Loading...
HomeMy WebLinkAbout96-88 RESOLUTION • iCI r \IFD RESOLUTION NO. 96_88 A RESOLUTION AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE AN AMENDMENT TO A CONTRACT WITH CH2M HILL FOR ENGINEERING SERVICES FOR THE WASTEWATER TREATMENT PLANT PROJECT. BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE CITY OF FAYETTEVILLE, ARKANSAS: That the Mayor and City Clerk are hereby authorized and directed to execute an amendment to a contract with CH2M Hill for engineering services for the Wastewater Treatment Plant Project. A copy of said amendment authorized for execution hereby is attached hereto marked Exhibit "A" and made a part hereof. PASSED AND APPROVED this _ 20th day of December 1988 . APPROVED By: Mayor (994"14*-- ATTEST By: e•DYi� Clerk , 1/4: a 4-4 s`:4:\ • 1. -c •. a ; • �,,, 3-1'1 a ' TASK ORDER NUMBER 10 , AMENDMENT 3 ADDITIONAL RESIDENT OBSERVATION AND ENGINEERING SERVICES This Amendment No. 3 amends Task Order Number 10 executed between CH2M HILL Southeast, Inc. (Engineer) , and the City of Fayetteville, Arkansas (Owner) , on the 25th day of April, 1987 . Article 1 The scope of work is to provide additional resident observation services and engineering services during construction for the added period from June 30, 1988, through September 24 , 1988 , resulting from the delay in construction, in addition to those services covered by the Amended Task Order Number 2 and Task Order Number 10 as previously amended for the Wastewater Treatment project. Article 2 As consideration for providing the services enumerated in Article 1 above, the Owner shall pay the Engineer on the basis of raw labor plus 163% for overhead plus 15% for profit plus all project related direct expenses. Subcontractor costs will be marked up 5% . The total additional cost is $ 44,000.00.71trTIie total for Task Order Number 10 as amended is thus $ 399,300.00.6 Article 3 Payment to the Engineer for services provided as described in Article 1 is due to be made within 30 days after date of billing. EXHIBIT A mgmDS7/061 -1- • Article 4 IN WITNESS WHEREOF, the parties hereto each herewith sub- scribe the same in triplicate. FOR THE CITY OF FAYETTEVILLE, ARKANSAS By: 111°.4114a-) 9°1"44..---d Title ATTEST: FOR CH2M HILL SOUTHEAST, INC. By: ame Title Dated this Le day of , 1987 ATTE ^'T mgmDS7/061 -2- Engineers ® Planers 7 ClfMHILL Economists - Scientists November 17, 1988 MGM18766 .FO Mr. Bob Franzmeier Project Coordinator City of Fayetteville • 113 West Mountain Street Fayetteville, Arkansas 72701 Dear Bob: Subject: Fayetteville Wastewater Treatment Plant Task Order No. 10, Amendment 3 As you know, the costs for our providing engineering services during construction and resident observation services since June 1988 have exceeded the amounts in Task Order 10, as amended. We have submitted monthly invoices showing the amount of additional costs since June. In the attached task order amendment, we have shown our cost for three different time periods for engineering services during construction and resident observation services (during regular hours) . The first time period is June 1, 1988 to July 1, 1988. For Task Order Amendment No. 2 we estimated our costs and thought the amount would be enough to carry us to July 1, 1988, although the time period stated in the Amendment was only to June 1 . We spent $6,574. 31 more than our estimate. This expense was incurred prior to the contract completion date for the construction that had been extended for 30 days from June 1, 1988, to July 1, 1988. The second period is between the contract completion date _ (July 1, 1988) and August 25, 1988, when the majority of the construction reached an acceptable level of completion as evidenced by a joint walk-through inspection by the ADPC&E, ourselves, and you. These costs we believe are appropriate to be assessed against the completion contractor (Huber, Hunt & Nichols) . CH2M HILL Montgomery Office 2567 Fairlane Drive P.O.Box 230548 205.271.1444 • Montgomery,Alabama 36123-0548 f Mr. Bob Franzmeier Page 2 November 17, "1988 MGM18766.FO a In a letter dated July 18, 1988, we informed the completion contractor, Huber, Hunt, and Nichols, that they were subject to the City assessing both liquidated and actual damages. In early October we met informally with Huber, Hunt, and Nichols, to see if our claim for engineering costs could be resolved. We attribute our claim to their not completing the work to an acceptable level by the contract completion date of July 1, 1988. In addition to the costs resulting from his not completing the construction by the contract • completion date, we have an outstanding claim of $6, 709. 12 for resident observation time (essentially for Jim Davis) incurred while the contractor was working overtime. The contractor has paid other resident overtime costs, both for Jim Davis and Charles Wentworth. The contractor recently refused to pay the charges based on their opinion that Jim Davis was not productive, especially during the transition period when both Jim Davis and Charles Wentworth were onsite. We do not accept that reason for refusing to pay those costs incurred between April 24, 1988, and June 25, 1988. The third period starts August 24 and includes our engineering costs that we believe cannot be assessed to the contractor. This period includes costs ($12, 648. 85) that we believe are outside of the contracted project performance evaluation task. During the period between September 25 and November 1, there were also costs (approximately $2, 958) that are appropriate to be included as a part of our original lump sum contract, since the tasks were related to performance evaluation issues. (These latter costs are not included in the attached Task Order Amendment No. 3 even though the performance evaluation period did not begin until November 1, 1988. ) In our October 4 meeting with the contractor, he indicated that the bonding company must be involved in any payment of the above contractor related charges (the second time period in the Task Order Amendment and resident overtime charges) . We therefore asked him to assist in facilitating a meeting with the bonding company. We have heard on several occasions that the bonding company was preparing a letter to us relative to a meeting with them, and that the letter would be forthcoming within a couple of days. Over a month has elapsed with no communication from the bonding company. We therefore believe that the City needs to assert the claim, which we believe is the City's right against the Contractor. • � f_ • • Mr. Bob Franzmeier Page 3 November 17, (1988 MGM18766.FO Regarding your rights against the contractor, the original Contract Documents specified deadlines for completion of construction for three phases. Individual amounts of liquidated damages were stated for time overruns beyond each deadline with the accumulation of damages for multiple deadlines being exceeded. During the period that the completion contractor was late, there were Phase 1, Phase 2 and Phase 3 items of work which had not been completed. Phases 1 and 2 had the second of the three deadlines and Phase 3 was the third. These items were not prohibiting the startup of the facilities, which had already been declared substantially complete. However, the Contract Documents establish damages for the lack of completion of the work, not lack of substantial completion. One interpretation of the contract documents could be that the cumulative sum of $600 for not completing Phases 1. and 2, and $600 for Phase 3 being incomplete could be assessed as liquidated damages. The maximum amount that you could consider the City's right to collect is $1, 200 per day for the period between July 1, 1988, and August 25, 1988, a total of 54 days for a total of $64, 800. In light of the above, on the next pay request from HH&N, we recommend withholding the sum of $32, 419.58 for engineering services between July 1, 1988, and August 25 , 1988, as actual damages and $6, 709 .12 for overtime resident observation services. In addition, you may deduct an amount of liquidated damages that you believe appropriate. We ask that the City approve the attached Task Order Amendment No. 3 for $58, 351. 86. Efforts to collect $39, 128. 70 from the contractor as stated above should also be made for that portion of the Amendment. Overall, the wastewater treatment plant project construction and non-reimbursed additional engineering costs (excluding the added belt filter press and assuming collection of $39, 128.70 from the contractor) result in a final cost $12, 190. 00 less than the original construction cost of $21, 232, 000. Sincerely, / Dennis A. Sandretto, P.E. Project Manager mgmDS7/060 cc: Johnny Quinn/McClelland Bob Blanz/LIT