HomeMy WebLinkAbout128-24 RESOLUTIONFile Number: 2024-24
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 128-24
DC SPARKS CONSTRUCTION, LLC. (CHANGE ORDER #2):
A RESOLUTION TO APPROVE CHANGE ORDER NO. 2 TO THE FLEET SHOP EXPANSION CONTRACT
WITH DC SPARKS CONSTRUCTION , LLC. IN THE AMOUNT OF $21 ,362 .56 TO RECONCILE ADDITIONS
TO THE CONTRACT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section I : That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign Change
Order No. 2 to the Fleet Shop Expansion Contract with DC Sparks Construction , LLC in the amount of $21 ,362.56 to
reconcile additions to the contract.
PASSED and APPROVED on May 7, 2024
Attest:
~~ Kara Paxton, City Clerk Treasurer
Page 1
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2024-24
MEETING OF MAY 7, 2024
TO: Mayor Jordan and City Council
THRU: Paul Becker, Chief Financial Officer
FROM: Waylon Abernathy, Bond Projects & Construction Dir
SUBJECT: Change Order #2 to Bid 23-29 Contract Fleet Shop Expansion with DC Sparks
Construction LLC.
RECOMMENDATION:
Approval of Change Order #2 to Bid 23-29 Contract Fleet Shop expansion with DC Sparks Construction, LLC.
in the amount of $21,362.56 to reconcile additions to the contract.
BACKGROUND:
In October 2023, Resolution 201-23 authorized the construction associated with the fleet shop expansion.
In February 2024, Resolution 47-24 authorized Change Order #1 to add a rail crane to the contract.
DISCUSSION:
This change reconciles the use of contingency funds and accounts for the additional scope and related costs.
Items added to the scope include removing and replacing additional concrete floor slab to provide a level
surface and structural concrete to accommodate mobile lifts. Plywood protection board was added for
additional wall protection.
BUDGET/STAFF IMPACT:
Funding Source 9700.770.1920-5804.00 Shop Funds Sub. 21006.1 Fleet Shop Expansion
ATTACHMENTS: SRF (#3), Fleet Bay Expansion - Change Order 2 (#4)
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2024-24
Change Order #2 to Bid 23-29 Contract Fleet Shop Expansion with DC Sparks Construction LLC.
A RESOLUTION TO APPROVE CHANGE ORDER NO. 2 TO THE FLEET SHOP EXPANSION
CONTRACT WITH DC SPARKS CONSTRUCTION, LLC. IN THE AMOUNT OF $21,362.56 TO
RECONCILE ADDITIONS TO THE CONTRACT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign Change Order No. 2 to the Fleet Shop Expansion Contract with DC Sparks Construction, LLC in
the amount of $21,362.56 to reconcile additions to the contract.
City of Fayetteville Staff Review Form
2024-24
Item ID
5/7/2024
City Council Meeting Date - Agenda Item Only
N/A for Non-Agenda Item
Wade Abernathy 4/17/2024 FACILITIES MANAGEMENT (140)
Submitted By Submitted Date Division / Department
Action Recommendation:
Approval of Change Order #2 to Bid 23-29 Contract Fleet Shop Expansion with DC Sparks Construction LLC., in the
amount of $21,362.56 to reconcile the contingency allowance for additional scope to the contract and approve a
Budget Adjustment.
Budget Impact:
9700.770.1920-5804.00 Shop Fund
Account Number Fund
21006.1 Fleet Shop Expansion
Project Number Project Title
Budgeted Item?Yes Total Amended Budget $426,139.00
Expenses (Actual+Encum)$400,025.25
Available Budget $26,113.75
Does item have a direct cost?Yes Item Cost $21,362.56
Is a Budget Adjustment attached?No Budget Adjustment $-
$224.00 Remaining Budget $4,751.19
V20221130
Purchase Order Number:2023-844 Previous Ordinance or Resolution #207-23
Change Order Number:1 Approval Date:10/3/2023
Original Contract Number:2023-51
Comments:
4/8/24, 12:18 PM Change Order Print
https://buildertrend.net/app/ChangeOrder/Print?ids=6978370 1/2
- Fay Fleet Shop Expansion
Change Order
Printed: Apr 8, 2024
8871 Lola Jeane Lane, Rogers, AR 72756
Phone: 479-365-2889
Owner Info
City of Fayetteville
113 West Mountain St
Fayetteville, AR 72701
Phone: 4795758323
Cell: +14795758361
Job Info
1525 S. Happy Hollow Rd.
Fayetteville, AR 72701
Change Order ID
CO-23-021-0012
CO ID Created / Approved Date Price
CO-23-021-0012 Created:Apr 8, 2024 $21,362.56
Description
Contingency Overage CO
Additional days added to the contract: 100 days
- Additional 60 days added to Fleet Shop Expansion project schedule of 120 days allotted per project specifications.
Starting
10/10/2023 from receipt of executed contract.
- Additional 40 days added to Fleet Overhead Crane project schedule of 120 days allotted per project specifications.
Starting
02/20/2024 from receipt of executed change order.
Crane Manufacturing Timelines:
- 3 weeks for shop drawing submittals
- 16 weeks for manufacturing & shipping
Crane Install Timeline:
- 1.5 weeks for installation
Items Cost Types Description Qty / Unit Unit Price Price
CO: 01-0010 - BONDS:
Billed to Contingency
01-0010 - Bonds
Other CO 01-0010 - Bonds: Billed
to Contingency $1,595.00
1 $0.00 $0.00
4/8/24, 12:18 PM
Items
CO: RFl#2 ENDWALL
COLUMNS: Billed to
Contingency
05-1223 -Structural
Steel for Buildings
CO : ASl#2 REVISIONS:
Billed to Contingency
05-1100 -Structural
Metal Framing
CO : ASl#3 CONCRETE
SLAB REVISIONS: Partial
Billed to Contingency
03-0000 -Concrete
CO: ASl#3 CONCRETE
SLAB REVISIONS:
Remaining Balance
03-0000 -Concrete
CO : PLYWOOD WALL
I PROTECTION :
Remaining Balance
06-1633 -Wood Board
Sheathing
Status
I Cost Types
Other
Other
Other
Other
Other
Approved by: Mayor Lione ld Jo rd an
Approved by: _______ _
Change Order Print
Description
CO : RFl#2 ENDWALL
COLUMNS : Billed to
Contingency $12,190.00
-
CO: ASl#2 REVISIONS : Billed
to Contingency $21,567 .55
--
CO: ASl#3 CONCRETE SLAB
REVISIONS: Partial Billed to
Contingency $28,450.45
CO : ASl#3 CONCRETE SLAB
REVISIONS : Remaining
Balance $14 ,674 .56
CO : PLYWOOD WALL
PROTECTION : Remaining
Balance $6,688.00
Qty I Unit
L
I 1 Is
1 Is
Unit Price
$0 .00
1
$0 .00
$0 .00
$14,674.56 I
Price I
$0 .00
$0.00
$0.00
$14,674.55
$6,688 .00 ~ $6,688.00
I ----'----''---j
Date
l -----
_j_j __
I confirm that my action here represents my electronic signature and is binding. Approval of this change order may also be
represented through email , text message, or other electronic communication from the project owner's representative to the DC
Sparks Project Manager.
TOTAL AMOUNT OF CHANGE ORDER : $21,362.55
https://bui ldertrend.net/app/ChangeOrder/Print?ids=6978370 2/2
Alexus Sparks 05/13/24
VALUE Prev Period This Period Materials Total % Comp Balance Retainage
01-2116 - Contingency Allowances $63,803.00 $46,131.28 $17,671.72 $0.00 $63,803.00 100.00%$0.00 $3,190.15
CO: 01-0010 - Bonds $1,595.00 $1,595.00 $0.00 $0.00 $1,595.00 100.00% $0.00 $79.75
CO: RFI#2 ENDWALL COLUMNS $12,190.00 $12,190.00 $0.00 $0.00 $12,190.00 100.00% $0.00 $609.50
CO: ASI#2 REVISIONS $21,567.55 $10,783.78 $10,783.78 $0.00 $21,567.55 100.00% $0.00 $1,078.38
CO: ASI#3 CONCRETE SLAB REVISIONS $43,125.00 $21,562.50 $6,887.95 $0.00 $28,450.45 65.97% $14,674.55 $1,422.52
CO: PLYWOOD WALL PROTECTION $6,688.00 $0.00 $0.00 $0.00 $0.00 0.00% $6,688.00 $0.00
$0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00
TOTAL PROJECT CO'S $85,165.55
TOTAL ESTIMATED DEFICIT ($21,362.55)
1525 S Happy Hollow Rd, Fayetteville, AR 72756
23-021 Fleet Shop Expansion Change Order Log