BENCHMARK CONSTRUCTION COMPANY OF NWA, INC. (CHANGE ORDER #1):
A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH BENCHMARK
CONSTRUCTION COMPANY OF NWA, INC. IN THE AMOUNT OF $537,471.41 FOR THE COLLEGE
AVENUE IMPROVEMENTS PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, on August 6, 2024, City Council approved a contract with Benchmark Construction for a portion of the
College Avenue Improvements Project between North Street and Sycamore Street, but the City was unable to receive
concurrence of award from ARDOT for the contract; and
WHEREAS, on December 17, 2024, City Council approved a new contract with Benchmark Construction and
received ARDOT approval; and
WHEREAS, after starting construction of the water and sewer lines for the project, City staff discovered that the bid
for the utilities did not include an adequate quantity for permanent pavement repair and this change order increases the
permanent pavement repair quantity to cover the necessary construction, extends traffic control by 60 days, and
increases the bond amount.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign Change
Order No. 1 to the contract with Benchmark Construction Company of NWA, Inc. in the amount of $537,471.41 for the
College Avenue Improvements Project. A copy of Change Order No. 1 is attached to this Resolution and made a part
hereof.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
Page 1
Resolution: 110-25
File Number. 2025-499
PASSED and APPROVED on May 6, 2025
Approved:
Molly Rawn, Mayor
Attest:
F FAYE�EV,
Kara Paxton, City Clerk Treasurer
Page 2
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF MAY 6, 2025
CITY COUNCIL MEMO
2025-499
TO: Mayor Rawn and City Council
THRU: Keith Macedo, Interim Chief of Staff
Chris Brown, Public Works Director
FROM: Matt Casey, Engineering Design Manager
SUBJECT: BENCHMARK CONSTRUCTION COMPANY OF NWA, INC. (CHANGE ORDER #1):
RECOMMENDATION:
Staff recommends approval of Change Order 1 with Benchmark Construction for the College Avenue
Improvements Project (North to Sycamore), which will increase the contract amount by $537,471.41 and
extend the contract time by 60 days and approval of a budget adjustment.
BACKGROUND:
The School Avenue and College Avenue corridors serve as major north -south routes through the central part
of the City and are major commercial and retail destinations. Maintaining and improving these corridors will
allow them to continue serving mobility needs and developing/redeveloping as commercial corridors.
Improvements to these corridors will include striping, widening and/or narrowing of the roadway, utility
relocation, sidewalk/trail installation, accommodations for transit systems, elimination or reconfiguration of
driveways, modification to traffic signals, medians, and other corridor improvements identified during the
design process.
The starting point for corridor designs was the 71 B Corridor Plan completed by RDG Planning. Goals and
aspirations of the Plan will be implemented to the greatest extent possible through the limits of the project
segments selected for design and construction, which include College Avenue between North Street and
Township Street, and School Avenue between Martin Luther King Jr. Boulevard and Cato Springs Road.
In December 2021, the City Council approved a design contract with Garver, LLC for the detailed design of this
project from North Street to Sycamore Street.
In addition to the transportation improvements, a new water main along this corridor is included in the
construction contract. Plans for the water main were prepared by McClelland Consulting Engineers.
On August 25, 2021, the Northwest Arkansas Regional Planning Commission (NWARPC) awarded this project
$1,500,000 from the IFFY 2022 STBGP-A (Surface Transportation Block Grant Program -Attributable). This
federal aid program is administered through the NWARPC.
In November 2021, the City of Fayetteville and ARDOT signed a supplemental agreement combining the
$1,500,000 in STBGP-A funds with funds from the 2019 agreement of understanding for Job 040746 (Truckers
Drive — Howard Nickell Road and Highway 71 B Improvements), which allocated $1,500,000 for improvements
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
to Highway 71 B.
On August 24, 2022, the NWARPC awarded the project an additional $1,800,000 from the FFY 2022 STBGP-
A, bringing the total federal aid to $4,800,000.
At the August 6, 2024, City Council meeting, the Council approved a contract with Benchmark Construction for
this project. Unfortunately, we were unable to receive concurrence of award from ARDOT for the contract. The
previous bid did not meet the Disadvantaged Business Enterprise (DBE) goal for the project. ARDOT has since
reevaluated and reduced the DBE goal from 11 % to 6% for the re -bid.
At the December 17, 2024, City Council meeting, the Council approved a new contract with Benchmark
Construction. This contract received ARDOT approval, and construction is currently underway. Construction
began in February 2025 and is scheduled for completion in January 2026.
DISCUSSION:
After starting construction of the water and sewer lines for the project, City staff discovered that the bid for the
utilities did not include an adequate quantity for permanent pavement repair. The permanent pavement repair
includes a 6" thick concrete slab with a 3" cap of asphalt. This type of repair is necessary to prevent settlement
along the trench line for the water and sewer mains, which is especially important since the trench is along one
of the inner lanes of College Avenue.
This change order increases the permanent pavement repair quantity to cover the necessary construction.
With the increased pavement repair, it is expected that additional time will be required for the contractor to
perform the work. The contractor is charged daily for the traffic control measures installed to protect workers
and drivers along the project corridor. An additional 60 days of traffic control is included in the change order to
cover this expense if necessary.
Lastly, with the increase in the contract amount, the bonding is required to be increased. The bonding increase
will include this change order plus the contingency amount previously approved by Council.
BUDGET/STAFF IMPACT:
Water and Sewer Line Improvement Funds will be used for the pavement repair and traffic control for this
change order ($500,869.20). The increase in bond amount to cover the project contingency will be paid for
using the Transportation Bond Funds ($36,602.21).
ACCOUNT
PROJECT
AMOUNT
4702.860.7221-5809.00
46020.7221.1020
$36,602.21
5400.860.5600-5808.00
11011.2019.7221
$500,869.20
ATTACHMENTS: SRF (#3) , BA (#4), Change Order #1 (#5)
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
== City of Fayetteville, Arkansas
y 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
- Legislation Text
File #: 2025-499
BENCHMARK CONSTRUCTION COMPANY OF NWA, INC. (CHANGE ORDER #1):
A RESOLUTION TO APPROVE CHANGE ORDER NO. 1 TO THE CONTRACT WITH
BENCHMARK CONSTRUCTION COMPANY OF NWA, INC. IN THE AMOUNT OF $537,471.41
FOR THE COLLEGE AVENUE IMPROVEMENTS PROJECT, AND TO APPROVE A BUDGET
ADJUSTMENT
WHEREAS, on August 6, 2024, City Council approved a contract with Benchmark Construction for a
portion of the College Avenue Improvements Project between North Street and Sycamore Street, but the
City was unable to receive concurrence of award from ARDOT for the contract; and
WHEREAS, on December 17, 2024, City Council approved a new contract with Benchmark
Construction and received ARDOT approval; and
WHEREAS, after starting construction of the water and sewer lines for the project, City staff
discovered that the bid for the utilities did not include an adequate quantity for permanent pavement
repair and this change order increases the permanent pavement repair quantity to cover the necessary
construction, extends traffic control by 60 days, and increases the bond amount.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to
sign Change Order No. 1 to the contract with Benchmark Construction Company of NWA, Inc. in the
amount of $537,471.41 for the College Avenue Improvements Project. A copy of Change Order No. 1
is attached to this Resolution and made a part hereof.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
Page 1
Matt Casey
Submitted By
City of Fayetteville Staff Review Form
2025-499
Item ID
5/6/2025
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
4/11/2025 ENGINEERING (621)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Change Order 1 with Benchmark Construction for the College Avenue Improvements
Project (North to Sycamore), which will increase the contract amount by $537,471.41 and extend the contract time
by 60 days and approval of a budget adjustment.
Budget Impact:
4702.860.7221-5809.00
Street Projects 2022 Bonds
5400.860.5600-5808.00
Water and Sewer
Account Number
Fund
46020.7221.1020
Hwy 71B Corridor - North to Township
11011.2019.7221
Water & Sewer Relocations - Bond Projects
Project Number
Project Title
Budgeted Item? Yes
Total Amended Budget $ 10,861,857.00
Expenses (Actual+Encum) $ 9,021,218.26
Available Budget $ 1,840,638.74
Does item have a direct cost? Yes
Item Cost $ 537,471.41
Is a Budget Adjustment attached? Yes
Budget Adjustment $ 537,473.00
Remaining Budget $ 1,840,640.33
V20221130
Purchase Order Number: 2025-00000241 Previous Ordinance or Resolution # 311-24
Change Order Number: 1
Approval Date:
Original Contract Number: 2024-00000041
Comments:
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division ENGINEERING (621) Adjustment Number
2025 /Org2
Requestor: Matt Casey
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Staff recommends approval of Change Order 1 with Benchmark Construction for the College Avenue Improvements
Project (North to Sycamore), which will increase the contract amount by $537,471.41 and extend the contract time by
60 days and approval of a budget adjustment.
COUNCIL DATE:
ITEM ID#:
5/6/2025
2025-499
Nolly Black
417412025 71:24 RM
Budget Division Date
TYPE: D - (City Council)
JOURNAL#:
RESOLUTION/ORDINANCE
I
GLDATE:
CHKD/POSTED:
TOTAL
Account Number
- -
Increase / (Decrease)
Expense Revenue
Prolect.Sub#
Project Sub.Detl
AT
v.2025411
Account Name
4702.860.7221-5809.00
36,603 -
46020
7221.1020
EX
Improvements - Street
4702.860.7221-5911.99
5400.860.5600-5808.00
(36,603) -
500,870 -
46020
11011
7221.1020
2019.7221
EX
EX
Contingency - Capital Project
Improvements - Water Line
5400.720.5600-5808.00
5400.720.5600-5810.00
(450,792) -
(50,078) -
10007
10007
1
1
EX
EX
Improvements - Water Line
Easements
G:\Divs\Engineering\Engineering Design Services\Projects\BOND PROGRAM\2019 Bond Program\Hwy 71 B Corridor 040887\Council
and Committee Items\Construction Change Order 1 \2025-499 BA Benchmark C01 Hwy 71 B Corr 1 of 1
CITY OF
FAYETTEVILLE
ARKANSAS
CHANGE ORDER
Contract Title: College Ave. Improvements (North to Sycamore)
Change Order No.
To Contractor: Benchmark Construction Company ofNWA, Inc.
The Contract is changed as follows:
Date of Issuance April 1, 2025
ORDINANCE/RESOLUTION:311-24
Effective December 27. 2024
Bid
Bid
Previous
Unit
Contract
Revised
Revised
Original
Revised
Contract
Item
Item
Estimated
of
Unit
Estimated
Unit
Estimated
Estimated
Changes
No.
Description
Quantity
Measure
Price
Quantity
Price
Cost
Cost
1.2
Insurance and Bonding
1
LS
$231,838.00
1
$268,440.21
$ 231,838.00
$268,440.21
1.136
Traffic Control and Maintentance (Beyond 4-Month Waterline Installation)
0
Day
$0.00
60
$1,740.17
$ -
$104,410.20
2.37
Permanent Pavement Repair
350
SY
$170.52
2675
$170.52
59,682.00
$456,141.00
Summation of Cost 291,520.00
$828,991.41
Net Cost for this Change Order
$537,471.41
Not valid until signed by the Owner
The original Contract Price was
................................................................................................................................................. $
8,693,634.49
Net change by previously authorized change orders
$
The Contract Price prior to this Change Order was
................................................................................................................................................. $
.................................................................................................................................................
8,693,634.49
The Contract Price will be adjusted by
.................................................................................................................................................
$537,471.41
The new Contract Price including this Change Order will be
............................................................. ------------------$
9,231,105.90
The Contract Time(s) will be increased by
60
calendar days
Required dates of Completion as of the date of this Change Order therefore are:
...............................................................................................
Substantial Completion
19-Feb-26
Final Completion------------------------------------------------------------------------------------------
21-Mar-26
NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have been authorized by Work Change Directives not incorporated in this or previous Change Orders.
BENCHMARK CONSTRUCTION COMPANY OF NWA, INC.
April1
25
BY
CITY OF FAYETTEVILLE
BY
DATE
2025