HomeMy WebLinkAbout04-25 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 4-25
File Number: 2024-01095
OLSSON, INC. (AMENDMENT NO. 1):
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL ENGINEERING SERVICES
AGREEMENT WITH OLSON, INC. IN THE AMOUNT OF $116,225.00 FOR FINAL ENGINEERING DESIGN
RELATED TO UPGRADES NEEDED AT THE MALLY WAGNON SEWER LIFT STATION
WHEREAS, the City's Mally Wagnon sewer lift station located at 5716 E. Norman Murphy Road receives sewer flow
from several residential areas east of the West Fork of the White River along Highway 16 and 100% of sewer from the
City of Elkins; and
WHEREAS, the City of Elkins is actively upgrading its sewer pumping capabilities and the City of Fayetteville will
not be able to accept maximum flows until this Mally Wagnon lift station is upgraded; and
WHEREAS, on June 4, 2024 City Council passed Resolution 155-24 that approved the original agreement with Olsson
for preliminary engineering and Amendment No. 1 will provide funds to complete detailed engineering design and
specification preparation so the project can be publicly bid.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn to sign
Amendment No. 1 to the Professional Engineering Services Agreement with Olsson, Inc. in the amount of $116,225.00
for final engineering design related to upgrades needed at the Mally Wagnon Sewer Lift Station.
PASSED and APPROVED on January 7, 2025
Approved:
E-SIGNED by Molly Rawn
on 2025-01-14 21:49:15 GMT
Molly Rawn, Mayor
Attest: \\\I111 II////
��RK TR',N/
E-SIGNED by Kara Paxton_ �G�TY 0'� 'r. r
on 2025-01-14 23:16:55 GMT': FAYETTEVILLE:
Kara Paxton, City Clerk TreasurerPC
G0�����`
Page 1
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF JANUARY 7, 2025
CITY COUNCIL MEMO
2024-01095
TO: Mayor Rawn and City Council
THRU: Susan Norton, Chief of Staff
FROM: Tim Nyander, Utilities Director
SUBJECT: Olsson, Inc. - Amendment No. 1 to the Engineering Services Agreement for the Mally
Wagnon Lift Station Improvements Project
RECOMMENDATION:
Staff recommends approval of Amendment No. 1 to the Engineering Services Agreement with Olsson, Inc. in
the amount of $116,225.00 for Final Engineering Design related to upgrades needed at the Mally Wagnon
Sewer Lift Station.
BACKGROUND:
The City's Mally Wagnon sewer lift station is located at 5716 E. Norman Murphy Road. This station receives
sewer flow from several residential areas east of the West Fork of the White River along Highway 16. The
station also receives 100% of sewer from the City of Elkins, metered wholesale to the Fayetteville from a lift
station owned by Elkins. The City of Elkins is actively upgrading their sewer pumping capabilities and the City
of Fayetteville will not be able to accept their max flows until this Mally Wagnon lift station is upgraded.
DISCUSSION:
The original agreement with Olsson (Res. 155-24) resulted in a Preliminary Engineering Report (PER) which
details expected combined flows that would come to the station and alternatives for upgrades to the station to
meet these future flows. The key takeaway from the PER is that the station can be upgraded, and does not
require complete replacement.
Amendment No. 1 will provide funds to complete detailed engineering design and specification preparation so
that the project can be publicly bid.
BUDGET/STAFF IMPACT:
Funds are available in the Sanitary Sewer Rehabilitation account within the Water & Sewer fund.
ATTACHMENTS: SRF (#3), Amendment No. 1 (#4), Scope and Fees (#5)
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
== City of Fayetteville, Arkansas
Y 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
- Legislation Text
File #: 2024-01095
Olsson, Inc. - Amendment No. 1 to the Engineering Services Agreement for the Mally Wagnon
Lift Station Improvements Project
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL ENGINEERING
SERVICES AGREEMENT WITH OLSON, INC. IN THE AMOUNT OF $116,225.00 FOR FINAL
ENGINEERING DESIGN RELATED TO UPGRADES NEEDED AT THE MALLY WAGNON
SEWER LIFT STATION
WHEREAS, the City's Mally Wagnon sewer lift station located at 5716 E. Norman Murphy Road
receives sewer flow from several residential areas east of the West Fork of the White River along
Highway 16 and 100% of sewer from the City of Elkins; and
WHEREAS, the City of Elkins is actively upgrading its sewer pumping capabilities and the City of
Fayetteville will not be able to accept maximum flows until this Mally Wagnon lift station is upgraded;
and
WHEREAS, on June 4, 2024 City Council passed Resolution 155-24 that approved the original
agreement with Olsson for preliminary engineering and Amendment No. 1 will provide funds to
complete detailed engineering design and specification preparation so the project can be publicly bid.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Rawn
to sign Amendment No. I to the Professional Engineering Services Agreement with Olsson, Inc. in the
amount of $116,225.00 for final engineering design related to upgrades needed at the Mally Wagnon
Sewer Lift Station.
Page 1
Tim Nyander
Submitted By
City of Fayetteville Staff Review Form
2024-1095
Item ID
1/7/2025
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
12/17/2024 WATER SEWER (720)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Amendment No. 1 to the Engineering Services Agreement with Olsson, Inc. in the
amount of $116,225.00 for Final Engineering Design related to upgrades needed at the Mally Wagnon Sewer Lift
Station.
5400.720.5700-5314.00
Account Number
02017.1
Project Number
Budgeted Item? Yes
Does item have a direct cost? Yes
Is a Budget Adjustment attached? No
Purchase Order Number:
Change Order Number:
Original Contract Number:
Comments:
Budget Impact:
Water and Sewer
Fund
Sanitary Sewer Rehabilitation
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$
1,287,629.00
$
598,248.62
689,380.38
$
116, 225.00
573,155.38
V20221130
2024-609 Previous Ordinance or Resolution # Res. 155-24
1 Approval Date:
2024-33
AMENDMENT NO. 1
To
AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES
Between
CITY OF FAYETTEVILLE, ARKANSAS
And
OLSSON INC.
MALLY WAGNON SEWER LIFT STATION UPGRADES
WHEREAS, on June 4, 2024, the City of Fayetteville, Arkansas (CITY OF FAYETTEVILLE) and
Olsson Inc. of Fayetteville, Arkansas (ENGINEER) entered into an Agreement for engineering services in
connection with the Mally Wagnon Sewer Lift Station Upgrades (the "Project"); and
WHEREAS, the scope of the current Agreement includes the ENGINEER providing services in
connection with the evaluation, design, and/or construction administration of capital improvement
projects, and
WHEREAS, the current Agreement must now be amended to provide the additional fee and amount of
compensation to the ENGINEER for the additional work; and
NOW THEREFORE, in consideration of the mutual covenants and Agreements herein contained, CITY
OF FAYETTEVILLE and the ENGINEER, the parties hereto, stipulate and agree that the Agreement for
Engineering Services dated June 4, 2024, is hereby amended in the following particulars:
SECTION 5 — PAYMENTS TO ENGINEER
Delete Paragraph 5.1 and replace with the following:
5.1 The maximum not -to -exceed amount authorized for this Agreement is $161,225.00. The CITY
OF FAYETTEVILLE shall compensate ENGINEER based on an hourly NTE basis as
described in Appendix A.
APPENDIX A — SCOPE OF SERVICES
A. Detailed Design
Delete First Paragraph and replace with the following:
Olsson will prepare detailed drawings and technical specifications for the recommended construction
work. The design will include:
Civil and Process engineering.
Mechanical, electrical, and plumbing (MEP) engineering.
Instrumentation and controls (I&C) engineering.
Olsson will submit construction documents to the Client at 60 and 90 percent design stages, conduct a
meeting with Client or Client's Designee to discuss their review comments, and resolve questions or
concerns.
Olsson will conduct internal quality reviews at 60 and 90 percent design stages.
024-03833 Amendment No.1 Page 1
Based upon final plans and specifications, Olsson will prepare an opinion of probable cost of the
authorized construction. It is understood and agreed that this opinion will be prepared for planning and
budgeting purposes only and that actual bids received for the construction work may exceed the opinion
of probable cost.
Olsson will submit documents for agency reviews, including the Arkansas Department of Health (ADH),
and coordinate approval by the agencies. ADH $500 review fee included.
B. Bidding Services
Delete First Paragraph and replace with the following:
Olsson will transmit Plans, Specifications, and additional contract documents to the Client and the
Client's purchasing department for distribution to bidders.
Olsson will coordinate answering questions raised by bidders. Addenda will be prepared, if needed, to
provide clarification to questions. The Client will be informed on a regular basis of project changes
resulting from bidders' questions.
Olsson will schedule and attend a pre -bid meeting with the project team and perspective bidders.
Olsson will attend the bid opening. Bids properly received will be reviewed. Inconsistencies or
irregularities found in the bids will be reported to the Client. Olsson will prepare a bid tabulation of bids
received and will make the bid tabulation available to bidders. Olsson will evaluate the bids and make a
written recommendation to the Client concerning contract award.
C. Project Schedule
Add the following to the end of the bulleted list:
• Water, Sewer Committee:
• Council Approval:
• Design Kickoff Meeting:
• Detailed Design:
• QA/QC:
• Submit to ADH:
• Est. Bid Advertisement:
• Bidding Phase Services:
D. Compensation
Tuesday, December 10, 2024
Tuesday, January 7, 2025
Tuesday, January 14, 2025
112 Days
14 Days
Monday, May 19, 2025
Sunday, July 13, 2025
21 Days
Delete Last Paragraph and replace with the following:
Olsson's Scope of Services will be provided on a time -and -expense basis not to exceed $161,225.00.
E. Additional Services
Delete the bulleted list and replace with the following:
024-03 83 3 Amendment No.I Page 2
• Construction testing, administration, and observation services
Amendment No. 1 increases the Mally Wagnon Sewer Lift Station Upgrades total project by $116,225.00
for additional services related to Detailed Design and Bid Advertisement.
All other provisions of the original Agreement remain in full force and effect.
IN WITNESS WHEREOF, CITY OF FAYETTEVILLE, ARKANSAS by and through its Mayor, and
ENGINEER, by its authorized officer have caused this Amendment to be duly executed this 7 day of
January ,2025.
CITY OF FAYETTEVILLE, ARKANSAS
E-SIGNED by Molly Rawn
By: on 2025-01-14 21:49:17 GMT
Mayor, Molly A. Rawn
K
ATTEST: TOF�s
"•-x
E-SIGNED by Kara Paxton- t:
By: on 2025-01-14 23:17:01 GMT v: FAYETTEVILLE:
City Clerk Treasurer, % �•:9 5••
' �9�; '4KANS?:
Kara Paxton i,. ti�..� • • • W!
OLSSON INC.
Li4
Chris Hall, P.E.; Water Market Leader
B
Chris Dougherty, .E.; eenior Engineer
END OF AMENDMENT NO. 1 TO
AGREEMENT FOR PROFESSIONAL ENGINEERING SERVICES
024-03 83 3 Amendment No.l Page 3
olsson QD
Appendix A
SCOPE OF SERVICES
Corey Granderson
Utilities Engineer
City of Fayetteville, Arkansas
PROJECT DESCRIPTION AND LOCATION
Project will be located at: 5716 E Norman Murphy Road, Fayetteville, AR
Project Description: Mally Wagnon Sewer Lift Station Upgrades
SCOPE OF SERVICES
Olsson hereby agrees to provide the following services ("Scope of Services") to the City of
Fayetteville ("Client") for the Project:
PHASE 100 PROJECT ADMINISTRATION
Project Management
Project management includes coordination of the various disciplines that have
involvement in the project, tracking work completion, maintenance of project schedule,
billings, and miscellaneous communication with the Client and internal staff.
Project Kickoff Meeting
Olsson will schedule and attend an in -person project kickoff meeting with the Client.
The purpose of the meeting will be to establish the project chain of communication,
discuss and clarify the Scope of Services, and finalize the project schedule.
Olsson will make a formal data request at the kickoff meeting to identify additional
information from the Client to complete the project. The information request is
anticipated to include, but is not limited to, the following:
• Existing Pump Data for Elkins Lift Station
• Existing Pump Data for Mally Wagnon Lift Station
• Shop Drawing information for Mally Wagnon Lift Station mechanical and
electrical equipment
• Previous Inspection Reports
• Facility Plans
Suite 310 / 3537 North Steele Blvd. / Fayetteville, AR 72703
o 479.443.3404 / f 479.443.4340 / olsson.com
Olsson will provide the Meeting Agenda and generate and distribute meeting minutes
within two days of the meeting's conclusion.
Monthly Progress Meetings
Olsson will schedule monthly in -person progress meetings involving its project staff
and the Client's personnel. The purpose of these meetings will be to keep all parties
informed concerning project status and to provide an opportunity to exchange
information.
Olsson will provide the Meeting Agenda and generate and distribute meeting minutes
within two days of the meeting's conclusion.
PHASE 200 PRELIMINARY DESIGN
Project Site Visit
Olsson personnel shall visit site to conduct inspection of existing mechanical,
structural, and electrical systems. Engineers will discuss with Operations and
Maintenance personnel the normal operating schedules and procedures for the
equipment to be upgraded.
Data Collection
Olsson will review current and past studies, design memorandums and reports, contract
record drawings, approved shop drawings, and other related documents associated
with the Elkins Lift Station that is operated by the City of Elkins, AR and for the
Mally Wagnon Lift Station operated by the City of Fayetteville, AR. Collect field data
to verify dimensions, operating characteristics, and physical condition of equipment,
structures, and electrical systems.
Design Analysis
Olsson will analyze collected data to determine current and future pumping capacity
requirements. Develop a list of potential improvements that could be implemented to meet
these requirements. Develop conceptual cost estimates for the potential improvements and
provide upgrade recommendation to the City of Fayetteville.
Preliminary Engineering Report
Compile results from research and analysis activities into a Preliminary Engineering
Report that will be submitted to the Client for review. Preliminary Engineering Report
will follow report requirements of Recommended Standards for Wastewater Facilities
Suite 310 / 3537 North Steele Blvd. / Fayetteville, AR 72703
o 479.443.3404 / f 479.443.4340 / olsson.com
(10 state standards) issued by Great Lakes -Upper Mississippi River Board of State and
Provincial Public Health and Environmental Managers as required by Arkansas
Department of Health.
Quality Control Review
Olsson will conduct an internal quality control review of the Preliminary Engineering
Report before it is forwarded to the Client for review.
Review Meeting and Follow Up
Olsson will schedule and attend a review meeting with the Client to discuss the
Preliminary Engineering Report. Olsson will provide the Meeting Agenda and generate
and distribute meeting minutes within one week of the meeting's conclusion.
The Preliminary Engineering Report will be revised in accordance with agreements
reached at the review meeting and a revised final draft will be submitted.
PHASE 300 DETAILED DESIGN
Olsson will prepare detailed drawings and technical specifications for the recommended
construction work. The design will include:
• Civil and Process engineering.
• Mechanical, electrical, and plumbing (MEP) engineering.
• Instrumentation and controls (I&C) engineering.
Olsson will submit construction documents to the Client at 60 and 90 percent design
stages, conduct a meeting with Client or Client's Designee to discuss their review
comments, and resolve questions or concerns.
Olsson will conduct internal quality reviews at 60 and 90 percent design stages.
Based upon final plans and specifications, Olsson will prepare an opinion of probable cost
of the authorized construction. It is understood and agreed that this opinion will be
prepared for planning and budgeting purposes only and that actual bids received for the
construction work may exceed the opinion of probable cost.
Olsson will submit documents for agency reviews, including the Arkansas Department of
Health (ADH), and coordinate approval by the agencies. ADH $500 review fee included.
PHASE 400 BIDDING SERVICES
Suite 310 / 3537 North Steele Blvd. / Fayetteville, AR 72703
o 479.443.3404 / f 479.443.4340 / olsson.com
Olsson will transmit Plans, Specifications, and additional contract documents to the Client
and the Client's purchasing department for distribution to bidders.
Olsson will coordinate answering questions raised by bidders. Addenda will be prepared,
if needed, to provide clarification to questions. The Client will be informed on a regular
basis of project changes resulting from bidders' questions.
Olsson will schedule and attend a pre -bid meeting with the project team and perspective
bidders.
Olsson will attend the bid opening. Bids properly received will be reviewed.
Inconsistencies or irregularities found in the bids will be reported to the Client. Olsson will
prepare a bid tabulation of bids received and will make the bid tabulation available to
bidders. Olsson will evaluate the bids and make a written recommendation to the Client
concerning contract award.
PHASE 500 ENGINEERING CONSTRUCTION ADMINISTRATION
Services for Engineering Construction Administration are not included. These services
are additional and shall be addressed by a Contract Amendment if requested.
PHASE 600 CONSTRUCTION OBSERVATION AND TESTING SERVICES
Construction Observation and Testing Services are not included. These services are
additional and shall be addressed by a Contract Amendment if requested.
PROJECT SCHEDULE
• Water, Sewer Committee:
• Council Approval:
• Design Kickoff Meeting:
• Detailed Design:
• QA/QC:
• Submit to ADH:
• Est. Bid Advertisement:
• Bidding Phase Services:
COMPENSATION
Tuesday, December 10, 2024
Tuesday, January 7, 2025
Tuesday, January 14, 2025
112 Days
14 Days
Monday, May 19, 2025
Sunday, July 13, 2025
21 Days
Client shall pay to Olsson for the performance of the Scope of Services, the actual hourly labor rates
of personnel performing such services on the project times a factor of 3.20, and all actual
reimbursable expenses in accordance with the Reimbursable Expense Schedule attached to this
Suite 310 / 3537 North Steele Blvd. / Fayetteville, AR 72703
o 479.443.3404 / f 479.443.4340 / olsson.com
agreement. Olsson shall submit invoices monthly, and payment is due within 30 calendar days of
invoice date.
Olsson's Scope of Services will be provided on a time -and -expense basis not to exceed
$161,225.00.
ADDITIONAL SERVICES
Should Client request work in addition to the Scope of Services, Olsson shall invoice Client for
such additional services (Optional Additional Services) at the standard hourly billing labor rate
charged for those employees performing the work, plus reimbursable expenses if any. Olsson
shall not commence work on Optional Additional Services without Client's prior written approval.
Optional Additional Services shall include, but not be limited to, the following:
• Construction testing, administration, and observation services
Olsson agrees to provide its services in a timely, competent, and professional manner, in
accordance with applicable standards of care, for projects of similar geographic location, quality
and scope.
EXCLUSIONS AND LIMITATIONS
This Scope of Services is limited to the items listed in the Tasks above. Excluded services include:
For this project the analysis shall commence with the introduction of flow into the Mally Wagnon
Lift Station wet well and shall conclude at the point where the force main discharges into the 36"
and 42" gravity service lines. Analysis of the capacity of these gravity sewer lines is not included
within this Scope of Services.
Suite 310 / 3537 North Steele Blvd. / Fayetteville, AR 72703
o 479.443.3404 / f 479.443.4340 / olsson.com
Client: City of fayetteville, AR
Project: Mally Wa¢non Sewer Lift Station Updates
Date: 11/18/2024
PHASE/Task
Engineer
(PM)
Group
Leader
Admin
Senior
Civil
Engineer
Associate
Civil
Engineer
MEP
Group
Leader
Associate
Electrical
Engineer
Associate
Mechanical
Engineer
TOTAL
HOURS
TOTAL
FEE
Phase 100 - Project Administration
Task 100001 -WTR WWW-GN Project Management
$ 11,500
Task 100001 - WTR WWW-GN Project Management
40
10
50
$ 8,260
$ 19,760
Phase 200 - Preliminary Design
Task 200001 - WTR WWW-GN Design
Task 200002 - STH FED-GN Electrical Facilities Eval
$ 33,500
Phase 300 - Detailed Design
Task 300001 - WTR WWW-GN Design
40
10
40
40
280
410
$ 58,750
Task 300002 - STH FED-GN Electrical Facilities
20
120
140
$ 20,000
Task 300003 - IND FED-GN I&C Detailed Design
4
20
120
144
$ 21,040
$ 99,790
Phase 400 - Bidding Services
Task 300001 - WTR WWW-GN Design (PER)
10
5
5
10
30
$ 4,375
Task 300002 - STH FED-GN Electrical Facilities Eval (PER)
4
5
9
$ 1,500
Task 300003 - IND FED-GN I&C Detailed Design
5
5
10
$ 1,750
$ 7,625
Phase 900 - Expenses
Task 900001 - ADH
$ 550
Total, Billings
240
249
120
281
427
269
255
255
793
$ 161,225