sanitary sewer upgrades to serve the Park Hotel and other planned
downtown developments; and
WHEREAS, during the construction, changes in the sewer installation scope were made that resulted in a reduction in
the total cost of the sewer, but a failing storm drain pipe was discovered in the project area that must be replaced.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas approves Amendment #1 to the cost share
agreement with Greater Productions, LLC in the amount of $160,729.00 for the installation of sanitary sewer and storm
drainage upgrades to serve the Park Hotel and other planned downtown developments.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on September 16, 2025
Approved:
_______________________________
Molly Rawn, Mayor
Attest:
_______________________________
Kara Paxton, City Clerk Treasurer
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2025-1521
MEETING OF SEPTEMBER 16, 2025
TO: Mayor Rawn and City Council
THRU: Keith Macedo, Chief of Staff
FROM: Chris Brown, Public Works Director
SUBJECT: Staff recommends approval of a cost share increase in the amount of $160,729 with
Greater Productions, LLC for the installation of sanitary sewer and storm drainage
upgrades to serve the Park Hotel and other downtown developments and approval of
a budget adjustment.
RECOMMENDATION:
Staff recommends approval of a cost share increase in the amount of $160,729 with Greater Productions, LLC
for the installation of sanitary sewer and storm drainage upgrades to serve the Park Hotel and other downtown
developments and approval of a budget adjustment to add stormwater funds to the project.
BACKGROUND:
A sewer study in the downtown area that was developed in response to multiple large development projects
has identified a sewer capacity issue on the segment of line that runs west of West Avenue along Spring Street
and then south to an existing line that was recently upsized and relocated as part of the development located
at 612 W Center Street.
A cost sharing contract with the developer of the hotel was developed for installation of sewer upgrades to
resolve the capacity issue. Work began on this project in May 2025 and is ongoing.
DISCUSSION:
During the construction of the project, changes in the sewer installation scope were made that resulted in a
reduction in the total cost of the sewer. However, a failing storm drain pipe was discovered in the project area;
this pipe was found to be in need of replacement at a cost of $212,050. Funding for the storm drainage
replacement will be taken from two projects:
02116 Cost Sharing: $100,000
02108 Other Drainage Projects: $112,050
The net increase of the contract with Greater Productions, LLC is $160,729.
BUDGET/STAFF IMPACT:
Changes to the project will result in a savings to the water and sewer fund; funding for the additional cost will
be funded by two projects in the sales tax capital improvement fund.
ATTACHMENTS: 3. Staff Review Form, 4. Budget Adjustment, 5. Signed Cost Share Agreement, 6.
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
Amendment 1 to Sewer Main Costs Share - Greater Productions - Park Hotel (8-27-2025)
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2025-1521
A RESOLUTION TO APPROVE AMENDMENT #1 TO THE COST SHARE AGREEMENT
WITH GREATER PRODUCTIONS, LLC IN THE AMOUNT OF $160,729.00 FOR THE
INSTALLATION OF SANITARY SEWER AND STORM DRAINAGE UPGRADES TO SERVE
THE PARK HOTEL AND OTHER DOWNTOWN DEVELOPMENTS, AND TO APPROVE A
BUDGET ADJUSTMENT
WHEREAS, on February 18, 2025, City Council passed Resolution 56-25 approving a cost share
agreement with Greater Productions, LLC for the installation of sanitary sewer upgrades to serve the
Park Hotel and other planned downtown developments; and
WHEREAS, during the construction, changes in the sewer installation scope were made that resulted in
a reduction in the total cost of the sewer, but a failing storm drain pipe was discovered in the project area
that must be replaced.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas approves Amendment #1 to the
cost share agreement with Greater Productions, LLC in the amount of $160,729.00 for the installation of
sanitary sewer and storm drainage upgrades to serve the Park Hotel and other planned downtown
developments.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
Comments:
Purchase Order Number:
Change Order Number:
Previous Ordinance or Resolution #
Approval Date:
Original Contract Number:
04039.2501
Project Number
Budget Impact:
Water & Sewer Impact Fee Cost Sharing - Greater
Productions Cost Share
Fund
Water & Sewer4470.621.8810-5817.00
Account Number
Project Title
City of Fayetteville Staff Review Form
2025-1521
Item ID
9/16/2025
City Council Meeting Date - Agenda Item Only
Staff recommends approval of a cost share increase in the amount of $160,729 with Greater Productions, LLC for
the installation of sanitary sewer and storm drainage upgrades to serve the Park Hotel and other downtown
developments and approval of a budget adjustment to add stormwater funds to the project.
N/A for Non-Agenda Item
Action Recommendation:
Submitted By
Chris Brown ENGINEERING (621)
Division / Department
8/14/2025
Submitted Date
Yes
250,142.24$
212,050.00$
V20221130
Budgeted Item?
Does item have a direct cost?
Is a Budget Adjustment attached?
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
1,156,513.00$
906,370.76$
No
Yes 212,050.00$
250,142.24$
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division
/Org2 ENGINEERING (621)
Adjustment Number
2025 Requestor:Chris Brown
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Staff recommends approval of a cost share increase in the amount of $160,729 with Greater Productions, LLC for the
installation of sanitary sewer and storm drainage upgrades to serve the Park Hotel and other downtown developments and
approval of a budget adjustment.
COUNCIL DATE:9/16/2025
ITEM ID#:2025-1521
Holly Black
8/28/2025 10:49 AM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.2025826TOTAL--
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
4470.800.8820-5809.00 (100,000)-02116 1 EX Improvements - Street
4470.621.8810-5817.00 (112,050)-02108 1 EX Improvements - Bridge & Drainage
4470.621.8810-5817.00 212,050 -02108 4039.2501 EX Improvements - Bridge & Drainage
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
1 of 1
AMENDMENT #1
to the Agreement for Cost Share of
Sanitary Sewer Improvement Costs
WHEREAS, on February 18, 2025, pursuant to Resolution 56-25, the City of
Fayetteville and Greater Productions, LLC entered into an Agreement for Cost Share of Sanitary
Sewer Improvement Costs (the “Agreement”) which provided for the City to reimburse Greater
Productions, LLC 89.8% of the cost to upgrade sanitary sewer infrastructure to allow the
development of property at 215 W. Spring Street and also provide for ample future capacity in
the area served by the sewer main, with the City receiving reimbursement from other planned
upstream developments; and
WHEREAS, as the project progressed, the City and Greater Productions found that it
was necessary to install new storm drainage pipe to replace some failing infrastructure causing
the total cost of the project to increase by $178,985, with the City’s share of the increase
amounting to $160,729.
NOW, THEREFORE, BE IT KNOWN TO ALL:
That the City of Fayetteville, Arkansas and Greater Productions, LLC on this ________
day of ______________, 2025, hereby agree that the Agreement for Cost Share of Sanitary Sewer
Improvements shall be amended to provide for reimbursement by the City up to the amount of
$1,217,242 as shown in the revised Cost Model attached hereto as Exhibit A.
The parties agree and understand that this Amendment is supplemental to their Agreement
and that it does not alter, amend or abridge any of the rights, obligations, or duties of the parties
not expressly addressed herein. Greater Productions, LLC agrees that it is and shall continue to be
bound by the provisions of the Agreement.
IN WITNESS WHEREOF, the parties hereto have caused their signatures to be set by
their authorized representative effective the date set forth herein above.
GREATER PRODUCTIONS, LLC CITY OF FAYETTEVILLE
By: _________________________________ By: ___________________________________
BRIAN REINDL, Manager MOLLY RAWN, Mayor
ATTEST:
By: ___________________________________
KARA PAXTON, City Clerk-Treasurer