Resolution: 154-24
J.R. STEWART PUMP & EQUIPMENT, INC. (PURCHASE AGREEMENT):
A RESOLUTION TO WAIVE COMPETITIVE BIDDING AND AUTHORIZE THE PURCHASE OF PARTS FOR A
PUMP AT THE HAMESTRING SEWER LIFT STATION IN THE AMOUNT OF $49 ,555.71 PLUS APPLICABLE
TAXES AND FREIGHT CHARGES FROM J.R . STEWART PUMP & EQUIPMENT INC .
WHEREAS, the Hamestring sewer lift station experienced a pump failure recently and it was determined that a full
pump rebuild is needed ; and
WHEREAS , the pump is a Cornell brand pump and J.R . Stewart Pump & Equipment is the only authorized distributor
of Cornell pump parts for municipal applications.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section I: That the City Council of the City of Fayetteville, Arkansas hereby determines an exceptional situation exists
in which competitive bidding is deemed not feasible or practical and therefore waives the requirements of formal
competitive bidding and authorizes the purchase of parts for a pump at the Hamestring Sewer Lift Station in the amount
of$49,555 .71 plus applicable taxes and freight charges from J.R. Stewart Pump & Equipment Inc.
PASSED and APPROVED on June 4 , 2024
Page 1
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2024-132
MEETING OF JUNE 4, 2024
TO: Mayor Jordan and City Council
THRU: Susan Norton, Chief of Staff
FROM: Tim Nyander, Utilities Director
SUBJECT: J.R. Stewart Pump & Equipment, Inc. – Parts for Cornell Pump for Hamestring Sewer
Lift Station
RECOMMENDATION:
Staff recommends approval of the purchase of parts for a pump at the Hamestring sewer lift station from J.R.
Stewart Pump & Equipment, Inc. in the amount of $49,555.71 plus applicable taxes and freight charges.
BACKGROUND:
The Hamestring sewer lift station experienced a pump failure recently, and the pump was sent to Jack Tyler
Engineering for a damage inspection. It was determined that a full pump rebuild is needed. It is a Cornell brand
pump, and Jack Tyler Engineering is not the authorized distributor of Cornell pump parts for municipal sales.
J.R. Stewart Pump & Equipment is the only authorized distributor of Cornell pump parts for municipal
applications.
Jack Tyler Engineering can still perform the pump repair, but they cannot sell the City the parts. Their repair on
the pump will still come with a standard warranty, but the City has to order the parts from J.R. Stewart first. The
repair service for the pump will be a separate PO for Jack Tyler Engineering after we receive the parts from
J.R. Stewart pending City Council approval.
DISCUSSION:
J.R. Stewart provided a quote for the required parts to repair the Cornell pump for Hamestring sewer lift station
in the amount of $49,555.71 plus freight and taxes. Freight is estimated at $1,000.00 and taxes are estimated
at $4,929.18 for an estimated total of $55,484.89. Staff recommends approval of a bid waiver resolution to
order the Cornell pump parts from J.R. Stewart so we can have Jack Tyler Engineering continue with the pump
repair.
BUDGET/STAFF IMPACT:
Funds are available in the WWTP Upgrade/Replace Lift Stations account.
ATTACHMENTS: SRF (#3), Quote from J.R. Stewart (#4)
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2024-132
J.R. Stewart Pump & Equipment, Inc. – Parts for Cornell Pump for Hamestring Sewer Lift
Station
A RESOLUTION TO WAIVE COMPETITIVE BIDDING AND AUTHORIZE THE PURCHASE OF
PARTS FOR A PUMP AT THE HAMESTRING SEWER LIFT STATION IN THE AMOUNT OF
$49,555.71 PLUS APPLICABLE TAXES AND FREIGHT CHARGES FROM J.R. STEWART PUMP
& EQUIPMENT INC.
WHEREAS, the Hamestring sewer lift station experienced a pump failure recently and it was
determined that a full pump rebuild is needed; and
WHEREAS, the pump is a Cornell brand pump and J.R. Stewart Pump & Equipment is the only
authorized distributor of Cornell pump parts for municipal applications.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby determines an exceptional
situation exists in which competitive bidding is deemed not feasible or practical and therefore waives the
requirements of formal competitive bidding and authorizes the purchase of parts for a pump at the
Hamestring Sewer Lift Station in the amount of $49,555.71 plus applicable taxes and freight charges
from J.R. Stewart Pump & Equipment Inc.
City of Fayetteville Staff Review Form
2024-132
Item ID
6/4/2024
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Tim Nyander 5/16/2024 WASTEWATER TREATMENT (730)
Submitted By Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of the purchase of parts for a pump at the Hamestring sewer lift station from J.R.
Stewart Pump & Equipment, Inc. in the amount of $49,555.71 plus applicable taxes and freight charges.
Budget Impact:
5400.730.5800-5414.00 Water & Sewer
Account Number Fund
02068.1 WWTP Upgrade/Replace Lift Stations
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $1,007,764.00
Expenses (Actual+Encum)$373,478.82
Available Budget $634,285.18
Does item have a direct cost?Yes Item Cost $55,484.89
Is a Budget Adjustment attached?No Budget Adjustment $-
Remaining Budget $578,800.29
V20221130
Purchase Order Number:Previous Ordinance or Resolution #
Change Order Number:Approval Date:
Original Contract Number:
Comments:Freight is estimated at $1,000.00 and taxes are estimated at $4,929.18 for an estimated total of
$55,484.89.
J.R. STEWART PUMP & EQUIP INC,
313 S.Second St West MEMPHIS AR
Office (870)-735-2484 Fax (870)-735-0763
Timothy Marr
City of Fayetteville
12NHG28-F20TB
SN 145781 22.06
1 AC20815-15-sg
SLV 4.00x3.50x5.75(400-500 BHN). $3,996.00 2 DAYS LEAD TIME
2 A15010D-40
Seal 4002S NC $3,887.00. 2DAYS LEAD TIME
3 A15251V-59-EB
O-Ring 3.50x3.75x.12THK. $ 34.00 2DAYS LEAD TIME
4 A15250U-59-EB
O-ring 2.62x2.81x.09 THICK (2-146) $14.00. 2 Days Lead Time
5 A659AI-197-GA
VOL Gasket $68.00 2 Days Lead Time
6 A21178D-18
LIP SEAL CR 46155 $233.00. 2days lead time
7 A21178E-18
LIP SEAL CR 48692. $394.00. 2 Days Lead time
JRS
8 A15018H-20
BALL BEARING 7226B,MP,UO $1,654.00. 2 Days Lead Time
9 A16814M-20
Ball BEARING 6324M.C3. $ 2,350.00. 4 WEEKS LEAD TIME
10 E4133-38-CP
BACKPL.20NHT2 SGL $13,135.00 7 WEEKS LEAD TIME
11 A20724B-28-KS
KEY 1.00 X5.00. $182.00. 2 DAYS LEAD TIME
12 A16757T-12 -SD
Lockscrew, 1.12NCx3.0LG $ 83.00 2 Days Lead time
13 A14432M-149-SD
SOC SET SCREW 3/8-24X1’’ LG 2 EACH 20.00 2DAYS LEAD TIME
14 A20687E-28-KS
KEY .88X3.50 $197.00 4 DAYS LEAD TIME
15 A12339K-107-SDA
SHIM, 1.25X3.44X0.015. 3EACH $102.00 2DAYS LEAD TIME
16 A20727B-107-AS
SHIM .010 THICK AS REQ’D. 4 EACH 416.00. 2 DAYS LEAD TIME
17 A20727A-107-AS
SHIM .005 THICK $ 73.00 2 DAYS LEAD TIME
18 A20976A-6SG $ 3,846.00. 7WEEKS LEAD TIME
19 A20976B-6- SG
WEAR RING DBL 12NHG28 IMP. 350-400BHN $ 4,846.00 7 WEEKS LEAD TIME
20 D5884-3PB-CI-L
IMPELLER 12NHG28 FULL BACK HROULD $14,005.00. 1 WEEK LEAD TIME
TOTAL PRICE FOR PARTS IS $49,555.71
FRIGHT AND TAX NOT INCLUDED IN PRICE ABOVE
FOR PURCHASE AND P.O. #
lead time but may vary
Patrick Hughey
Director of Sales & Service
WWW.JRSPUMP.COM
Office: 870-735-2484
Cell: 901-461-7603
$4095.00 List Price each
$2538.90 Net Price each @ .62 multiplier
Bolted AOD Pump Model: AOD2-PTTT
Wet end materials: Polypropylene/Teflon
$4665.00 List Price each
$2892.30 Net Price each @ .62 multiplierBolted AOD Pump
Model: AOD2-PEE
$4095.00 List Price each
$253 Net Price each @ .62 multiplier
Bolted AOD PuOffice 870-735-2484Cell 901-461-7603