MCCLELLAND CONSULTING ENGINEERS, INC. (AMENDMENT NO. 1):
A RESOLUTION TO APPROVE AMENDMENT NO. I TO THE PROF ESS IONAL ENGINEERING SERVICES
AGREEMENT WITH MCCLELLAND CONSUL TING ENGINEERS, INC. IN THE AMOUNT OF $35 ,300.00 FOR
CONSTRUCTION PHASE SERVICES FOR THE COLLEGE A VENUE WATERLINE REPLACEMENT PROJECT
WHEREAS, on June 5, 2018 , City Council passed Resolution No. 119-18 approving a Profess ional Engineering
Services Agreement with McClelland Consulting, Inc . for engineering services associated with the replacement of
existing water mains along N. College Ave. between North Street and E. Mil sap Rd.; and
WHEREAS , Amendment No. I provides for support services needed by McClelland Consulting Engineers, Inc.
including administrative tasks and closeout support.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section I: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign
Amendment No. I to the Professional Engineering Services Agreement with McClelland Consulting Engineers, Inc . in
the amount of $35,300.00 for construction phase services for the College Avenue Waterline Replac e ment Project.
PASSED and APPROVED on October I , 2024
Attest:
Page 1
Amendment No. 1 to the Engineering Services Agreement for
North College Avenue Water Main Replacement
Date: 10-01-2024
WHEREAS, the CITY OF FAYETTEVILLE and McClelland Consulting Engineers , Inc.
(ENGINEER) entered into an Agreement for Professional Engineering Services
(AGREEMENT) on June 5, 2018; and ,
WHEREAS, the CITY OF FAYETTEVILLE has requested that ENGINEER perform additional
services outside of the scope of the AGREEMENT.
NOW THEREFORE, the following modifications will be made to the AGREEMENT to
include the additional services requested:
MODIFICATIONS:
1. Section 2 .1.1 -the additional scope of services is included in the attached
Appendix "A-1 ".
2. Section 5.1 -the maximum not-to-exceed amount is increased from $128 ,930.00 to
$164,230.00 . Modifications to compensation are included in the attached
Appendix "A-2 ".
IN WITNESS WHEREOF, the parties execute this Amendment No. 1, to be effective on the
date set out above .
McClelland Consulting Engineers , Inc.
BY:
Nicholas R. Batker, P .E.
Senior Associate
City of Fayetteville , Arkansas
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2024-529
MEETING OF OCTOBER 1, 2024
TO: Mayor Jordan and City Council
THRU: Susan Norton, Chief of Staff
FROM: Tim Nyander, Utilities Director
SUBJECT: Amendment No. 1 to the Engineering Services Agreement with McClelland
Consulting Engineers, Inc. for Construction Phase Services for the College Avenue
Waterline Replacement Project
RECOMMENDATION:
Staff recommends approval of Amendment No. 1 to the Engineering Services Agreement with McClelland
Consulting Engineers, Inc. for Construction Phase Services for the College Avenue Waterline Replacement
Project from North St. to Sycamore St. in the amount of $35,300.00.
BACKGROUND:
In conjunction with the City’s roadway improvements along College Avenue from North St. to Sycamore St. the
existing waterline is being replaced due to age, poor condition, and need for additional capacity. The waterline
improvements were bid together with the roadway project and the City Council recently approved the
construction award (Res. 206-24).
DISCUSSION:
The water/sewer division intends to provide daily observation and inspection with in-house staff, but support
services are needed by the Engineer of Record, McClelland, for administrative tasks, and closeout support.
These services will be provided through Amendment No. 1 in an amount not to exceed $35,300.00. Staff
recommends approval of this amendment.
BUDGET/STAFF IMPACT:
Funds are available for this project in the Water System Rehabilitation/Replacement account.
ATTACHMENTS: SRF MCE Amendment No. 1 (#3), Amendment No. 1 (#4)
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2024-529
Amendment No. 1 to the Engineering Services Agreement with McClelland Consulting Engineers,
Inc. for Construction Phase Services for the College Avenue Waterline Replacement Project
A RESOLUTION TO APPROVE AMENDMENT NO. 1 TO THE PROFESSIONAL ENGINEERING
SERVICES AGREEMENT WITH MCCLELLAND CONSULTING ENGINEERS, INC. IN THE
AMOUNT OF $35,300.00 FOR CONSTRUCTION PHASE SERVICES FOR THE COLLEGE
AVENUE WATERLINE REPLACEMENT PROJECT
WHEREAS, on June 5, 2018, City Council passed Resolution No. 119-18 approving a Professional
Engineering Services Agreement with McClelland Consulting, Inc. for engineering services associated
with the replacement of existing water mains along N. College Ave. between North Street and E. Milsap
Rd.; and
WHEREAS, Amendment No. 1 provides for support services needed by McClelland Consulting
Engineers, Inc. including administrative tasks and closeout support.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign Amendment No. 1 to the Professional Engineering Services Agreement with McClelland
Consulting Engineers, Inc. in the amount of $35,300.00 for construction phase services for the College
Avenue Waterline Replacement Project.
City of Fayetteville Staff Review Form
2024-529
Item ID
10/1/2024
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Tim Nyander 9/11/2024 WATER SEWER (720)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of Amendment No. 1 to the Engineering Services Agreement with McClelland
Consulting Engineers, Inc. for Construction Phase Services for the College Avenue Waterline Replacement Project
from North St. to Sycamore St. in the amount of $35,300.00.
Budget Impact:
5400.720.5600-5314.00 Water and Sewer
Account Number Fund
12009.1 Water System Rehabilitation/Replacement
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $14,500,643.00
Expenses (Actual+Encum)$14,227,983.95
Available Budget $272,659.05
Does item have a direct cost?Yes Item Cost $35,300.00
Is a Budget Adjustment attached?No Budget Adjustment $-
Remaining Budget $237,359.05
V20221130
Purchase Order Number:Previous Ordinance or Resolution #
Change Order Number:Approval Date:
Original Contract Number:
Comments:The previous PO was closed. This amendment will have a new purchase order created.
Appendix A-1 – Scope of Additional Services Page 1 of 2
North College Avenue Water Main Replacement
APPENDIX A-1 – SCOPE OF ADDITIONAL SERVICES
AMENDMENT NO. 1 TO THE ENGINEERING SERVICES AGREEMENT FOR THE
NORTH COLLEGE AVENUE WATER MAIN REPLACEMENT
1.0 General
The scope of additional services includes limited construction administration and construction
observation services for the referenced project, which consists of approximately 3,000 linear feet
of 12-inch water main, 360 linear feet of 8-inch sewer main and related water and sewer
appurtenances along North College Avenue between North Street and Sycamore Street. This
project is part of the North College Avenue roadway improvements, Bid 24-34. Construction is
anticipated to commence in late 2024 and a duration of 210 calendar days is assumed for
construction of the water and sewer improvements.
2.0 Construction Phase Services
2.1 Construction Administration
The ENGINEER will provide limited construction administration services to the CITY
OF FAYETTEVILLE in this Amendment No. 1 as it relates only to the water and sewer
portion of the overall project. The following services are included in this task:
Attend the pre-construction meeting with the Contractor.
Review and respond to Contractor submittals for conformance to the Contract
Documents, Drawings, and Specifications.
Review Contractor’s Requests for Information (RFIs) and issue clarifications as
required.
Assist the CITY OF FAYETTEVILLE with the evaluation, negotiation, and
processing of Contractor change order requests.
Assist the CITY OF FAYETTEVILLE with review of Pay Estimates and associated
quantities as requested. It is assumed that CITY OF FAYETTEVILLE and/or
design engineer for the roadway improvements project will process Pay Estimates.
Conduct site visits to observe the progress and quality of the completed work to
determine compliance with the Contract Documents. Attend monthly progress
meetings if requested by the CITY OF FAYETTEVILLE. A total of twelve (12) site
visits/progress meetings are estimated.
Conduct final inspection and develop punch list. Review punch list of outstanding
items and closeout documents provided by the Contractor.
Prepare Record Drawings based upon as-built survey and information furnished
by the Contractor and field representatives and provide to the CITY OF
FAYETTEVILLE in AutoCAD and PDF format.
Appendix A-1 – Scope of Additional Services Page 2 of 2
North College Avenue Water Main Replacement
2.2 Construction Observation
The CITY OF FAYETTEVILLE intends to provide comprehensive construction
observation services on this project with in-house staff. However, if requested in writing
by the CITY OF FAYETTEVILLE with minimum three (3) business days’ notice, the
ENGINEER will provide construction observation services up to a maximum of 50
hours on this project. ENGINEER will not provide construction observation services
without prior authorization by the CITY OF FAYETTEVILLE.
3.0 Project Deliverables
The ENGINEER will provide the following deliverables to the CITY OF FAYETTEVILLE. Unless
otherwise noted, deliverables will be in PDF format and transmitted via email or file share service.
3.1 Record Drawings
AutoCAD files
PDF copy
One (1) full-size hard copy
3.2 Daily Construction Observation Reports (if Construction Observation Services are
requested and authorized by the CITY OF FAYETTEVILLE).
3.3 Other electronic files as requested by the CITY OF FAYETTEVILLE.
4.0 Compensation
In consideration of the performance of the foregoing services by the ENGINEER, the CITY OF
FAYETTEVILLE will by to the ENGINEER compensation as follows:
4.1 Compensation will be paid to the ENGINEER on the basis of ENGINEER’s standard
hourly rates in effect at the time the work is performed, plus reimbursable expenses.
A task hour fee breakdown is provided as Appendix A-2. ENGINEER’s current rate
schedule is attached hereto as Appendix A-3.
4.2 The maximum not-to-exceed for Amendment No. 1 will be $35,300.
4.3 The maximum not-to-exceed total contract amount is increased from $128,930.00 to
$164,230.00
5.0 Additional Services
Should Additional Services be required, the ENGINEER and CITY OF FAYETTEVILLE will agree
on the scope and not-to-exceed amount of the Additional Services, and said Additional Services
will be authorized under a future amendment to this Agreement.
APPENDIX A-2
City of Fayetteville - N College Avenue Water Main Replacement
Amendment No. 1 - Services During Construction
Personnel Hour Fee Estimate
8/23/2024
Task Description Sr. Project
Manager
Project
Manager
Project
Engineer/
Designer
CAD/GIS
Technician
Const
Observer Extended Cost
Pre-Construction Meeting 2 2 $700.00
Review Contractor's Submittals 8 20 $4,600.00
Review Contractor's RFIs, Field Orders, & Work Change Directives 1 8 20 4 $5,250.00
Change Management (Change Orders)1 6 8 4 $3,050.00
Assist with Pay Estimates and Quantities 8 8 $2,800.00
Monthly Progress Meetings/Site Visits (12 total assumed)16 16 $5,600.00
Final Inspection and Project Closeout 1 4 12 $2,850.00
Prepare Record Drawings and Final Deliverables 1 4 12 24 $5,250.00
Subtotal Labor Hours / Fee - Scope Item 2.1 4 56 98 32 0 $30,100.00
Estimated Reimbursable Expenses
Mileage $100.00
Subtotal Reimbursable Expenses - Scope Item 2.1 $100.00
Total Scope Item 2.1 - Construction Administration 4 56 98 32 0 $30,200.00
Field Observation Services - Requires Prior Authorization by City of Fayetteville 0 0 0 0 50 $5,000.00
Subtotal Labor Hours / Fee - Scope Item 2.2 0 0 0 0 50 $5,000.00
Estimated Reimbursable Expenses
Mileage $100.00
Subtotal Reimbursable Expenses - Scope Item 2.2 $100.00
Total Scope Item 2.2 - Construction Observation 0 0 0 0 50 $5,100.00
GRAND TOTAL AMENDMENT NO. 1 4 56 98 32 50 $35,300.00
Scope Item 2.1 - Construction Administration
Scope Item 2.2 - Construction Observation
Page 1 of 1
Chief Draftsman $110 - $120
Clerical $45 - $85
Construction Observer $75 - $165
Draftsman $70 - $120
Environmental Scientist/Designer $125 - $145
Geotech Engineer $125 - $200
GIS Technician $80 - $140
HR/Payroll Admin $75-$115
Landscape Architect $95 - $200
Media Specialist $85 - $120
Principal $185 - $275
Project Accountant $70 - $155
Project Designer - Intern $50 - $80
Project Designer $80 - $165
Project Engineer $120 - $175
Project Manager $130 - $210
Registered Land Surveyor $100 - $175
Soils Lab Technician $50 - $140
Specification Writer $50 - $100
Sr. Project Manager $160 - $250
Structural Engineer $140 - $180
Survey (2 man or Robotic) Crew $115 - $165
Survey (3 man) Crew $150 - $200
Survey Field (1 Man or Rodman) $45 - $120
Survey GPS $75 - $135
Survey Technician $65 - $110
Expenses @ Cost
Mileage .705/mi
* Standard Hourly Rates may be adjusted annually in accordance with
the normal salary review practices of McClelland Consulting Engineers.
8/7/2023
McCLELLAND CONSULTING ENGINEERS, INC.
*STANDARD HOURLY RATES
APPENDIX A-3