HomeMy WebLinkAbout45-23 RESOLUTION113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 45-24
File Number: 2024-1682
BLACK HILLS ENERGY ARKANSAS, INC. (SERVICE AGREEMENT):
A RESOLUTION TO APPROVE AN AGREEMENT WITH BLACK HILLS ENERGY ARKANSAS, INC. IN THE
AMOUNT OF $90,950.84 FOR UTILITY RELOCATIONS ASSOCIATED WITH THE MIDTOWN CORRIDOR
PROJECT ALONG DEANE STREET, AND TO APPROVE A BUDGET ADJUSTMENT - 2019 STREET
IMPROVEMENT BOND PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign an
agreement with Black Hills Energy Arkansas, Inc. in the amount of $90,950.84 for utility relocations associated with
the Midtown Corridor Project along Deane Street.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on February 6, 2024
Page 1
Attest: `wi n
Y OF • 1. �?
Kara Paxton, City Clerkl reasurer _FAYEI-i E V!i_t •;
1�`vv�```
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF FEBRUARY 6, 2024
CITY COUNCIL MEMO
2024-1682
TO: Mayor Jordan and City Council
THRU: Chris Brown, Public Works Director
Susan Norton, Chief of Staff
FROM: Matt Casey, Engineering Design Manager
DATE:
SUBJECT: Black Hills Energy Agreement for Utility Relocations for the Midtown Corridor Project
RECOMMENDATION:
Staff recommends approval of an agreement with Black Hills Energy Arkansas, Inc. in the amount of
$90,950.84 for utility relocations associated with the Midtown Corridor Project along Deane Street and
approval of a budget adjustment.
BACKGROUND:
The Midtown Corridor is a project in the 2019 Transportation Bond Program and includes several different
components. The corridor is 2.3 miles in length and runs in an east -west direction through a flat part of the
middle of the city from 1-49 at Porter to College Avenue at Poplar Street. The project includes vehicular
improvements along Stephen Carr Blvd. and Deane Street from the interstate to Garland Avenue. The project
includes street improvements with new turn lanes and drainage as well as separated pedestrian and bicycle
facilities. The street, drainage pedestrian, and bicycle improvements will continue along Sycamore Street from
Garland Avenue to the Razorback Greenway. From the Greenway to College Avenue, the project will include
multi -use trail construction along the Poplar Street alignment. Finally, a connection to the south from Poplar
Street to Gregory Park was included in the design.
The first phase of this corridor included the improvements to Stephen Carr Blvd. and Deane Street from 1-49 to
the east side of the new fire station. Construction is complete for this phase.
In August of 2022, the City Council approved a contract with Crossland Heavy Contractors, Inc. to provide
construction manager at risk pre -bidding services for the second phase of this project. In September of 2023,
the City Council approved a change order for the construction of the second phase. This phase includes the
remainder of the overall project scope.
DISCUSSION:
After the start of construction along Deane Street, Black Hills Energy identified portions of their natural gas
system outside of the city right of way that will need to be relocated in order to construct this project. Black
Hills Energy has provided a proposal of $90,950.84 for this relocation.
BUDGET/STAFF IMPACT:
These utility relocations are funded by the 2019 Transportation Bond Program.
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
ATTACHMENTS: SRF (#3), BA (#4), Utility Work Agreement -Midtown Corridor (#5)
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
== City of Fayetteville, Arkansas
Y 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
- Legislation Text
File #: 2024-1682
Black Hills Energy Agreement for Utility Relocations for the Midtown Corridor Project
A RESOLUTION TO APPROVE AN AGREEMENT WITH BLACK HILLS ENERGY ARKANSAS,
INC. IN THE AMOUNT OF $90,950.84 FOR UTILITY RELOCATIONS ASSOCIATED WITH THE
MIDTOWN CORRIDOR PROJECT ALONG DEANE STREET, AND TO APPROVE A BUDGET
ADJUSTMENT - 2019 STREET IMPROVEMENT BOND PROJECT
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan
to sign an agreement with Black Hills Energy Arkansas, Inc. in the amount of $90,950.84 for utility
relocations associated with the Midtown Corridor Project along Deane Street.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
Page 1
Matt Casey
Submitted By
City of Fayetteville Staff Review Form
2024-1682
Item ID
2/6/2024
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
1/17/2024 ENGINEERING (621)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of an agreement with Black Hills Energy Arkansas, Inc. in the amount of $90,950.84 for
utility relocations associated with the Midtown Corridor Project along Deane Street and approval of a budget
adjustment.
4702.860.7218-5809.00
Account Number
46020.7218.1020
Project Number
Budgeted Item? Yes
Budget Impact:
Street Projects 2022 Bonds
Fund
Streets Projects - Midtown Corridor
Project Title
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Does item have a direct cost? Yes Item Cost
Is a Budget Adjustment attached? Yes Budget Adjustment
Remaining Budget
$
15,252,773.00
$
12,701,768.01
a
2,551,004.99
$
90,950.84
$
90,951.00
$ 2,551,005.15
V20221130
Purchase Order Number: Previous Ordinance or Resolution #
Change Order Number: Approval Date:
Original Contract Number:
Comments:
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division ENGINEERING (621) Adjustment Number
2024 /Org2
Requestor: Matt Casey
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Staff recommends approval of an agreement with Black Hills Energy Arkansas, Inc. in the amount of $90,950.84 for
utility relocations associated with the Midtown Corridor Project along Deane Street and approval of a budget
adjustment.
COUNCIL DATE:
ITEM ID#:
2/6/2024
2024-1682
Noll y Black
717712024 7:24 P/VI
Budget Division
TYPE:
JOURNAL #:
Date
D - (City Council)
RESOLUTION/ORDINANCE
I GLDATE:
CHKD/POSTED:
TOTAL
Account Number
- -
Increase / (Decrease)
Expense Revenue
Prolect.Sub#
Project Sub.Detl AT
v.2024116
Account Name
4702.860.7218-5809.00
90,951 -
46020 7218.1020 EX
Improvements - Street
4702.860.7999-5899.00
(90,951) -
46020 7999 EX
Unallocated - Budget
K:\Engineering Design Services\Projects\BOND PROGRAM\2019 Bond Program\Porter-Deane-Sycamore-Poplar\Council and
Committee Actions\Black Hills Agree ment\2024-1682 BA Midtown Corr BHE utility relocate 1 of 1
Black Hills Energy
UTILITY WORK AGREEMENT
(DEVELOPER)
Developer: City of Fayetteville
Developer's Address: 113 W Mountain St. Favetteville. Ar 72701
Job Location: Deane St- UofA
This Utility Work Agreement ("Agreement") is made and entered into this 11th
day of January, 2024, by and between City of Fayetteville (hereinafter referred to as
"Developer"), and Black Hills Energy Arkansas, Inc. (hereinafter referred to as "Black
Hills").
WHEREAS, Developer proposes to make certain improvements at the location
designated above, and as a result of such improvements, Black Hills must adjust,
enhance, locate, observe, and/or relocate certain of its existing facilities, or construct
additional facilities; and
WHEREAS, in connection with Developer's proposed improvements, Developer
wishes Black Hills to do the following:
Project to begin at GPS 36.086384,-94.190492 where BlackHills will tie onto
existing 4" steel gas main and extend east, installing 2100' of 4" steel gas main to
tie back into existing gas main at GPS 36.086185,-94.183692. Once new 4" steel
aas main is installed, the old 4" steel aas main will be retired in place.
(hereinafter referred to as the "Work"); and
WHEREAS, such Work is shown in detail in Black Hills' plans, sketches, estimate
of cost, and specifications (when applicable), which are attached to this Agreement and
made a part hereof; and
WHEREAS, Developer agrees to pay for the cost of such Work to the extent
herein agreed upon.
Impnovinglife with energy
www.blackhillsenergy.com
Energy
NOW, THEREFORE, IN CONSIDERATION OF THE PROMISES AND OTHER
VALUABLE CONSIDERATION HEREIN ACKNOWLEDGED, DEVELOPER AND
BLACK HILLS AGREE AS FOLLOWS:
1. Where applicable hereunder by reason of new utility occupancy or
crossing of Developer's property, Developer hereby grants to Black Hills an easement
or license to install and operate utility facilities on or across Developer's property as
shown on the approved plans or sketch maps attached hereto and made a part hereof.
Prior to Black Hills beginning the Work, Developer will, at no cost to Black Hills, furnish
Black Hills with all necessary easements, rights of way and permits. Those easements,
rights of way and permits shall release Black Hills from any and all claims for damage
done to streets, land, fences, and crops arising out of the performance of the Work.
2. Where applicable hereunder by reason of new construction on existing
utility rights of way, Black Hills hereby grants to Developer the right to use for
Developer's purposes the lands within the limits of the improvement project limits on or
across which Black Hills holds a valid property interest antedating Developer's rights
which were subsequently acquired in the same lands, and which property rights Black
Hills shall retain so long as Black Hills, its successors or assigns continues such use
and occupancy and does not abandon, and thereby release, such property interest to
Developer through removal of facilities in performing the Work or by subsequent
removal of facilities for Black Hills' convenience; and Developer hereby agrees that
Black Hills, by granting said right and by said continued joint use and occupancy, does
not waive any future claim for reimbursement for any costs as may be eligible for
reimbursement by reason of such prior property interest, nor does Black Hills waive any
other legal or property right held under the laws or Constitution of the State of Arkansas
or the United States.
3. In the event that future construction, reconstruction, expansion, relocation,
rehabilitation, betterment, maintenance, or other work on the facilities owned and
operated by either Developer or Black Hills in the area jointly occupied or used under
either or both Paragraphs 1 or 2 of this Agreement will disturb, detrimentally affect,
interfere, or be inconvenient to the facilities or responsibilities of either party, the parties
hereto shall reach agreement in writing as to locations, extent, and methods of such
work before the work is undertaken. In a case of emergency, and where immediate
action is necessary for the protection of the public and to minimize damage to or loss of
investment in the property of Developer or of Black Hills, either party hereto may, at its
own responsibility and risk, make any necessary emergency repairs, and shall notify the
other party hereto of such action as soon as practicable.
2
Black Nils Energy
4. The estimated cost of the Work is $90,950.84. After it has completed the
Work, Black Hills will bill Developer for the actual cost of the Work. Developer shall pay
such invoice within 30 days of Developer's receipt of the invoice. The estimated and
actual cost of the Work includes a tax gross up amount. The tax gross up amount will
appear as a separate line item on Developer's bill. The tax gross up reimburses
Company for Company's federal and state income tax expense, on a net present value
basis, associated with the collection of the cost of the Work from Developer. For
refundable contributions, the same percentage rate is applied to refund the tax gross -up
to Developer.
5. Black Hills will perform the Work, as described on the first page of this
Agreement. Black Hills will endeavor to perform the Work within a reasonable time
period, subject to applicable laws, rules and regulations of governmental authorities,
and subject to any delay occasioned by lack of right of way, availability of materials and
supplies, force majeure or events or conditions of whatsoever nature reasonably
beyond Black Hills' control, and further conditioned upon the receipt of all required
approvals and consents in form and substance acceptable to Black Hills. Black Hills
shall not be obligated to commence the Work unless and until, at no cost to Black Hills,
all necessary easements and rights of way have been executed, acknowledged and
delivered to Black Hills in a form acceptable to Black Hills.
6. Title to and ownership of facilities which are the subject of the Work shall
forever be and remain exclusively and unconditionally vested in Black Hills. Developer
understands, acknowledges and agrees that Developer shall have no title to, interest in,
or ownership of those facilities.
7. It is mutually agreed by the parties hereto that the provisions of this
Agreement pertaining to property rights, right of way occupancy permission, access for
servicing when applicable, and joint use of rights of way shall continue in full force and
effect from the date of this Agreement, and shall be perpetually binding upon each
party, and its representatives, successors and assigns.
8. Developer and Black Hills acknowledge that there are no agreements or
understandings, either written or oral, between the parties related to the Work, other
than as set forth in this Agreement, and that this Agreement (including any attachments
hereto) contains the entire agreement between the parties regarding the Work.
9. This Agreement shall be governed in accordance with the laws of the
State of Arkansas, the rules and regulations of the Arkansas Public Service
Commission, and the Tariff of Black Hills. In the event of a conflict between this
Agreement and any such laws, rules, regulations or Tariff, such laws, rules, regulations
or Tariff shall control.
BlaodrHMFEMPY
10. In the event Black Hills is required to initiate litigation to enforce the terms
and conditions of this Agreement, then Black Hills shall have the right to recover from
Developer Black Hills' costs and expenses of such litigation, including reasonable
attorney fees.
11. Developer acknowledges that it has been afforded an opportunity to have
its attorney review and explain the terms of this Agreement.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be
executed in duplicate by their duly authorized representatives on the date stated above.
BLACK H4SNERGY ARKANSAS INC.
By: Tron Hodges
Its: Senior Manager- Gas Operations
Federal Tax I.D. No.:
0
P1