HomeMy WebLinkAbout241-23 RESOLUTION113 West Mountain Street Fayetteville, AR 72701 (479) 575-8323 Resolution: 241-23 File Number: 2023-1211 CLABBER CREEK SEWER REPAIR (BUDGET ADJUSTMENT): A RESOLUTION TO APPROVE A BUDGET ADJUSTMENT IN THE AMOUNT OF $344,960.00 TO FUND THE REPAIR OF A 48-INCH SEWER MAIN IN THE CLABBER CREEK AREA WHEREAS, a section of 48-inch pipeline near Clabber Creek was televised in July of 2021 and did not show signs of failure; and WHEREAS, in July 2023, the line was televised again and revealed a major failure in the original Hobas pipe allowing water to enter the sewer line; and WHEREAS, during the excavation, it was determined the scope of the repair would need to be much more extensive, so only a temporary repair was completed at that time. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution, in the amount of $344,960.00 to fund the repair of a 48-inch water main in the Clabber Creek area. PASSED and APPROVED on November 7, 2023 Page 1 Attest: % '0Z 11:; , :. ;r�4 �.•' CITY ;•�.4'�� Kara Paxton, City CI Treasurer :�. C: • ' CITY OF FAYETTEVILLE ARKANSAS MEETING OF NOVEMBER 7, 2023 CITY COUNCIL MEMO TO: Mayor Jordan and City Council THRU: Susan Norton, Chief of Staff FROM: Tim Nyander, Utilities Director DATE: SUBJECT: Budget Adjustment for Clabber Creek 48-Inch Sewer Main Repair RECOMMENDATION: 2023-1211 Staff recommends approval of a budget adjustment in the amount of $344,960.00 to fund the repair of a 48- inch sewer main in the Clabber Creek area, to be completed by City crews. BACKGROUND: This section of the 48-in pipeline was televised in July of 2021 and did not show signs of failure. After a report of Clabber Creek disappearing in July of 2023 the line was again televised. This inspection revealed a major failure in the original Hobas pipe allowing water to enter the sewer line. In September 2023 Water/Sewer excavated to repair the failed section of line. During this excavation it was determined the scope of the repair would need to be much more extensive. Given this, only a temporary repair was completed in September. DISCUSSION: The Water & Sewer department has determined that replacing the existing Hobas pipe with new 48-inch PVC pipe would be the best solution at this location. Considerations included availability of 48-inch PVC pipe, the depth of the line, and the ability to install utilizing Water/Sewer staff. It is recommended this repair be completed as quickly as possible due to the high probability of failure and high cost of failure. This repair is estimated to cost $344,960.00 in parts, rental equipment, fuel, and a project contingency as detailed below: $190,000.00 — 48-in PVC pipe and material $81,500.00 — Sewer pump around $22,500.00 — Rental equipment $15,000.00 — Fuel $2,400.00 — Trench safety $2,200.00 — Sewer plugs $31,360.00 - Contingency Repairs will be made utilizing Water/Sewer crews. The sewer pump around system must be staffed 24/7. BUDGET/STAFF IMPACT: A budget adjustment is attached to move funds from the Lake Sequoyah Dredging account to the Water & Mailing address: 113 W. Mountain Street www.fayetteville-ar.gov Fayetteville, AR 72701 Sewer operations budget to fund the emergency repair. ATTACHMENTS: SRF (#3), BA (#4) Mailing address: 113 W. Mountain Street www.fayetteville-ar.gov Fayetteville, AR 72701 == City of Fayetteville, Arkansas y 113 West Mountain Street Fayetteville, AR 72701 (479)575-8323 - Legislation Text File #: 2023-1211 Budget Adjustment for Clabber Creek 48-Inch Sewer Main Repair A RESOLUTION TO APPROVE A BUDGET ADJUSTMENT IN THE AMOUNT OF $344,960.00 TO FUND THE REPAIR OF A 48-INCH SEWER MAIN IN THE CLABBER CREEK AREA WHEREAS, a section of 48-inch pipeline near Clabber Creek was televised in July of 2021 and did not show signs of failure; and WHEREAS, in July 2023, the line was televised again and revealed a major failure in the original Hobas pipe allowing water to enter the sewer line; and WHEREAS, during the excavation, it was determined the scope of the repair would need to be much more extensive, so only a temporary repair was completed at that time. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE, ARKANSAS: Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of which is attached to this Resolution, in the amount of $344,960.00 to fund the repair of a 48-inch water main in the Clabber Creek area. Page 1 Tim Nyander Submitted By City of Fayetteville Staff Review Form 2023-1211 Item ID 11/7/2023 City Council Meeting Date - Agenda Item Only N/A for Non -Agenda Item 10/18/2023 WATER SEWER (720) Submitted Date Division / Department Action Recommendation: Staff recommends approval of a budget adjustment in the amount of $344,960.00 to fund the repair of a 48-inch sewer main in the Clabber Creek area, to be completed by City crews. Budget Impact: 5400.720.4410-5216.00/5400.720.4410- 5308.03/5400.720.4410-5213.04 Account Number N/A Project Number Budgeted Item? Yes Does item have a direct cost? Yes Is a Budget Adjustment attached? Yes Purchase Order Number: Change Order Number: Original Contract Number: Comments: Total Amended Budget Expenses (Actual+Encum) Available Budget Item Cost Budget Adjustment Remaining Budget Water and Sewer Fund N/A Project Title $ 358,907.00 $ 193,272.16 165,634.84 $ 344,960.00 $ 344,960.00 165,634.84 Previous Ordinance or Resolution # Approval Date: V20221130 City of Fayetteville, Arkansas - Budget Adjustment (Agenda) Budget Year Division Adjustment Number WATER SEWER (720) /Org2 2023 Requestor: Cheryl Partain BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION: A budget adjustment is needed in the water/sewer operational budget to fund the repair of a 48-Inch sewer main in the Clabber Creek area. City Crews will complete the work. Budgeted funds will be moved from the Lake Sequoyah Sediment Removal/Dredging Project. The project is closed and the available remaining budget is being moved to fund the repair costs. COUNCIL DATE: 11/7/2023 ITEM ID#: 2023-1211 Nolly Black 7017912023 7.77 RIn RESOLUTION/ORDINANCE Budget Division Date TYPE: D - (City Council) JOURNAL #: GLDATE: CHKD/POSTED: TOTAL Account Number - - Increase / (Decrease) Expense Revenue Project.Sub# Project Sub.Detl AT v.2023109 Account Name 5400.720.4410-5216.00 190,000 - EX Construction Materials 5400.720.4410-5308.03 5400.720.4410-5213.04 139,960 - 15,000 - EX EX Rental - Equipment Fuel - Unleaded/Diesel 5400.720.5600-5808.00 (344,960) - 17004 1 EX Improvements - Water Line I of 1