Resolution: 191-23
File Number: 2023-1023
STRUCTURAL PRESERVATION SYSTEMS, LLC (CHANGE ORDER NO. 3):
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE DESIGN -BUILD CONTRACT WITH
STRUCTURAL PRESERVATION SYSTEMS, LLC IN AN AMOUNT NOT TO EXCEED $7,884,343.00 TO
REHABILITATE THE SEWER PIPELINE AND STABILIZE THE TUNNEL UNDER THE SOUTHBOUND
HIGHWAY 112 EXIT RAMP ON I-49, AND TO APPROVE A BUDGET ADJUSTMENT
WHEREAS, on January 3, 2023, the City Council passed Resolution 6-23 authorizing Mayor Jordan to sign a design -
build contract with Structural Preservation Systems, LLC (SPS) to develop a plan for repairs to the sewer pipe under
the southbound Highway 112 exit ramp on I-49; and
WHEREAS, during the investigation, SPS determined the pipe and tunnel system is "unsafe in its current condition"
and "subject to imminent collapse" because of the lack of grouting in the space outside the pipe, between the pipe wall
and the tunnel encasement and tunnel walls; and
WHEREAS, SPS proposes to completely rehabilitate the pipeline and stabilize the tunnel, filling all void spaces which
will require four months of additional construction time and a change order cost of $7,884,343.00; and
WHEREAS, the Utilities Department has considered alternatives to this proposed change order but none resolves the
issue as safely and efficiently as the SPS proposal.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF FAYETTEVILLE,
ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order No. 3 to the
design -build contract with Structural Preservation Systems, LLC, a copy of which is attached to this Resolution, in an
amount not to exceed $7,884,343.00 to rehabilitate the sewer pipeline and stabilize the tunnel under the southbound
Highway 112 exit ramp on I-49.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget adjustment, a copy of
which is attached to this Resolution.
PASSED and APPROVED on September 5, 2023
Page 1
Resolution: 191-23
File Number: 2023-1023
Approved:
Attest:
1�
an Paxton, City 40e.,Treasurer
Page 2
CITY OF
FAYETTEVILLE
ARKANSAS
MEETING OF SEPTEMBER 5, 2023
CITY COUNCIL MEMO
TO:
Mayor Jordan and City Council
THRU:
Susan Norton, Chief of Staff
FROM:
Tim Nyander, Utilities Director
DATE:
SUBJECT:
Structural Preservation Systems, LLC - Change Order No. 3
RECOMMENDATION:
2023-1023
Staff recommends approval of a change order to the Design -Build contract with Structural Preservation
Systems, LLC in an amount not to exceed $7,884,343.00, and approval of a budget adjustment.
BACKGROUND:
In 2021 City Water/Sewer Staff performed an inspection of the 48-inch gravity sewer line that extends from
Gregg Avenue to Sunshine Road. Visual inspections of each manhole were conducted, and a `boat' was
constructed to float down each line segment and record video. Overall, the line was in excellent shape,
however, one area in the vicinity of Interstate-49 has experienced damage at some point during its 15-years of
service. This segment of line cannot be repaired with typical excavation techniques due to its location under
the Southbound Highway-112 Exit Ramp on 1-49.
City Council approved a design -build contract (Res. 6-23) with Structural Preservation Systems, LLC (SPS), a
national leader in trenchless pipe point repairs, to develop a plan for repairs in this location. Once mobilized,
SPS created a bypass system to dry the work zone, then entered the pipe for initial shoring and sanitizing.
Then a detailed engineering in -pipe investigation was conducted to determine exact location and extent of
repairs necessary. During this investigation, the pipe and tunnel system were found to be "unsafe in its current
condition" and "subject to imminent collapse."
DISCUSSION:
The root cause of the failure of this pipeline is the lack of grouting in the annular space outside the pipe,
between the pipe wall and the tunnel encasement and tunnel walls. Without this grout the original steel tunnel
liner plates have corroded and the tunnel has started to collapse, thereby crushing the sewer pipe.
The original design -build contract cost (Res. 6-23) was $2,477,644.00 with a $375,000.00 contingency. SPS
proposes a solution to completely rehabilitate the pipeline and stabilize the tunnel, filling all void spaces. This
solution will require four months additional construction time and a change order cost of $7,884,343.00.
Staff has considered alternatives to this proposed change order. For example, installing a new, independent
sewer line in a new parallel tunnel. This option could be a lower cost at first glance. However, it would take
approximately two years to design, permit, and construct. All the while the active sewer would be bypass
pumping, at risk of failure, and at a significant operational cost. Furthermore, the existing line would still need a
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
high -cost grouting abandonment. Other pipe -lining technologies have been considered as well such as cured
in place pipe. However, these technologies would likely create a very deformed final pipe shape due to existing
deflections and failed pipe segments. Furthermore, these liners would not address existing void spaces nearby
the tunnel that could contribute to surface settlement. Finally, these liners would require all existing safety
shoring in the pipe to be removed, a very high life -safety risk.
BUDGET/STAFF IMPACT:
A budget adjustment is attached to move funds into the Sanitary Sewer Rehabilitation account within the Water
& Sewer fund to pay for Change Order No. 3.
ATTACHMENTS: SRF Structural Preservation Systems CO3, 2023-1023 BA Structural Preservation CO3,
Change Order 3 (signed by sps), Change Order Request 635148-03
Mailing address:
113 W. Mountain Street www.fayetteville-ar.gov
Fayetteville, AR 72701
== City of Fayetteville, Arkansas
Y 113 West Mountain Street
Fayetteville, AR 72701
(479)575-8323
- Legislation Text
File #: 2023-1023
Structural Preservation Systems, LLC - Change Order No. 3
A RESOLUTION TO APPROVE CHANGE ORDER NO. 3 TO THE DESIGN -BUILD CONTRACT
WITH STRUCTURAL PRESERVATION SYSTEMS, LLC IN AN AMOUNT NOT TO EXCEED
$7,884,343.00 TO REHABILITATE THE SEWER PIPELINE AND STABILIZE THE TUNNEL
UNDER THE SOUTHBOUND HIGHWAY 112 EXIT RAMP ON I-49, AND TO APPROVE A
BUDGET ADJUSTMENT
WHEREAS, on January 3, 2023, the City Council passed Resolution 6-23 authorizing Mayor Jordan to
sign a design -build contract with Structural Preservation Systems, LLC (SPS) to develop a plan for
repairs to the sewer pipe under the southbound Highway 112 exit ramp on I-49; and
WHEREAS, during the investigation, SPS determined the pipe and tunnel system is "unsafe in its
current condition" and "subject to imminent collapse" because of the lack of grouting in the space
outside the pipe, between the pipe wall and the tunnel encasement and tunnel walls; and
WHEREAS, SPS proposes to completely rehabilitate the pipeline and stabilize the tunnel, filling all
void spaces which will require four months of additional construction time and a change order cost of
$7,884,343.00; and
WHEREAS, the Utilities Department has considered alternatives to this proposed change order but
none resolves the issue as safely and efficiently as the SPS proposal.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
FAYETTEVILLE, ARKANSAS:
Section 1: That the City Council of the City of Fayetteville, Arkansas hereby approves Change Order
No. 3 to the design -build contract with Structural Preservation Systems, LLC, a copy of which is
attached to this Resolution, in an amount not to exceed $7,884,343.00 to rehabilitate the sewer pipeline
and stabilize the tunnel under the southbound Highway 112 exit ramp on I-49.
Section 2: That the City Council of the City of Fayetteville, Arkansas hereby approves a budget
adjustment, a copy of which is attached to this Resolution.
Page 1
Tim Nyander
Submitted By
City of Fayetteville Staff Review Form
2023-1023
Item ID
9/5/2023
City Council Meeting Date - Agenda Item Only
N/A for Non -Agenda Item
8/17/2023 WATER SEWER (720)
Submitted Date Division / Department
Action Recommendation:
Staff recommends approval of a change order to the Design -Build contract with Structural Preservation Systems,
LLC in an amount not to exceed $7,884,343.00, and approval of a budget adjustment.
5400.720.5700-5815.00
Account Number
02017.1
Project Number
Budgeted Item? Yes
Does item have a direct cost? Yes
Is a Budget Adjustment attached? Yes
Purchase Order Number:
Change Order Number:
Original Contract Number:
Comments:
Budget Impact:
Water/Sewer
Fund
Sanitary Sewer Rehabilitation
Total Amended Budget
Expenses (Actual+Encum)
Available Budget
Item Cost
Budget Adjustment
Remaining Budget
Project Title
$
7,218,253.00
$
4,949,784.91
2,268,468.09
$
7,884,343.00
$
7,300,000.00
1,684,125.09
V20221130
2023-205 Previous Ordinance or Resolution # 06-23
3 Approval Date:
2023-11
City of Fayetteville, Arkansas - Budget Adjustment (Agenda)
Budget Year Division Adjustment Number
WATER SEWER (720)
/Org2
2023
Requestor: Cheryl Partain
BUDGET ADJUSTMENT DESCRIPTION / JUSTIFICATION:
A budget adjustment is needed in the Sanitary Sewer Rehabilitation project to cover the cost for the Change Order No. 3 to
the Design -Build contract with Structural Preservation Systems, LLC for engineering and construction services related to the
emergency trenchless repair of a 48-inch diameter sanitary sewer line under Interstate 49. Moving budgeted funds from
multiple Water/Sewer projects to cover the emergency repair.
COUNCIL DATE:
ITEM ID#:
9/5/2023
2023-1023
Holly Black
0/16'/2023 11:56 ql;l
RESOLUTION/ORDINANCE
Budget Division Date
TYPE: D - (City Council)
JOURNAL#:
GLDATE:
CHKD/POSTED:
TOTAL
Account Number
- -
Increase / (Decrease)
Expense Revenue
Project.Sub#
Project Sub.Detl AT
v.202388
Account Name
5400.720.5700-5815.00
7,300,000 -
02017
1 EX
Improvements - Sewer
5400.720.5600-5808.00
5400.720.5600-5808.00
(228,364) -
(1,171,636) -
12009
12009
1700 EX
1 EX
Improvements - Water Line
Improvements - Water Line
5400.730.5800-5801.00
5400.730.5800-5818.00
(200,000) -
(300,000) -
13018
13018
1 EX
1 EX
Fixed Assets
Wastewater Treatment Plant - Improvemei
5400.720.5600-5808.00
5400.730.5800-5801.00
(500,000) -
(4,000,000) -
14010
15023
1 EX
1 EX
Improvements - Water Line
Fixed Assets
5400.720.5600-5808.00
(900,000) -
17004
1 EX
Improvements - Water Line
I of 1
Ii
Change Order No.
CITY OF
FAYETTEVILLE
ARKANSAS
CHANGE ORDER
Contract Title:
Date of Issuance:
Design -Build Contract: Emergency Sewer Line Repair
To Contractor: Structural Preservation Systems, LLC. ORDINANCE/RESOLUTION: 6-23
Effective: January 3, 2023
The Contract is changed as follows:
August 4, 2023
Bid
Bid
Previous
Unit
Contract
Revised
Revised
Original
Revised
Item
Item
Estimated
of
Unit
Estimated
Unit
Estimated
Estimated
No.
Description
Quantity
Measure
Price
Quantity
Price
Cost
Cost
Submittals, Engineering and up-
1
front Project Planning
1
LS
$ 63,250.00
1
$ 63,250.00
$ 63,250.00
$63,250.00
2
Mobilization
1
LS
$ 299,499.80
1
$ 299,499.80
$ 299,499.80
$299,499.80
Bypass System Installation and
3
Pressure Testing
1
LS
$ 567,000.00
1
$ 567,000.00
$ 567,000.00
$567,000.00
Bypass System with Rental,
4
Fueling and Pump Watch
40
DAYS
$ 12,556.53
40
$ 12,556.53
$ 502,261.20
$502,261.20
5
Rescue Team
1
LS
$ 143,545.00
1
$ 143,545.00
$ 143,545.00
$143,545.00
Pipeline Sanitizing and Safety
6
Shoring
1
LS
$ 71,050.00
1
$ 71,050.00
$ 71,050.00
$71,050.00
Inspection & Design
7
Modifications
1
LS
$ 86,275.00
1
$ 86,275.00
$ 86,275.00
$86,275.00
8
CFRP Materials Delivered to Site
0
LS
$ 175,000.00
0
$ 175,000.00
$ -
$0.00
9
CFRP Installation
0
LF
$ 5,234.05
0
$ 5,234.05
$ -
$0.00
10
Demobilization
1
LS
$ 30,193.20
1
$ 30,193.20
$ 30,193.20
$30,193.20
11
Closeout Report
1
LS
$ 16,164.80
1
$ 16,164.80
$ 16,164.80
$16,164.80
COLT
Feasibility and Shoring Design
1
LS
$ 50,000.00
1
$ 50,000.00
$ 50,000.00
$50,000.00
Updated Shoring - materials,
CO2.1
freight, re -mobilization,
1
LS
$ 715,000.00
1
$ 715,000.00
$715,000.00
engineering, labor, installation,
entire 925-LF
$ 715,000.00
CO2.2
Extended Bypass Pumping
13
DAYS
$ 7,155.00
13
$ 7,155.00
$93,015.00
Duration be and 40-da s
$ 93,015.00
Page 1 of 3
CO2.3
On -site supervision and facilities
40
DAYS
$ 656.00
40
$ 656.00
$26,240.00
costs while de -mobilized
$ 26,240.00
CO3.1
Rescue Team Additional Days
0
DAYS
$ -
64
$ 3,589.00
$ -
$229,696.00
CO3.2
Bypass Pumping Additional Days
0
DAYS
$ -
94
$ 7,155.00
$ -
$672,570.00
CO3.3
Secondary Bypass System for Wet
0
LS
$ -
1
$ 520 000.00
$520 000.00
Weather
$ -
'
CO3.4
Polyurethane Foam Bulkhead
0
LS
$ -
1
$ 423 000.00
$423 000.00
Installation
$ -
'
CO3.5
Cellular Concrete Annular
0
LS
$ -
1
$ 830,000.00
$830,000.00
Grouting$
-
0O3.6
Sail Stabilization (up to 25,000
0
LS
$ -
1
$ 1,266,447.00
$1,266,447.00
$ -
CO3.7
CFRP Materials Delivered to Site
0
LS
$ -
1
$ 175,000.00
$
$175,000.00
Establish Environmental
CO3.8
Conditions and Install CFRP on
0
LF
$ -
100
$ 5,234.05
$523,405.00
,Original 100-LF
$ -
CFRP Rehabilitation on All
CO3.9
ungrouted Sections of HOBAS
0
LF
$ -
755
$ 2,970.00
$2,242,350.00
Pie
$ -
CO3.10
Bypass Pumping, Additional Days
0
DAYS
$ -
30
$ 7,155.00
$214,650.00
for Secondary Bypass System
$ -
CO3.11
Soil Stabilization Allowance (up
0
GALLONS
$ -
25000
$ 21.73
$543,250.00
to 25,000 add'1gallons)$
-
0O3.12
CFRP Rehabilitation in grouted
0
LF
$ -
70
$ 2,970.00
$207,900.00
areas near manholes
$ -
0O3.13
Daily Rate for Second Pump
0
DAYS
$ -
15
$ 2,405.00
$36,075.00
Watch DuringRain Events
$ -
Summation of Cost $ 2,663,494.00 $10,547,837.00
Net Cost for this Change Order $7,884,343.00
Not valid until signed by the Owner
The original Contract Price was $ 2,477,644.00
Net change b previously authorized change orders 185 850.00
g Yp Y g $
The Contract Price prior to this Change Order was 2 663 494.00
P g $ >
The Contract Price will increase by $7,884,343.00
Page 2 of 3
The new Contract Price including this Change Order will be
The Contract Time(s) will increase by
Required dates of Completion as of the date of this Change Order therefore are:
10,547,837.00
0 calendar days
Substantial Completion n/a
Final Completion n/a
NOTE: This summary does not reflect changes in the Contract Price or Time(s) which have been authorized by Work Change Directives not incorporated in this or
previous Change Orders.
Structural Preservation Systems, LLC. CIT
YOF FA
B' DATE BAY
Jeffrey M. Venanzi - President
,� Oq /05 W23
DATE
Page 3 of 3
StructuraK'l
PROJECT NAME/ADDRESS:
City of Fayetteville
Design -Build 48" HOBAS Sewer Repair
Client:
City of Fayetteville
113 West Mountain Street
Fayetteville, AR 72701
The contract is changed as follows:
STRUCTURAL to
Initiated by:
OWNER ❑
CONTRACTOR
SUBCONTRACTOR ❑
CHANGE ORDER REQUEST
CHANGE ORDER NUMBER: 635148-03
DATE OF CHANGE ORDER: 8/03/23
CONTRACT DATE: 1/3/23
CONTRACT SCOPE: IDB 48" HOBAS Sewer Repair
• Provide 64 Additional Days of Confined Space Rescue Team*
• Provide 94 Additional Days of Primary Critical Bypass System*
• Install secondary 13MGD Bypass System and operate for 60 Days per owner's direction
• Install Polyurethane Foam Bulkheads as necessary to support successful annular grouting operation
• Fill annulus space between 48" HOBAS Pipe ad 72" Steel Casing with cellular, sulfate -resistant grout
• Perform soil stabilization around the 72" Steel Tunnel using cementitious grout and sodium silicate injection
• Install CFRP Stand-alone rehabilitation of damaged HOBAS Piping
*Billed at daily rates
Cost Summary:
Total change order amount reflects highest assumed durations and material quantities in SOV. Work will be billed per the pricing
table attached.
Total Change Order Amount: $7,884,343.00
Original Contract Sum.................................................................................................$2,477,644.00
Net change by previously authorized Change Orders...............................................$185,850.00
Contract Sum prior to this Change Order...................................................................$2,663,494.00
Amount of increase authorized by this Change Order
.............................................$7,884,343.00
New Contract Sum including this Change Order.....................................................$10,547,837.00
NOTE: This summary does not reflect adjustments in Subcontract Sum or Subcontract Time for changes
authorized by Construction Change Directive but not yet finalized by Contractor and Subcontractor.
The adjustments to the contract, if any, specified above shall constitute a full and final settlement of any and all
claims arising out of or related to the change set forth herein, including claims for impact and delay costs. Except as
expressly modified herein, all terms and conditions of the contract remain unchanged and in full force and effect.
CITY OF FAYETTEVILLE
m
STRUCTURAL PRESERVATION SYSTEMS, LLC
BY:
DATE: DATE:
Item No.
Cost
UOM
Quantity
Extended Cost
1
Submittals, Engineering, and up -front Project Planning
$ 63,250.00
LS
1
$ 63,250.00
2
Mobilization
$ 299,499.80
LS
1
$ 299,499.80
3
Bypass System Installation and Pressure Testing
$ 567,000.00
LS
1
$ 567,000.00
4
Bypass System with Rental, Fueling and Pump Watch
$ 12,556.53
Days
40
$ 502,261.20
5
Rescue Team
$ 143,545.00
LS
1
$ 143,545.00
6
Pipeline Sanitizing and Safety Shoring
$ 71,050.00
LS
1
$ 71,050.00
7
Inspection and Design Modifications
$ 86,275.00
LS
1
$ 86,275.00
10
CFRP to Site
F
Demobilization
5,000.00
234.05
$ 30,193.20
LS
LF
LS
0
1
$
$ 30,193.20
11
Closeout Report
$ 16,164.80
LS
1
$ 16,164.80
Original Contract Value:
$ 1,779,239.00
co1.1 Feasibility and Shoring Design $ 50,000.00 LS 1 1
$ 50,000.00
Change Order 01:
$ 50,000.00
Total Contract With Change Order 01:
$ 1,829,239.00
co2.i
Shoring Materials, Freight, Re -Mobilization, Engineering, Labor, Installation
$ 715,000.00
LS
1
$ 715,000.00
CO2.2
Extended Bypass Pumping Rental, Fueling, and Pump Watch Beyond 40 Days
$ 7,155.00
Days
13
1
$ 93,015.00
CO2.3
CO3.1
On -Site Supervision and Facilities Costs While De -Mobilized
otal
Rescue Team (After 40 days captured on line item 3)
$ 656.00
RW
Contract With
$ 3,589.00
1 Days
Change
Change
DAY
40
Order 02:
Order 02:
64
$ 26,240.00
$ 834,255.00
$ 2,663,494.00
$ 229,696.00
CO3.2
Bypass Operation of Original Bypass System (in addition to the 40 days captured on line item 4)
$ 7,155.00
DAY
94
$ 672,570.00
CO3.3
Secondary Stand Alone Bypass (Installation and 60 days of Bypass Operation)
$ 520,000.00
LS
1
$ 520,000.00
CO3.4
Bulkheads for Annular Grouting (Polyurethane Foam):
$ 423,000.00
LS
1
1 $ 423,000.00
CO3.s
Annular Grouting (Cellular Concrete):
$ 830,000.00
LS
1
$ 830,000.00
CO3.6
Soil Stabilization (Lump Sum up to 25,000 Gallons)
$ 1,266,447.00
LS
1
$ 1,266,447.00
CO3.7
CFRP Materials Delivered to Site
$ 175,000.00
LS
1
$ 175,000.00
COM
Establish Environmental Conditions and Install CFRP on Original 100LF
$ 5,234.05
LF
100
$ 523,405.00
CO3.9
CFRP Rehabilitation on All Un-Grouted Sections of HOBAS Pipe
$ 2,970.00
LF
755
$ 2,242,350.00
003.10
Bypass Operation of Secondary Bypass System (After 60 days captured on line item 18)
$ 7,155.00
DAY
30
$ 214,650.00
003.11
Soil Stabilization Allowance (Up to 25,000 Additional Gallons)
$ 21.73
GALLON
25000
$ 543,250.00
c03.12
CFRP Rehabilitation From Manhole to Manhole (Additional 70LF)
$ 2,970.00
LF
70
$ 207,900.00
CO3.13
Daily rate for second Pump Watch during Rain Events
$ 2,405.00
DAY
15
$ 36,075.00
Change Order 03:
$ 7,884,343.00
Total Contract With Change Order 03:
$ 10,547,837.00
Owner Option:
$ 1,001,875.00
Potential Final Contract Value:
I $ 9,545,962.00
STRUCTURAL will make every effort to expedite the project to minimize days of Bypass operation. Line Items 3.1, 3.2, 3.10, and 3.13 will be invoiced for Days used so this is a potential area of savings. For
example, if the project is completed 3 days ahead of schedule, there are potential large savings from this final contract value.