Resolution: 306-24
File Number: 2024-0901
PORTER WAREHOUSE STABILIZATION (CHANGE ORDER #1):
A RESOLUTION TO APPROVE CHANGE ORDER #1 TO THE CONTRACT WITH JBZ INC. DB/A
ELLINGSON CONTRACTING IN THE AMOUNT OF $178,526.13 FOR THE PORTER WAREHOUSE
STABILIZATION PROJECT
WHEREAS, on May 7, 2019, the City Council approved Resolution 116-19 authorizing a contract with Revival
Architecture, Inc. for a building conditions assessment, historical report and temporary stabilization drawings for the
Porter Warehouse Stabilization Project; and
WHEREAS, on February 20, 2024, City Council approved Resolution 70-24 authorizing a construction contract with
JBZ Inc. d/b/a Ellingson Contracting for the stabilization project; and
WHEREAS, Change Order #1 authorizes additional work on the project, including the construction of a new roof,
interior framing improvements, roof decking replacement, increased insulation thickness, and new entry deck, stairs,
and railing.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order # 1 to the contract
with JBZ Inc. d/b/a Ellingson Contracting in the amount of $178,526.13 for the Porter Warehouse Stabilization Project,
contingent upon approval of the 2025 Capital Budget.
PASSED and APPROVED on December 17, 2024
Page 1
Attest:
i
A. G\1 Y 0'r •'G'A
=v; FAYETTEV!i I.r. • ��—
Kara Paxton, City Cl Treasurer
CCEllingson Contracting
ellingson contracting PO Box 7202
Siloam Springs,AR 72761
Porter Warehouse I Prime Change Order#1
Date: 11/25/2024
To: Wade Abernathy
City of Fayetteville
Re: Porter Warehouse Stabilization
406 W Spring St
Fayetteville,AR 72701
Description of Proposed Change:
Increase contract value by$178,526.13 for the following additional work:
-Provide new roof
-Provide interior framing improvements
-Provide roof decking replacement
-Provide increased insulation thickness to achieve R-38
-Provide new entry deck,stairs,and railing
-Provide(2)new columns and footings on West end of building
-Extended general conditions for added work(2mo)
Line Item Breakout
Description Material Labor Equipment Sub/Other Total
PCO-01-New Roof $ 74,508.00 $ 74,508.00
PCO-01-Framing Improvements $ 29,750.00 $ 29,750.00
PCO-01-Roof Decking Replacement $ 2,536.00 $ 2,536.00
PCO-02-R-38 Insulation $ 11,177.95 $ 11,177.95
PCO-05-Entry Deck $ 18,344.69 $ 18,344.69
PCO-07-Columns&Footings $ 2,425.86 $ 2,425.86
PCO-12-Extended GCs(2mo) $ 39,783.63 $ 39,783.63
$
$
Subtotal $ $ • $ - $ 178,526.13
Previous Contract Value I $ 733,746.00
Lump Sum Total with Proposed Revisions S 912,272.13
Time Extension Requested: 63 Days
New Contract Completion Date 2/17/2025
If you have any questions please feel free to contact me.
Sincerely, Acceptance of Change
Nathan Greathouse:=-^sr.•:-:, Name neld dan or
Nathan Greathouse Signature,
Ellingson Contracting
Project Manager Date
CITY OF CITY COUNCIL MEMO
�® FAYETTEVILLE
ARKANS
A R KA N S AS 2024-0901
MEETING OF DECEMBER 17, 2024
TO: Mayor Jordan and City Council
THRU: Paul Becker, Chief Financial Officer
FROM: Waylon Abernathy, Bond Projects & Construction Dir
SUBJECT: Change Order #1 to Bid 23-47 Construction Contract with JBZ Inc., dba Ellingson
Contracting for Porter Warehouse Stabilization.
RECOMMENDATION:
Approval of Change Order #1 to Bid 23-47 Construction Contract with JBZ Inc. for Porter Warehouse
Stabilization in the amount of $178,526.13. Contingent on approval of 2025 Capital Budget.
BACKGROUND:
2019, Revial Architetecture provided a building condition assessment, historical report, and temporary
stabilization drawings.
2020, Placed on the Historical Register.
2023 Revival Architectural Contract for Bid Documents and Construction Administration
2024 Resolution 70-24 Authorized a construction contract for the stabilization.
DISCUSSION:
There was concern of the weight associated with the many number of layers of roofing, and the current metal
had signs of leaking. It was determined that with this investment, it was best to replace the roof system with
TPO, and R-38 ISO insulation to meet the current code.
Research shows that originally, there was a platform for loading rail cars. The new entry platform will mimic
that.
Rotten decking was replaced, along with additional framing, and added columns @ footings to take some
weight off of the exterior walls.
BUDGET/STAFF IMPACT:
Funding for the Change Order will be from 2024 Sales Tax Capital Improvements 4470.090.8900-5400.00
Porter Warehouse Stabilization Project, contingency funds, and 2025 Sales Tax Capital Improvements.
This change is contingent on approval 2025 capital. Budget.
ATTACHMENTS: SRF (#3), Prime Change Order #1 - Signed (#4)
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
== City of Fayetteville, Arkansas
y 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
- Legislation Text
File #: 2024-0901
Change Order #1 to Bid 23-47 Construction Contract with JBZ Inc., dba Ellingson Contracting
for Porter Warehouse Stabilization.
A RESOLUTION TO APPROVE CHANGE ORDER #1 TO THE CONTRACT WITH JBZ INC.
D/B/A ELLINGSON CONTRACTING IN THE AMOUNT OF $178,526.13 FOR THE PORTER
WAREHOUSE STABILIZATION PROJECT
WHEREAS, on May 7, 2019, the City Council approved Resolution 116-19 authorizing a contract with
Revival Architecture, Inc. for a building conditions assessment, historical report and temporary
stabilization drawings for the Porter Warehouse Stabilization Project; and
WHEREAS, on February 20, 2024, City Council approved Resolution 70-24 authorizing a construction
contract with JBZ Inc. d/b/a Ellingson Contracting for the stabilization project; and
WHEREAS, Change Order #1 authorizes additional work on the project, including the construction of a
new roof, interior framing improvements, roof decking replacement, increased insulation thickness, and
new entry deck, stairs, and railing.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order #1
to the contract with JBZ Inc. d/b/a Ellingson Contracting in the amount of $178,526.13 for the Porter
Warehouse Stabilization Project, contingent upon approval of the 2025 Capital Budget.
Page 1
Wade Abernathy
Submitted By
City of Fayetteville Staff Review Form
2024-901
Item ID
12/17/2024
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
11/25/2024 FACILITIES MANAGEMENT (140)
Submitted Date Division / Department
Action Recommendation:
Approval of Change Order #2 Bid 23-47 Construction Contract with JBZ Inc. dba Ellingson in the amount of
$178,526.13 for the stabilization of the Porter warehouse, contingent on approval of 2025 capital budget.
4470.090.8900-5400.00
Account Number
20001.1
Project Number
Budgeted Item? Yes
Does item have a direct cost? Yes
Is a Budget Adjustment attached? No
Budget Impact:
Building Grounds and Maintenance
Fund
Porter Warehouse Stabilization
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$ 985,600.00
$ 779,196.00
206,404.00
$ 178,526.13
27,877.87
V20221130
Purchase Order Number:
Change Order Number:
Original Contract Number:
2024-638
1
2024-14
Previous Ordinance or Resolution # 70-24
Approval Date: 2/20/2024
Comments: Total amended budget amount includes $150,000 in the 2025 budget.