HomeMy WebLinkAbout36-24 RESOLUTIONFile Number: 2023-1549
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
Resolution: 36-24
HA WK.INS WEIR ENGINEERS, INC. (CONTRACT AMENDMENT):
A RESOLUTION TO APPROVE AMENDMENT NO. 4 TO THE PROFESSIONAL ENGINEERING SERVICES
AGREEMENT WITH HAWKINS-WEIR ENGINEERS , INC. IN THE AMOUNT OF $28,780 .00 FOR
ADDITIONAL SERVICES ASSOCIATED WITH THE PROJECT TO ALLEVIATE FLOODING NEAR THE
NORTH COLLEGE A VENUE AND EAST SUNBRIDGE DRIVE INTERSECTION , AND TO APPROVE A
BUDGET ADJUSTMENT-2019 DRAINAGE BOND PROJECT
WHEREAS , on September 17 , 2019 , the City Council passed Resolution 211-19 to authorize Mayor Jordan to sign a
Professional Engineering Services Agreement with Hawkins-Weir Engineers , Inc. for conceptual drainage design
services to alleviate the flooding at the intersection of North College Avenue and East Sunbridge Drive ; and
WHEREAS , bids on the original design far exceeded available funding and Amendment No. 4 provides for additional
design services to reconfigure the project plans and reduce the scope of work.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section I : That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to sign
Amendment No . 4 to the Professional Engineering Services Agreement with Hawkins-Weir Engineers, Inc. in an
amount of $28 ,780 .00 for engineering design services and construction phase services associated with the project to
alleviate flooding near the intersection of North College Avenue and East Sunbridge Avenue .
Section 2 : That the City Council of the City of Fayetteville , Arkansas hereby approves a budget adjustment, a copy of
which is attached to thi s Resolution .
PASSED and APPROVED on January 18 , 2024
Approved: Attest:
Page 1
Mailing address:
113 W. Mountain Street
Fayetteville, AR 72701
www.fayetteville-ar.gov
CITY COUNCIL MEMO
2023-1549
MEETING OF JANUARY 18, 2024
TO: Mayor Jordan and City Council
THRU: Chris Brown, Public Works Director
FROM: Alan Pugh, Staff Engineer
DATE:
SUBJECT: Approval of a contract amendment #4 with Hawkins Weir Engineers, Inc. in the
amount of $28,780 for a total contract amount not to exceed $483,940 for additional
engineering design services associated with flooding near the intersection of N
College Ave and E Sunbridge Dr. and approval of a budget adjustment.
RECOMMENDATION:
Staff recommends approval of a contract amendment #4 with Hawkins Weir Engineers, Inc. in the amount of
$28,780 for a total contract amount not to exceed $483,940 for additional engineering design services
associated with flooding near the intersection of N College Ave and E Sunbridge Dr. and approval of a budget
adjustment.
BACKGROUND:
This project has been identified as one of the projects to be funded by the 2019 Drainage Bond Program.
Hawkins Weir was selected for this project by RFQ 19-01 selection #15 with the original contract being
approved through resolution 211-19. That contract included conceptual drainage work to determine the
impacts of proposed detention basins and the original proposed routing. Subsequently the contract was
amended twice to include an investigation of alternative storm drain routing, additional design services to
include deductive alternates prior to bidding the project and construction phase services.
DISCUSSION:
Hawkins-Weir Engineers, Inc has provided a proposed scope and an additional fee/reimbursables in the
amount of $28,780 to complete additional design/bidding phase services. Bids were recently received on the
project and unfortunately the bids far exceeded the available funding. The proposed contract amendment
includes design services to reconfigure the plans in preparation to bid the project again. This will include a
reduction in the scope of work in order to hopefully bring the project within budget. The contract will be paid
based on hourly rates for work completed, up to the total contract amount (currently $483,940 including this
amendment). The current total estimated project amount is $5.5 million for construction however, the bids were
significantly higher.
BUDGET/STAFF IMPACT:
The design for this project will be paid for with the funds from the 2019 Drainage Bond Project.
ATTACHMENTS: SRF (#3), BA (#4), HW Amendment No. 4 - Dec. 2023 (#5)
Page 1
City of Fayetteville, Arkansas
Legislation Text
113 West Mountain Street
Fayetteville, AR 72701
(479) 575-8323
File #: 2023-1549
Approval of a contract amendment #4 with Hawkins Weir Engineers, Inc. in the amount of
$28,780 for a total contract amount not to exceed $483,940 for additional engineering design
services associated with flooding near the intersection of N College Ave and E Sunbridge Dr. and
approval of a budget adjustment.
A RESOLUTION TO APPROVE AMENDMENT NO. 4 TO THE PROFESSIONAL ENGINEERING
SERVICES AGREEMENT WITH HAWKINS-WEIR ENGINEERS, INC. IN THE AMOUNT OF
$28,780.00 FOR ADDITIONAL SERVICES ASSOCIATED WITH THE PROJECT TO ALLEVIATE
FLOODING NEAR THE NORTH COLLEGE AVENUE AND EAST SUNBRIDGE DRIVE
INTERSECTION, AND TO APPROVE A BUDGET ADJUSTMENT– 2019 DRAINAGE BOND
PROJECT
WHEREAS, on September 17, 2019, the City Council passed Resolution 211-19 to authorize Mayor
Jordan to sign a Professional Engineering Services Agreement with Hawkins-Weir Engineers, Inc. for
conceptual drainage design services to alleviate the flooding at the intersection of North College Avenue
and East Sunbridge Drive; and
WHEREAS, bids on the original design far exceeded available funding and Amendment No. 4 provides
for additional design services to reconfigure the project plans and reduce the scope of work.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby authorizes Mayor Jordan to
sign Amendment No. 4 to the Professional Engineering Services Agreement with Hawkins-Weir
Engineers, Inc. in an amount of $28,780.00 for engineering design services and construction phase
services associated with the project to alleviate flooding near the intersection of North College Avenue
and East Sunbridge Avenue.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
12/18/2023
Submitted Date
Yes
751.59$
28,780.00$
V20221130
Budgeted Item?
Does item have a direct cost?
Is a Budget Adjustment attached?
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
139,184.00$
138,432.41$
Yes
Yes 28,780.00$
751.59$
46040.7415.1000
Project Number
Budget Impact:
Drainage Projects (2019/2022 Bonds),
Sunbridge/College
Fund
Drainage Projects (2019/2022 Bonds)4704.860.7415-5860.02
Account Number
Project Title
City of Fayetteville Staff Review Form
2023-1549
Item ID
1/16/2024
City Council Meeting Date - Agenda Item Only
Approval of a contract amendment #4 with Hawkins Weir Engineers, Inc. in the amount of $28,780 for a total
contract amount not to exceed $483,940 for additional engineering design services associated with flooding near
the intersection of N College Ave and E Sunbridge Dr. and approval of a budget adjustment.
N/A for Non-Agenda Item
Action Recommendation:
Submitted By
Chris Brown ENGINEERING (621)
Division / Department
Comments:
2019-661Purchase Order Number:
Change Order Number:
Previous Ordinance or Resolution #211-19; 124-20; 278-20; 74-23
Approval Date:
Original Contract Number:2019-36
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division
/Org2 ENGINEERING (621)
Adjustment Number
2024 (BY) Requestor:Chris Brown
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
Approval of a contract amendment #4 with Hawkins Weir Engineers, Inc. in the amount of $28,780 for a total contract
amount not to exceed $483,940 for additional engineering design services associated with flooding near the intersection of
N College Ave and E Sunbridge Dr. and approval of a budget adjustment.
COUNCIL DATE:1/16/2024
ITEM ID#:2023-1549
Holly Black
12/22/2023 1:46 PM
Budget Division Date
TYPE:D - (City Council)
JOURNAL #:
GLDATE:
RESOLUTION/ORDINANCE CHKD/POSTED:/
v.20231213TOTAL--
Increase / (Decrease)Project.Sub#
Account Number Expense Revenue Project Sub.Detl AT Account NameGLACCOUNTEXPENSEREVENUEPROJECTSUBATDESCRIPTION X
4704.860.7999-5899.00 (28,780)-46040 7999 EX Unallocated - Budget
4704.860.7415-5860.02 28,780 -46040 7415.1000 EX Capital Prof Svcs - Engineering/Architectural
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
1 of 1
Amendment No. 4 - Dec. 2023.docx Page 1 of 2 December 19, 2023
AMENDMENT NO. 4
TO THE
AGREEMENT For PROFESSIONAL ENGINEERING SERVICES
BETWEEN
CITY OF FAYETTEVILLE, ARKANSAS
AND
HAWKINS-WEIR ENGINEERS, INC.
In accordance with the AGREEMENT For PROFESSIONAL ENGINEERING SERVICES for the
Sunbridge/College, Phase 1 Drainage Project (HW Project No. 2019070), dated September 17, 2019,
between the City of Fayetteville, Arkansas (hereinafter called Owner) and Hawkins-Weir Engineers, Inc.
(hereinafter called Engineer), Owner hereby authorizes Engineer to proceed with engineering services as
modified by this Amendment No. 4.
SECTION 1 – SCOPE OF SERVICES
1.1 The City of Fayetteville Engineering Department has directed the Engineer to amend services
included in the AGREEMENT on the PROJECT. These amended services include the additional
engineering design services necessary to complete the final design of the project (Task 6 and Task 7).
Detailed services included in AMENDMENT NO. 4 are included in the attached Appendix A, Scope of
Services.
SECTION 2 – TIME OF SERVICE
2.1 The additional scope of services defined as Amendment No. 4, Task 6 and Task 7 above will be
completed within 60 calendar days added to the 735 calendar days provided in the AGREEMENT and
previous AMENDMENT NOS. 1, 2, AND 3.
SECTION 3 -COMPENSATION
3 .1 Owner shall compensate Engineer for providing the services set forth herein in accordance with the
terms of the Agreement. Total payment for Scope of Services described herein shall not exceed Twenty
Eight Thousand. Seven Hundred Eight and 00/100 Dollars ($28,780 .00) without written approval of Owner.
These additional services adjust the Agreement's not to exceed fee to $459,640.00 and the not to exceed
reimbursable expenses to $24 ,300.00, for a total contract amount of $483,940.00 .
Attachments : Appendix A, Scope of Services dated December 2023
Appendix B, Fee Proposal Breakdown dated December 2023
AUTHORIZATION BY:
CITY OF FAYETTEVILLE, ARKANSAS
ACCEPTED BY:
HA WKfNS-WEIR ENGfNEERS, fNC.
By :--'---9 ·¥-=----~_,c._z _
J. Kyle Salyer, P.E., P.S .
Vice President
Date: __ IZ.~/l_t_t ~h_z_~-----
Amendment No . 4 • Dec. 2023 .docx
Date : 01/18/2024
Page 2 of2 December 19, 2023
Appendix A
Amendment No. 4 Scope of Services
Sunbridge Drive and College Avenue
Drainage Improvements
City of Fayetteville, Arkansas
HWEI Project No. 2019070
December 2023
2019070\Scope of Services – Amendment No. 4.docx
Hawkins-Weir Engineers, Inc. (HW) proposes to provide the following additional engineering
design services for the referenced project.
Task Description:
Task 6 – Additional Design Services (Revising Deductive Alternates)
1. Revise plans with updated Deductive Alternates
2. Update Cost Estimate
3. Revise Specifications and Bid Form with Deductive Alternates
4. Revise Drainage Report to incorporate all changes
Task 7 – Additional Design Services
1. Revise Plans to reduce construction scope to STA 0+00 to STA 15+64
2. Update Cost Estimate
3. Revise Specifications and Bid Form
Task 6 - Additional Design Services revising Deductive Alternates Engr Engr Engr Tech Tech
VII V I IV I
1.2 24 8 24
2.2 4 16
3.2 16 8 16
4.2 8 8 8
TOTAL HOURS =8 52 40 24 24
$18,700
Task 7 - Additional Design Services Engr Engr Engr Tech Tech
VII V I IV I
1.1 20 24
2.1 4 4
3.2 8 4 8
TOTAL HOURS =4 32 8 24 8
$10,080
Engineering Services Summary
Task 6 - Additional Design Services revising Deductive Alternates $18,700
Task 7 - Additional Design Services $10,080
Total Amendment No. 4 Fee - Not to Exceed $28,780
Revise Specifications and Bid Form
Appendix B
Sunbridge Drive and College Avenue
HWEI Project No. 2019070
December 2023
Revise Plans to reduce construction scope to STA 0+00 to STA 15+64
Drainage Improvements
City of Fayetteville, Arkansas
Amendment No. 4 Fee Proposal
Update Cost Estimate
Revise Plans with updated Deductive Alternates
Update Cost Estimate
Revise Specifications and Bid form with Deductive Alternates
Revise Drainage Report to incorporate all changes
2019070\Scope of Services and Fee Proposal Amendment No. 4.xlsx