HomeMy WebLinkAbout164-24 RESOLUTIONFile Number: 2024-171
113 West Mountain Street
Fayetteville , AR 72701
(479) 575-8323
Resolution: 164-24
AP AC-CENTRAL, INC. (CHANGE ORDER #1):
A RESOLUTION TO APPROVE CHANGE ORDER NO. I TO THE CONTRACT WITH APAC-CENTRAL, INC .
IN THE AMOUNT OF $371 ,992 .50 FOR THE CONSTRUCTION OF THE 15TH AND RAZORBACK ROAD
INTERSECTION IMPROVEMENTS PROJECT, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, City Staff recommends adding to the contracted work with APAC-Central , Inc . for the 15 th Street and
Razorback Road Intersection Improvement the asphalt overlay and striping of Razorback Road from 15 th Street to
Martin Luther King Boulevard which is on the 2024 asphalt overlay list.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section I : That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign Change
Order No . I to the contract with AP AC-Central , Inc . in the amount of $371 ,992 .50 for the construction of the 15 th and
Razorback Road Intersection Improvements Project to add asphalt overlay and striping of Razorback Road from 15 th
Street to Martin Luther King Boulevard. A copy of Change Order No . I is attached to this Re so lution and made a part
hereof.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution .
PASSED and APPROVED on June 18 , 2024
Attest: L
Page 1
...... CITY OF
~~ FAYETTEVILLE
,,., ARKANSAS
MEETING OF JUNE 18, 2024
TO:
THRU:
FROM:
Mayor Jordan and City Council
Chris Brown , Public Works Director
Susan Norton , Ch ief of Staff
Matt Casey , Engineering Design Manager
CITY COUNCIL MEMO
2024-171
SUBJECT: Approval of Change Order #1 in the amount of $371 ,992 .50 with APAC-Central, Inc.
for the construction of the 15th and Razorback Rd. Intersection Improvements
Project, and approval of a budget adjustment.
RECOMMENDATION:
Staff recommends approval of Change Order #1 in the amoun t of $371 ,992 .50 with APAC-Central , Inc . for the
construction of the 15 th and Razorback Rd. Intersection Improvements Project, and approval of a budget
adjustment.
BACKGROUND:
The intersection of Razorback Road and 15 th Street is a large intersection with multiple lanes entering the
intersection on each leg . The intersection is currently controlled as a four way stop with stop signs on each
leg. Being located in close vicinity of the Baum-Walker Stadium , Pinnacle Foods , and multiple apartment
complexes , this intersection sees a high volume of traffic. Improvements to this intersection were identified as
a priority project in the 2019 Transportation Bond Program .
The City of Fayetteville Engineering Division has prepared the design for this project. On September 5, 2023 ,
the City Council approved a construction contract with APAC-Central , Inc. in the amount of $1,809,765.00.
The construction is currently underway and will be completed in July of 2024 .
DISCUSSION:
Razorback Road from the intersection with 15th Street to the Intersection with MLK Jr. Blvd. is on the 2024 list
to receive an asphalt overlay . Staff has worked with the contractor to provide pr icing fo r the overlay and
striping since the contractor is already onsite . This work will be done in conjunction with the paving planned for
the 15th street intersection project. In addition to the pavement addition , th is change orde r adds an item for
some additional concrete removal that was encountered during the construction . This amount ($1 ,680 .00) will
be covered by the approved project contingency .
BUDGET/STAFF IMPACT:
The change order is funded by the 2019 Transportation Bond Program using funds from t he Pavement
Maintenance and Overlays Project. The Budget Adjustment moves the funds from this project into the 15 th
and Razorback Project.
Mailing address :
113 W . Mounta i n Street
Fayettev i lle, AR 72701
www. fayettevi lie -a r.gov
CCOUNT PROJECT
702. 860 . 7222-5809 . 0046020 . 7222
AMOUNT
$371 ,992 .50
ATTACHMENTS: SRF (#3), BA (#4), Change Order #1 -Signed (#5)
Mailing address :
113 W. Mountain Street
Fayetteville, AR 72701
www. fayettevi lie-a r.gov
City of Fayetteville, Arkansas
Legislation Text
File#: 2024-171
113 West Mountain Street
Fayetteville , AR 72701
(479) 575-8323
Approval of Change Order #1 in the amount of $371,992.50 with AP AC-Central, Inc. for the
construction of the 15 th and Razorback Rd. Intersection Improvements Project, and approval of a
budget adjustment.
A RESOLUTION TO APPROVE CHANGE ORDER NO. I TO THE CONTRACT WITH APAC-
CENTRAL , INC. IN THE AMOUNT OF $371 ,992.50 FOR THE CONSTRUCTION OF THE 15TH
AND RAZORBACK ROAD INTERSECTION IMPROVEMENTS PROJECT, AND TO APPROVE A
BUDGET ADJUSTMENT
WHEREAS , City Staff recommends adding to the contracted work with APAC-Central , Inc . for the
I 5th Street and Razorback Road Intersection Improvement the asphalt overlay and striping of Razorback
Road from 15 th Street to Martin Luther King Boulevard which is on the 2024 asphalt overlay list.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville , Arkansas hereby authorizes Mayor Jordan
to sign Change Order No . 1 to the contract with APAC-Central , Inc. in the amount of $371 ,992.50 for
the construction of the 15 th and Razorback Road Intersection Improvements Project to add asphalt
overlay and striping of Razorback Road from I 5th Street to Martin Luther King Boulevard. A copy of
Change Order No. I is attached to this Resolution and made a part hereof.
Section 2: That the City Council of the City of Fayetteville , Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
Page 1
Matt Casey
Submitted By
City of Fayetteville Staff Review Form
2024-171
Item ID
6/18/2024
City Council Meeting Date -Agenda Item Only
N/ A for Non-Agenda Item
5/30/2024
Submitted Date
Action Recommendation:
ENGINEERING (621)
Division/ Department
Approval of Change Order #1 in the amount of $371,992.50 with APAC-Central, Inc. for the construction of the 15th
and Razorback Rd . Intersection Improvements Project, and approval of a budget adjustment.
Budget Impact:
4 702.860. 7222-5809.00 Street Project 2022 Bonds
Account Number Fund
46020.7222 15th St/ Razorback Rd. Int
Project Number Project Title
Budgeted Item? Yes Total Amended Budget $ 2,163,018.00
Expenses (Actual+Encum) $ 1,903,017.93
Available Budget I s 260,000.07 1
Does item have a direct cost? Yes Item Cost $ 371,992.50
Is a Budget Adjustment attached? Yes Budget Adjustment $ 371,993.00
Remaining Budget $ 260,ooo.s1 I
V20221130
Purchase Order Number: 2023-00000780 Previous Ordinance or Resolution # 183-23
Change Order Number: 1 Approval Date:
Original Contract Number: 2023-00000046
Comments:
City of Fayetteville, Arkansas -Budget Adjustment (Agenda)
Budget Year Division
/Org2
ENGINEERING (621)
Adjustment Number
2024 Requester: Matt Casey
BUDGET ADJUSTMENT DESCRIPTION/ JUSTIFICATION:
Approval of Change Order #1 in the amount of $371,992 .50 with APAC-Central , Inc. for the construction of the 15th and
Razorback Rd . Intersection Improvements Project, and approval of a budget adjustment .
RESOLUTION/ORD INANCE
TOTAL
Account Number
4702 .860 . 7222-5809 .00
4702 .860. 7252-5417 .00
4 702.860. 7222-5911 .99
Increase/ (Decrease)
Expens e
371 ,993
(370,313)
(1,680)
Revenue
COUNCIL DATE : 6/18/2024 --------------1 TE M ID#: 2024-171
/.-lolly Black
5/30/2024 77:74 fl/YI
Budget Division Date
TYPE: D -(City Council)
JOURNAL#:
GLDATE:
CH KO /POSTED : I
Project .Sub#
Project Sub.Detl AT Account Name
46020
46020
46020
7222
7252
7222
EX Improvements -St r eet
EX Maintenance -Street
EX Contingency -Capital Project
v.202 45 22
G :\Divs\Engineering\Engineering Des ign Serv ices\Projects\BOND PROGRAM\20 19 Bo nd Progra m \Razorb ack and 15th\Council and
Com m ittee Actions\Change Order 1\2024-171 BA COl Razo rback 1 o f 1
Change O rd er No.
C I TY OF
FAYETTEVILLE
ARKANSAS
To Co ntractor: APAC Ce ntral
T he Contract is changed as fo llows:
Bid Bid
Co ntract Item Item
C han ges No. Descript i on
I OI R & D of PCC Base CO-I
102 Mobilization CO-I
103
2" Asp halt Co ncrete Hot Mix
Surface Co urse CO-I
6" So lid W hite Pave ment
104 Marking Thermo CO-I
105 Maintenance of Traffic CO-I
6" Solid Double Yellow
106 Paveme nt Marking T herm o CO
I
12" So lid White Pavement
107 Marking Thermo CO-I
108
Brick Panem Trail Crossing
T hermo CO-I
109
Left A rrow Paveme nt Sy mbol
T hermo CO-I
11 0
Only Pave ment Sy mb ol
T hermo CO-I
Not valid until signed by the Owner
T he original Co ntract Price was
Ne t change by previous ly auth orize d change ord ers
T he Contract Price pri or to th is C hange Ord er was
Th e Co ntrac t Price will be adj usted by
Prev i ous
Est imated
Quant ity
0
0
0
0
0
0
0
0
0
0
T he new Contract Price including thi s Change O rd er w ill be
T he Contrac t Time(s) w ill be increased by
CHANGE ORDER
Co ntra ct Titl e: Razo rba ck and 15th Int ersec tion Improvements
Date of Iss uance May 29 , 2024
ORDINANCE/RESOLUTION : 183-23
Effec ti ve Se pt ember 5, 2023
Unit Co nt rac t Revised Revised Origi nal
of U nit Es timated Unit Es timated
Measure Price Qua nt ity Pri ce Cos t
SY $0 .00 15 $11 2.00 -
LS $0 00 I $5 ,000 .00 -
SY $0 .00 18,483 $16 .50 -
LF $0 .00 2,256 $2 .00 -
LS $0 .00 I $2 1,500 .00 -
LF $0 .00 898 $2 .00 -
LF $0 .00 63 1 $17.00 -
LF $0 .00 34 $480 .00 -
EA $0 .00 7 $364 .00 -
EA $0.00 7 $420.00 -
S ummation of Cost
Net Cos t for thi s C han ge Order
Revised
Es timated
Cos t
$1,680 .00
$5,000 .00
$304 ,969 .50
$4 ,5 12.00
$2 1,500 .00
$1,796 .00
$10,727 .00
$16,320 .00
$2 ,548 .00
$2 ,940 .00
$37 1,992.50
$37 1,992.50
............................................... ----·············· .......................................................... _ ___;s ___ ""'1,-'-so_9 .... ,1_6'-5.;...o""'o_
$ ----········ .................................................................................................................. _________ _
$ 1,809 ,76 5.00 .......................................................................................................................................................... ·----~-~---
........................................................................................................................................................... _$ ____ 3_7_1,'-9_92_.5_0_
$ 2,181,757.50 ................................................................... -------------------~-~--
65 ca lend ar days ......................................................... ·----------"-'-'--"-'......C=;..._-
Required da tes of Co mpl eti on as of the date of thi s Change Ord er th erefore are: ------..................................... _________ _
Sub stantial Completion
Final Co mpleti on
----------------------------------------------------------------------5'--.;..A;..;;u._g...;-2;_4;..._ __
---------------------------------------------------4-Sep-24
NOTE : ll1is s wnmary does not re fl ect changes in th e Contract Price or Time(s) whi ch have been authorized by Work Change Directi ve s not incorporated
in thi s or previous Change Orders.
A PA C CENTRAL
05-30-24
BY D ATE